Revised tech spec Section 01 33 22

View the file

Other files

File Type Posted
B.01.02_-_17B008_ABSTRACT_-_PORTRAIT.pdf PDF
10_56_29.16_-_R0003.pdf PDF
ES102_-_R0003.pdf PDF
08_33_23_-_R0003.pdf PDF
TOC_-_R0003.pdf PDF
E-102_-_R0003.pdf PDF
S-501_-_R0003.pdf PDF
DLA_Arch_-_Interior_Drawings_-_R0003.pdf PDF
W912DW-17-B-0008_Amendment_R0003.pdf PDF
03_01_30.71_-_R0003.pdf PDF
00_73_00-A_-_R0003.pdf PDF
01_45_00.00_10_-_R0003.pdf PDF
01_50_00_-_R0003.pdf PDF
W912DW-17-B-0008-0002.pdf PDF
Amendment_0001_Pkg.pdf PDF
DRAWINGS_2_of_3.pdf PDF
DRAWINGS__3_of_3.pdf PDF
DRAWINGS_1_of_3.pdf PDF
Solicitation_W912DW-17-B-0008_Aug_23,_2017.pdf PDF
Show all 19

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

DLA Warehouse Bldg #9670 15013 Joint Base Lewis-McChord, WA W912DW-17-B-0008

SECTION TABLE OF CONTENTS

DIVISION 01 - GENERAL REQUIREMENTS

SECTION 01 33 22

CONSTRUCTION PHASE CAD REQUIREMENTS

10/12

PART 1 GENERAL

1.1 DEFINITIONS

1.1.1 "CAD" - Computer Aided Drafting

1.1.2 "Workspace"

1.2 REFERENCES

1.3 SUBMITTALS

1.4 DELIVERABLE FILES SOFTWARE VERSIONS

1.5 QUALITY CONTROL

1.5.1 CAD Standards Checks

1.5.2 Visual Checks

1.6 CONTRACTOR COORDINATION

PART 2 PRODUCTS

2.1 GOVERNMENT FURNISHED MATERIAL

2.1.1 Variation with Contract Drawings

2.1.2 Drawing Completion and Quality

2.1.3 Data Loss, Corruption, and Error

2.2 RECORD FILE CONTENT

2.3 MINIMUM CONTENT REQUIREMENTS

2.3.1 Architectural and Interior Design

2.3.1.1 Spaces

2.3.1.2 Walls and Curtain Walls

2.3.1.3 Doors, Windows, and Louvers

2.3.1.4 Roof

2.3.1.5 Ceilings

2.3.1.6 Vertical Circulation

2.3.1.7 Specialties and Woodwork

2.3.1.8 Signage

2.3.2 Structural

2.3.2.1 Foundations

2.3.2.2 Floor Slabs

2.3.2.3 Structural Steel

2.3.2.4 Cast-In-Place Concrete

2.3.2.5 Joints

2.3.2.6 Stairs

2.3.2.7 Shafts and Pits

2.3.3 Mechanical

2.3.3.1 HVAC

2.3.3.2 Mechancial Piping

2.3.3.3 Plumbing

2.3.3.4 Elevator Equipment

2.3.4 Electrical and Telecommunications

2.3.4.1 Interior Electrical Power and Lighting

2.3.4.2 Security and Fire Detection

2.3.4.3 Grounding Systems

2.3.4.4 Communications

SECTION 01 33 22 Page 1 R0003

2.3.4.5 Exterior Building Lighting

2.3.5 Fire Protection

2.3.5.1 Fire Protection System

2.3.6 Civil and Site

2.3.6.1 Terrain

2.3.6.2 Drainage

2.3.6.3 Storm Water and Sanitary Sewers

2.3.6.4 Utilities

2.3.6.5 Hardstands

2.4 OWNERSHIP AND RIGHTS IN DATA

PART 3 EXECUTION

3.1 INTERIM SUBMITTALS

3.1.1 General Document and File Review Requirements

3.1.2 Interim Record CAD Drawings

3.2 CONSTRUCTION CLOSEOUT SUBMITTALS

-- End of Section Table of Contents --

SECTION 01 33 22 Page 2

SECTION 01 33 22

CONSTRUCTION PHASE CAD REQUIREMENTS

10/12

PART 1 GENERAL

1.1 DEFINITIONS

The following definitions apply specifically to the USACE CAD Requirements.

1.1.1 "CAD" - Computer Aided Drafting

Digital drawing files including plans, elevations, sections, schedules, details, etc..

1.1.2 "Workspace"

A collection of content libraries and supporting files that define and embody a CAD standard. A workspace includes element libraries such as wall types, steel shapes, furniture, etc.. It also contains sheet libraries such as print/plot configurations, text fonts and styles, and sheet borders and title blocks.

