DLA Warehouse Bldg #9670 15013 Joint Base Lewis-McChord, WA W912DW-17-B-0008
SECTION TABLE OF CONTENTS
DIVISION 01 - GENERAL REQUIREMENTS
SECTION 01 33 22
CONSTRUCTION PHASE CAD REQUIREMENTS
10/12
PART 1 GENERAL
1.1 DEFINITIONS
1.1.1 "CAD" - Computer Aided Drafting
1.1.2 "Workspace"
1.2 REFERENCES
1.3 SUBMITTALS
1.4 DELIVERABLE FILES SOFTWARE VERSIONS
1.5 QUALITY CONTROL
1.5.1 CAD Standards Checks
1.5.2 Visual Checks
1.6 CONTRACTOR COORDINATION
PART 2 PRODUCTS
2.1 GOVERNMENT FURNISHED MATERIAL
2.1.1 Variation with Contract Drawings
2.1.2 Drawing Completion and Quality
2.1.3 Data Loss, Corruption, and Error
2.2 RECORD FILE CONTENT
2.3 MINIMUM CONTENT REQUIREMENTS
2.3.1 Architectural and Interior Design
2.3.1.1 Spaces
2.3.1.2 Walls and Curtain Walls
2.3.1.3 Doors, Windows, and Louvers
2.3.1.4 Roof
2.3.1.5 Ceilings
2.3.1.6 Vertical Circulation
2.3.1.7 Specialties and Woodwork
2.3.1.8 Signage
2.3.2 Structural
2.3.2.1 Foundations
2.3.2.2 Floor Slabs
2.3.2.3 Structural Steel
2.3.2.4 Cast-In-Place Concrete
2.3.2.5 Joints
2.3.2.6 Stairs
2.3.2.7 Shafts and Pits
2.3.3 Mechanical
2.3.3.1 HVAC
2.3.3.2 Mechancial Piping
2.3.3.3 Plumbing
2.3.3.4 Elevator Equipment
2.3.4 Electrical and Telecommunications
2.3.4.1 Interior Electrical Power and Lighting
2.3.4.2 Security and Fire Detection
2.3.4.3 Grounding Systems
2.3.4.4 Communications
SECTION 01 33 22 Page 1 R0003
2.3.4.5 Exterior Building Lighting
2.3.5 Fire Protection
2.3.5.1 Fire Protection System
2.3.6 Civil and Site
2.3.6.1 Terrain
2.3.6.2 Drainage
2.3.6.3 Storm Water and Sanitary Sewers
2.3.6.4 Utilities
2.3.6.5 Hardstands
2.4 OWNERSHIP AND RIGHTS IN DATA
PART 3 EXECUTION
3.1 INTERIM SUBMITTALS
3.1.1 General Document and File Review Requirements
3.1.2 Interim Record CAD Drawings
3.2 CONSTRUCTION CLOSEOUT SUBMITTALS
-- End of Section Table of Contents --
SECTION 01 33 22 Page 2
SECTION 01 33 22
CONSTRUCTION PHASE CAD REQUIREMENTS
10/12
PART 1 GENERAL
1.1 DEFINITIONS
The following definitions apply specifically to the USACE CAD Requirements.
1.1.1 "CAD" - Computer Aided Drafting
Digital drawing files including plans, elevations, sections, schedules, details, etc..
1.1.2 "Workspace"
A collection of content libraries and supporting files that define and embody a CAD standard. A workspace includes element libraries such as wall types, steel shapes, furniture, etc.. It also contains sheet libraries such as print/plot configurations, text fonts and styles, and sheet borders and title blocks.
1.2 REFERENCES
The publications listed below form a part of this specification to the extent referenced. The publications are referred to within the text by the basic designation only.
U.S. ARMY ENGINEER RESEARCH AND DEVELOPMENT CENTER (ERDC)
ERDC/ITL TR-09-2 (2009) A/E/C CAD Standard, Release 4.0
ERDC/ITL TR-12-1 (2012) CAD Drafting Standard
1.3 SUBMITTALS
Government approval is required for submittals with a "G" designation;
submittals not having a "G" designation are for information only. When used, a designation following the "G" designation identifies the office that will review the submittal for the Government. Submit the following in accordance with Section 01 33 00 SUBMITTAL PROCEDURES:
SD-05 Design Data
Interim Record CAD Drawings; G
Submitted Files List; G
SD-07 Certificates
Contractor Quality Control Certification; G
SECTION 01 33 22 Page 3
1.4 DELIVERABLE FILES SOFTWARE VERSIONS
Deliver record digital CAD drawing files in Autodesk Autocad 2012 software format.
