PROJECT TITLE: Retrof it Channel/Infiiltration Sw ale B620 See attached Statement of Work w ith Project Draw ings for Project #03051

This acquisition is 100% set aside for Woman Ow ned Small Business under the NAICS 237990 w ith a size standard of $36.5M. Product Service Code Z2QA.

Magnitude of proposed construction is betw een $250,000 and $500,000.

Site visit w ill be held on 13 Aug 19 at 1000 hours (PST).

Questions are due by 15 Aug 19 by 1000 hours (PST).

POC: Brittney Wilson by phone (831) 242-4078 or you may send an email to brittney.j.w ilson4.civ@mail.mil

BIDS ARE DUE NO LATER THAN 9 Sep 2019 AT 1000 hours (PST).

As a result of this solicitation, the Government anticipates aw arding a Firm-Fixed Price Contract.

X

BRITTNEY J. WILSON 831-242-7012

NOTE: In sealed bid solicitations "offer" and "offeror" mean "bid" and "bidder".

10. THE GOVERNMENT REQUIRES PERFORMANCE OF THE WORK DESCRIBED IN THESE DOCUMENTS

NEGOTIATED

08-Aug-2019

(RFP)

(IFB)

CALL:

Retrofit Channel/Infiltration Sw ale

B. TELEPHONE NO. (Include area code) (NO COLLECT CALLS)

See Item 7

2. TYPE OF SOLICITATION

SEALED BID

3. DATE ISSUED

9. FOR INFORMATION A. NAME

SOLICITATION

NSN 7540-01-155-3212 1442-101 STANDARD FORM 1442 (REV. 4-85)

Prescribed by GSA

FAR (48 CFR) 53.236-1(e)

11. The Contractor shall begin performance w ithin _______10 calendar days and complete it w ithin ________365 calendar days after receiving aw ard, X notice to proceed. This performance period is X mandatory, negotiable. (See _________________________52.211-10

12 A. THE CONTRACTOR MUST FURNISH ANY REQUIRED PERFORMANCE AND PAYMENT BONDS?

(If "YES," indicate within how many calendar days after award in Item 12B.)

X YES NO

13. ADDITIONAL SOLICITATION REQUIREMENTS:

A. Sealed offers in original and __________1 copies to perform the w ork required are due at the place specif ied in Item 8 by ___________ local time ______________09 Sep 2019 (date). If this is a sealed bid solicitation, offers must be publicly opened at that time.

shall be marked to show the offeror's name and address, the solicitation number, and the date and time offers are due.

B. An offer guarantee X is, is not required.

C. All of fers are subject to the (1) w ork requirements, and (2) other provisions and clauses incorporated in the solicitation in full text or by reference.

D. Offers providing less than _______90 calendar days for Government acceptance after the date offers are due w ill not be considered and w ill be rejected.

SOLICITATION, OFFER,

AND AWARD

(Construction, Alteration, or Repair)

1. SOLICITATION NO.

IMPORTANT - The "offer" section on the reverse must be fully completed by offeror.

4. CONTRACT NO.

7. ISSUED BY CODE

MICC - PRESIDIO OF MONTEREY

BUILDING 4385 1ST FLOOR

400 GIGLING ROAD

SEASIDE CA 93955-6771

W9124N

PAGE OF PAGES

1 OF

CODE

(Title, identifying no., date):

12B. CALENDAR DAYS

10:00 AM (hour)

Sealed envelopes containing offers

5. REQUISITION/PURCHASE REQUEST NO. 6. PROJECT NO.

DPW - 03051

8. ADDRESS OFFER TO (If Other Than Item 7)

FAX:TEL: TEL: FAX:

W9124N19B0002 40

20B. SIGNATURE

(REV. 4-85)STANDARD FORM 1442 BACK

TO SIGN

NSN 7540-01-155-3212

SOLICITATION, OFFER, AND AWARD (Continued) (Construction, Alteration, or Repair)

CODE FACILITY CODE

17. The offeror agrees to perform the w ork required at the prices specified below in strict accordance w ith the terms of this solicitation, if this offer is accepted by the Government in w riting w ithin ________ calendar days after the date offers are due.

the minimum requirements stated in Item 13D. Failure to insert any number means the offeror accepts the minimum in Item 13D.)

AMOUNTS SEE SCHEDULE OF PRICES

18. The offeror agrees to furnish any required performance and payment bonds.

19. ACKNOWLEDGMENT OF AMENDMENTS

(The offeror acknowledges receipt of amendments to the solicitation -- give number and date of each)

AMENDMENT NO.

