This document provides an amendment to a solicitation for a construction contract. The amendment revises the drawings and specifications, answers bidders' questions, and modifies the solicitation notes. Key changes include revising air permit notification timelines, clarifying that a UXO technician will not be required onboard dredges unless dredging screens fail, adjusting option exercise and completion deadlines, and clarifying the official project name as the Seabright to Manasquant, Section II NJ project. Eligible bidders must acknowledge this amendment by the date specified in the solicitation to have their bids considered.

View the file

Other files

File Type Posted
Abstract W912DS21B0015.xlsx XLSX spreadsheet
W912DS21B0015-Amendment 0003.pdf PDF
5035_SeaBright-to-Manasquan_15ft_thinned_30ft_sorted_navd88_elev.txt TXT text file
01 11 00.pdf PDF
01 57 19.pdf PDF
W912DS21B0015Amendment0001.pdf PDF
SEABRIGHTMANRENO_100PCNT-20210729_RTA.pdf PDF
SB-M-21_PLANS_072821.pdf PDF
W912DS21B0015.pdf PDF
Draft USACE annual NOx calculator ACNJ (27 Jul 21).xlsx XLSX spreadsheet

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

AMENDMENT OF SOLICITATION/MODIFICATION OF CONTRACT

Except as provided herein, all terms and conditions of the document referenced in Item 9A or 10A, as heretofore changed, remains unchanged and in full force and effect.

15A. NAME AND TITLE OF SIGNER (Type or print)

30-105-04EXCEPTION TO SF 30

APPROVED BY OIRM 11-84

STANDARD FORM 30 (Rev. 10-83) Prescribed by GSA

FAR (48 CFR) 53.243

The purpose of this amendment is to:

Answ er questions for informational purposes only.

Revise and Reissue Specs Revise and Reissue Note section

Off eror must acknow ledge receipt of this amendment by the date specif ied in the proposal (or as amended) by one of the follow in methods: in the space provided on SF1442, by separate letter, or by signing block 15 below FAILURE TO ACKNOWLEDGE AMENDMENTS BY THE DATE AND TIME SPECIFIED MAY RESULT IN REJECTION OF YOUR OFFER IN ACCORDANCE WITH THE SUBMISSION, MODIFICATION, REVISION, AND WITHDRAWAL OF PROPOSALS (FAR 15.208).

1. CONTRACT ID CODE PAGE OF PAGES

J 1 5

16A. NAME AND TITLE OF CONTRACTING OFFICER (Type or print)

16C. DATE SIGNED

BY 23-Aug-2021

16B. UNITED STATES OF AMERICA15C. DATE SIGNED15B. CONTRACTOR/OFFEROR

(Signature of Contracting Officer)(Signature of person authorized to sign)

8. NAME AND ADDRESS OF CONTRACTOR (No., Street , County, State and Zip Code) X W912DS21B0015

X 9B. DATED (SEE ITEM 11)

30-Jul-2021

10B. DATED (SEE ITEM 13)

9A. AMENDMENT OF SOLICITATION NO.

11. THIS ITEM ONLY APPLIES TO AMENDMENTS OF SOLICITATIONS

X The above numbered solicitation is amended as set forth in Item 14. The hour and date specified for receipt of Offer is extended, X is not extended.

Offer must acknowledge receipt of this amendment prior to the hour and date specified in the solicitation or as amended by one of the following methods:

(a) By completing Items 8 and 15, and returning 1 copies of the amendment; (b) By acknowledging receipt of this amendment on each copy of the offer submitted;

or (c) By separate letter or telegram which includes a reference to the solicitation and amendment numbers. FAILURE OF YOUR ACKNOWLEDGMENT TO BE RECEIVED AT THE PLACE DESIGNATED FOR THE RECEIPT OF OFFERS PRIOR TO THE HOUR AND DATE SPECIFIED MAY RESULT IN

REJECTION OF YOUR OFFER. If by virtue of this amendment you desire to change an offer already submitted, such change may be made by telegram or letter, provided each telegram or letter makes reference to the solicitation and this amendment, and is received prior to the opening hour and date specified.

12. ACCOUNTING AND APPROPRIATION DATA (If required)

13. THIS ITEM APPLIES ONLY TO MODIFICATIONS OF CONTRACTS/ORDERS.

IT MODIFIES THE CONTRACT/ORDER NO. AS DESCRIBED IN ITEM 14.

A. THIS CHANGE ORDER IS ISSUED PURSUANT TO: (Specify authority) THE CHANGES SET FORTH IN ITEM 14 ARE MADE IN THE

CONTRACT ORDER NO. IN ITEM 10A.

