RFP: W912ER19R0005 P2# 459013
PROJECT: Consolidated Squadron Operations Facility PROPOSER:
LOCATION: Al Udeid Air Base (AUAB), Qatar DATE:
Mobilization and Demobilization in accordance with the contract documents
State Of Qatar Licensed Grade A
Consultant, in accordance with the contract documents
Construct Squadron Operations
Facility in accordance with the contract documents
0003AA
Construct Squadron Operations Facility less the Direct Expansion HVAC
System in accordance with the contract documents
0003AB
Construct Direct Expansion HVAC
System complete for Squadron
Operations Facility in accordance with the contract documents
Construct Supporting Facilities in accordance with the contract documents
0004AA
Site Demolition in accordance with the contract documents
0004AB
Construct Site Electrical Distribution
System in accordance with the contract documents
0004AC
Construct Site Water Distribution & Fire
Distribution System in accordance with the contract documents
0004AD
Construct Site Sanitary Sewer
Collection System in accordance with the contract documents
0004AE
Construct Site Communication
Distribution System in accordance with the contract documents
0004AF
Construct Site Storm Water Collection
System in accordance with the contract documents
0004AG
Construct Site Improvements, Access
Road, Parking Lots, and Walkways in accordance with the contract documents
OVERHEAD/
INDIRECT COST
PROFIT
TOTAL PROPOSED
COST
COST BREAKDOWN
ITEM DESCRIPTION
DIRECT
MATERIALS COST
SUB
CONTRACTOR
COST
TOTAL
DIRECT
COST
LABOR MAN-HOURS
DIRECT LABOR
COST
DIRECT
EQUIPMENT COST
TOTAL BASE BID PRICE (ITEMS 0001 - 0004)
EXHIBIT 1 Page 1 of 2
RFP: W912ER19R0005 P2# 459013
PROJECT: Consolidated Squadron Operations Facility PROPOSER:
LOCATION: Al Udeid Air Base (AUAB), Qatar DATE:
OVERHEAD/
INDIRECT COST
PROFIT
TOTAL PROPOSED
COST
COST BREAKDOWN
ITEM DESCRIPTION
DIRECT
MATERIALS COST
SUB
CONTRACTOR
COST
TOTAL
DIRECT
COST
LABOR MAN-HOURS
DIRECT LABOR
COST
DIRECT
EQUIPMENT COST
Option # 1 - M403/M506 - Air Cooled
Chilled Water HVAC System, and associated electrical and plumbing systems, and equipment sunshade (in lieu of direct expansion air conditioning units), construct in accordance with the contract documents.
Option # 2 - Parking sunshades on first row of parking spaces, construct in accordance with the contract documents.
Option # 3 - Asphalt pavement (in lieu of aggregate), pavement marking for perpendicular parking stall, concrete wheel stop, and hatched markings, construct in accordance with the contract documents.
Option # 4 - Heavy duty concrete pavement for buses, and thickened asphalt edge, construct in accordance with the contract documents.
Option # 5 - Provide Forty-Eight (48) hour capacity potable water storage tank (in lieu of 24-hour capacity), construct in accordance with the contract documents.
Option # 6 - Provide Pre-action wet sprinkler systems in the Electrical
Telecommunication and Server rooms, construct in accordance with the contract documents.
TOTAL BASE + OPTIONS PRICE (ITEMS 0001 - 0010)
TOTAL OPTIONS PRICE (ITEMS 0005 - 0010)
EXHIBIT 1 Page 2 of 2