DATE

20A. NAME AND TITLE OF PERSON AUTHORIZED TO SIGN

OFFER (Type or print)

AWARD (To be completed by Government)

21. ITEMS ACCEPTED:

22. AMOUNT 23. ACCOUNTING AND APPROPRIATION DATA

24. SUBMIT INVOICES TO ADDRESS SHOWN IN ITEM

(4 copies unless otherwise specified)

CODE

(Insert any number equal to or greater than

20C. OFFER DATE

25. OTHER THAN FULL AND OPEN COMPETITION PURSUANT TO

10 U.S.C. 2304(c) 41 U.S.C. 253(c)

CODE27. PAYMENT WILL BE MADE BY:26. ADMINISTERED BY

(Include ZIP Code)14. NAME AND ADDRESS OF OFFEROR 15. TELEPHONE NO. (Include area code)

See Item 14

(Include only if different than Item 14)16. REMITTANCE ADDRESS

30B. SIGNATURE

29. AWARD (Contractor is not required to sign this document.)

document and return _______ copies to issuing office.) Contractor agrees Your of f er on this solicitation, is hereby accepted as to the items listed. This award con-to f urnish and deliv er all items or perf orm all work, requisitions identif ied summates the contract, which consists of (a) the Gov ernment solicitation and on this f orm and any continuation sheets f or the consideration stated in this y our of f er, and (b) this contract award. No f urther contractual document is contract. The rights and obligations of the parties to this contract shall be necessary .

gov erned by (a) this contract award, (b) the solicitation, and (c) the clauses, representations, certif ications, and specif ications or incorporated by ref er-ence in or attached to this contract.

30A. NAME AND TITLE OF CONTRACTOR OR PERSON AUTHORIZED 31A. NAME OF CONTRACTING OFFICER (Type or print)

30C. DATE

(Type or print)

TEL: EMAIL:

31B. UNITED STATES OF AMERICA 31C. AWARD DATE

BY

CONTRACTING OFFICER WILL COMPLETE ITEM 28 OR 29 AS APPLICABLE

(Contractor is required to sign this28. NEGOTIATED AGREEMENT

(M ust be fully completed by offeror)OFFER

W9124N19B0002

Section A - Solicitation/Contract Form

ADDITIONAL INFORMATION

Title: Retrofit Channel/Infiltration Swale B620

Period of Performance (POP): The Period of Performance (POP) will commence upon issue of the Notice to Proceed (NTP) and shall be finished within ninety (365) calendar days, after the issuance of the NTP – includes lead and delivery time for material, cleanup after the project is complete and project closeout documentation.

1. Disclosure of Magnitude: between $250,000 and $500,000.

2. NAICS CODE: 237990, SIZE STANDARD: $36,500,000.

3. The bid is due in this office by:

9 September 2019, at 10:00AM, Pacific Time

CLAUSES AND PROVISIONS

(a) Clauses and provisions from the Federal Acquisitions Regulation (FAR) and supplements thereto are incorporated in this document by reference or in full text. Those incorporated by reference have the same force and effect as if they were given in full text.

(b) Clauses and provisions in this document will be numbered in sequence, but will not necessarily appear in consecutive order.

(c) Sections K, L, and M will be physically removed by the Government from and resultant award, but will be deemed to be incorporated by reference in that award.

Section B - Supplies or Services and Prices

ITEM NO SUPPLIES/SERVICES QUANTITY UNIT UNIT PRICE AMOUNT

0001 1 Job

DPW-ENVR PROJECT# 03051

FFP

Retrofit Channel/Infiltration Swale for Bldg. 620 FOB: Destination

PSC CD: Z2QA

NET AMT

Section C - Descriptions and Specifications

DESCRIPTION AND SPECS

Title: Bldg 620 Retrofit Channel/Infiltration Swale Project No.:03051 Attch. 1 - SOW

Section E - Inspection and Acceptance

INSPECTION AND ACCEPTANCE TERMS

Supplies/services will be inspected/accepted at:

CLIN INSPECT AT INSPECT BY ACCEPT AT ACCEPT BY

0001 Destination Government Destination Government

CLAUSES INCORPORATED BY REFERENCE

52.246-12 Inspection of Construction AUG 1996 252.201-7000 Contracting Officer's Representative DEC 1991

