WATERVLIETWHSE_100PCNT_SPECS_RTA.pdf

PDF 26 MB Posted

Attached to
General Purpose Storage Building, Watervliet, NY Federal contract opportunity
Solicitation number
W912DS-18-B-0014
Issued by
Department of the Army Corps of Engineers Engineering District New York

About this file

Specifications - W912DS18B0014

View the file

Other files for this federal contract opportunity

Other files attached to General Purpose Storage Building, Watervliet, NY, newest first.
File Type Posted
Bid_Abstract_-__W912DS18B0014.pdf PDF
EP-602_-_PANEL_SCHEDULES.PDF PDF
10_44_16.pdf PDF
photo 11.jpg JPG image
S-001.pdf PDF
G-003.pdf PDF
EP-602_-_PANEL_SCHEDULES_(24jul18).pdf PDF
photo 22.jpg JPG image
photo 19.jpg JPG image
Watervliet_Arsenal_1A1_Approvals.pdf PDF
A-401.pdf PDF
photo 3.jpg JPG image
SUBMITTAL_REGISTER.PDF PDF
photo 12.jpg JPG image
EP-101_24jul18.pdf PDF
photo 20.jpg JPG image
photo 1.jpg JPG image
photo 18.jpg JPG image
photo 7.jpg JPG image
photo 17.jpg JPG image
photo 6.jpg JPG image
A-103.pdf PDF
M-603.pdf PDF
photo 8.jpg JPG image
03_30_00.pdf PDF
A-501.pdf PDF
A-601.pdf PDF
photo 9.jpg JPG image
03_30_00._00_10.pdf PDF
A-101.pdf PDF
photo 5.jpg JPG image
W912DS18B0014-0006.pdf PDF
03_33_00.pdf PDF
22_00_00.pdf PDF
08_71_00.pdf PDF
W912DS18B0014-0005_-_Revised_7.27.pdf PDF
08_33_23.pdf PDF
00_73_00.00_18.pdf PDF
09_30_10.pdf PDF
12_21_00.pdf PDF
41_22_13.14.pdf PDF
S-404_Watervliet_Warehouse_Loading_Dock_Amendment.pdf PDF
C-101_AMENDMENT.pdf PDF
W912DS18B0014-0005.pdf PDF
W912DS18B0014_-_0003.pdf PDF
specification_41_22_13.14.pdf PDF
WVA_Storage_Warehouse_sign_in_sheet.pdf PDF
W912DS18B0014_-_0001.pdf PDF
75906_WVA_Warehs_Dwg_RTA.pdf PDF
W912DS18B0014.pdf PDF
Show all 50

General Purpose Storage Building, Watervliet, NY has more files on GovTribe.

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

NEW YORK DISTRICT

Construct Warehouse

Watervliet Arsenal, NY

100% Submission RTA

Specifications

31 May 2018

Small Business Set – Aside

IFB NO. W912DS-17-_-00XX

WATERVLIET WAREHOUSE WATERVLIETWHSE

100% SUBMISSION

PROJECT TABLE OF CONTENTS

DIVISION 00 - PROCUREMENT AND CONTRACTING REQUIREMENTS

00 00 01 COVER SHEET

00 00 02 CHECK LIST FOR BIDDERS

00 10 00 SF 1442 AND BIDDING SCHEDULE

00 21 16 INSTRUCTIONS, CONDITIONS, AND NOTICE TO BIDDERS

00 22 10 TECHNICAL PROPOSAL DESIGN -BID-BUILD SELECTION PROCEDURES

00 22 20 PROPOSAL SUBMISSION REQUIREMENTS AND INSTRUCTIONS

00 24 00 EVALUATION FACTORS FOR AWARD

00 45 00 REPRESENTATIONS AND CERTIFICATIONS

00 72 00 CONTRACT CLAUSES

00 73 00.00 18 SPECIAL CONTRACT REQUIREMENTS

00 90 00 WAGE RATES

00 90 01 GEOTECHNICAL REPORT

DIVISION 01 - GENERAL REQUIREMENTS

01 11 00 SUMMARY OF WORK

01 14 00 WORK RESTRICTIONS

01 22 00.00 10 PRICE AND PAYMENT PROCEDURES

01 30 00 ADMINISTRATIVE REQUIREMENTS

01 32 01.00 10 PROJECT SCHEDULE

01 33 00 SUBMITTAL PROCEDURES

01 33 29 SUSTAINABILITY REPORTING

01 35 26 GOVERNMENTAL SAFETY REQUIREMENTS

01 42 00 SOURCES FOR REFERENCE PUBLICATIONS

01 45 00.00 10 QUALITY CONTROL

01 45 00.15 10 RESIDENT MANAGEMENT SYSTEM CONTRACTOR MODE(RMS CM)

