1. SOLICITATION NO. 2. DATE ISSUED 3. DATE OPENED PAGE 1 OF 2 PAGES
2/3/2017 3/21/2017
4. ISSUING OFFICE
DISTRICT ENGINEER CONTRACT SPECIALIST SIGNATURE CONTRACTING OFFICER SIGNATURE
PORTLAND DISTRICT, CORPS OF ENGINEERS
P.O. BOX 2946
PORTLAND, OR 97208-2946
5. PROJECT TITLE 8. GOVERNMENT ESTIMATE 9. OFFERS
(CHECK A, B, OR C AND COMPLETE NO.1 NO.2 NO.3
D, E, AND F.) A. OFFEROR A. OFFEROR A. OFFEROR
A. HIRED LABOR
B. REASONABLE CONTRACT B. BID SECURITY
X (WITHOUT PROFIT) 20% of bid price or $3 million 20% of bid price or $3 million
C. REASONABLE CONTRACT C. ADDENDA ACKNOWLEDGED C. ADDENDA ACKNOWLEDGED ADDENDA ACKNOWLEDGED (INCLUDING PROFIT) Amd. 0001 through 0004 Amd. 0001 through 0004
6. NUMBER OF ADDENDA ISSUED 4
7A.
ITEM E. UNIT F. ESTIMATED D. UNIT F. ESTIMATED D. UNIT F. ESTIMATED D. UNIT F. ESTIMATED NO. QUANTITY UNIT PRICE AMOUNT PRICE AMOUNT PRICE AMOUNT PRICE AMOUNT No. 1 vs IGE No. 2 vs IGE No. 3 vs IGE
0001 Mobilization and Demobilization 1 JOB 6,218,113.00$ 6,218,113.00$ 7,465,000.00$ 7,465,000.00$ 5,850,000.00$ 5,850,000.00$ -$ 20.1% -5.9% 0002 Government Directed Stand-by (OPTION) 8 HOURS 3,699.00$ 29,592.00$ 3,180.00$ 25,440.00$ 2,500.00$ 20,000.00$ -$ -14.0% -32.4% 0003 Government Directed Stand-by (OPTION) 8 HOURS 3,494.00$ 27,952.00$ 3,180.00$ 25,440.00$ 2,500.00$ 20,000.00$ -$ -9.0% -28.4% 0004 Government Directed Stand-by (OPTION) 8 HOURS 3,494.00$ 27,952.00$ 3,180.00$ 25,440.00$ 2,500.00$ 20,000.00$ -$ -9.0% -28.4%
HUM, Bin Measure to Required Depth, HOODS Ocean Disposal 300000 CY 4.10$ 1,230,000.00$ 3.23$ 969,000.00$ 3.65$ 1,095,000.00$ -$ -21.2% -11.0%
HUM, Bin Measure to Required Depth, HOODS Ocean Disposal (OPTION) 250000 CY 4.08$ 1,020,000.00$ 2.96$ 740,000.00$ 3.50$ 875,000.00$ -$ -27.5% -14.2%
0007 HUM, Contractor Survey 1 JOB 75,656.00$ 75,656.00$ 42,500.00$ 42,500.00$ 45,000.00$ 45,000.00$ -$ -43.8% -40.5% 0008 HUM, Contractor Survey (OPTION) 1 JOB 75,656.00$ 75,656.00$ 42,500.00$ 42,500.00$ 45,000.00$ 45,000.00$ -$ -43.8% -40.5%
CLW Maintenance, RM 3+00 to RM 105+00, Bin Measure, Flow Lane (FL) Placement 200000 CY 3.06$ 612,000.00$ 1.88$ 376,000.00$ 2.40$ 480,000.00$ -$ -38.6% -21.6%
CLW Maintenance, RM 3+00 to RM 105+00, Pre/Post Dredge Survey, (FL) Placement (OPTION) 175000 CY 3.14$ 549,500.00$ 1.86$ 325,500.00$ 3.00$ 525,000.00$ -$ -40.8% -4.5%
CLW Maintenance, RM 3+00 to RM 105+00, Pre/Post Dredge Survey, (FL) Placement (OPTION) 150000 CY 3.06$ 459,000.00$ 1.86$ 279,000.00$ 3.00$ 450,000.00$ -$ -39.2% -2.0%
CLW Maintenance, RM 3+00 to RM 105+00, Pre/Post Dredge Survey, (FL) Placement (OPTION) 150000 CY 3.06$ 459,000.00$ 1.86$ 279,000.00$ 3.00$ 450,000.00$ -$ -39.2% -2.0%
CLW Maintenance, RM 3+00 to RM 105+00, Bin Measure to Required Depth, Work Area Qty 30,000 to 75,000 cy, (FL) Placement 375000 CY 3.56$ 1,335,000.00$ 2.30$ 862,500.00$ 2.70$ 1,012,500.00$ -$ -35.4% -24.2%
CLW Maintenance, RM 3+00 to RM 105+00, Bin Measure to Required Depth, Work Area Qty Greater than 75,000 cy, (FL) Placement 375000 CY 3.56$ 1,335,000.00$ 1.90$ 712,500.00$ 2.70$ 1,012,500.00$ -$ -46.6% -24.2%
CLW Increment Times Transit Mile for Material Placement Site (beyond five miles one-way), Pre/Post (OPTION)
0015AA First 850,000 Cubic Yards (OPTION) 850000 CY 0.10$ 85,000.00$ 0.16$ 136,000.00$ 0.20$ 170,000.00$ -$ 60.0% 100.0%
ABSTRACT OF OFFERS
W9127N-17-B-0005
I CERTIFY THAT I HAVE OPENED, READ, AND RECORDED ON THIS ABSTRACT
ALL OFFERS RECEIVED IN RESPONSE TO THIS SOLICITATION.