QUANTITY SHIP TO ADDRESS DODAAC /

CAGE

Section F - Deliveries or Performance

DELIVERY INFORMATION

CLIN DELIVERY DATE

0001 365 calendar days after receiving NTP

1 W6CG USAG PRESIDIO

W6CG USAG PRESIDIO

289 FT MERVINE PLACE, BLDG 235

PRESIDIO OF MONTEREY CA 93944

FOB: Destination

W912A8

CLAUSES INCORPORATED BY REFERENCE

52.211-13 Time Extensions SEP 2000 52.242-14 Suspension of Work APR 1984

CLAUSES INCORPORATED BY FULL TEXT

52.211-10 COMMENCEMENT, PROSECUTION, AND COMPLETION OF WORK (APR 1984)

The Contractor shall be required to (a) commence work under this contract within ten (10) calendar days after the date the Contractor receives the notice to proceed, (b) prosecute the work diligently, and (c) complete the entire work ready for use not later than 365 calendar days. The time stated for completion shall include final cleanup of the premises.

(End of clause)

52.211-12 LIQUIDATED DAMAGES--CONSTRUCTION (SEP 2000)

(a) If the Contractor fails to complete the work within the time specified in the contract, the Contractor shall pay liquidated damages to the Government in the amount of $250.82 for each calendar day of delay until the work is completed or accepted.

(b) If the Government terminates the Contractor's right to proceed, liquidated damages will continue to accrue until the work is completed. These liquidated damages are in addition to excess costs of repurchase under the Termination clause.

(End of clause)

Section G - Contract Administration Data

52.232-5 Payments under Fixed-Price Construction Contracts MAY 2014 252.232-7003 Electronic Submission of Payment Requests and Receiving

Reports

DEC 2018

CLAUSES INCORPORATED BY FULL TEXT

252.204-7006 BILLING INSTRUCTIONS (OCT 2005)

When submitting a request for payment, the Contractor shall--

(a) Identify the contract line item(s) on the payment request that reasonably reflect contract work performance; and

(b) Separately identify a payment amount for each contract line item included in the payment request.

252.232-7006 WIDE AREA WORKFLOW PAYMENT INSTRUCTIONS (DEC 2018)

(a) Definitions. As used in this clause—

“Department of Defense Activity Address Code (DoDAAC)” is a six position code that uniquely identifies a unit, activity, or organization.

“Document type” means the type of payment request or receiving report available for creation in Wide Area WorkFlow (WAWF).

“Local processing office (LPO)” is the office responsible for payment certification when payment certification is done external to the entitlement system.

“Payment request” and “receiving report” are defined in the clause at 252.232-7003, Electronic Submission of Payment Requests and Receiving Reports.

(b) Electronic invoicing. The WAWF system provides the method to electronically process vendor payment requests and receiving reports, as authorized by Defense Federal Acquisition Regulation Supplement (DFARS) 252.232- 7003, Electronic Submission of Payment Requests and Receiving Reports.

(c) WAWF access. To access WAWF, the Contractor shall—

(1) Have a designated electronic business point of contact in the System for Award Management at https://www.sam.gov; and

(2) Be registered to use WAWF at https://wawf.eb.mil/ following the step-by-step procedures for self-registration available at this web site.

(d) WAWF training. The Contractor should follow the training instructions of the WAWF Web-Based Training Course and use the Practice Training Site before submitting payment requests through WAWF. Both can be accessed by selecting the “Web Based Training” link on the WAWF home page at https://wawf.eb.mil/.

(e) WAWF methods of document submission. Document submissions may be via web entry, Electronic Data Interchange, or File Transfer Protocol.

(f) WAWF payment instructions. The Contractor shall use the following information when submitting payment requests and receiving reports in WAWF for this contract or task or delivery order:

(1) Document type. The Contractor shall submit payment requests using the following document type(s):

2 in 1 Invoice

(i) For cost-type line items, including labor-hour or time-and-materials, submit a cost voucher.

(ii) For fixed price line items—

(A) That require shipment of a deliverable, submit the invoice and receiving report specified by the Contracting Officer.

(B) For services that do not require shipment of a deliverable, submit either the Invoice 2in1, which meets the requirements for the invoice and receiving report, or the applicable invoice and receiving report, as specified by the Contracting Officer.

(iii) For customary progress payments based on costs incurred, submit a progress payment request.

(iv) For performance based payments, submit a performance based payment request.

(v) For commercial item financing, submit a commercial item financing request.

(2) Fast Pay requests are only permitted when Federal Acquisition Regulation (FAR) 52.213-1 is included in the contract.

[Note: The Contractor may use a WAWF “combo” document type to create some combinations of invoice and receiving report in one step.]