01 45 35 SPECIAL INSPECTIONS

01 50 00 TEMPORARY CONSTRUCTION FACILITIES AND CONTROLS

01 57 19 TEMPORARY ENVIRONMENTAL CONTROLS

01 58 00 PROJECT IDENTIFICATION

01 74 19 CONSTRUCTION AND DEMOLITION WASTE MANAGEMENT

01 78 00 CLOSEOUT SUBMITTALS

01 78 23 OPERATION AND MAINTENANCE DATA

DIVISION 02 - EXISTING CONDITIONS

02 41 00 DEMOLITION

DIVISION 03 - CONCRETE

03 11 13.00 10 STRUCTURAL CAST-IN-PLACE CONCRETE FORMING

03 15 00.00 10 CONCRETE ACCESSORIES

03 20 00.00 10 CONCRETE REINFORCING

03 30 00.00 10 CAST-IN-PLACE CONCRETE

03 33 00 CAST-IN-PLACE ARCHITECTURAL CONCRETE

03 35 00.00 10 CONCRETE FINISHING

DIVISION 04 - MASONRY

04 20 00 UNIT MASONRY

DIVISION 05 - METALS

05 05 23.16 STRUCTURAL WELDING

05 12 00 STRUCTURAL STEEL

PROJECT TABLE OF CONTENTS Page 1

05/31/18 1:30 PM

05 21 00 STEEL JOIST FRAMING

05 30 00 STEEL DECKS

05 40 00 COLD-FORMED METAL FRAMING

05 50 13 MISCELLANEOUS METAL FABRICATIONS

05 51 33 METAL LADDERS

05 52 00 METAL RAILINGS

DIVISION 06 - WOOD, PLASTICS, AND COMPOSITES

06 10 00 ROUGH CARPENTRY

DIVISION 07 - THERMAL AND MOISTURE PROTECTION

07 11 13 BITUMINOUS DAMPPROOFING

07 21 13 BOARD AND BLOCK INSULATION

07 27 36 SPRAY FOAM AIR BARRIERS

07 41 63 FABRICATED ROOF PANEL ASSEMBLIES

07 42 63 FABRICATED WALL PANEL ASSEMBLIES

07 60 00 FLASHING AND SHEET METAL

07 84 00 FIRESTOPPING

07 92 00 JOINT SEALANTS

DIVISION 08 - OPENINGS

08 11 13 STEEL DOORS AND FRAMES

08 33 23 OVERHEAD COILING DOORS

08 51 13 ALUMINUM WINDOWS

08 51 23 STEEL WINDOWS

08 71 00 DOOR HARDWARE

08 81 00 GLAZING

08 91 00 METAL WALL LOUVERS

DIVISION 09 - FINISHES

09 29 00 GYPSUM BOARD

09 30 10 CERAMIC, AND QUARRY TILING

09 51 00 ACOUSTICAL CEILINGS

09 65 00 RESILIENT FLOORING

09 67 23.15 FUEL RESISTIVE RESINOUS FLOORING, 3-COAT SYSTEM

09 90 00 PAINTS AND COATINGS

DIVISION 10 - SPECIALTIES

10 14 00.10 EXTERIOR SIGNAGE

10 14 00.20 INTERIOR SIGNAGE

10 28 13 TOILET ACCESSORIES

10 44 16 FIRE EXTINGUISHERS

DIVISION 11 - EQUIPMENT

11 13 19.13 LOADING DOCK LEVELERS AND EQUIPMENT

DIVISION 12 - FURNISHINGS

12 21 00 WINDOW BLINDS

12 48 13 ENTRANCE FLOOR MATS AND FRAMES

DIVISION 13 - SPECIAL CONSTRUCTION

PROJECT TABLE OF CONTENTS Page 2

13 34 19 METAL BUILDING SYSTEMS

DIVISION 21 - FIRE SUPPRESSION

21 13 13.00 10 WET PIPE SPRINKLER SYSTEM, FIRE PROTECTION

21 30 00 FIRE PUMPS

DIVISION 22 - PLUMBING

22 00 00 PLUMBING, GENERAL PURPOSE

DIVISION 23 - HEATING, VENTILATING, AND AIR CONDITIONING (HVAC)

23 00 00 AIR SUPPLY, DISTRIBUTION, VENTILATION, AND EXHAUST SYSTEMS

23 07 00 THERMAL INSULATION FOR MECHANICAL SYSTEMS

23 22 26.00 20 STEAM SYSTEM AND TERMINAL UNITS

DIVISION 26 - ELECTRICAL

26 00 00.00 20 BASIC ELECTRICAL MATERIALS AND METHODS

26 09 26 LIGHTING CONTROL SYSTEM AND CONTROL DEVICES

26 20 00.23 INTERIOR DISTRIBUTION SYSTEM

26 27 13.10 30 ELECTRIC METERS

26 28 01.00 10 COORDINATED POWER SYSTEM PROTECTION AND ARC FLASH HAZARD

ANALYSIS

26 29 23 VARIABLE FREQUENCY DRIVE SYSTEMS UNDER 600 VOLTS

26 41 00 LIGHTNING PROTECTION SYSTEM

26 51 00.00 23 INTERIOR LIGHTING

26 56 00 EXTERIOR LIGHTING (LED)

DIVISION 27 - COMMUNICATIONS

27 10 00 BUILDING TELECOMMUNICATIONS CABLING SYSTEM

DIVISION 28 - ELECTRONIC SAFETY AND SECURITY

28 31 64.00 10 FIRE DETECTION AND ALARM SYSTEM, ADDRESSABLE

DIVISION 31 - EARTHWORK

31 00 00 EARTHWORK

31 05 19 GEOTEXTILE

DIVISION 32 - EXTERIOR IMPROVEMENTS

32 01 16.71 COLD MILLING ASPHALT PAVING

32 01 19 FIELD MOLDED SEALANTS FOR SEALING JOINTS IN RIGID

PAVEMENTS

32 12 10 BITUMINOUS TACK AND PRIME COATS

32 12 16 HOT-MIX ASPHALT (HMA) FOR ROADS

32 13 13.06 PORTLAND CEMENT CONCRETE PAVEMENT FOR ROADS AND SITE

FACILITIES

32 16 13 CONCRETE SIDEWALKS AND CURBS AND GUTTERS

32 17 23 PAVEMENT MARKINGS

32 92 19 SEEDING

DIVISION 33 - UTILITIES

33 11 00 WATER UTILITY DISTRIBUTION PIPING

PROJECT TABLE OF CONTENTS Page 3

33 30 00 SANITARY SEWERS

33 32 16 PACKAGED UTILITY WASTEWATER PUMPING STATIONS

33 40 00 STORM DRAINAGE UTILITIES

33 63 23 EXTERIOR ABOVEGROUND STEAM DISTRIBUTION

33 70 02.00 10 ELECTRICAL DISTRIBUTION SYSTEM, UNDERGROUND

33 82 00 TELECOMMUNICATIONS OUTSIDE PLANT (OSP)

DIVISION 41 - MATERIAL PROCESSING AND HANDLING EQUIPMENT

41 22 13.13 BRIDGE CRANES

-- End of Project Table of Contents --

PROJECT TABLE OF CONTENTS Page 4

PROCUREMENT AND

CONTRACTING

REQUIREMENTS

SECTION 00 00 01

COVER SHEET

01/18

PART 1 GENERAL

NEW YORK DISTRICT

CORPS OF ENGINEERS

NEW YORK, NEW YORK 10278-0090

INVITATION FOR BIDS

FOR

Construct Warehouse

Watervliet Arsenal, NY

1. Attached is INVITATION FOR BIDS (IFB) NO. W912DS-18-_-00XX

2. BIDS MUST BE SET FORTH full, accurate, and complete information as required by this Invitation for Bids, including attachments. The penalty for making false statements in bids is prescribed under Title 18, United States Code, Section 1001.

3. SUBMISSION OF BIDS: Complete details concerning proper submission of bids are contained in the INSTRUCTIONS, CONDITIONS, AND NOTICES TO BIDDERS (Section 00 21 16 ).

4. Note the REQUIREMENT FOR AFFIRMATIVE ACTION of the EQUAL OPPORTUNITY clause as it applies to the contract resulting from this solicitation. (See paragraph NOTICE OF REQUIREMENT FOR AFFIRMATIVE ACTION TO ENSURE EQUAL EMPLOYMENT OPPORTUNITY in Section 00 21 16 of this IFB).

5. REPRESENTATIONS AND CERTIFICATIONS - SECTION 00 45 00 Bidders and Offerors are required to complete the REPRESENTATIONS AND CERTIFICATIONS and submit them with their bids.

Within Section 00 45 00 , note in particular the PROHIBITION SEGREGATED FACILITIES. Failure of a bidder or offeror to agree to the certification will render his bid or offer non-responsive to the terms of solicitations involving awards of contracts exceeding $10,000 which are not exempt from the provisions of the Equal Opportunity Clause

(1984 APR).

