20230522 Amendment 05 - Corrosion Control.docx
DOCX document 17 KB Posted
- Attached to
- ADAL Corrosion Control
- Solicitation number
- W912LM23R1000
About this file
This document contains an amendment to a request for proposal for corrosion control renovation services. The amendment provides responses to contractor questions, clarifying that assembled equipment will be contractor installed but using non-union labor. Acceptable pipe insulation alternatives are also specified, and compressed air piping material is identified. The closing date is unchanged. Contractors must acknowledge this amendment when submitting proposals. The related opportunity posted by the Minnesota Army National Guard seeks proposals for corrosion control renovation at the 133rd Airlift Wing in Saint Paul, Minnesota, with a magnitude between $1,000,000 to $5,000,000. The project is set aside for small businesses with a NAICS code of 236220 and size standard of $45 million in average annual receipts.
View the file
Other files
| File | Type | Posted |
|---|---|---|
| 20230522 Geotech report.pdf | ||
| 20230512 Amendment 04 - Corrosion Control.docx | DOCX document | |
| 20230512 Amendment 03 - Corrosion Control.docx | DOCX document | |
| 20230509 Amendment 02 - Corrosion Control.docx | DOCX document | |
| 20230501 Amendment 01 - Corrosion Control.docx | DOCX document | |
| 20230508 Corrosion Control Signin.pdf | ||
| 20230509 Amendment 02 - Corrosion Control.docx | DOCX document | |
| 20230406 QJKL149550 CorrosionControl Drawing 1 Nov 21.pdf | ||
| 20230417 W912LM23R1000 Corrosion Control.pdf | ||
| 20230406 Specification.pdf | ||
| EAL Request-Company-2023MMDD.xlsx | XLSX spreadsheet | |
| EXHIBIT A Cor Ctl(Attachment).docx | DOCX document | |
| EXHIBIT B Cor Ctl Ld (Attachment).docx | DOCX document | |
| EXHIBIT D Letter of Commitment Ld Cor Ctl (Attachment).docx | DOCX document | |
| EXHIBIT C Reference_Questionnaire_Package Cor Ctl (Attachment).docx | DOCX document |
Show all 15
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
NOTICE OF PROPOSED TASK ORDER
REQUEST FOR PROPOSAL
Amendment 05
DATE: 22 May 2023
| PROJECT TITLE & NUMBER: | Corrosion Control |
| PN: QJKL149550 |
1. This amendment is being issued to answer questions.
Do we have cut sheets or a list of connections for the GFCI equipment? As the mechanical contractor what would we be responsible for? Are these pre-assembled skids or is additional set up involved?
Repsonse: The Government Furnished Contractor Installed units are to be assembled by supplier not the contractor but will be limited to non-union labor. Installation of the equipment to supporting utilities such as duct work, electrical, gas, etc. are within contractor’s scope.
Would 1" or 1 1/2" pre-molded fiberglass jacketed pipe insulation be an acceptable alternative for the rainwater pipe insulation as we have used on other projects on this Base? In my opinion, cellular glass and Polyiso are not very good choices for rainwater insulation. Using 1/2" closed cell may not provide enough insulation on larger pipes.
Response: Follow specs and if a no cost change, can bring up during the submittal process.
Please specify what type of piping material is to be used for the compressed air piping as the Specifications do not call out what kind of piping material to use.
Response: Section 20 05 13, par. 3.08 Pipe schedule Compressed air ASTM B88 Hard-Drawn Copper (ACU1) or ASTM A53 Gr. B Steel (ACS6). Where multiple Pipe Class Specifications are specified, selection of material is at Contractor’s option.
2. With this amendment the closing date will not be extended:
3. This amendment must be acknowledged when submitting your proposal.