(3) Document routing. The Contractor shall use the information in the Routing Data Table below only to fill in applicable fields in WAWF when creating payment requests and receiving reports in the system.

Routing Data Table*

Field Name in WAWF Data to be entered in WAWF

Pay Official DoDAAC HQ0490

Issue By DoDAAC W9124N

Admin DoDAAC** W9124N

Inspect By DoDAAC W912A8

Ship To Code N/A

Ship From Code N/A

Mark For Code N/A

Service Approver (DoDAAC) W912A8

Service Acceptor (DoDAAC) W912A8

Accept at Other DoDAAC N/A

LPO DoDAAC N/A

DCAA Auditor DoDAAC N/A

Other DoDAAC(s) N/A

(4) Payment request. The Contractor shall ensure a payment request includes documentation appropriate to the type of payment request in accordance with the payment clause, contract financing clause, or Federal Acquisition Regulation 52.216-7, Allowable Cost and Payment, as applicable.

(5) Receiving report. The Contractor shall ensure a receiving report meets the requirements of DFARS Appendix F.

The Contractor shall enter the email address identified below in the “Send Additional Email Notifications” field of WAWF once a document is submitted in the system.

Contracting Admin: Brittney Wilson, brittney.j.wilson4.civ@mail.mil

Contracting Officer: Mihui Toves, mihui.k.toves2.civ@mail.mil

(g) WAWF point of contact.

Erick Marx, 831-242-7925, Erick.r.marx.civ@mail.mil

(1) The Contractor may obtain clarification regarding invoicing in WAWF from the following contracting activity’s WAWF point of contact.

(2) Contact the WAWF helpdesk at 866-618-5988, if assistance is needed.

5152.233-4000 AMC-LEVEL PROTEST PROGRAM (Feb 2014) (LOCAL CLAUSE)

Prior to submitting an agency protest, it is preferable that you first attempt to resolve your concerns with the responsible contracting officer. However, you may also file a protest to the Headquarters (HQ), Army Materiel Command (AMC). The HQ AMC-Level Protest Program is intended to encourage interested parties to seek resolution of their concerns within AMC as an Alternative Dispute Resolution forum, rather than filing a protest with the Government Accountability Office (GAO) or other external forum. Contract award or performance is suspended during the protest to the same extent, and within the same time periods, as if filed at the GAO. The AMC protest decision goal is to resolve protests within 35 calendar days from filing. To be timely, protests must be filed within the periods specified in FAR 33.103. If you want to file a protest under the HQ AMC-Level Protest Program, the protest must request resolution under that program and be sent to the address below.

Headquarters U.S. Army Materiel Command Office of Command Counsel-Deputy Command Counsel 4400 Martin Road Rm: A6SE040.001 Redstone Arsenal, AL 35898-5000 Fax: (256) 450-8840 or email usarmy.redstone.usamc.mbx.protests@mail.mil

The AMC-Level Protest procedures are found at: http://www.amc.army.mil/amc/commandcounsel.html.

If internet access is not available, contact the contracting officer or HQ, AMC to obtain the HQ AMC-Level Protest Procedures.

(End of Clause)

Section H - Special Contract Requirements

SPECIAL CONTRACT REQUIREMENTS

I. GENERAL:

Pre‐Construction Conference: The Contracting Officer will schedule a pre‐construction conference after contract award and prior to commencement of work. The Contracting Officer will notify the contractor of the time, date, and place set for the meeting, which will be held at a location to be designated by the Contracting Officer. At this meeting, the contractor will be oriented with respect to Government procedures and lines of authority, as well as contractual, administrative, and construction matters.

II. WORK RESTRICTIONS:

a. Installation Rules and Regulations: Rules and regulations of the installation cited in the contract apply to all contractors and their employees. Regulations include, but are not limited to, presenting valid picture identification for base entrance, obtaining and using vehicle passes for all contractor‐owned and/or privately owned vehicles, and obeying all posted directives. Keep within the limits of the work and avenues of ingress and egress as directed. Wear hard hats in designated areas. Do not enter restricted areas unless required to do so and until cleared for such entry. Permission to interrupt any station roads, parking lots, or utility services shall be requested in writing a minimum of fifteen (15) calendar days prior to the desired date of interruption. The Contractor’s equipment shall be conspicuously marked for identification.

b. Working Hours: Unless otherwise specified, the Contractor shall work with/around the Government’s schedule to minimize interruption. Working hours will be from 8:00 AM to 4:30 PM, Monday through Friday. Federal holidays (New Year’s Day, Martin Luther King JR’s Birthday, Presidents’ Day, Memorial Day, Independence Day, Labor Day, Columbus Day, Veterans’ Day, Thanksgiving Day, and Christmas Day), that fall within the workweek will not be considered workdays. Whenever a holiday falls on a Saturday or Sunday, the preceding Friday or following Monday respectively will be observed as a holiday.