6. THIS PROJECT IS A MILITARY PROGRAM PROCUREMENT AND IS FUNDED BY THE

DEPARTMENT OF DEFENSE. BUY AMERICAN ACT - CONSTRUCTION MATERIALS (MAY

1993) IN ACCORDANCE WITH FAR 52.225-5 APPLIES.

7. Please review all bonds and accompanying documents required to be submitted. Bonds, Powers of Attorney, statements of authenticity and continuing validity, and all related documents MUST NOT bear computer printer-generated signatures and/or seals. Documents bearing signatures and/or seals generated as part of a document, as opposed to being affixed to the document after its generation, will not be

DOCUMENT 00 00 01 Page 1 accepted. Submission of such documents may render the bid or offer non-responsive and ineligible for award.

PART 2 PRODUCTS

Not Used

PART 3 EXECUTION

Not Used

-- End of Section --

DOCUMENT 00 00 01 Page 2

SECTION 00 00 02

CHECK LIST FOR BIDDERS

01/18

PART 1 GENERAL

ATTACHED IS IFB NO. W912DS-[___]

Construct Warehouse Watervliet Arsenal, NY

ALL INFORMATION REQUIRED BY THE TERMS OF THIS SOLICITATION MUST BE

FURNISHED. MISTAKES OR OMISSIONS MAY RENDER YOUR OFFER INELIGIBLE FOR

AWARD. IMPORTANT ITEMS FOR YOU TO CHECK ARE INCLUDED IN BUT NOT LIMITED

TO THOSE LISTED BELOW. THIS INFORMATION IS FURNISHED ONLY TO ASSIST YOU

IN SUBMITTING A PROPER BID

____HAVE YOU ACKNOWLEDGED ALL AMENDMENTS?

____HAVE YOU COMPLETED THE "REPRESENTATIONS AND CERTIFICATIONS" (SECTION

00 45 00) PORTION OF THE SOLICITATION?

____IS YOUR DUNS NUMBER LISTED ON THE STANDARD FORM 1442?

____IS YOUR BID GUARANTEE PROPERLY SIGNED BY BOTH THE BIDDER AND SURETY

AND ARE ALL SEALS AFFIXED?

____DO THE BID BOND AND ACCOMPANYING DOCUMENTS BEAR SIGNATURES AND SEALS

AFFIXED AFTER THE DOCUMENT WAS GENERATED, AS OPPOSED TO COMPUTER

PRINTER-GENERATED SIGNATURES AND/OR SEALS?

____HAVE YOU ENSURED THAT YOU HAVE NOT RESTRICTED YOUR OFFER BY ALTERING

THE PROVISIONS OF THE SOLICITATION?

____WHEN REQUIRED, HAVE YOU ENTERED A UNIT PRICE FOR EACH PRICE ITEM?

(THE SOLICITATION SPECIFICALLY STATES WHEN THIS IS NECESSARY.)

____ARE DECIMALS IN YOUR PRICES IN THE PROPER PLACE? ARE YOUR FIGURES

LEGIBLE?

____IF YOU HAVE MADE ERASURES OR CORRECTIONS ON YOUR BID, ARE THEY

INITIALED BY THE PERSON SIGNING THE BID?

____DOES THE ENVELOPE CONTAINING YOUR BID PROPERLY IDENTIFY THAT IT ISA

SEALED BID AND DOES IT CONTAIN THE CORRECT SOLICITATION NUMBER AND BID

OPENING TIME?

____WILL YOUR OFFER ARRIVE ON TIME? (SEE PARAGRAPH ENTITLED "LATE

SUBMISSIONS, MODIFICATIONS, AND WITHDRAWALS OF BIDS" IN THE

INSTRUCTIONS, CONDITIONS, AND NOTICES TO BIDDERS, SECTION 00 21 16 OF

THE SOLICITATION.)

____WILL YOUR OFFER ARRIVE ON TIME? (SEE PARAGRAPH ENTITLED "LATE

SUBMISSIONS, MODIFICATIONS, AND WITHDRAWALS OF BIDS" IN THE

INSTRUCTIONS, CONDITIONS, AND NOTICES TO BIDDERS, SECTION 00 21 16 OF

THE SOLICITATION.)

DOCUMENT 00 00 02 Page 1

NOTE: THERE ARE INCREASED SECURITY MEASURES AT JACOB K. JAVITS

FEDERAL BUILDING, 26 FEDERAL PLAZA THAT MAY AFFECT THE TIME IT TAKES

TO ENTER THE BUILDING. BIDDERS IS RESPONSIBLE TO ENSURE THAT ITS BID

IS SUBMITTED TIMELY.

PART 2 PRODUCTS

Not Used

PART 3 EXECUTION

Not Used

-- End of Section --

DOCUMENT 00 00 02 Page 2

SECTION 00 10 00

SF 1442 AND BIDDING SCHEDULE

12/17

PART 1 GENERAL

1.1 SF 1442 SOLICITATION, OFFER, AND AWARD

To be provided by Contracting Division.

1.2 [[NOTE:][BID SCHEDULE]]

To be provided by Contracting Division.

ITEM NO. DESCRIPTION ESTIMATED QUANTITY UNIT UNIT PRICE AMOUNT

BASE BID:

OPTIONS:

DOCUMENT 00 10 00 Page 1

ITEM NO. DESCRIPTION ESTIMATED QUANTITY UNIT UNIT PRICE AMOUNT

TOTALS:

TOTAL BASE NO OPTIONS (ITEMS [___] thru [___])

TOTAL OPTIONS (ITEMS [___] thru [___])

TOTAL BASE PLUS OPTIONS (ITEMS [___] thru [___])

NOTES:

1. Note

PART 2 PRODUCTS

Not Used

PART 3 EXECUTION

Not Used

-- End of Section --

DOCUMENT 00 10 00 Page 2

SECTION 00 21 16

INSTRUCTIONS, CONDITIONS, AND NOTICE TO BIDDERS

09/16

PART 1 GENERAL

1.1 NOTE:

To be provided by Contracting Division.

PART 2 PRODUCTS

Not Used

PART 3 EXECUTION

Not Used

-- End of Section --

DOCUMENT 00 21 16 Page 1

LEFT BLANK INTENTIONALLY

DOCUMENT 00 21 16 Page 2

SECTION 00 22 10

TECHNICAL PROPOSAL DESIGN -BID-BUILD SELECTION PROCEDURES

09/17

PART 1 GENERAL

1.1 NOTE:

To be provided by Contracting Division.

PART 2 PRODUCTS

Not Used

PART 3 EXECUTION

Not Used

-- End of Section --

DOCUMENT 00 22 10 Page 1

LEFT BLANK INTENTIONALLY

DOCUMENT 00 22 10 Page 2

SECTION 00 22 20

PROPOSAL SUBMISSION REQUIREMENTS AND INSTRUCTIONS

09/17

PART 1 GENERAL

1.1 NOTE:

To be provided by Contracting Division.