B. THE ABOVE NUMBERED CONTRACT/ORDER IS MODIFIED TO REFLECT THE ADMINISTRATIVE CHANGES (such as changes in paying office, appropriation date, etc.) SET FORTH IN ITEM 14, PURSUANT TO THE AUTHORITY OF FAR 43.103(B).

C. THIS SUPPLEMENTAL AGREEMENT IS ENTERED INTO PURSUANT TO AUTHORITY OF:

D. OTHER (Specify type of modification and authority)

E. IMPORTANT: Contractor is not, is required to sign this document and return copies to the issuing office.

14. DESCRIPTION OF AMENDMENT/MODIFICATION (Organized by UCF section headings, including solicitation/contract subject matter where feasible.)

10A. MOD. OF CONTRACT/ORDER NO.

2. AMENDMENT/MODIFICATION NO. 5. PROJECT NO.(If applicable)

6. ISSUED BY

3. EFFECTIVE DATE

23-Aug-2021

CODE

US ARMY CORPS OF ENGINEERS, NEW YORK

26 FEDERAL PLAZA, RM 16-300

NEW YORK NY 10278-0090

W912DS 7. ADMINISTERED BY (If other than item 6)

4. REQUISITION/PURCHASE REQ. NO.

CODE

See Item 6

FACILITY CODECODE

EMAIL:TEL:

W912DS21B0015

SECTION SF 30 BLOCK 14 CONTINUATION PAGE

SUMMARY OF CHANGES

SECTION SF 30 - BLOCK 14 CONTINUATION PAGE (SF 30)

The following have been added by full text:

AMENDMENT 0002

W912DS-21-B-0015

Amendment No.002

To Bidders The following changes shall be made to the drawings and specifications.

DRAWINGS

1. The following DRAWINGS have been REVISED and REISSUED:

-None

2. The following DRAWINGS have been ADDED:

-None

3. The following DRAWINGS have been REVISED but NOT REISSUED:

-None

SPECIFICATIONS:

1. The following SPECIFICATION SECTIONS have been ADDED and are provided in their entirety herein:

-None

2. The following SPECIFICATIONS SECTIONS have been DELETED in their entirety:

3. The following SPECIFICATION SECTIONS have been REVISED and REISSUED in their entirety:

- Section 01 57 19

- Section 01 11 00

4. The following SPECIFICATION SECTIONS have been REVISED but NOT REISSUED:

REVISED SPECIFICATIONS:

- Section 01 57 19 par 3.3.1 Preconstruction Air Permits was revised –

3.3.1 Preconstruction Air Permits

Notify the Air Program Manager, through the Contracting Officer, at least 15 days prior to bringing equipment, assembled or unassembled, onto the construction site, so that air permits can be secured, if required. Necessary permitting time must be considered in regard to construction activities. Clean Air Act (CAA) permits must be obtained prior to bringing equipment, assembled or unassembled, to the construction site.

- Section 01 11 00 par 1.1 was revised to state 120 days of NTP.

Questions and Answers:

The following questions and answers are provided for information only. Nothing contained below amends or revises any provision of the solicitation.

This is for bidder’s reference only, and is not to be considered as a part of the Contract Documents.

Contract award will be based on what is contained in the printed Plans and Specifications in a hard copy format or Electronic Bid Set if provided and as posted in the sam.gov.

RFI SET #1:

Question 1. Please provide the most recent hydrographic survey data for the borrow areas available for use on this project, preferably in XYZ format.

Response: Provided most recent hydrographic survey data xyz.

Question 2. Bid Item 0011 is labeled as Option 7 and Bid Item 012 is labeled as Option 7. Should these be labeled Option 7 and Option 8?

Response: Correct; bid item 0011 is option 7 and bid item 0012 is option 8.

Question 3. Should the contractor include the cost for a 24 hour UXO Personnel on board the hopper dredge for the duration of the project?

Response: No, contractor should not include the cost for a 24-hour UXO Personnel on board the hopper dredge for the duration of the project. The government will determine, based on the type, frequency, and quantity of any MEC identified as being dredged from the borrow area, if a UXO technician or technicians are required, refer to specification section 01 35 30 par 1.6 c. If required, these additional labor resources will be negotiated and added to the contract by a contract modification, in accordance with the “changes” clause of the contract. This response does not in any way revise the requirements for land based UXO technicians, refer to specifications section 01 35 30 par 1.6 a & b.

Question 4. Will the dredge be allowed to continue to work while a UXO tech is mobilized to site? If not, due to the extended time needed to bring a UXO tech to site, please provide a line item to include standby time that may be occurred while waiting for a UXO tech to be found and mobilized to site..

Response: No, the contractor will not be allowed to continue dredging and/or beachfill work if the requirements of specification section 01 35 30 par 3.4 & 3.5 are met. An additional line item for stand-by time will not be added since this is a key indication that the dredge screens have failed and require immediate repair.