Prior to the contractor performing the work on days or at times other than those specified, the contractor shall submit a written request to the Contracting Officer’s Representative (COR) for approval by the Contracting Officer. Requests for deviation shall be submitted at least 72 hours prior to the time the contractor desires to work.

c. Work Outside Regular Hours: Work outside regular working hours requires Contracting Officer approval. Provide written request at least 72 hours prior to such work to allow arrangements to be made by the Government for inspecting the work in progress.

d. Work Performance: All work performed under this contract shall conform to the best practices of the trade or class of work involved and shall be executed in a careful and orderly manner by workmen skilled in their respective trades. All work shall be performed in strict accordance with the drawings and/or specifications or to current industry standards when not specified.

e. Occupancy: The areas in which the work is to be done may be occupied during the performance of work under this contract. Other maintenance and repair construction may also be concurrently being performed in the building. The Contractor shall not receive any additional compensation due to the conditions brought about by this occupancy and usage by the Government. It shall be the Contractor’s responsibility to coordinate with the Contracting Officer’s Representative (COR), and to schedule and perform his work in such a manner as to create the least possible interference with the conduct of normal activities within the areas. The Contractor shall not block more than one access of the building at any time, nor shall he disrupt the existing parking arrangement at any of the building parking areas without prior coordination with the COR.

f. Utilities: The Contractor shall be permitted to use existing utilities at each building location when available, to the extent needed to accomplish work on a “no charge” basis. Contractor owned construction sheds, trailers, offices or other such facilities requiring utility services shall be metered for each utility involved, and all costs involved up to the point of connection to Government owned utility systems shall be at the contractor’s expense. Final connection of Contractor supplied service laterals to existing Government owned utility systems will be made at the Contractor’s expense.

g. Sanitary Conveniences: The Contractor’s personnel shall be permitted to use a toilet room at the building, subject to the regulations and control of the COR. The responsible contractor shall ensure that the toilet premises are maintained in a clean and sanitary condition on a daily basis.

h. Cleaning: The Contractor shall at the end of each working day remove from the site all debris resulting from the performance of work. The debris will not be dumped on Government property unless a nongovernment owned dumpster is used. If the Contractor uses a dumpster, it shall be emptied before becoming full as to prevent debris from spilling onto the surrounding area. The area around the dumpster shall be kept free of debris. The daily cleaning work will not alleviate the Contractor from the responsibility of the final cleaning for acceptance, upon completion of all work. Federal, State and Local laws and regulations regarding hauling and disposal shall apply.

i. Damage: The Contractor shall be responsible to repair and/or replace any damage caused by the Contractor at the site of construction, at no additional cost to the Government, and at the discretion of the Contracting Officer.

j. Storage Shed and On‐Site Accommodations: The Contractor shall provide his own storage shed or trailer for on‐site office accommodations and for storing of equipment and material. The COR will assign the contractor a location for placement of his shed or trailer upon request.

III. ADMINISTRATIVE REQUIREMENTS:

a. Insurance Coverage: Pursuant to the clause "Insurance ‐ Work on a Government Installation (FAR 52.228‐5)", the Contractor will be required to present evidence to show, as a minimum, the amounts of insurance coverage indicated below:

Reference FAR clause entitled "Insurance – Work on a Government Installation (FAR 52.228-5)” the Contractor shall, at its own expense, procure and thereafter maintain the following kinds of insurance with respect to performance under the contract.

The contractor shall acquire and maintain during the entire performance of the contract period the following insurance in accordance with FAR 28.306.

a. Workmen’s Compensation and Employers Liability Insurance as required to comply with applicable Federal and State workers' compensation and occupational disease statutes. If occupational diseases are not compensable under those statutes, they shall be covered under the under the employer's liability section of the insurance policy, except when contract operations are so commingled with a contractor's commercial operations that it would not be practical to require this coverage. Employer's liability coverage of at least $100,000 shall be required, except in States with exclusive or monopolistic funds that do not permit workers' compensation to be written by private carriers.

b. General Liability Insurance. Bodily injury liability insurance, in the minimum limits of $500,000 per occurrence shall be required on the comprehensive form of policy.

c. Automobile Liability Insurance. This insurance shall be required on the comprehensive form of policy and shall provide bodily injury liability and property damage liability covering the operation of all automobiles used in connection with the performance of the contract. At least the minimum limits of $200,000 per person and $500,000 per occurrence for bodily injury and $20,000 per occurrence for property damage shall be required.