PART 2 PRODUCTS

Not Used

PART 3 EXECUTION

Not Used

-- End of Section --

DOCUMENT 00 22 20 Page 1

LEFT BLANK INTENTIONALLY

DOCUMENT 00 22 20 Page 2

SECTION 00 24 00

EVALUATION FACTORS FOR AWARD

06/17

PART 1 GENERAL

1.1 NOTE:

To be provided by Contracting Division.

PART 2 PRODUCTS

Not Used

PART 3 EXECUTION

Not Used

-- End of Section --

DOCUMENT 00 24 00 Page 1

LEFT BLANK INTENTIONALLY

DOCUMENT 00 24 00 Page 2

SECTION 00 45 00

REPRESENTATIONS AND CERTIFICATIONS

09/16

PART 1 GENERAL

1.1 NOTE:

To be provided by Contracting Division.

PART 2 PRODUCTS

Not Used

PART 3 EXECUTION

Not Used

-- End of Section --

DOCUMENT 00 45 00 Page 1

LEFT BLANK INTENTIONALLY

DOCUMENT 00 45 00 Page 2

SECTION 00 72 00

CONTRACT CLAUSES

09/16

PART 1 GENERAL

1.1 NOTE:

To be provided by Contracting Division.

PART 2 PRODUCTS

Not Used

PART 3 EXECUTION

Not Used

-- End of Section --

DOCUMENT 00 72 00 Page 1

LEFT BLANK INTENTIONALLY

DOCUMENT 00 72 00 Page 2

SECTION 00 73 00.00 18

SPECIAL CONTRACT REQUIREMENTS

03/15

PART 1 GENERAL

1.1 REFERENCES

The publications listed below form a part of this specification to the extent referenced. The publications are referred to within the text by the basic designation only.

U.S. ARMY CORPS OF ENGINEERS (USACE)

EM 385-1-1 (2014) Safety and Health Requirements Manual

1.2 FAR 52.211-10, COMMENCEMENT, PROSECUTION, AND COMPLETION OF WORK

a. The Contractor shall be required to (i) commence work under this contract within five (5) calendar days after the date the Contractor receives the Notice to Proceed, (ii) prosecute the work diligently, and

(iii) complete the entire work ready for use, not later than 365 calendar days after the date the Contractor receives the notice to proceed.

b. Location: The site of work is located at Watervliet Arsenal, Watervliet, New York . The site of the work is on a military reservation and all rules and regulations issued by the Commanding Officer covering general safety, security, and sanitary requirements, etc., shall be observed by the Contractor.

c. The Contractor shall furnish all labor, materials, equipment, and services for the following work: Construction as described in the solicitation package (except those furnished by the Government).

d. All work shall be in accordance with the drawings and specifications or instructions attached hereto and made a part thereof, or to be furnished hereafter by the Contracting Officer and subject, in every detail, to his supervision, direction, and instructions.

1.3 DFARS 236.204, Disclosure of the Magnitude of Construction Projects

This project is estimated between $ 2.5 M and $ 5 M.

1.4 GOVERNMENT RESIDENT MANAGEMENT SYSTEM AND CONTRACTOR QUALITY CONTROL

SYSTEM (QCS) MODULE

The Government will utilize an in-house Contract Administration program entitled "Resident Management System" (RMS). The Contractor shall utilize a Government furnished Quality Control System (QCS) Programming Module.

See Section 01 45 00.15 10 RESIDENT MANAGEMENT SYSTEM CONTRACTOR MODE(RMS CM) for requirements.

DOCUMENT 00 73 00.00 18 Page 1

1.5 PRECONSTRUCTION CONFERENCE

a. The Contracting Officer, or his Representative, will arrange a preconstruction conference after award of contract and before commencement of work. The Contracting Officer's representative will notify the Contractor of the time and date set for the meeting. At this conference, the Contractor shall be oriented with respect to Government procedures and line of authority, contractual, administrative, and construction matters.

Additionally, a schedule of required submittals will be discussed.

b. The Contractor shall bring to this conference the following items in either completed or draft form:

-The Contractor's order of work -Accident Prevention Plan (See Accident Prevention Clause in Section 00 72 00 and paragraph SAFETY AND HEALTH REQUIREMENTS MANUAL in this Section) -Quality Control Plan (See Section 01 45 00.00 10 QUALITY CONTROL) -Letter appointing Superintendent -List of subcontractors, if any -Environmental Protection Plan (See Section 01 57 19 TEMPORARY

ENVIRONMENTAL CONTROLS)

1.6 COORDINATION PERIOD

In addition to contract clause titled PRECONSTRUCTION CONFERENCE, the Contractor shall reserve a 2 workday period of time no later than one month following the contract preconstruction conference for coordination.

The Contractor's project management team responsible for this project shall participate. During the 2-day coordination period the Contractor and the Government will exchange information related to the government regulations and procedures, points of contact, relevant design information and general discussion about the execution and coordination of the project. The Contractor shall dedicate his management team for this 2-day coordination period.

1.7 FAR 52.211-12, Liquidated Damages--Construction

a. If a delay to the NTP date is a result of the Contractor, an extension will not be given. If the Contractor fails to complete the work within the time specified in the contract, or any extension, the Contractor shall pay to the Government as liquidated damages, the sum of $ 1,654 for each day of delay.

b. If the Government terminates the Contractor's right to proceed, the resulting damage will consist of liquidated damages until such reasonable time as may be required for final completion of the work together with any increased costs occasioned the Government in completing the work.

c. If the Government does not terminate the Contractor's right to proceed, the resulting damage will consist of liquidated damages until the work is completed or accepted. (FAR 52.212-5)

d. At a time before the project is physically complete but is functionally complete to the satisfaction of the Government, the Government at its sole discretion may agree to accept transfer of the facility or project provided that the remaining work to be done ("punchlist") is completed no later than 30 days from the date of transfer. In this case the contractor shall pay liquidated damages for punchlist items not completed in the

DOCUMENT 00 73 00.00 18 Page 2 daily amount of $ 413 per day commencing after 30 days of project transfer or after date required for project completion (including all extensions), whichever occurs later.

1.8 EQUAL OPPORTUNITY PREAWARD CLEARANCE OF SUBCONTRACTORS

Notwithstanding the clause of this contract entitled “Subcontracts”, the Contractor shall not enter into a first-tier subcontract for an estimated or actual amount of $1 million or more without obtaining in writing from the Contracting Officer a clearance that the proposed subcontractor is in compliance with the equal opportunity requirements and therefore is eligible for award.

