A.07.24_W912EF17B000300001.pdf

PDF 119 KB Posted

Attached to
Lower Monumental Drainange and Unwatering Pumps
Solicitation number
W912EF-18-B-0003
Issued by

About this file

Amendment 0001 to incorporate FAR 52.211-10

View the file

Other files

Show all 17

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

AMENDMENT OF SOLICITATION/MODIFICATION OF CONTRACT

Except as provided herein, all terms and conditions of the document referenced in Item 9A or 10A, as heretofore changed, remains unchanged and in full force and effect.

15A. NAME AND TITLE OF SIGNER (Type or print)

30-105-04EXCEPTION TO SF 30

APPROVED BY OIRM 11-84

STANDARD FORM 30 (Rev. 10-83)

Prescribed by GSA

FAR (48 CFR) 53.243

The purpose of this amendment is to include FAR 52.211-10.

Bid date remains unchanged.

1. CONTRACT ID CODE PAGE OF PAGES

1 2

16A. NAME AND TITLE OF CONTRACTING OFFICER (Type or print)

16C. DATE SIGNED

BY 10-Oct-2017

16B. UNITED STATES OF AMERICA15C. DATE SIGNED15B. CONTRACTOR/OFFEROR

(Signature of Contracting Officer)(Signature of person authorized to sign)

8. NAME AND ADDRESS OF CONTRACTOR (No., Street, County, State and Zip Code) X W912EF-18-B-0003

X 9B. DATED (SEE ITEM 11)

03-Oct-2017

10B. DATED (SEE ITEM 13)

9A. AMENDMENT OF SOLICITATION NO.

11. THIS ITEM ONLY APPLIES TO AMENDMENTS OF SOLICITATIONS

X The above numbered solicitation is amended as set forth in Item 14. The hour and date specified for receipt of Offer is extended, X is not extended.

Offer must acknowledge receipt of this amendment prior to the hour and date specified in the solicitation or as amended by one of the following methods:

(a) By completing Items 8 and 15, and returning 1 copies of the amendment; (b) By acknowledging receipt of this amendment on each copy of the offer submitted;

or (c) By separate letter or telegram which includes a reference to the solicitation and amendment numbers. FAILURE OF YOUR ACKNOWLEDGMENT TO BE

RECEIVED AT THE PLACE DESIGNATED FOR THE RECEIPT OF OFFERS PRIOR TO THE HOUR AND DATE SPECIFIED MAY RESULT IN

REJECTION OF YOUR OFFER. If by virtue of this amendment you desire to change an offer already submitted, such change may be made by telegram or letter, provided each telegram or letter makes reference to the solicitation and this amendment, and is received prior to the opening hour and date specified.

12. ACCOUNTING AND APPROPRIATION DATA (If required)

13. THIS ITEM APPLIES ONLY TO MODIFICATIONS OF CONTRACTS/ORDERS.

IT MODIFIES THE CONTRACT/ORDER NO. AS DESCRIBED IN ITEM 14.

A. THIS CHANGE ORDER IS ISSUED PURSUANT TO: (Specify authority) THE CHANGES SET FORTH IN ITEM 14 ARE MADE IN THE

CONTRACT ORDER NO. IN ITEM 10A.

B. THE ABOVE NUMBERED CONTRACT/ORDER IS MODIFIED TO REFLECT THE ADMINISTRATIVE CHANGES (such as changes in paying office, appropriation date, etc.) SET FORTH IN ITEM 14, PURSUANT TO THE AUTHORITY OF FAR 43.103(B).

C. THIS SUPPLEMENTAL AGREEMENT IS ENTERED INTO PURSUANT TO AUTHORITY OF:

D. OTHER (Specify type of modification and authority)

E. IMPORTANT: Contractor is not, is required to sign this document and return copies to the issuing office.

14. DESCRIPTION OF AMENDMENT/MODIFICATION (Organized by UCF section headings, including solicitation/contract subject matter where feasible.)

10A. MOD. OF CONTRACT/ORDER NO.

2. AMENDMENT/MODIFICATION NO. 5. PROJECT NO.(If applicable)

6. ISSUED BY

3. EFFECTIVE DATE

10-Oct-2017

CODE

USAED, WALLA WALLA - CONTRACTING DIV.

KENT R. BERNARD 201 N. THIRD AVENUE

WALLA WALLA WA 99362-1876

W912EF 7. ADMINISTERED BY (If other than item 6)

4. REQUISITION/PURCHASE REQ. NO.

CODE

See Item 6

FACILITY CODECODE

EMAIL:TEL:

W912EF-18-B-0003

SECTION SF 30 BLOCK 14 CONTINUATION PAGE

SUMMARY OF CHANGES

SECTION F - DELIVERIES OR PERFORMANCE

The following have been added by full text:

52.211-10 COMMENCEMENT, PROSECUTION, AND COMPLETION OF WORK (APR 1984)

The Contractor shall be required to (a) Commence work under this contract within 10 calendar days after the date the Contractor receives the notice of award, (b) prosecute the work diligently, and (c) complete the entire work ready for use not later than the dates listed below.

(1) Onsite construction at Lower Monumental Dam may begin anytime after the contractor receives Notice to

Proceed (NTP), all preconstruction contract requirements to include required payment and performance bonds are completed, and all required preconstruction submittals are approved, subject to restrictions outlined below. Payment and Performance bonds shall be submitted no later than 15 March 2018.

The Drainage Pumps, Oil Water Separator and Low Voltage Motor Control Center Out of Service (OOS) Work

Window is 4 June 2018 through 27 September 2018. The Unwatering Pumps and Medium Voltage Motor Control

Center OOS Work Window is 28 September 2018 through 25 January 2019 provided that the drainage sump is fully functioning with all testing, inspections and commissioning completed. If the drainage sump is fully functional prior to 27 September 2018 then the Unwatering Pumps and Medium Voltage Motor Control Center OOS Work

Window may begin prior to the OOS Work Window stated above.

(2) All systems at Lower Monumental must be fully functioning with all testing, inspections and commissioning completed not later than 25 January 2019.

(3) The Contractor shall complete final cleanup and demobilization by not later than 15 calendar days after completion of work in (2) above.

(4) The Contractor shall complete final submission of O&M manuals, working “as-built” contract drawings and final approved versions of Contractor prepared drawings (see SECTION 01 78 00.00 28) by not later than 30 calendar days after completion of work in (2) above.

(End of Clause)

(End of Summary of Changes)