Question 5. Referencing Section 01 11 35, Air Emissions Requirements, Notify the Air Program Manager, through the Contracting Officer, at least 6 months prior to bringing equipment onto the construction site so that air permits can be secured. Given the accelerated schedule for this project, please confirm that the permits have already been secured or that the minimum 6 month notification requirement will be waived.

Response: Specifications Section 01 57 19 par 3.3.1 Preconstruction Air Permits was revised to the following –

3.3.1 Preconstruction Air Permits

Notify the Air Program Manager, through the Contracting Officer, at least 15 days prior to bringing equipment, assembled or unassembled, onto the construction site, so that air permits can be secured, if required. Necessary permitting time must be considered in regard to construction activities. Clean Air Act (CAA) permits must be obtained prior to bringing equipment, assembled or unassembled, to the construction site.

Question 6. In the Section 01 11 00, 1.1 FAR 52.211-10, Commencement, Prosecution and Completion states “if Options are exercised within 150 days from NTP the contractor shall be required to complete these options and remove all equipment from the contract area no later than March 1, 2023. In the bid schedule, Note #8. States If any other option is excised within 120 days of NTP, work must be complete by March 1, 2023. Please clarify the number of days the options can be exercised, 150 days or 120 days?

Response: 120 days is correct, section 01 11 00 par 1.1 was revised to state 120 days.

Question 7. After reviewing the specs and schedule for the project. We request the Corps to make the following changes to Note #8 and add Note #9 so that Contractors can responsibly respond to this Solicitation:

a. Note #8. The government may exercise options within 30 days of NTP. All option work, if exercised, must be completed by March 1, 2023.

b. Note #9. Item 0009 (Option 5) will be exercised if option work exercised cannot be completed by March 1, 2021.

c. Note #10. No work will occur between March 1, 2022, and October 15, 2022. No work will be allowed after March 1, 2023.

d. Note #11. The Government is under no obligation to exercise/award any option.

In addition all other relevant sections of the specifications which pertain to schedule and ward of options should be updated in accordance with the above changes.

Response: Notes were revised to the following –

Note 8 - The government may exercise options within 120 days of NTP. If options are exercised within 60 days of NTP, optional work must be completed by March 1, 2022.

Note 9 - The government may exercise options within 120 days of NTP. If options are exercised after 60 days of NTP, optional work must be completed by March 1, 2023. Item 0009 (Option 5 Re-mobilization & Demobilization for Hydraulic Beach Fill) may be exercised only if options (optional line items 0005-0008) are exercised after 60 days.

Note 10 - Optional line items may be independently awarded in accordance with the above timeline.

Note 11 - No work will occur between March 1, 2022, and October 15, 2022. No work will be allowed after March 1, 2023.

Note 12 - The Government is under no obligation to exercise/award any option.

Question 8 The posting on sam.gov says “Sandy Hook to Barnegat Inlet Beach Erosion Control Project Section II”. The SF 1442 Project Title is “Sea Bright to Manasquan, Section II NJ”. The plans and spec reads “Coastal Storm Risk Management Sea Bright to Manasquan Project, Elberon to Manasquan Reaches”. The bid bond is required to have the official name from the SF 1442. Can you please clarify which is the official project title?

Response: The Offical Title of the project: Seabright to Manasquant, Section II NJ

SECTION 00 10 00 - SOLICITATION

The following have been modified:

TOTALS

NOTES:

1. Materially unbalanced bids will be rejected. An unbalanced bid is one which is based on prices significantly less than cost for some work and prices which are significantly overstated for other work.

2. The bidders are required to bid on all items or their bid will be rejected.

3. The low bidder for the purpose of award will be the conforming responsible bidder offering the lowest amount for the Total Base Bid and Optional Bid items.

4. Line item 0003 is pre-priced at $100,000 and this price shown may not be changed. See Section 01 78 00 for Final Record Drawing definition and requirement.

5. The Bid Acceptance Period is as stated on Standard Form 1442.

6. Tapering are included in the items and exact locations are on the plan sheets.

7. All base work must be completed by March 1, 2022 due to environmental restrictions.

8. The government may exercise options within 120 days of NTP. If options are exercised within 60 days of NTP, optional work must be completed by March 1, 2022.

9. The government may exercise options within 120 days of NTP. If options are exercised after 60 days of NTP, optional work must be completed by March 1, 2023. Item 0009 (Option 5 Re-mobilization & Demobilization for Hydraulic Beach Fill) may be exercised only if options (optional line items 0005-0008) are exercised after 60 days.

10. Optional line items may be independently awarded in accordance with the above timeline.

11. No work will occur between March 1, 2022, and October 15, 2022. No work will be allowed after March 1, 2023.

12. The Government is under no obligation to exercise/award any option.

(End of Summary of Changes)