1.9 FAR 52.228-5 -- Insurance -- Work on a Government Installation

a. Refer to section 01 30 00 ADMINISTRATIVE REQUIREMENTS.

b. Before commencing work under this contract, the Contractor shall notify the Contracting Officer in writing that the required insurance has been obtained. The policies evidencing required insurance shall contain an endorsement to the effect that any cancellation or any material change adversely affecting the Government's interest shall not be effective for such a period as may be prescribed by the laws of the State in which this contract is to be performed and in no event less than thirty (30) days after written notice thereof to the Contracting Officer.

c. The Contractor shall insert the substance of this clause, including this paragraph (c), in subcontracts under this contract that require work on a Government installation and shall require subcontractors to provide and maintain the insurance required in the Schedule or elsewhere in the contract. The Contractor shall maintain a copy of all subcontractors' proofs of required insurance, and shall make copies available to the Contracting Officer upon request.

1.10 IMPLEMENTING WARRANTY

Refer to section 01 78 00 CLOSEOUT SUBMITTALS

1.11 CERTIFICATES OF COMPLIANCE

Any certificates required for demonstrating proof of compliance of materials with specification requirements shall be executed in 4 copies.

Each certificates shall be signed by an official authorized to certify in behalf of the manufacturing company and shall contain the name and address of the Contractor, the project name and location, and the quantity and date or dates of shipment or delivery to which the certification apply.

Copies of laboratory tests reports submitted with certificates shall contain the name and address of the testing laboratory and the date or dates of the tests to which the report applies. Certification shall not be construed as relieving the Contractor from furnishing satisfying material, if, after tests are performed on selected samples, the material is found not to meet the specific requirements

1.12 VERIFICATION OF SMALL BUSINESS UTILIZATION

a. This clause is applicable to small business concerns whose contracts exceed $1,000,000.

b. In accordance with the clause at FAR 52.219-8, entitled UTILIZATION OF

DOCUMENT 00 73 00.00 18 Page 3

SMALL BUSINESS CONCERNS AND DISADVANTAGED BUSINESS CONCERNS, in effect on the date of this Contract, the Contracting Office may survey the extent of small and small disadvantaged business utilization under this Contract.

The Contractor may be required to report to the Contracting Officer statistical data on the number and dollars amounts of subcontracting awards with small business and small disadvantaged businesses.

c. As appropriate, the Contracting Officer may require one or more follow-up reports to the initial report.

d. The Contractor agrees to insert this clause in any subcontract that may exceed $1,000,000, including this subparagraph d.

1.13 BID GUARANTEE

See contract clause entitled BID GUARANTEE in Specifications section

00 72 00 CONTRACT CLAUSES.

1.14 CONTRACT DRAWINGS AND SPECIFICATIONS

See contract clause entitled CONTRACT DRAWINGS AND SPECIFICATIONS in Specifications section 00 72 00 CONTRACT CLAUSES.

For a listing of the contract drawings see Index Drawing.

1.15 RECORD DRAWINGS

See specifications section 01 78 00 CLOSEOUT SUBMITTAL for as-built and Record Drawings requirements for CAD Drafting Standard.

1.16 AVAILABILITY OF CAD DRAWING FILES

Refer to SOURCE DRAWING FILES in specifications section 01 78 00 CLOSEOUT

SUBMITTALS.

1.17 PHYSICAL DATA (FAR 52.236-4)(APR 1984)

Data and information furnished or referred to below is for the Contractor's information only. The Government will not be responsible for any interpretation of or conclusion drawn from the data or information by the Contractor.

a. Weather Conditions: Climatological data determined from records of the U.S. Weather Bureau station, Albany, New York

Mean Annual Temperature: 47.3 degrees F.

Mean Annual Precipitation: 37.74 inches

1.18 GOVERNMENT-FURNISHED PROPERTY

For a list government furnished properties, refer to SECTION 01 11 00

SUMMARY OF WORK, GOVERNMENT-FURNISHED MATERIAL AND EQUIPMENT.

1.19 LAYOUT OF WORK

The contractor shall lay out his work from the dimensions indicated on the drawings and shall be responsible for all measurements in connection therewith.

DOCUMENT 00 73 00.00 18 Page 4

1.20 BULLETIN BOARD

Refer to section 01 50 00 TEMPORARY CONSTRUCTION FACILITIES AND CONTROLS, paragraph BULLETIN BOARD.

1.21 AVAILABILITY AND USE OF UTILITY SERVICES

Refer to section 01 50 00 TEMPORARY CONSTRUCTION FACILITIES AND CONTROLS, paragraph AVAILABILITY AND USE OF UTILITY SERVICES.

1.22 NO WAIVER BY GOVERNMENT

The failure of the Government, in any one or more instances, to insist upon the strict performance of any of the terms of this Contract or to exercise any option herein conferred shall not be construed as a waiver or relinquishment to any extent of the right to assert or rely upon such terms or option on any future occasion.

1.23 DEFAULT (FIXED-PRICE CONSTRUCTION) (TIME EXTENSIONS FOR UNUSUALLY

SEVERE WEATHER)

1. This provision specifies the procedure for determination of time extension for usually severe weather in accordance with the contract clause entitled “Default: (Fixed Price Construction).” In order for the Contracting Officer to award a time extension under this clause, the following conditions must be satisfied:

a. The weather experienced at the project site during the contract period must be found to be unusually severe, that is, more severe than the adverse weather anticipated for the project location during any given month.

b. The unusually severe weather must actually cause a delay to the completion of the project. The delay must be beyond the control and without the fault or negligence of the Contractor.

2. The following schedule of monthly anticipated adverse weather delays is based on National Oceanic and Atmospheric Administration (NOAA) or similar data for the project location and will constitute the base line for monthly weather time evaluations. The Contractor’s progress schedule must reflect these anticipated adverse weather delays in all weather dependent activities.

MONTHLY ANTICIPATED ADVERSE WEATHER DELAY

WORK DAYS BASED ON (5) DAY WORK WEEK

JAN FEB MAR APR MAY JUN JUL AUG SEP OCT NOV DEC

8 7 8 8 9 6 6 6 5 6 7 8

3. Upon acknowledgment of the Notice to Proceed (NTP) and continuing throughout the contract, the Contractor will record on the daily CQC report, the occurrence of adverse weather and resultant impact to normally scheduled work. Actual adverse weather delay days must prevent work on critical activities for 50 percent or more of the Contractor’s scheduled workday. The number of actual adverse weather delay days shall include days impacted by actual adverse weather (even if adverse weather occurred in previous month), be calculated chronologically from the first to the last day of each month, and be

DOCUMENT 00 73 00.00 18 Page 5 recorded as full days. If the number of actual adverse weather delay days exceeds the number of days anticipated in paragraph 2 above, the Contracting Officer will convert any qualifying delays to calendar days, giving full consideration for equivalent fair weather work days, and issue a modification in accordance with the contract clause entitled “Default (Fixed Price Construction)”.

1.24 FIELD OFFICE

The Contractor is not required to provide a field office for Government employees.

