More swithboard Answers 15 JULY.pdf
PDF 146 KB Posted
- Attached to
- Main Switchboard Panel Install
- Solicitation number
- W912HQ26S0034
About this file
This is a Request for Information (RFI) regarding the replacement of the main switchboard in Building 2593.
The RFI addresses five key areas related to the 2000A switchboard replacement project. Regarding manufacturer preference, four primary options are presented: Schneider Electric (Square D MasterPact/Model 6) is noted for excellent federal support and common use in USACE facilities; Eaton Pow-R-Line/Magnum DS for military installations; Siemens Sivacon/Sentron for selective coordination capabilities; and ABB/GE ReliaGear for legacy system support. For temporary backup power during weekday outages, four Priority 1 panels require support: Fire Alarm Control Panel, Server Room, Security systems, and Building Automation System (BAS). Priority 2 includes Telecom, Priority 3 includes HVAC serving IT, and Priority 4 includes general office panels (not backed up) and lighting panels (case-by-case determination). During long weekend outages, the facility must maintain Fire Alarm, Security/Access Control, Server Room, Network equipment, BAS, and any systems supporting adjacent facilities, while most office lighting and receptacle panels can remain offline until Monday morning. The base utility company will shut down the utility transformer, with Government personnel operating all Government-owned medium-voltage switching equipment; contractor personnel are prohibited from operating primary distribution equipment unless specifically authorized. The facility currently has no maintenance history for the utility transformer disconnect switch, requiring the contractor to perform testing before any planned outage.
View the file
Other files
| File | Type | Posted |
|---|---|---|
| Switchboard Answers 15 JULY.pdf | ||
| 2593 Kingman Drawings 85.pdf | ||
| 2593 Kingman Drawings 103.pdf | ||
| Contractor Questions and Answers.pdf | ||
| SOW.pdf | ||
| CSS_Main Switchboard Panel Install_revised (002).pdf |
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
RFI #1 - Building 2593 – Main Switchboard Replacement
1. Is there a preferred manufacturer for the new 2000A switchboard?
Typical manufacturers include:
Manufacturer Comments Schneider Electric (Square D MasterPact / Model 6)
Excellent federal support, very common in USACE faciliƟes
Eaton Pow-R-Line / Magnum DS Widely used on military installaƟons Siemens Sivacon / Sentron Excellent selecƟve coordinaƟon capabiliƟes ABB / GE (ReliaGear) Strong replacement support for legacy GE systems
2. Which panels need temporary backup if the outage occurs during weekdays?
AnƟcipate criƟcal loads / temporary power to support:
CriƟcal Panels
• Fire Alarm Control Panel (FACP)
• Emergency CommunicaƟons
• IT / Server Room
• Network switches
Security system
• Card access system
• CCTV equipment
• Building AutomaƟon System (BAS)
• Telephone system
• CriƟcal HVAC serving communicaƟons rooms
• Elevator controller
• Emergency lighƟng
Office receptacle panels are not backed up unless mission requirements dictate otherwise.
Priority Panel Temporary Power 1 Fire Alarm Yes 1 Server Room Yes 1 Security Yes 1 BAS Yes 2 Telecom Yes 3 HVAC serving IT Yes 4 General Office Panels No 4 LighƟng Panels Case-by-case
3. Which panels require backup during a long weekend outage?
Maintain:
• Fire Alarm
• Security
• Access Control
• Server Room
• Network equipment
• BAS
• Any systems supporƟng adjacent faciliƟes
Most office lighƟng and receptacle panels can remain offline unƟl Monday morning.
4. Will the base uƟlity company shut down the uƟlity transformer?
YES
Government personnel shall operate all Government-owned medium-voltage switching equipment.
Contractor personnel shall not operate Government-owned primary distribuƟon equipment unless specifically authorized.
5. Is there any record of exercising the switch to de-energize the uƟlity transformer?
Currently, there is no maintenance history. The Contractor shall perform tesƟng before a planned outage.