Prior to the issuance of the Notice to Proceed, the contractor shall furnish to the Contracting Officer a certificate or written statement of the above required insurance. The policies evidencing required insurance shall contain an endorsement to the effect that cancellation or any material change in the policies adversely affecting the interests of the Government in such insurance shall not be effective for such periods as may be prescribed by the laws of the State in which this contract is to be performed and in no event less than thirty (30) days after written notice thereof to the Contracting Officer.

The contractor agrees to insert the substance of this clause, including this paragraph (iii), in all subcontracts hereunder.

b. Vehicle Operations and Registration: The prime contractor is responsible for all employees or subcontracting employees performing duties on the installation cited in the contract. The Contractor shall be required to register all motor vehicles and trucks with the COR.

c. Speed Limits: The Contractor’s personnel, when operating motor vehicles, shall not exceed ten (10) miles per hours when passing military troops on the roadways, and abide by post speed limits otherwise.

IV. CONTRACTOR PERSONNEL REQUIREMENTS:

a. The Contractor shall furnish a list of contract personnel of the Contractor and Subcontractor. As changes occur and additional information becomes available, the Contractor shall provide the Contracting Officer an updated list.

b. Point of Contact: The Contractor shall provide a local telephone number, or a long distance telephone number, as applicable, that is answered 24 hours a day, seven (7) days a week at which they can be notified of emergency work. The Government shall not be expected to call a series of phone numbers in order to locate the Contractor or his designated representative.

c. Supervision: The Contractor shall have at least one qualified supervisor or project manager capable of reading, writing and conversing fluently in the English language on the job site during working hours. In addition, if a Quality Control representative is required on the contract, then that individual shall also have fluent English communication skills.

d. Conduct of Employees: The contractor is fully responsible for the performance and conduct of his employees at all times while on post performing under the contract. The Contractor shall not allow any employee to perform work under the contract while under the influence of alcohol, drugs or any other incapacitating agent. Military police and other law enforcement personnel on post have the right to deny entry to post or remove from post any contractor employee for misconduct, which endangers the health or safety of people or property or for reasons of security. In addition, the Post Commander may bar an individual from entering the post under the authority of 18 U.S.C. 1382. Removal from post of a contractor employee in accordance with above shall not relieve the Contractor from the requirement to meet all of the terms and conditions of the contract.

e. Smoking Policy: Contractor employees will abide by the DOD Smoking Policy.

V. SECURITY:

a. At all times during the performance of work within this facility, the Contractor and his or her employees shall remain cognizant of the security restrictions existing within the facility. The Contractor’s employees shall ensure that any doors, windows or access panels which may have been opened for them during the course of the work period are secured at the end of the day. The Contractor and his or her employees may store tools and equipment within the work area. However, recognize that they do so at their own risk even if the area can be secured. Circumstances that appear unusual, unhealthy, or otherwise hazardous shall be reported to the COR immediately. Other circumstances that should be reported to the COR shall include, but not be limited to, the following:

b. Lack of an Escort: The Contractor shall report any incident in which no escort is provided for scheduled work within secured areas of the building or any occurrence during which an escort leaves the Contractor’s employees while within a secure area.

VI. CONTRACTOR QUALITY CONTROL:

a. The Contractor shall provide and maintain an effective quality control program that complies with the Contract Clause entitled “Inspection of Construction”, the below stated quality control requirements and the quality control requirements stated in the respective section of the specifications.

(1) The Contractor shall establish a quality control system to perform sufficient inspection and testing of all items of work, including that of his subcontractors. The quality control system shall ensure conformance with applicable specifications and drawings with respect to materials, workmanship, construction, finish, functional performance, and identification. The quality control system will be established for all construction except where the technical provisions of the contract provide for specific Government control by inspections, tests, or other means. The Contractor’s quality control system will specifically include the surveillance and tests required in the technical provisions of the contract specifications. For purposes of the above description, shop manufacture or standard products is not defined as construction. Quality control personnel shall also be charged with the responsibility of policing Contractor’s Safety Program. This duty shall be clearly set forth in the quality control program.