1.25 PROCEDURES FOR SUBMISSION AND PAYMENT OF ALL CONTRACTS PAYMENTS

In addition to the requirements contained in contract clause titled PAYMENTS UNDER FIXED-PRICE CONSTRUCTION CONTRACTS, and PROMPT PAYMENT FOR CONSTRUCTION CONTRACTS the following will apply to all payments made under this contract:

a. At the time of submission of the project schedule, the Contractor shall submit for approval by the Contracting Officer or his authorized representative a breakdown of the contract work which shall be to the degree of detail required by the Contracting Officer or his representative to effect reasonable progress payments. The Contracting Officer or his representative will review this breakdown within 30 calendar days after receipt and either advise the Contractor that it is approved or disapproved, and if disapproved the reasons for disapproval. Only after the breakdown is approved will any payment invoice be accepted from the Contractor. The Contracting Officer can determine it is in the best interest of the Government to make payment without an approved breakdown, however, in no case will more than 10% of the contract amount be paid unless the breakdown is approved.

b. The Contractor shall submit requests for payment through submission of a proper invoice to the office or person(s) designated in subparagraph (c). For purposes of payment a "proper invoice" is defined as the following:

(1) An estimate of the work completed in accordance with the approved breakdown indicating the percentage of work of each item and the associated costs.

(2) A properly completed ENG Form 93 and 93a (where required).

(3) All contractual submissions indicated elsewhere in this contract to be submitted with payment, such as updated progress schedules, updated submittal registers, etc.

(4) The following certification executed by a responsible official of the organization authorized to bind the firm. A "responsible official" is either a corporate officer, partner, or owner, in the case of a sole proprietorship.

I hereby certify, to the best of my knowledge and belief, that:

(1) The amounts requested are only for performance in accordance with the specifications, terms and conditions of the contract;

DOCUMENT 00 73 00.00 18 Page 6

(2) Payments to subcontractors and suppliers have been made from previous payments received under the contract, and timely payments will be made from the proceeds of the payment covered by this certification, in accordance with subcontract requirements and the requirements of Chapter 39 of Title 31, United States Code; and

(3) This request for progress payments does not include any amounts, which the prime Contractor intends to withhold or retain from a subcontractor or supplier in accordance with the terms and conditions of the subcontract;

(4) This certification is not to be construed as final acceptance of a subcontractor's performance; and

(5) All required prime and subcontractor payrolls have been submitted.

(Name)

(Title)

(Date)

c. The Government will designate the office or person(s) who shall first receive the invoice submissions and the Contractor shall be so notified at the pre-construction conference. In addition to the designated Project Engineer, the Contractor shall at the same time submit one copy of the detailed breakdown and the ENG Form 93 and 93a to the Area Engineer.

d. The Government representative will return any request for payment that is deemed improper within 7 days of receipt and will specify the defects.

If the defect concerns a disagreement as to the amount of work performed and/or the amount of the payment being submitted, the Government and the Contractor's representative will meet to resolve the differences and reach agreement. Upon agreement, the Contractor shall submit a new breakdown and ENG Form 93 and 93a and any other submissions requiring correction. These shall be incorporated with the previous submittal and will then constitute a proper invoice.

e. If agreement cannot be reached, the Government will determine the proper amount per contract clause, PAYMENTS UNDER FIXED-PRICE CONSTRUCTION CONTRACTS and process the payment accordingly. In this event, a "proper invoice" for prompt payment purposes will not have been submitted to the Government.

f. The Government will pay the Contractor in accordance with the following time frames:

(1) Progress Payments. From the date a "proper invoice" is received, in accordance with subparagraphs b and d, the Government will issue a check within 14 calendar days.

(2) Reduction in Retainage Payment. If during the course of the contract, a reduction in retainage payment is required, the Government

DOCUMENT 00 73 00.00 18 Page 7 will issue a check within 14 calendar days after the approval of the release to the Contractor by the Contracting Officer or his authorized representative.

(3) Final Payment. A final payment request will not be considered valid until the Contractor has fulfilled all contract requirements including all administrative items, as-built drawings, training, payrolls, warranties, etc. and has submitted a release of claims. When the Contractor has fulfilled all contract requirements and a "proper invoice" has been submitted, the Government shall issue a check within 14 days from the date of acceptance of the project by the Contracting Officer.

1.26 PAYMENTS FOR MATERIALS DELIVERED OFF-SITE (52.232-5000)

(a) Pursuant to FAR 52.232-5, Payments Under Fixed Price Construction Contracts, materials delivered to the contractor at locations other than the site of the work may be taken into consideration in making payments if included in payment estimates and if all the conditions of the General Provisions are fulfilled. Payment for items delivered to locations other than the work site shall be limited to:

(1) Materials which have been approved, if required by the technical provisions; or

(2) Materials that have been fabricated to the point where they are identifiable to an item of work required under this contract; or

(b) Payment for materials delivered off-site shall be made only after receipt of paid invoices listing the value of material and labor incorporated in the items along with a canceled check showing the prime contractor's title to the items delivered off site.

1.27 PROGRESS PAYMENTS

Progress Payments made pursuant to the PAYMENTS TO CONTRACTOR clause for any item of work in the bid schedule shall be based on the Contract unit price or lump sum amount set forth in the bid schedule for that item of work. If the amount of the unit price or lump sum bid for any item of work is in excess of 125% of the Government estimate for such item, the Contracting Officer may require the Contractor to produce cost data to justify the price of the bid item. Failure to justify the bid item price to the satisfaction of the Contracting Officer may result in payment of an amount equal to 125% of the Government estimate for such bid item upon completion of work on the item and payment of the remainder of the bid item price upon final acceptance of all contract work.

1.28 PRICING OF ADJUSTMENTS

When costs are a factor in any determination of a contract price adjustment pursuant to the Changes clause or any other clause of this contract, such costs shall be in accordance with Part 31 of the Federal Acquisition Regulation and DFARS 252.215-7000 (Dec. 1991) as follows:

PRICE ADJUSTMENTS (DEC 2012)

The term “pricing adjustments”, as used in paragraph (a) of the clauses entitled “Price Reduction for Defective Certified Cost or Pricing Data-Modifications”, “Subcontractor Certified Cost or Pricing Data,” and “Subcontractor Certified Cost or Pricing Data- Modifications,” means the

DOCUMENT 00 73 00.00 18 Page 8 aggregate increases and/or decreases in cost plus applicable profits.

1.29 LABOR-ADDITIONAL REQUIREMENTS

Fringe benefits statement: The method of payment of applicable fringe benefits will be indicated on DD Form 879, Statement of Compliance, and attached to each weekly payroll.