1.2 REFERENCES

The publications listed below form a part of this specification to the extent referenced. The publications are referred to within the text by the basic designation only.

U.S. ARMY ENGINEER RESEARCH AND DEVELOPMENT CENTER (ERDC)

ERDC/ITL TR-09-2 (2009) A/E/C CAD Standard, Release 4.0

ERDC/ITL TR-12-1 (2012) CAD Drafting Standard

1.3 SUBMITTALS

Government approval is required for submittals with a "G" designation;

submittals not having a "G" designation are for information only. When used, a designation following the "G" designation identifies the office that will review the submittal for the Government. Submit the following in accordance with Section 01 33 00 SUBMITTAL PROCEDURES:

SD-05 Design Data

Interim Record CAD Drawings; G

Submitted Files List; G

SD-07 Certificates

Contractor Quality Control Certification; G

SECTION 01 33 22 Page 3

1.4 DELIVERABLE FILES SOFTWARE VERSIONS

Deliver record digital CAD drawing files in Autodesk Autocad 2012 software format.

1.5 QUALITY CONTROL

Implement quality control measures for the models and files, including but not limited to, the following activities:

1.5.1 CAD Standards Checks

Use software content auditing tools to ensure that CAD drawing standards including fonts, dimensions, line styles, layers, and other formatting issues are compliant per ERDC/ITL TR-09-2 and ERDC/ITL TR-12-1.

1.5.2 Visual Checks

Perfom visual checks to ensure the files reflect recorded construction conditions and that there are no unintended elements and/or artifacts in the models and drawings.

1.6 CONTRACTOR COORDINATION

The Contractor's shall provide digital file updates to subcontractors.

Provide drawing files in the format(s) required by the subcontractors.

Establish and maintain a schedule of CAD coordination meetings for subcontractors and field personnel to ensure that all changes and corrections are incorporated into the as-built drawings.

PART 2 PRODUCTS

2.1 GOVERNMENT FURNISHED MATERIAL

The Government will provide CAD files and reference drawings which include the original construction drawings for the structure and several renovations as Government Furnished Material (GFM) for the Contractor's use. The GFM will include Autodesk AutoCAD digital files created for producing the Contract Drawings. The information and level of detail contained in the GFM shall be maintained in the Record Drawings.

The Contractor has the option of preparing their own CAD drawings as a basis for Record CAD drawings, and interim submittals. If so, the drawings must incorporate the same level of detail, properties, and functionality that is included in the GFM.

2.1.1 Variation with Contract Drawings

The Government makes no warranty that the the GFM CAD files and reference drawings are complete or fully consistent with the Contract Drawings. The digital CAD files provided are not part of the Contract Documents. If there is any discrepency between the CAD Drawings, the reference drawings, and the Contract Drawings, the Contract Drawings shall govern. The Government has no responsibility to modify any GFMs due to changes in the design that occur after award.

SECTION 01 33 22 Page 4 R0003

G3ENDRDN

Polygon

G3ENDRDN

Polygon

2.1.2 Drawing Completion and Quality

The Government makes no guarantee that the CAD files provide the level of completeness or quality required for closeout submittal. It is the Contractor's responsibility to complete the drawings to completely and correctly represent the as-built conditions of the facility and the site.

2.1.3 Data Loss, Corruption, and Error

Transfer of GFM files to the Contractor may result in corrupted files resulting in data loss and/or errors. Use of GFM files is at the Contractor's risk. Verify data integrity upon receipt and request a replacement if necessary.

Any adjustment of file structure, format, or software version required to make GFM compatible with the Contractor's computer systems and/or software is the responsibility of the Contractor.

2.2 RECORD FILE CONTENT

The interim and final submittal digital record files at a minimum shall contain the content below.

2.3 MINIMUM CONTENT REQUIREMENTS

The Record Drawings shall include the content described below to reflect completed construction conditions.

2.3.1 Architectural and Interior Design

2.3.1.1 Spaces

Spaces must be drawn to produce accurate net square footage and data for producing room finish schedules including room names, numbers, and occupancies.

2.3.1.2 Walls and Curtain Walls

Every wall shall be delineated to the length, width, and performance ratings (thermal, acoustic, fire) and correctly reflect defined wall types and to produce accurate plans, sections, and elevations.

2.3.1.3 Doors, Windows, and Louvers

Doors, windows, and louvers shall be delineated to represent their actual size, type, and location.

2.3.1.4 Roof

The drawings shall include the roof configuration, drainage system, penetrations, and specialty fixtures.

2.3.1.5 Ceilings

Ceilings including heights and other dimensions, soffits, materials, and other fixtures shall be accurately drawn.

SECTION 01 33 22 Page 5

2.3.1.6 Vertical Circulation

Vertical shafts and components shall be accurately delineated.