1.5 QUALITY CONTROL
Implement quality control measures for the models and files, including but not limited to, the following activities:
1.5.1 CAD Standards Checks
Use software content auditing tools to ensure that CAD drawing standards including fonts, dimensions, line styles, layers, and other formatting issues are compliant per ERDC/ITL TR-09-2 and ERDC/ITL TR-12-1.
1.5.2 Visual Checks
Perfom visual checks to ensure the files reflect recorded construction conditions and that there are no unintended elements and/or artifacts in the models and drawings.
1.6 CONTRACTOR COORDINATION
The Contractor's shall provide digital file updates to subcontractors.
Provide drawing files in the format(s) required by the subcontractors.
Establish and maintain a schedule of CAD coordination meetings for subcontractors and field personnel to ensure that all changes and corrections are incorporated into the as-built drawings.
PART 2 PRODUCTS
2.1 GOVERNMENT FURNISHED MATERIAL
The Government will provide CAD files and reference drawings which include the original construction drawings for the structure and several renovations as Government Furnished Material (GFM) for the Contractor's use. The GFM will include Autodesk AutoCAD digital files created for producing the Contract Drawings. The information and level of detail contained in the GFM shall be maintained in the Record Drawings.
The Contractor has the option of preparing their own CAD drawings as a basis for Record CAD drawings, and interim submittals. If so, the drawings must incorporate the same level of detail, properties, and functionality that is included in the GFM.
2.1.1 Variation with Contract Drawings
The Government makes no warranty that the the GFM CAD files and reference drawings are complete or fully consistent with the Contract Drawings. The digital CAD files provided are not part of the Contract Documents. If there is any discrepency between the CAD Drawings, the reference drawings, and the Contract Drawings, the Contract Drawings shall govern. The Government has no responsibility to modify any GFMs due to changes in the design that occur after award.
SECTION 01 33 22 Page 4 R0003
G3ENDRDN
Polygon
G3ENDRDN
Polygon
2.1.2 Drawing Completion and Quality
The Government makes no guarantee that the CAD files provide the level of completeness or quality required for closeout submittal. It is the Contractor's responsibility to complete the drawings to completely and correctly represent the as-built conditions of the facility and the site.
2.1.3 Data Loss, Corruption, and Error
Transfer of GFM files to the Contractor may result in corrupted files resulting in data loss and/or errors. Use of GFM files is at the Contractor's risk. Verify data integrity upon receipt and request a replacement if necessary.
Any adjustment of file structure, format, or software version required to make GFM compatible with the Contractor's computer systems and/or software is the responsibility of the Contractor.
2.2 RECORD FILE CONTENT
The interim and final submittal digital record files at a minimum shall contain the content below.
2.3 MINIMUM CONTENT REQUIREMENTS
The Record Drawings shall include the content described below to reflect completed construction conditions.
2.3.1 Architectural and Interior Design
2.3.1.1 Spaces
Spaces must be drawn to produce accurate net square footage and data for producing room finish schedules including room names, numbers, and occupancies.
2.3.1.2 Walls and Curtain Walls
Every wall shall be delineated to the length, width, and performance ratings (thermal, acoustic, fire) and correctly reflect defined wall types and to produce accurate plans, sections, and elevations.
2.3.1.3 Doors, Windows, and Louvers
Doors, windows, and louvers shall be delineated to represent their actual size, type, and location.
2.3.1.4 Roof
The drawings shall include the roof configuration, drainage system, penetrations, and specialty fixtures.
2.3.1.5 Ceilings
Ceilings including heights and other dimensions, soffits, materials, and other fixtures shall be accurately drawn.
SECTION 01 33 22 Page 5
2.3.1.6 Vertical Circulation
Vertical shafts and components shall be accurately delineated.
2.3.1.7 Specialties and Woodwork
Architectural fixtures including toilet room accessories, partitions, lockers, display cases, etc., and casework including cabinets, counters, etc. shall be accurately depicted.
2.3.1.8 Signage
The drawings shall include signage.
2.3.2 Structural
2.3.2.1 Foundations
Foundation and/or footing elements including curbs, joints, grade beams, etc.
