Amendment_0002_Proposal_Schedule_and_Cost_Breakdown_Camp_Buehring.xlsx

XLSX spreadsheet 28 KB Posted

Attached to
Camp Buehring Electric Line/Rings Federal contract opportunity
Solicitation number
W912ER19R0024
Issued by
Department of the Army Corps of Engineers Engineering District Middle East

About this file

This document contains an amendment to a proposal schedule and cost breakdown for an underground electric lines project at Camp Buehring in Kuwait. The amendment provides pricing details for base bid items including mobilization, construction of 11kV underground electric lines and packaged substations, and site work, with a total base bid price of $8,611,972. Optional items include additional work on packaged substations and low voltage lines, with a total optional price of $805,900 and potential maximum total project price of $8,611,972 if all options are exercised. The cost breakdown sheet further specifies labor, equipment, material, and other costs associated with each item.

A related federal contract opportunity seeks responses for solicitation number W912ER19R0024 to construct a medium voltage electrical distribution ring and potential additional power lines at Camp Buehring, Kuwait. The estimated budget range for the project is $1-5 million and responses were due by May 6, 2019. The U.S. Army Corps of Engineers district in the Middle East intends to use full and open competition and best value tradeoff for a firm-fixed price contract.

Amendment 0002 Proposal Schedule and Cost Breakdown Excel Version

View the file

Other files for this federal contract opportunity

Other files attached to Camp Buehring Electric Line/Rings, newest first.
File Type Posted
Drawing_XE-504.pdf PDF
Amendment_0002_Cost_Breakdown_Camp_Buehring.pdf PDF
Amendment_0002_Proposal_Schedule_Camp_Buehring.pdf PDF
Specifications_Amendment_0002_Camp_Buehring.pdf PDF
W912ER-19-R-0024_Amendment_0002.pdf PDF
Attachment_E_Relevancy_Matrix_Rev1.pdf PDF
W912ER19R0024_Amend_01_Camp_Buehring.pdf PDF
Specifications_Camp_Buehring_Amendment_01.pdf PDF
Attachment_F_Past_Performance_Questionnaire_PPQ-0.pdf PDF
Vol_I_W912ER19R0024_Camp_Buehring_Electric_Lines.pdf PDF
Attachment_C_Experience_Overview_Sheet.pdf PDF
Vol_III_Drawings_Camp_Buehring_Underground_Electric_Lines.pdf PDF
Attachment_G_Cost_Breakdown_and_Proposal_Schedule_Camp_Buehring.xlsx XLSX spreadsheet
Vol_II_Specifications_Camp_Buehring_Electric_Lines.pdf PDF
Attachment_E_Relevancy_Matrix.pdf PDF
Attachment_G_Cost_Breakdown_and_Proposal_Schedule_Camp_Buehring.pdf PDF
Attachment_A_and_B_Financial_Standing_Quest_and_Calc_Self_Performed_Work.pdf PDF
Attachment_D_Construction_Experience_Form.pdf PDF
Camp_Buerhing_Underground_Electric_Lines_Specifications.pdf PDF
Underground_Electric_Lines_Camp_Buehring.pdf PDF
Camp_Buehring_Underground_Electric_Lines_Drawings.pdf PDF
Camp_Buehring_Site_Visit_19AUG2019_-_Base_Access_Instruction.docx DOCX document
Camp_Buehring_Site_Visit_-_Map.pdf PDF
Camp_Buehring_Site_Visit_-_Base_Access_Instruction.docx DOCX document
Camp_Buehring_Site_Visit_-_Map.pdf PDF
Camp_Buehring_Kuwait_Capabilities_Statement.pdf PDF
Show all 26

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Proposal Schedule

PROPOSAL SCHEDULE
RFP:W912ER19R0024P2#474411
PROJECT:Underground Electric Lines
LOCATION:Camp Buehring, Kuwait12-Aug-08
ITEM NO.DESCRIPTIONQTYUNITAMOUNTTOTALTOTAL
Base Bid Items
0001Mobilization and Demobilization in accordance with the contract documents1JA
0002Construct 11 KV Underground Electric Lines in accordance with the contract documents1JA$$$
0003Construct Packaged Substations in accordance with the Contract Documents1JA
0004Site Work in accordance with the Contract Documents1JA
TOTAL BASE BID PRICE (ITEMS 0001 - 0004)
Optional Bid Items
0005Option #1 Construct Packaged Substation 18 in accordance with the Contract Documents1JA$$$
0006Option #2 Construct Low Voltage Lines in accordance with the Contract Documents1JA
TOTAL OPTIONS PRICE (ITEM(S) 0005-0006)
TOTAL BASE + OPTIONS PRICE (ITEMS 0001 - 0006)$805,900

*OUSD has mandated that the "dollars" or "lump sum" units of measure no longer be used on DoD contracts. "JA" will be used for "LS" $805,900

$8,611,972

$805,900

$805,900

$805,900

$8,611,972

$8,611,972

$8,611,972

&9&P of &N

Cost Breakdown Sheet

COST BREAKDOWN
RFP:W912ER19R0024P2#474411
PROJECT:Underground Electric LinesPROPOSER:
LOCATION:Camp Buehring, KuwaitDATE:
ITEMDESCRIPTIONLABOR MAN-HOURSDIRECT LABOR COSTDIRECT EQUIPMENT COSTDIRECT MATERIALS COSTSUB CONTRACTOR COSTTOTAL DIRECT COSTJOOHHOOHBONDTOTAL OVERHEAD/ INDIRECT COSTPROFITTOTAL PROPOSED COST
0001Mobilization and Demobilization in accordance with the contract documents
0001AAMobilization
0001ABDemobilization
Total Price (Items 0001AA - AB)
0002Construct 11 KV Underground Electric Lines in accordance with the contract documents
0002AANew 11 KV Cable
0002ABCable Terminations
Total Price (Items 0002AA - AB)
0003Construct Packaged Substations in accordance with the Contract Documents
0003AAPackaged Substation 14
0003ABPackaged Substation 15
0003ACPackaged Substation 16
0003ADPackaged Substation 17
Total Price (Items 0003AA - 0003AD)
0004Site Work in accordance with the Contract Documents
0004AADemolition
0004ABRoad Crossings
0004ACSite Earthwork
0004ADSite Improvements
Total Price (Items 0004AA - AD)
TOTAL BASE BID PRICE (ITEMS 0001 - 0004)
Optional Bid Items
0005Option #1 Construct Packaged Substation 18 in accordance with the Contract Documents
0005AAPackaged Substation 18
0005ABSite Civil Work associated with Construction of Packaged Substation 18
Total Option #1 Price (Item(s) 0005AA - 0005AB)
0006Option #2 Construct Low Voltage Cable Lines in accordance with the Contract Documents
0006AALow Voltage (415) Lines
0006ABSite Civil Work associated with Construction of Low Voltage (415) Lines
Total Option #2 Price (Item(s) 0006AA - 0006AB)
TOTAL OPTIONS PRICE (ITEM(S) 0005-0006)
TOTAL BASE + OPTIONS PRICE (ITEMS 0001 - 0006)