AMENDMENT OF SOLICITATION/MODIFICATION OF CONTRACT
Except as provided herein, all terms and conditions of the document referenced in Item 9A or 10A, as heretofore changed, remains unchanged and in full force and effect.
15A. NAME AND TITLE OF SIGNER (Type or print)
30-105-04EXCEPTION TO SF 30
APPROVED BY OIRM 11-84
STANDARD FORM 30 (Rev. 10-83) Prescribed by GSA
FAR (48 CFR) 53.243
As an amendment to the solicitation the follow ing changes are made:
1. The price schedule quantity for CLIN 0006 HUM, Bin Measure to Required Depth, HOODS Ocean Disposal is increased by 150,000 cubic yards, from 100,000 cubic yards to 250,000 cubic yards. The attached revised price schedule is incorporated in full and replaces the previous version in its entirety.
2. Section 00800 Clause 52.211-10 Commencement, Prosecution, and Completion of Work is updated to reflect an increase in the number of days the contract w ill be extended if Optional CLIN 0006 is exercised from 4 days to 10 days. See Continuation Page for additional details.
3. The bid opening date is extended from 7 March 2017 at 2:00 PM Pacific Time to 14 March 2017 at 2:00 PM Pacific Time.
1. CONTRACT ID CODE PAGE OF PAGES
J 1 4
16A. NAME AND TITLE OF CONTRACTING OFFICER (Type or print)
16C. DATE SIGNED
BY 23-Feb-2017
16B. UNITED STATES OF AMERICA15C. DATE SIGNED15B. CONTRACTOR/OFFEROR
(Signature of Contracting Officer)(Signature of person authorized to sign)
8. NAME AND ADDRESS OF CONTRACTOR (No., Street, County, State and Zip Code) X W9127N-17-B-0005
X 9B. DATED (SEE ITEM 11)
03-Feb-2017
10B. DATED (SEE ITEM 13)
9A. AMENDMENT OF SOLICITATION NO.
11. THIS ITEM ONLY APPLIES TO AMENDMENTS OF SOLICITATIONS
X The above numbered solicitation is amended as set forth in Item 14. The hour and date specified for receipt of Offer X is extended, is not extended.
Offer must acknowledge receipt of this amendment prior to the hour and date specified in the solicitation or as amended by one of the following methods:
(a) By completing Items 8 and 15, and returning 1 copies of the amendment; (b) By acknowledging receipt of this amendment on each copy of the offer submitted;
or (c) By separate letter or telegram which includes a reference to the solicitation and amendment numbers. FAILURE OF YOUR ACKNOWLEDGMENT TO BE RECEIVED AT THE PLACE DESIGNATED FOR THE RECEIPT OF OFFERS PRIOR TO THE HOUR AND DATE SPECIFIED MAY RESULT IN
REJECTION OF YOUR OFFER. If by virtue of this amendment you desire to change an offer already submitted, such change may be made by telegram or letter, provided each telegram or letter makes reference to the solicitation and this amendment, and is received prior to the opening hour and date specified.
12. ACCOUNTING AND APPROPRIATION DATA (If required)
13. THIS ITEM APPLIES ONLY TO MODIFICATIONS OF CONTRACTS/ORDERS.
IT MODIFIES THE CONTRACT/ORDER NO. AS DESCRIBED IN ITEM 14.
A. THIS CHANGE ORDER IS ISSUED PURSUANT TO: (Specify authority) THE CHANGES SET FORTH IN ITEM 14 ARE MADE IN THE
CONTRACT ORDER NO. IN ITEM 10A.
B. THE ABOVE NUMBERED CONTRACT/ORDER IS MODIFIED TO REFLECT THE ADMINISTRATIVE CHANGES (such as changes in paying office, appropriation date, etc.) SET FORTH IN ITEM 14, PURSUANT TO THE AUTHORITY OF FAR 43.103(B).
C. THIS SUPPLEMENTAL AGREEMENT IS ENTERED INTO PURSUANT TO AUTHORITY OF:
D. OTHER (Specify type of modification and authority)
E. IMPORTANT: Contractor is not, is required to sign this document and return copies to the issuing office.
14. DESCRIPTION OF AMENDMENT/MODIFICATION (Organized by UCF section headings, including solicitation/contract subject matter where feasible.)
10A. MOD. OF CONTRACT/ORDER NO.