2.3.1.7 Specialties and Woodwork

Architectural fixtures including toilet room accessories, partitions, lockers, display cases, etc., and casework including cabinets, counters, etc. shall be accurately depicted.

2.3.1.8 Signage

The drawings shall include signage.

2.3.2 Structural

2.3.2.1 Foundations

Foundation and/or footing elements including curbs, joints, grade beams, etc.

2.3.2.2 Floor Slabs

Structural floor slabs shall be depicted, including recesses, curbs, pads, closure pours, and major penetrations.

2.3.2.3 Structural Steel

Steel columns, primary and secondary framing members, and steel bracing for the roof and floor systems (including decks).

2.3.2.4 Cast-In-Place Concrete

Walls, columns, beams and all other cast-in-place concrete members.

2.3.2.5 Joints

Joints shall be accurately depicted and located.

2.3.2.6 Stairs

The structural drawings shall include openings and structural framing and support members for stair systems.

2.3.2.7 Shafts and Pits

The structural drawings shall include shafts, pits, and openings.

2.3.3 Mechanical

2.3.3.1 HVAC

Installed heating, ventilating, air-conditioning, and specialty equipment including air distribution ducts, exhaust ducts, registers, diffusers, grills, and hydronic components including control system.

2.3.3.2 Mechancial Piping

HVAC related piping and fixtures, and related equipment.

SECTION 01 33 22 Page 6

2.3.3.3 Plumbing

Plumbing piping and fixtures, floor and area drains, and related equipment.

2.3.3.4 Elevator Equipment

The drawings shall include the manufacturer's equipment and control system.

2.3.4 Electrical and Telecommunications

2.3.4.1 Interior Electrical Power and Lighting

Interior electrical components including lighting fixtures, receptacles, panel boards, and control systems.

2.3.4.2 Security and Fire Detection

Special electrical components including mass notification, public address, intrusion detection, security cameras, card readers and keypads, system panels, and all other related items.

2.3.4.3 Grounding Systems

Grounding system components including lightning protection, static grounding, electrical and communications grounding, etc..

2.3.4.4 Communications

Communications service components and connections, both above ground and underground, including telephone and data. Cable tray routing shall be drawn without detail of cable contents.

2.3.4.5 Exterior Building Lighting

Exterior lighting fixtures and controls, relevant existing and proposed support utility lines, and all other equipment.

2.3.5 Fire Protection

2.3.5.1 Fire Protection System

Relevant fire protection components including piping, sprinkler heads, fittings, drains, pumps, tanks, sensors, and control panels.

2.3.6 Civil and Site

The drawings may vary in level of detail for individual elements, but at a minimum must include all features that would be included on a one inch equals 100 feet (1"=100') scaled drawing. Additional minimum drawing requirements include:

2.3.6.1 Terrain

Site conditions and grading necessary to produce accurate site topographical plans and cross sections.

SECTION 01 33 22 Page 7

2.3.6.2 Drainage

Existing and new drainage piping including upgrades.

2.3.6.3 Storm Water and Sanitary Sewers

Existing and new sewer structures and piping including upgrades, and connections to mains or other distribution points as appropriate.

2.3.6.4 Utilities

Utilities connections from the building(s) to the existing or newly-created utilities, and existing above ground and underground utility conduits, including necessary properties data to produce accurate plans and site-sections.

2.3.6.5 Hardstands

Roadways, parking lots, walkways, equipment pads, and all other site paving.

2.4 OWNERSHIP AND RIGHTS IN DATA

Upon submittal, the Government retains all rights to ownership of all CAD files developed for the project, and as modified by the Contractor, in accordance with FAR Part 27.4 and clauses incorporated elsewhere in the Contract. The Government may make use of this data following any deliverable.

PART 3 EXECUTION

3.1 INTERIM SUBMITTALS

Within thirty days after the 50 percent construction progress milestone, submit the following items:

3.1.1 General Document and File Review Requirements

For each submittal provide the following:

All workspace files, and CAD files in the software versions and formats as required for Interim Record Submittal.

A Submitted Files List. The list should include a description, directory, and file name for each file submitted. For all CAD sheet files, include the sheet number and sheet title.

Contractor Quality Control Certification confirming that all quality control checks as listed in Paragraph "Quality Control" above have been completed. This certification shall be discussed as part of the interim review process and shall address cross-discipline interferences, if any.

3.1.2 Interim Record CAD Drawings

Submit the interim Record CAD files reflecting current site and facility conditions.

SECTION 01 33 22 Page 8

3.2 CONSTRUCTION CLOSEOUT SUBMITTALS

See Section 01 78 00 CLOSEOUT SUBMITTALS for information regarding required submittals of CAD drawings at completion of construction.

-- End of Section --