Site_Visit_Minutes_1st.pdf
PDF 233 KB Posted
- Attached to
- Hangar 36 Multiple Projects Federal contract opportunity
- Solicitation number
- W912JB-19-B-5007
About this file
Site Visit Meeting Minutes
View the file
Other files for this federal contract opportunity
| File | Type | Posted |
|---|---|---|
| Bid_Opening_Sign_In_Sheet.pdf | ||
| Bid_Opening_Abstract_H36_MP_Updated.pdf | ||
| RFI_DOCUMENT_1.pdf | ||
| RFI_DOCUMENT_2.pdf | ||
| Sign_In_Sheet.pdf | ||
| W912JB-19-B-5007_AMENDMENT_0004.pdf | ||
| Site_Visit_Minutes_2nd.pdf | ||
| Sign_In_Sheet_2nd.pdf | ||
| W912JB-19-B-5007_AMENDMENT_0003.pdf | ||
| W912JB19B5007_Amendment_0002a.pdf | ||
| W912JB-19-B-5007_Solicitation_Amendment_0002.pdf | ||
| W912JB-19-B-5007_AMENDMENT_0001.pdf | ||
| S1.pdf | ||
| H36_Design_Drawings_00.pdf | ||
| Manufacturer_Details_Drawing.pdf | ||
| W912JB-19-B-5007_SOLICITATION.pdf | ||
| Vetting_Access_Request_List_Blank.pdf | ||
| SOW_Hangar_36_Multi_Project_-_Rev_01b.pdf | ||
| Hangar_36_-_AF_Form_66_Rev_00.pdf | ||
| Presolicitation_Announcement_H36_Multiple_Projects.pdf |
Show all 20
On GovTribe
Work with this file on GovTribe
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
MICHIGAN AIR NATIONAL GUARD
127th MISSION SUPPORT GROUP
SELFRIDGE ANG BASE MICHIGAN
23 August 2019
MEMORANDUM FOR RECORD
FROM: 127 MSC
Contracting Division
43200 Maple St, Bldg. 105
Selfridge ANGB, MI 48045-5213
SUBJECT: Pre-Proposal Conference for Solicitation W912JB-19-B-5008, Project No. VGLZ 192038:
HANGAR 36 MULTIPLE PROJECTS.
1. Site visit held this date at the Contracting Division conference room commencing at: 8:00AM in conjunction with subject Request for Proposal. For list of attendees see sign in sheet.
2. Contract Specialist David Brown introduced himself and Tom Resh from the government’s team for the project. Steven Stocking was introduced as the Contracting Officer.
A. PROJECT DESCRIPTION:
The contractor shall schedule, mobilize and perform a complete construction project on Hangar 36 with several areas of work. The work will be general construction work as described by the contract drawings and this Statement of Work. The work will be multidiscipline and will utilize many diffident trades to be accomplished. The work will be in multiple areas of the building.
3. Bids are due NLT Tuesday 10 September 2019 at 2:00PM local time. Offerors are to hand carry bids to 127 MSC Lobby/Conference Room and deposit bids in a bid depository. Offerors are advised that this project is not currently funded and that offers must be good for 112 days.
a. Project Magnitude is between $250,000.00 and $500,000.00
b. After the notice to proceed is issued the project has a performance time of 200 calendar days for project completion.
c. A Site Visit will be held immediately after this pre-proposal conference at the construction site.
d. When amendments are issued they will be posted to the FBO website.
e. Bid, Payment, and Performance Bonds will be required for this project based on
Independent Government Estimate.
f. Liquidated damages are not applicable to this project.
g. Warranty of Construction clause is incorporated and applies to this project.
h. The most current wage determination is incorporated into the solicitation and will be made part of the resultant contract but it is the contractor's responsibility to keep track of the most current wage rate. Currently DBA MI20190091 Mod 5 dated 16 August
2019.
i. Safety measures are always a part of Government contracts and the Army Corp of
Engineers manual is incorporated in the contract.
j. RFI procedures were reviewed as follows:
i. Email technical questions in RFI format to the Contracting for resolution.
ii. All RFI questions and answers will be emailed out as soon as possible.
k. Please recall that only the Contracting Officer can approve changes such as price, schedule, specifications, and clauses with formal written notice typically in the form of a solicitation amendment or task order modification. Work undertaken regarding changes not formally approved by the Contracting Officer (save for COR approved no cost field changes) is at the Contractor’s risk.
l. This requirement is currently not funded.
4. The project description was stated in the FBO announcement package repair transformers project announcement notice sent out with the Notice of Solicitation Form on 10 July 2019.
5. Any project specific questions were referred to the RFI submittal process. Question was asked on period of performance time, and government will amend the solicitation if need
be. Period of performance is 200 calendar days. Due to the time change from 10am to 8am, a 2nd site visit will be scheduled to accommodate those that might have missed the earlier time.
6. The site visit concluded at 9:00am on Friday 23 August 2019.
8/23/2019
X David Brown
David Brown
Contract Specialist
Signed by: BROWN.DAVID.ALLAN.1096981950
File details come from the government source that posted it.