Great Lakes Dredge & Dock Company, LLC
2122 York Road Oak Brook, IL 60523
West Coast Hopper Dredging 2017
7B. DESCRIPTION OF OFFERED ITEM
7C. EST D.
Manson Construction Co.
5209 E. Marginal Way S.
Seattle, WA 98134
B. BID SECURITY B. BID SECURITY
0015AB Over 850,000 Cubic Yards (OPTION) 150000 CY 0.10$ 15,000.00$ 0.16$ 24,000.00$ 0.20$ 30,000.00$ -$ 60.0% 100.0%
CLW Incremental Time Transit Mile for Material Placement Site (beyond five miles one-way), Bin Measure and/or Bin Measure to Required Depth (OPTION)
0016AA First 850,000 Cubic Yards (OPTION) 850000 CY 0.10$ 85,000.00$ 0.18$ 153,000.00$ 0.20$ 170,000.00$ -$ 80.0% 100.0% 0016AB Over 850,000 Cubic Yards (OPTION) 150000 CY 0.10$ 15,000.00$ 0.18$ 27,000.00$ 0.20$ 30,000.00$ -$ 80.0% 100.0%
0017 CLW Intra-Project Transit Miles -$ -$ -$ -$ 0017AA First 150 miles 150 MILES 441.00$ 66,150.00$ 500.00$ 75,000.00$ 300.00$ 45,000.00$ -$ 13.4% -32.0% 0017AB Over 150 miles 50 MILES 415.00$ 20,750.00$ 500.00$ 25,000.00$ 300.00$ 15,000.00$ -$ 20.5% -27.7%
0018 COO, Bin Measure to Required Depth, Site F Placement 500000 CY 2.82$ 1,410,000.00$ 2.41$ 1,205,000.00$ 2.50$ 1,250,000.00$ -$ -14.5% -11.3%
COO, Bin Measure to Required Depth, Site F Placement (OPTION) 200000 CY 2.76$ 552,000.00$ 2.21$ 442,000.00$ 2.20$ 440,000.00$ -$ -19.9% -20.3%
0020 COO, Contractor Survey (OPTION) 1 JOB 75,656.00$ 75,656.00$ 28,000.00$ 28,000.00$ 45,000.00$ 45,000.00$ -$ -63.0% -40.5%
MCR, Bin Measure, Shallow Water Site (SWS) or North Jetty Site (NJS) Placement 1700000 CY 3.09$ 5,253,000.00$ 1.96$ 3,332,000.00$ 2.30$ 3,910,000.00$ -$ -36.6% -25.6%
MCR, Bin Measure, Shallow Water Site (SWS) or North Jetty Site (NJS) Placement (OPTION) 300000 CY 3.04$ 912,000.00$ 1.79$ 537,000.00$ 2.15$ 645,000.00$ -$ -41.1% -29.3%
MCR, Bin Measure, Shallow Water Site (SWS) or North Jetty Site (NJS) Placement (OPTION) 250000 CY 3.04$ 760,000.00$ 1.79$ 447,500.00$ 2.15$ 537,500.00$ -$ -41.1% -29.3%
MCR, Bin Measure , Increment for Operations and Maintenance Deep Water Site (DWS) Placement 300000 CY 1.07$ 321,000.00$ 1.17$ 351,000.00$ 2.00$ 600,000.00$ -$ 9.3% 86.9%
MCR, Bin Measure , Increment for Operations and Maintenance Deep Water Site (DWS) Placement (OPTION)
300000 CY 1.07$ 321,000.00$ 1.11$ 333,000.00$ 1.75$ 525,000.00$ -$ 3.7% 63.6%
MCR, Bin Measure , Increment for Operations and Maintenance Deep Water Site (DWS) Placement (OPTION)
300000 CY 1.07$ 321,000.00$ 1.11$ 333,000.00$ 1.50$ 450,000.00$ -$ 3.7% 40.2%
SUBTOTAL FOR MANDATORY LINE ITEMS 17,876,669.00$ 15,415,500.00$ 15,315,000.00$ -$ -13.8% -14.3% SUBTOTAL FOR OPTIONAL LINE ITEMS 5,790,308.00$ 4,202,820.00$ 5,447,500.00$ -$ -27.4% -5.9%
23,666,977.00$ 19,618,320.00$ 20,762,500.00$ -$ -17.1% -12.3%
NSN 7540-01-150-0981 1419-101
TOTAL
ACCEPTANCE LIMITATION - DAYS
INFORMALITIES
STANDARD FORM 1419 (10-3)
Sheet1
| 2017-03-22T09:11:58-0700 | |
| BOONE.DAVID.C.1272229755 |
| 2017-03-22T10:32:31-0700 | |
| KOVAR.KIMBERLY.A.1075767583 |