1.30 DAMAGE TO WORK

The responsibility for damage to any part of the permanent work shall be as set forth in the article of the contract clause entitled "PERMITS AND RESPONSIBILITIES". However, if in the judgment of the Contracting Officer, any part of the permanent work performed by the Contractor is damaged by flood, earthquake, hurricane, severe coastal storm or tornado, which damage is not due to the failure of the Contractor to take reasonable precautions or to exercise sound engineering and construction practices in the conduct of the work, the Contractor will make the repairs as ordered by the Contracting Officer and full compensation for such repairs will be made at the applicable Contract unit or lump-sum prices as fixed and established in the Contract. If, in the opinion of the Contracting Officer, there are no Contract unit or lump sum prices applicable to any part of such work, an equitable adjustment, pursuant to Contract Clause entitled CHANGES, will be made as full compensation for the repairs of that part of the permanent work for which there are not applicable Contract unit or lump-sum prices. Except as herein provided, damage to all work, utilities, materials, equipment, and plant, including temporary construction and utilities, pavements, and other property along the routes used by the Contractor's pipelines and/or land vehicles, shall be repaired to the satisfaction of the Contracting Officer, the State of New York , and the utilities companies, at the Contractor's expense regardless of the cause of such damage.

1.31 SITE INSPECTIONS

The site safety officer shall perform daily inspection of the job sites and the work in progress to ensure compliance with EM 385-1-1 and to determine the effectiveness of the Accident Prevention Plan. Daily inspection logs shall be used to document inspections noting safety and health deficiencies, deficiencies in the effectiveness of the accident prevention plan, and corrective actions including timetable and responsibilities. The daily inspection logs will be attached to and submitted with the Daily Quality Control Reports. Each entry shall include date, work area checked, employee present in work area, protective equipment and work equipment in use, special safety and health issues and notes, and signature of the preparer.

1.32 52.223-3 - HAZARDOUS MATERIAL IDENTIFICATION AND MATERIAL SAFETY DATA

a. "Hazardous material," includes any material defined as hazardous under the latest version of Federal Standard No. 313 (including revisions adopted during the term of the contract).

b. The Contractor shall submit, a Material Safety Data Sheet, (OUS Department of Labor Form OSHA 174) meeting the requirements of 29 CFR 1910.1200(g) and the latest version of Federal Standard No. 313, for all hazardous material 5 days before delivery of the material, whether or not the Contractor is the manufacturer of these items. This obligation applies to all materials delivered under this contract that will involve exposure

DOCUMENT 00 73 00.00 18 Page 9 to hazardous materials or items containing these materials.

c. Neither the requirements of contract clause titled HAZARDOUS MATERIAL IDENTIFICATION AND MATERIAL SAFETY DATA nor any act or failure to act by the Government shall relieve the Contractor of any responsibility or liability for the safety of Government, Contractor, or subcontractor personnel or property.

d. Nothing contained in this contract clause titled HAZARDOUS MATERIAL IDENTIFICATION AND MATERIAL SAFETY DATA shall relieve the Contractor from complying with applicable Federal, State, and local laws, codes, ordinances, and regulations (including the obtaining of licenses and permits) in connection with hazardous material.

e. The Government's rights in data furnished under this contract with respect to hazardous material are as follows:

(1) To use, duplicate and disclose any data to which this clause is applicable. The purposes of this right are to (i) Apprise personnel of the hazards to which they may be exposed in using, handling, packaging, transporting, or disposing of hazardous materials; (ii) Obtain medical treatment for those affected by the material; and (iii) Have others use, duplicate, and disclose the data for the Government for these purposes.

(2) To use, duplicate, and disclose data furnished under this clause, in accordance with subparagraph (h)(1) of this clause, in precedence over any other clause of this contract providing for rights in data.

(3) The Government is not precluded from using similar or identical data acquired from other sources.

f. The Contractor shall insert this requirement, including this paragraph (f), with appropriate changes in the designation of the parties, in subcontracts at any tier (including purchase designations or purchase orders) under this contract involving hazardous material.

g. SAFETY AND HEALTH REQUIREMENTS MANUAL if this contract is for construction or dismantling, demolition, or removal of improvements with any Department of Army agency or component, the Contractor shall comply with all pertinent provisions of EM 385-1-1 . EM 385-1-1 is available at http://www.hq.usace.army.mil (at the HQ homepage select Safety and Occupational Health). Contractor shall be responsible for complying with the current edition and all changes posted on the web as of effective date of this solicitation.

h. Before commencing the work, the Contractor shall: (1) Submit a written proposal for implementing the Accident Prevention Plan; and (2) Meet with representatives of the Contracting Officer to discuss and develop a mutual understanding relative to administration of the overall safety program.

1.33 CONSTRUCTION PROJECT SIGNS, PUBLIC SAFETY SIGNS

Refer to section 01 50 00 TEMPORARY CONSTRUCTION FACILITIES AND CONTROLS, paragraph "Project and Safety Signs" and 01 58 00 PROJECT IDENTIFICATION, paragraph "PROJECT SIGN." No separate payment will be made for erecting and maintaining the signs and all costs in connection therewith will be considered the obligation of the Contractor. Upon completion of the project, the Contractor shall remove the signs from the project site.

DOCUMENT 00 73 00.00 18 Page 10

1.34 VEHICULAR AND OTHER TRAFFIC CONTROL

Refer to section 01 50 00 TEMPORARY CONSTRUCTION FACILITIES AND CONTROLS, paragraph TEMPORARY TRAFFIC CONTROL

1.35 ROAD CLOSURES AND UTILITY OUTAGES

a. Utility Outages:

(1) The Contractor is advised that the existing utilities service other buildings or areas adjacent to the specific work sites. These buildings will be active and utilized for the entire period of this contract. The Contractor shall maintain all utilities and systems operational at all times except outages approved by the Contracting Officer.

(2) All utility outages shall be scheduled by the Contractor and approved by the Contracting Officer. No outage will be approved which will adversely affect the current operation or mission accomplishment.

Outages shall only be approved to perform tie-ins of new or temporary utilities to existing lines. No electric or gas outages will be approved during the Fort Drum heating season. "Live"/"hot" utility connections shall be used whenever possible. Contractor shall submit a written work plan & have it approved by Fort Drum DPW 30 days prior to planned outage. (Required union notice.) The Contractor shall also be responsible for any repairs or start-up procedures in the affected facilities caused by the outages. The Contractor shall coordinate with the Contracting Officer and representatives of the Installation regarding the work that the Contractor must accomplish in various buildings to re-establish the utilities to proper working conditions.

The request for the approval of a utility outage shall include, at minimum, the following: description of the utility; time and duration of the outage; areas and systems affected; proof that all preparatory work is complete; proof that all necessary materials, equipment and manpower are in place; utility lines have been verified; and a contingency plan is in place.

(3) Times frames during which the Contracting Officer may approve utility outages:

(4) The Contractor shall have on-site all materials, equipment, manpower, etc. to complete all work during the approved duration of the outage. All utilities and systems shall be fully tested and operational prior to the end of the approved outage. Unscheduled outages shall be repaired immediately. Repairs and corrective actions shall proceed continuously in a diligent manner until all services and utilities are restored to their original condition.

b. Road Closures: Refer to section 01 50 00 TEMPORARY CONSTRUCTION FACILITIES AND CONTROLS, paragraph "TRAFFIC PROVISIONS."