2. AMENDMENT/MODIFICATION NO. 5. PROJECT NO.(If applicable)
6. ISSUED BY
3. EFFECTIVE DATE
23-Feb-2017
CODE
USACE PORTLAND DISTRICT
333 SW 1ST AVE
PORTLAND OR 97204-3440
W9127N 7. ADMINISTERED BY (If other than item 6)
4. REQUISITION/PURCHASE REQ. NO.
CODE
See Item 6
FACILITY CODECODE
EMAIL:TEL:
W9127N-17-B-0005
SECTION SF 30 BLOCK 14 CONTINUATION PAGE
SUMMARY OF CHANGES
SECTION 00010 - SOLICITATION CONTRACT FORM
The required response date/time has changed from 07-Mar-2017 02:00 PM to 14-Mar-2017 02:00 PM.
SECTION 00100 - BIDDING SCHEDULE / INSTRUCTIONS TO BIDDERS
CLIN 0006
The pricing detail quantity has increased by 150,000.00 from 100,000.00 to 250,000.00.
The following Delivery Schedule item for CLIN 0006 has been changed from:
DELIVERY DATE QUANTITY SHIP TO ADDRESS UIC
POP 14-APR-2017 TO
17-JAN-2018
N/A PORTLAND DISTRICT RESIDENT OFFICE
CENWP-EC-CV
USACE PORTLAND DISTRICT
4480 SE COLUMBIA WAY
VANCOUVER WA 98661
360-448-7796 FOB: Destination
960439
To:
DELIVERY DATE QUANTITY SHIP TO ADDRESS UIC
POP 14-APR-2017 TO
17-JAN-2018
N/A PORTLAND DISTRICT RESIDENT OFFICE
CENWP-EC-CV
USACE PORTLAND DISTRICT
4480 SE COLUMBIA WAY
VANCOUVER WA 98661
360-448-7796
SECTION 00800 - SPECIAL CONTRACT REQUIREMENTS
The following have been modified:
52.211-10 COMMENCEMENT, PROSECUTION, AND COMPLETION OF WORK (APR 1984)
The Contractor shall be required to (a) commence work under this contract after the date the Contractor receives the notice to proceed as stated in Section 01 10 10.00 82 paragraph 1.1.2 a. “Order of Work” as follows:
(1) Humboldt Bay, California: Commence work accordingly to complete all awarded base and optional work by 20 June 2017.
(2) Mouth of the Columbia River and/ or the Columbia River: Commence work between 15 June 2017 and 1
July 2017
(3) The following work windows apply to locations contained within this Contract.
HUM: No environmental restrictions.
CLW: Dredging must take place between 1 June and 15 December.
COO: 15 June to 31 Oct.
MCR: All dredging at MCR must take place between June 1st and November 30th. No placement in the North Jetty Site is allowed on or after October 1st.
(b) Prosecute the work diligently, and (c) complete the entire work ready for use not later than:
FINAL CONSTRUCTION PHYSICAL COMPLETION date is 17 October 2017.
CONTRACT END DATE: 17 January 2018.
The time stated for FINAL CONSTRUCTION PHYSICAL COMPLETION includes physical completion of all site work, site cleanup, and demobilization.
The time stated for CONTRACT END DATE includes submission and approval of all final remaining work documents.
