This document includes a cost breakdown spreadsheet and proposal schedule for an underground electric lines project at Camp Buehring, Kuwait, as well as a related federal contract opportunity notice.
The cost breakdown spreadsheet provides labor, equipment, material, and other cost details for base bid items including mobilization, constructing 11kV underground electric lines, packaged substations, and site work, as well as optional items for an additional substation and low voltage lines. The total proposed cost is $8,611,972. The proposal schedule lists the same bid line items and provides the total base bid price of $805,900, with optional items totaling an additional $805,900 and a total base plus options price of $8,611,972.
The federal contract opportunity is a sources sought notice for a medium voltage electrical distribution ring project at Camp Buehring, Kuwait, with an estimated budget between $1-5 million and anticipated period of performance of 365 days. Interested firms are requested to provide capabilities statements by May 6, 2019 to the Army Corps of Engineers contract specialist. The solicitation will utilize full and open competition and a best value tradeoff evaluation.
Attachment G Cost Breakdown & Proposal Schedule Excel Version 10 of 10 attachments
View the file
Other files for this federal contract opportunity
Show all 26
On GovTribe
Work with this file on GovTribe
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Proposal Schedule
| PROPOSAL SCHEDULE | ||||
| RFP: | W912ER19R0024 | P2# | 474411 | |
| PROJECT: | Underground Electric Lines | |||
| LOCATION: | Camp Buehring, Kuwait | 12-Aug-08 |
| ITEM NO. | DESCRIPTION | QTY | UNIT | AMOUNT | TOTAL | TOTAL | ||
| Base Bid Items | ||||||||
| 0001 | Mobilization and Demobilization in accordance with the contract documents | 1 | JA | |||||
| 0002 | Construct 11 KV Underground Electric Lines in accordance with the contract documents | 1 | JA | $ | $ | $ | ||
| 0003 | Construct Packaged Substations in accordance with the Contract Documents | 1 | JA | |||||
| 0004 | Site Work in accordance with the Contract Documents | 1 | JA | |||||
| TOTAL BASE BID PRICE (ITEMS 0001 - 0004) | ||||||||
| Optional Bid Items | ||||||||
| 0005 | Option #1 Construct Packaged Substation 18 in accordance with the Contract Documents | 1 | JA | $ | $ | $ | ||
| 0006 | Option #2 Construct Low Voltage Lines in accordance with the Contract Documents | 1 | JA | |||||
| TOTAL OPTIONS PRICE (ITEM(S) 0005-0006) | ||||||||
| TOTAL BASE + OPTIONS PRICE (ITEMS 0001 - 0006) | $805,900 |
*OUSD has mandated that the "dollars" or "lump sum" units of measure no longer be used on DoD contracts. "JA" will be used for "LS" $805,900
$8,611,972
$805,900
$805,900
$805,900
$8,611,972
$8,611,972
$8,611,972
&9&P of &N
Cost Breakdown Sheet
| COST BREAKDOWN | |||||||||||||
| RFP: | W912ER19R0024 | P2# | 474411 | ||||||||||
| PROJECT: | Underground Electric Lines | PROPOSER: | |||||||||||
| LOCATION: | Camp Buehring, Kuwait | DATE: | |||||||||||
| ITEM | DESCRIPTION | LABOR MAN-HOURS | DIRECT LABOR COST | DIRECT EQUIPMENT COST | DIRECT MATERIALS COST | SUB CONTRACTOR COST | TOTAL DIRECT COST | JOOH | HOOH | BOND | OVERHEAD/ INDIRECT COST | PROFIT | TOTAL PROPOSED COST |
| 0001 | Mobilization and Demobilization in accordance with the contract documents | ||||
| 0001AA | Mobilization | ||||
| 0001AB | Demobilization | ||||
| Total Price (Items 0001AA - AB) | ERROR:#REF! | ERROR:#REF! | ERROR:#REF! | ERROR:#REF! | |
| 0002 | Construct 11 KV Underground Electric Lines in accordance with the contract documents | ||||
| 0002AA | New 11 KV Cable | ||||
| 0002AB | Cable Terminations | ||||
| Total Price (Items 0002AA - AB) | ERROR:#REF! | ERROR:#REF! | ERROR:#REF! | ERROR:#REF! | |
| 0003 | Construct Packaged Substations in accordance with the Contract Documents | ||||
| 0003AA | Packaged Substation 14 | ||||
| 0003AB | Packaged Substation 15 | ||||
| 0003AC | Packaged Substation 16 | ||||
| 0003AD | Packaged Substation 17 | ||||
| Total Price (Items 0003AA to 0003AD) | ERROR:#REF! | ERROR:#REF! | ERROR:#REF! | ERROR:#REF! | |
| 0004 | Site Work in accordance with the Contract Documents | ||||
| 0004AA | Demolition | ||||
| 0004AB | Road Crossings | ||||
| 0004AC | Site Earthwork | ||||
| 0004AD | Site Improvements | ||||
| Total Price (Items 0004AA - AD) | |||||
| TOTAL BASE BID PRICE (ITEMS 0001 - 0004) | |||||
| Optional Bid Items | |||||
| 0005 | Option #1 Construct Packaged Substation 18 in accordance with the Contract Documents | ||||
| 0005AA | Packaged Substation 18 | ||||
| Total Option #1 Price (Item(s) 0005AA) | |||||
| 0006 | Option #2 Construct Low Voltage Cable Lines in accordance with the Contract Documents | ||||
| 0006AA | Low Voltage (415) Lines | ||||
| Total Option #2 Price (Item(s) 0006AA) | |||||
| TOTAL OPTIONS PRICE (ITEM(S) 0005-0006) | |||||
| TOTAL BASE + OPTIONS PRICE (ITEMS 0001 - 0006) |