DOCUMENT 00 73 00.00 18 Page 11

1.36 ACCESS ROUTES, CONTRACTOR AREAS, DELIVERY, STORAGE AREA AND VISITOR

CONTROL

a. The Contractor shall utilize only entry points designated by the Contracting Officer Representative. Contractor's personnel and construction equipment will not be permitted in any place other than the project site and the haul route for the borrow and spoil sites, unless specifically authorized by the Contracting Officer. A request for authorization to use alternate limited access shall be made by the Contractor to the Contracting Officer at least 7 calendar days in advance.

b. The Contractor shall utilize the project site areas for his daily staging. Trailers, materials, or equipment shall not be placed or stored outside the project site unless such trailers, materials or equipment are assigned a separate and distant storage area by the Contracting Officer away from the vicinity of the staging area but within military boundaries.

At the end of each work day mobile equipment, such as tractors, wheeled lifting equipment, cranes, backhoes and like equipment, shall be parked within the project site. The following shall remain fully accessible:

sally ports, hydrants, standpipes and access ways. The Contractor shall be responsible for all temporary connections (power, water telephone, etc.)

to the project site. The Contractor shall maintain the area in a clean and neat condition. Parking for Contractor's employees shall be on the project site. The Contractor will return all disturbed areas to their original condition unless specifically authorized by the Contracting Officer.

c. Off-site storage areas are not available.

d. The Contractor shall be responsible for the control of material deliveries, vendors, suppliers, prospective employees and other authorized personnel entering the project area as relates to this contract. The Contractor shall install signs at entrances to the project directing deliveries and visitors to the proper entry points.

e. The Contractor shall be permitted to utilize the area for material storage and unloading, material hoists, rubbish containers, rubbish chutes (if any), temporary office and personnel dressing facilities, and all other items required for staging. Contractor shall maintain the grounds within his area. Grass and weeds shall be cut at least weekly during the growing season.

f. The Contractor shall provide chemical toilets for his personnel in the project site, and shall be responsible for cleaning and servicing these toilets in accordance with pertinent health regulations and assure a frequency of service as required to prevent odors or other nuisance. Use of toilet facilities by Contractor's employees within surrounding buildings will not be permitted.

g. The Contractor shall provide weather tight and waterproof storage facilities for all materials stored at the site and required to be incorporated into the work.

h. The Contractor shall remove rubbish containers when full or every 2 weeks which ever comes first.

i. The color of dumpsters, trailers, and storage sheds and portable latrines shall be approved by the Contracting Officer.

j. All materials, trailers, and storage sheds in staging and construction

DOCUMENT 00 73 00.00 18 Page 12 areas shall be elevated and stored a minimum of 3 feet from any structure or fixed object. Trailers shall have doors on both ends.

k. Contractor shall limit employees to his work site.

1.37 EXISTING PARKING

The existing parking for visitors and Government employees shall not be used by the Contractor. No contractor or subcontractor employee parking is available near the immediate facility and no parking on the shoulders of the roads is allowed.

1.38 MAINTENANCE OF ACCESS ROADS

a. The Contractor shall be responsible for the maintenance of access roads at the construction site. Maintenance of access roads shall include snow removal. The Contractor shall remove snow piles and rows when they affect safety, hamper emergency and fire vehicles, or block proper drainage.

b. The Contractor shall provide and allow full access to the project site to all traffic, except as noted, to other contractors and authorized personnel as designated by the Contracting Officer.

c. The Contractor shall not inflict damage upon land properties, roads outside the authorized construction areas by unwarranted entry upon, driving over curbs, passage through, damage to or disposal of, material on such land or property, or overloading of roads. The Contractor may make a separate agreement with any other party, regarding the use of, or right to, land or facilities outside the Installation. If such an agreement is made, it shall be in writing and a copy shall be furnished to the Contracting Officer. The Contractor shall hold and save the Government, its officers and agents free from liability of any nature or kind arising from any trespassing or damage occasioned by Contractor operations.

d. Refer to section 01 50 00 , paragraph "Maintenance of Traffic"

1.39 FIRE PROTECTION

The Contractor will provide fire protection in accordance with Section 9 of EM 385-1-1 . The Contractor's means of providing such protection will be included in his Health and safety plan as required by the contract. The plan shall include fire exits and access routes during construction and during partial acceptance of the facilities, if any. Although the Fire department and local departments with whom the installation has mutual aid agreements will respond to emergencies, the capabilities of these departments will be limited by their available equipment and access to the construction sites.

The Fire Department does not permit open flame heating devices or tar kettles on roofs.

1.40 SITE AND BUILDING SECURITY AND VEHICLE IDENTIFICATION

Refer to section 01 14 00 Work Restrictions

1.41 UTILITY LOCATION VERIFICATION

Refer to section 01 35 26 GOVERNMENTAL SAFETY REQUIREMENTS, paragraph

"EXCAVATIONS"

DOCUMENT 00 73 00.00 18 Page 13

1.42 ARTIFACTS, PRESERVATION & PROTECTION OF HISTORICAL, ARCHAEOLOGICAL

AND CULTURAL RESOURCES

Refer to section 01 57 19 TEMPORARY ENVIRONMENTAL CONTROLS, paragraph

"PROTECTION OF CULTURAL RESOURCES"

1.43 CONNECTION WITH WORK OF OTHER CONTRACTS

During the period of this contract, other contracts may be in force for the construction of other features of work on or adjacent to the site of work being accomplished under this contract. The Contractor shall arrange his plant and shall schedule and perform the work as to effectively cooperate with all other contractors and Government agencies. It is the Contractor's responsibility to know the extent of the limits of his contract. No direct or extra compensation will be allowed on account of the cooperation required.

a. At all points of connection with work of other contracts, the Contractor shall have weekly coordination meetings until all connections have been completed with the adjoining contractor(s) to insure proper and timely connections.

b. Where the work under this contract is completed before that of the adjoining contractor, the Contractor shall terminate his work in an approved manner ready for future connection by the adjoining contractor.

Pipes and conduits shall be closed with suitable caps or plugs that will prevent entry of dirt or debris, but that are readily removable when final connections are made. For underground lines that are back-filled, approved type markers that extend above the ground surface shall be provided to facilitate future location of the lines by the adjoining contract.

c. Where the work of the adjoining contractor is already in place, the Contractor shall perform all work required to effect the necessary connection, including locations of underground lines, removing of caps, providing necessary adapters or joining pieces, and all related incidental work for necessary for a proper, secure connection.

1.44 WORKING CONDITIONS, WORKING HOURS, AND NON-WORKING DAYS

Refer to section 01 14 00 WORK RESTRICTIONS

1.45 COORDINATION OF TRADES

a. The contract drawings are in part diagrammatic and show the general arrangement of duct, piping and other mechanical and electrical trades.

The Contractor must have a competent engineer on the project site to coordinate all fieldwork and shop…

This is the start of the file's text. The full file is on GovTribe.