The contract will be extended with the award of each optional item, based on the table below:
Bid Item Description Days
0006 Humboldt Bay Bar and Entrance Maintenance Dredging and Placement
0011 Columbia River RM 3+00 to RM 105+00, Pre/Post Dredge Survey, Flow Lane Placement
0012 Columbia River RM 3+00 to RM 105+00, Pre/Post Dredge Survey, Flow Lane Placement
0014 Columbia River RM 3+00 to RM 105+00, Bin Measure to Required Depth, Flow Lane Placement
0019 Coos Bay Entrance Channel Maintenance Dredging and Placement
0022 Mouth of the Columbia River (MCR) Maintenance Dredging and Placement
0023 Mouth of the Columbia River (MCR) Maintenance Dredging and Placement
NOTES:
*Definition: Commence work means having dredge on site and ready to dredge **The Government intends to issue NTP on or about 14 April 2017
(End of clause)
(End of Summary of Changes)
Section 00010 - Solicitation Contract Form
ITEM DESCRIPTION QUANTITY UNIT UNIT PRICE TOTAL
0001 Mobilization and Demobilization
1 Job
Funded:
0002 Government
Directed Stand-by
8 Hours
OPTION Funded:
0003 Government
0004 Government
0005 Humboldt Bay
Bar/Entrance Channel (HUM)
300,000 Cubic Yard EST
HUM, Bin Measure to Required Depth, HOODS Ocean Disposal
0006 Humboldt Bay
250,000 Cubic Yard EST
OPTION HUM, Bin Measure to Required Depth, HOODS Ocean Disposal
0007 Humboldt Bay
Contractor Survey
0008 Humboldt Bay
OPTION Contractor Survey
0009 Columbia River
(CLW)
200,000 Cubic Yard EST
CLW Maintenance, RM 3+00 to RM 105+00, Bin Measure, Flow Lane (FL) Placement
0010 Columbia River
375,000 Cubic Yard EST
CLW Maintenance, RM 3+00 to RM 105+00, Pre/Post Dredge Survey, (FL) Placement
0011 Columbia River
150,000 Cubic Yard EST
OPTION CLW Maintenance, RM 3+00 to RM 105+00, 0012 Columbia River
OPTION CLW Maintenance, RM 3+00 to RM 105+00, 0013 Columbia River
375,000 Cubic Yard EST
CLW Maintenance, RM 3+00 to RM 105+00, Bin Measure to Required Depth, (FL) Placement
0014 Columbia River
175,000 Cubic Yard EST
OPTION CLW Maintenance, RM 3+00 to RM 105+00, Bin
Measure to Required Depth, (FL) Placement
0015 Columbia River
OPTION CLW Increment Times Transit Mile for Material Placement Site (beyond five miles one-way), Pre/Post
0015AA Columbia River
850,000 Cubic Yard EST
OPTION First 850,000 Cubic Yards
0015AB Columbia River
OPTION Over 850,000 Cubic Yards
0016 Columbia River
OPTION CLW Incremental Time Transit Mile for Material Placement Site (beyond five miles one-way), Bin Measure and/or Bin Measure to Required Depth
0016AA Columbia River
850,000 Cubic Yard EST
OPTION First 850,000 Cubic Yards
0016AB Columbia River
OPTION Over 850,000 Cubic Yards
0017 Columbia River
CLW Intra-Project Transit Miles
0017AA Columbia River
150 Miles EST
First 150 miles
0017AB Columbia River
50 Miles EST
Over 150 miles
0018 Coos Bay
Entrance Channel (COO)
500,000 Cubic Yard EST
COO, Bin Measure to Required Depth, Site F
0019 Coos Bay
200,000 Cubic Yard EST
OPTION COO, Bin Measure to Required Depth, Site F
0020 Coos Bay
OPTION Contractor Survey
0021 Mouth of the
Columbia River
(MCR)
1,700,000 Cubic Yard EST
MCR, Bin Measure, Shallow Water Site (SWS) or North Jetty Site (NJS) Placement
0022 Mouth of the
OPTION MCR, Bin Measure, Shallow Water Site (SWS) or
0023 Mouth of the
250,000 Cubic Yard EST
OPTION MCR, Bin Measure, Shallow Water Site (SWS) or
0024 Mouth of the
MCR, Bin Measure , Increment for Operations and Maintenance Deep Water Site (DWS) Placement
0025 Mouth of the
OPTION MCR, Bin Measure , Increment for Operations and
0026 Mouth of the
OPTION MCR, Bin Measure , Increment for Operations and
TOTALS
SUBTOTAL FOR MANDATORY LINE ITEMS
SUBTOTAL FOR OPTIONAL LINE ITEMS
TOTAL FOR ALL LINE ITEMS
INSPECTION AND ACCEPTANCE TERMS