(2) The Contractor’s quality control system is the means by which he assures himself that his construction complies with the requirements of the contract plans and specifications. The controls shall be adequate to cover all construction operations, including both on‐site and offsite fabrication and shall be keyed to the proposed construction sequence and shall include as a minimum at least three phases of inspection for all definable items or segments of work as follows:

(a) Preparatory Inspection: To be performed prior to beginning any work on any definable segment of work. To include a review of contract requirements; a check to assure that all materials and/or equipment have been tested, submitted, and approved; a check to assure that provisions have been made to provide required control testing; examination of the work area to ascertain that all preliminary work has been completed; a physical examination of materials and equipment to assure that they conform to approved shop drawings or submittal data and that all materials and/or equipment are on hand. The Contracting Officer shall be notified at least 48 hours in advance of the preparatory inspection and such inspection shall be made a matter of record in the Contractor’s quality control documentation as required by subparagraph c.

(b) Initial Inspection: To be performed as soon as a representative segment of the particular item of work has been accomplished and to include examination of the quality of dimensional requirements.

(c) Follow‐up Inspection: To be performed daily or as frequently as necessary to assure continuing compliance with contract requirements, including control testing, until completion of the particular segment of work.

b. The Contractor shall maintain current records of all inspections and tests performed on an appropriate approved format to be determined in the pre‐construction conference and to be approved by the Contracting Officer. These records shall provide factual evidence that the required inspection ortests have been performed, including type and number of inspections or tests involved; results of inspections or tests; nature of defects, causes for rejection, etc; proposed remedial action; and corrective actions taken. The Contractor shall not build up or conceal any feature of the work containing uncorrected defects, and payment on deficient items will be withheld until they are satisfactorily corrected or other action has been taken as authorized pursuant to the Contract Clause entitled “Inspection of Construction”. These records must cover both conforming and defective items and must include a statement that all supplies and materials incorporated in the work are in full compliance with the terms of the contract. Legible copies of these records must be furnished through the Quality Assurance Representative, to the Contracting Officer daily. The Prime Contractor’s designated representative shall verify these records on a daily basis.

c. The Contractor’s job supervisory staff may be used for quality control, supplemented, as necessary, by special technicians or testing facilities to perform all specified tests, balancing, adjusting and/or regulating mechanical and electrical devices, equipment and/or systems. As an option, an industry recognized testing laboratory approved by the Contracting Officer may be used for said testing.

VII. SAFETY AND ACCIDENT PREVENTION: In performing work under this contract, the contractor shall

a. Conform to the specific safety requirements established by this contract;

b. Comply with the safety rules of the Government installation that concern related activities not directly addressed in this contract. The Installation Safety Officer will be responsible for monitoring the contractor in the area of safety and accident prevention;

c. Take all reasonable steps and precautions to prevent accidents and preserve the life and health of contractor and Government personnel performing or in any way coming on contact with the performance of this contract;

d. Take such additional immediate precautions as the Contracting Officer may reasonably require for safety and accident prevention purposes; and

e. Shall comply with all OSHA Rules, Regulations and US Army Corps of Engineers Safety and Health Requirements Manual, http://www.usace.army.mil/inet/usace‐docs/eng‐ manuals/em385‐1‐ 1/toc.htm

VIII. FIRE AND SAFETY REQUIRMENTS:

a. The Contractor shall comply with the most current edition of the National Fire Codes, installation fire prevention standards and Army Regulation 420‐90, http://www.usapa.army.mil.

b. The Contractor shall comply with all Federal, state, local and installation safety regulations, Engineer Manual, EM 385‐1‐1 (http://www.usace.army.mil/inet/usace‐ docs/eng‐ manuals/em385‐ 1‐1/toc.htm) and all applicable OSHA Standards.

c. The Contractor shall ensure compliance with all federal, state and local environmental regulations.

The Contractor shall provide material safety data sheets (MSDS) for all hazardous materials used on the job site. The Contractor shall not turn in hazardous waste generated during performance of the contract, for disposal by the government, unless such disposal is explicitly provided for in the contract. If specified in the contract, the Contractor shall provide an MSDS for each hazardous material/waste turned in to the government for disposal. The contractor shall not dispose hazardous materials/waste in any dumpster, sanitary sewer, storm sewer or dispose of hazardous materials/waste by any other means on government property without authorization from the government. The contractor shall not sign any hazardous waste manifest. Signature authority for hazardous waste manifests is delegated only to certain personnel within the Environmental Office. The contractor shall provide copies of all manifests or bills of lading for the transportation and disposal of all asbestos or asbestos containing materials to the Environmental Office. The contractor shall immediately report all spills or release of hazardous materials, including all motor vehicle fuels, motor oil, anti‐ freeze and hydraulic fluid to the Contracting Officer’s Representative.

