Q A 3-1-2011.docx
DOCX document 12 KB Posted
- Attached to
- OK MATOC IDIQ Federal contract opportunity
- Solicitation number
- W912L611R0004
View the file
Other files for this federal contract opportunity
| File | Type | Posted |
|---|---|---|
| Contractor list.xlsx | XLSX spreadsheet | |
| Q A Final Revsion.pdf | ||
| Q A Final.pdf | ||
| Q A 3-11-2011.docx | DOCX document | |
| Q A 3-10-2011.docx | DOCX document | |
| Q A 3-9-2011.docx | DOCX document | |
| Q A 3-8-2011 1400.docx | DOCX document | |
| Q A 3-8-2011 1200.docx | DOCX document | |
| Q A 3-8-2011.docx | DOCX document | |
| Q A 3-7-2011.docx | DOCX document | |
| Pre-Proposal Attendance List.pdf | ||
| Q A 3-6-2011.docx | DOCX document | |
| Q A 3-4-2011.docx | DOCX document | |
| Q A 3-4-2011.docx | DOCX document | |
| MATOC EXHIBIT E Jan 2011.doc | DOC document | |
| RFI Sample Bldg 1033.docx | DOCX document | |
| Q A 2-25-2011.docx | DOCX document | |
| MATOC EXHIBITS A-D F and G Jan 11.doc | DOC document | |
| Sub-Contractor times.docx | DOCX document | |
| set-aside Exhibit E-1.doc | DOC document | |
| MATOC EXHIBIT E Jan 2011.doc | DOC document | |
| MATOC EXHIBIT E Jan 2011.doc | DOC document | |
| 11-R-0004.pdf | ||
| MATOC EXHIBITS A-D F and G Jan 11.doc | DOC document |
Show all 24
On GovTribe
Work with this file on GovTribe
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
What are the procedures to turn-in the RFP to get on base?
By Thursday, March 18th with employee, Driver License number, and company name.
137arw.msc@ang.af.mil What is the Period of Performance for the Bldg 1033 Project?
210 days Fed Biz ops change on 24-FEB references a change in due date. Is it the bid date that is changing?
No, the questionnaire form had the wrong date The finish schedule, sheet A-611, calls out for room 115 to have an epoxy coated floor. I cant seem to find anything in the specs on this material, also what is to be done with the existing floor?? Is there a material that needs to be removed?
The epoxy flooring is referenced in spec section 09 90 00 paragraph 3.13.2.A. The existing concrete flooring is to be prepared according to the epoxy manufacturer's installation instructions.
Sheet A-101, note 2. Calls out for a 1hr fire rated wall from the CMU to the deck. Where is the detail for this showing how many sheets of GWB will be needed on each side and the width of the wall?
The note indicates that the one hour fire barrier is for the height of the existing CMU portion of the wall. Reference General Note #2 and note on plan A-101 that states "One hour fire barrier shall be maintained to the top of the existing CMU". This note does not indicate a one hour fire rated wall from the CMU to the deck. Date of signed/sealed drawings is January 12, 2011.
Would the government allow roof mounted HVAC equipment, the new UPS project at this building has some equipment on the roof?
The HVAC units are to be relocated to the roof, see A-103 and M-201.
Is there natural gas available in this area and would gas fired equipment be acceptable?
Gas heat is required and gas is available.
Does each of the office areas require individual t-stat control ? The current system appears to have a VAV box for each office area?
Each office area does not require individual t-stat control.
Will exposed duct be allowed in the server room?
All ceiling except for the Mechanical Room have drop ceilings. No room is call out as the server room, however there is a comm closet (with a drop ceiling).
File details come from the government source that posted it. Updated .