Supplies/services will be inspected/accepted at:
CLIN INSPECT AT INSPECT BY ACCEPT AT ACCEPT BY
0001 Destination Government Destination Government 0002 Destination Government Destination Government 0003 Destination Government Destination Government 0004 Destination Government Destination Government 0005 Destination Government Destination Government 0006 Destination Government Destination Government 0007 Destination Government Destination Government 0008 Destination Government Destination Government 0009 Destination Government Destination Government 0010 Destination Government Destination Government 0011 Destination Government Destination Government 0012 Destination Government Destination Government 0013 Destination Government Destination Government 0014 Destination Government Destination Government 0015 Destination Government Destination Government 0015AA Destination Government Destination Government 0015AB Destination Government Destination Government 0016 Destination Government Destination Government 0016AA Destination Government Destination Government 0016AB Destination Government Destination Government 0017 Destination Government Destination Government 0017AA Destination Government Destination Government 0017AB Destination Government Destination Government 0018 Destination Government Destination Government 0019 Destination Government Destination Government 0020 Destination Government Destination Government 0021 Destination Government Destination Government 0022 Destination Government Destination Government 0023 Destination Government Destination Government 0024 Destination Government Destination Government 0025 Destination Government Destination Government 0026 Destination Government Destination Government
DELIVERY INFORMATION
CLIN DELIVERY DATE QUANTITY SHIP TO ADDRESS UIC
0001 POP 14-APR-2017 TO
17-JAN-2018
N/A PORTLAND DISTRICT RESIDENT OFFICE
CENWP-EC-CV
USACE PORTLAND DISTRICT
4480 SE COLUMBIA WAY
VANCOUVER WA 98661
360-448-7796
0002 POP 14-APR-2017 TO
17-JAN-2018
N/A (SAME AS PREVIOUS LOCATION)
0003 POP 14-APR-2017 TO
N/A (SAME AS PREVIOUS LOCATION)
0004 POP 14-APR-2017 TO
N/A (SAME AS PREVIOUS LOCATION)
0005 POP 14-APR-2017 TO
N/A (SAME AS PREVIOUS LOCATION)
0006 POP 14-APR-2017 TO
N/A (SAME AS PREVIOUS LOCATION)
0007 POP 14-APR-2017 TO
N/A (SAME AS PREVIOUS LOCATION)
0008 POP 14-APR-2017 TO
N/A (SAME AS PREVIOUS LOCATION)
0009 POP 14-APR-2017 TO
N/A (SAME AS PREVIOUS LOCATION)
0010 POP 14-APR-2017 TO
N/A (SAME AS PREVIOUS LOCATION)
0011 POP 14-APR-2017 TO
N/A (SAME AS PREVIOUS LOCATION)
0012 POP 14-APR-2017 TO
N/A (SAME AS PREVIOUS LOCATION)
0013 POP 14-APR-2017 TO
N/A (SAME AS PREVIOUS LOCATION)
0014 POP 14-APR-2017 TO
N/A (SAME AS PREVIOUS LOCATION)
0015 POP 14-APR-2017 TO
N/A (SAME AS PREVIOUS LOCATION)
0015AA POP 14-APR-2017 TO
N/A (SAME AS PREVIOUS LOCATION)
0015AB POP 14-APR-2017 TO
N/A (SAME AS PREVIOUS LOCATION)
0016 POP 14-APR-2017 TO
N/A (SAME AS PREVIOUS LOCATION)
0016AA POP 14-APR-2017 TO
N/A (SAME AS PREVIOUS LOCATION)
0016AB POP 14-APR-2017 TO
N/A (SAME AS PREVIOUS LOCATION)
0017 POP 14-APR-2017 TO
N/A (SAME AS PREVIOUS LOCATION)
0017AA POP 14-APR-2017 TO
N/A (SAME AS PREVIOUS LOCATION)
0017AB POP 14-APR-2017 TO
N/A (SAME AS PREVIOUS LOCATION)
0018 POP 14-APR-2017 TO
N/A (SAME AS PREVIOUS LOCATION)
0019 POP 14-APR-2017 TO
N/A (SAME AS PREVIOUS LOCATION)
0020 POP 14-APR-2017 TO
N/A (SAME AS PREVIOUS LOCATION)
0021 POP 14-APR-2017 TO
N/A (SAME AS PREVIOUS LOCATION)
0022 POP 14-APR-2017 TO
N/A (SAME AS PREVIOUS LOCATION)
0023 POP 14-APR-2017 TO
N/A (SAME AS PREVIOUS LOCATION)
0024 POP 14-APR-2017 TO
N/A (SAME AS PREVIOUS LOCATION)
0025 POP 14-APR-2017 TO
N/A (SAME AS PREVIOUS LOCATION)
0026 POP 14-APR-2017 TO
N/A (SAME AS PREVIOUS LOCATION)