2.3.2.2 Floor Slabs
Structural floor slabs shall be depicted, including recesses, curbs, pads, closure pours, and major penetrations.
2.3.2.3 Structural Steel
Steel columns, primary and secondary framing members, and steel bracing for the roof and floor systems (including decks).
2.3.2.4 Cast-In-Place Concrete
Walls, columns, beams and all other cast-in-place concrete members.
2.3.2.5 Joints
Joints shall be accurately depicted and located.
2.3.2.6 Stairs
The structural drawings shall include openings and structural framing and support members for stair systems.
2.3.2.7 Shafts and Pits
The structural drawings shall include shafts, pits, and openings.
2.3.3 Mechanical
2.3.3.1 HVAC
Installed heating, ventilating, air-conditioning, and specialty equipment including air distribution ducts, exhaust ducts, registers, diffusers, grills, and hydronic components including control system.
2.3.3.2 Mechancial Piping
HVAC related piping and fixtures, and related equipment.
SECTION 01 33 22 Page 6
2.3.3.3 Plumbing
Plumbing piping and fixtures, floor and area drains, and related equipment.
2.3.3.4 Elevator Equipment
The drawings shall include the manufacturer's equipment and control system.
2.3.4 Electrical and Telecommunications
2.3.4.1 Interior Electrical Power and Lighting
Interior electrical components including lighting fixtures, receptacles, panel boards, and control systems.
2.3.4.2 Security and Fire Detection
Special electrical components including mass notification, public address, intrusion detection, security cameras, card readers and keypads, system panels, and all other related items.
2.3.4.3 Grounding Systems
Grounding system components including lightning protection, static grounding, electrical and communications grounding, etc..
2.3.4.4 Communications
Communications service components and connections, both above ground and underground, including telephone and data. Cable tray routing shall be drawn without detail of cable contents.
2.3.4.5 Exterior Building Lighting
Exterior lighting fixtures and controls, relevant existing and proposed support utility lines, and all other equipment.
2.3.5 Fire Protection
2.3.5.1 Fire Protection System
Relevant fire protection components including piping, sprinkler heads, fittings, drains, pumps, tanks, sensors, and control panels.
2.3.6 Civil and Site
The drawings may vary in level of detail for individual elements, but at a minimum must include all features that would be included on a one inch equals 100 feet (1"=100') scaled drawing. Additional minimum drawing requirements include:
2.3.6.1 Terrain
Site conditions and grading necessary to produce accurate site topographical plans and cross sections.
SECTION 01 33 22 Page 7
2.3.6.2 Drainage
Existing and new drainage piping including upgrades.
2.3.6.3 Storm Water and Sanitary Sewers
Existing and new sewer structures and piping including upgrades, and connections to mains or other distribution points as appropriate.
2.3.6.4 Utilities
Utilities connections from the building(s) to the existing or newly-created utilities, and existing above ground and underground utility conduits, including necessary properties data to produce accurate plans and site-sections.
2.3.6.5 Hardstands
Roadways, parking lots, walkways, equipment pads, and all other site paving.
2.4 OWNERSHIP AND RIGHTS IN DATA
Upon submittal, the Government retains all rights to ownership of all CAD files developed for the project, and as modified by the Contractor, in accordance with FAR Part 27.4 and clauses incorporated elsewhere in the Contract. The Government may make use of this data following any deliverable.
PART 3 EXECUTION
3.1 INTERIM SUBMITTALS
Within thirty days after the 50 percent construction progress milestone, submit the following items:
3.1.1 General Document and File Review Requirements
For each submittal provide the following:
All workspace files, and CAD files in the software versions and formats as required for Interim Record Submittal.
A Submitted Files List. The list should include a description, directory, and file name for each file submitted. For all CAD sheet files, include the sheet number and sheet title.
Contractor Quality Control Certification confirming that all quality control checks as listed in Paragraph "Quality Control" above have been completed. This certification shall be discussed as part of the interim review process and shall address cross-discipline interferences, if any.
3.1.2 Interim Record CAD Drawings
Submit the interim Record CAD files reflecting current site and facility conditions.
SECTION 01 33 22 Page 8
3.2 CONSTRUCTION CLOSEOUT SUBMITTALS
See Section 01 78 00 CLOSEOUT SUBMITTALS for information regarding required submittals of CAD drawings at completion of construction.
-- End of Section --
SECTION 01 33 22 Page 9