Attachment_C_-_Construction_Experience_Form_Instructions.docx
DOCX document 27 KB Posted
- Attached to
- Consolidated Squadron Operations Facility
- Solicitation number
- W912ER19R0005
About this file
Attachment C - Construction Experience Form Instructions
View the file
Other files
Show all 21
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
ATTACHMENT C
CONSTRUCTION EXPERIENCE FORM - INSTRUCTIONS
1. Use one form for each contract.
2. Forms may expand to more than one page, but remember that the entire Factor is limited to sixteen (16) pages.
3. Do not make changes to any of the shaded blocks.
4. Complete all non-shaded blocks in the top summary section.
5. Place an “x” next to all Topics that are applicable to the specific contract (not all topics need to be addressed for each contract).
6. Complete the non-shaded “How experience gained” column to describe your experience with that specific topic and how it will enable successful performance on this project.
7. See example below for details.
Summary Section
| # |
| Contract Name / Title |
| 1 |
| D/B Genesis Operational Facilities |
| Location (Country/Base or City) |
| Role |
| Value ($) |
| Start / End Dates |
| Al Udeid Air Base, Qatar |
| Prime |
| $93.7 M |
| May 2016 – Jul 2018 |
Contract Description - briefly describe the scope and summarize the salient features of the contract
Design and construct environmentally controlled pre-engineered structures with vertical fabric doors for four (4) Genesis aircrafts for the U.S. Naval Facilities Engineering Command (NAVFAC) at Al Udeid Air Base, Qatar. The structures will serve as hangar space for one or more aircrafts of the Genesis Aircraft System platform and each may contain organizational, maintenance, and administration spaces. The facilities shall be of semi-permanent construction which can be disassembled and removed from the site. Supply space shall be provided within one of the structures. Hangar access and parking aprons will also be constructed. The facilities will include the construction of a shielded Forward Operating Base (FOB) Mission Control System (MCS) with an associated communications tower and an emergency generator.
Specific Experience (paragraph letters below align with the solicitation evaluation criteria)
| Topic |
| How experience gained on listed contract will enable successful performance on Falcon 3-Facilities and Infrastructure, Phase 2SAMPLE |
| x |
| a. |
Hiring / maintaining workforce Due to last-minute requirements initiated by the customer after contract award, the FOB MCS and Comms Tower were modified to have a phased completion date prior to the remainder of the contract. We requested and received authorization to add night shifts, plus weekend/holiday/overtime work. Using our local labor broker, we hired nearly 100 additional laborers and mechanics. The man-hours worked during this phase increased from a typical 2000/week to 26000/week, an increase of more than 300%. We completed the FOB MCS and Comms tower 2 weeks ahead of schedule, allowing the customer to meet their emergency needs. Our proven ability to ramp-up our labor force quickly means that we have the experience to perform similarly on this project, if necessary.
| x |
| b. |
Long Lead Procurement Procurement of the Comms Tower described above was originally scheduled for 4-months after submittal approval. We suggested that representatives from the Corps and other approving agencies meet at the fabricator’s plant to expedite review/approval. All concerns were addressed at the meeting, allowing fabrication to start much sooner than in the typical submit/approve process. In addition, we convinced the fabricator to support Qatar national interests to expedite their fabrication and delivery. Our innovative procurement solutions gives us the experience to smoothly handle long lead items on this project.
| x |
| c. Work Access |
| See below concerning Passes / badges on Qatar military base |
| x |
| d. Obtaining Permits and Approvals |
| See below concerning Permits / Approvals in Qatar |
| x |
| e. Phasing, including active airfield |
| Due to last-minute requirements initiated by the customer after contract award, the FOB MCS and Comms Tower were modified to have a phased completion date prior to the remainder of the contract. We mobilized additional equipment and workforce, and received authorization to add night shifts, plus weekend/holiday/overtime work. The man-hours worked during this phase increased from a typical 2000/week to 26000/week, an increase of more than 300%. We completed the FOB MCS and Comms tower 2 weeks ahead of schedule, allowing the customer to meet their emergency needs. This experience will enable us to successfully perform this project.SAMPLE |
| x |
| Greater Weight a. |
Similar scope, $, complexity The hangar access and parking aprons are similar to the airfield paving requirements of Falcon 3. The total paving of this contract, approximately $20M, is similar in magnitude to Falcon 3. Our experience with work of similar scope, $, and complexity will enable us to perform similarly on this project.
Greater Weight b.
Phasing on active airfield
| x |
| Greater Weight c. |
Qatar military installation Work was performed completely within the Al Udeid Air Base confines, giving us ample construction experience on a Qatar military installation. This experience will enable us to successfully perform this project.
| x |
| Greater Weight d. |
Passes / badges on Qatar military base Work was performed on Al Udeid Air Base, giving us considerable experience obtaining base passes and badges. We appoint an in-house Security Coordinator to manage the Site Security Plan and liaise with the Al Udeid authorities and the subcontracted private security firm, XXX company. The XXX company provided security and escorts, and has worked on Al Udeid Air Base for more than 20 years. This experience will enable us to successfully perform this project.
| x |
| Greater Weight e. |
Permits / Approvals in Qatar As described above in the Long Lead Procurement section, we obtained approval for the Comms Tower in an innovative method, allowing fabrication to start much sooner than in the typical submit/approve process. In addition, because this contract was in Qatar, we worked all the permits and approvals through QCDD (Fire Protection), QEC (Building and Utility Permits), and/or Kharama (Electrical). This experience will enable us to successfully perform this project.