52.236-4 PHYSICAL DATA (APR 1984)

Data and information furnished or referred to below is for the Contractor's information. The Government shall not be responsible for any interpretation of or conclusion drawn from the data or information by the Contractor.

(a) The indications of physical conditions on the drawings and in the specifications are the result of site investigations by (not applicable).

(b) Weather conditions: The following table reflects historical meteorological data in Monterey, CA and will be used to evaluate request for time extensions due to abnormal weather. These calculations are used to determine the periods of performance at the Presidio of Monterey, CA. Requests for time extensions due to poor weather conditions will only be considered if the conditions present during performance exceed the climatic data listed in the below chart.

(c) Transportation facilities (not applicable).

(d) Other pertinent information (not applicable).

MONTH MONTHLY MEAN OF

PRECIPITATION IN

INCHES

MONTHLY MEAN

RELATIVE

HUMIDITY

MONTHLY MEAN OF

HIGH/LOW

TEMPERATURES

January 4.40 70% 58/44 February 4.05 72% 60/45

March 3.38 72% 61/43 April 1.49 69% 62/45 May .56 71% 62/46 June .20 72% 66/52 July .05 74% 66/53

August .07 75% 68/53 September .24 74% 70/51

October 1.06 71% 68/51 November 2.32 69% 63/47 December 3.41 69% 58/44

Section I - Contract Clauses

52.202-1 Definitions NOV 2013 52.203-3 Gratuities APR 1984 52.203-5 Covenant Against Contingent Fees MAY 2014 52.203-6 Restrictions On Subcontractor Sales To The Government SEP 2006 52.203-7 Anti-Kickback Procedures MAY 2014 52.203-8 Cancellation, Rescission, and Recovery of Funds for Illegal or

Improper Activity

MAY 2014

52.203-10 Price Or Fee Adjustment For Illegal Or Improper Activity MAY 2014 52.203-12 Limitation On Payments To Influence Certain Federal

Transactions

OCT 2010

52.204-4 Printed or Copied Double-Sided on Postconsumer Fiber Content Paper

MAY 2011

52.204-7 System for Award Management OCT 2018 52.204-9 Personal Identity Verification of Contractor Personnel JAN 2011 52.204-10 Reporting Executive Compensation and First-Tier

Subcontract Awards

OCT 2018

52.204-13 System for Award Management Maintenance OCT 2018 52.204-18 Commercial and Government Entity Code Maintenance JUL 2016 52.204-19 Incorporation by Reference of Representations and

Certifications.

DEC 2014

52.204-22 Alternative Line Item Proposal JAN 2017 52.209-6 Protecting the Government's Interest When Subcontracting

With Contractors Debarred, Suspended, or Proposed for Debarment

OCT 2015

52.209-10 Prohibition on Contracting With Inverted Domestic Corporations

NOV 2015

52.215-2 Audit and Records--Negotiation OCT 2010 52.215-8 Order of Precedence--Uniform Contract Format OCT 1997 52.219-8 Utilization of Small Business Concerns OCT 2018 52.219-14 (Dev) Limitations on Subcontracting (DEVIATION 2019-O0003). JAN 2019 52.219-30 (Dev) Notice of Set-Aside for, or Sole Source Award to, Women-

Owned Small Business Concerns Eligible Under the Women- Owned Small Business Program (DEVIATION 2019-O0003).

JAN 2019

52.222-1 Notice To The Government Of Labor Disputes FEB 1997 52.222-3 Convict Labor JUN 2003 52.222-4 Contract Work Hours and Safety Standards - Overtime

Compensation

MAY 2018

52.222-6 Construction Wage Rate Requirements AUG 2018 52.222-7 Withholding of Funds MAY 2014 52.222-8 Payrolls and Basic Records AUG 2018 52.222-9 Apprentices and Trainees JUL 2005 52.222-10 Compliance with Copeland Act Requirements FEB 1988 52.222-11 Subcontracts (Labor Standards) MAY 2014 52.222-12 Contract Termination-Debarment MAY 2014 52.222-13 Compliance With Construction Wage Rate Requirements and

Related Regulations

MAY 2014

52.222-14 Disputes Concerning Labor Standards FEB 1988 52.222-15 Certification of Eligibility MAY 2014 52.222-21 Prohibition Of Segregated Facilities APR 2015 52.222-26 Equal Opportunity SEP 2016

52.222-27 Affirmative Action Compliance Requirements for Construction

APR 2015

52.222-40 Notification of Employee Rights Under the National Labor Relations Act

DEC 2010

52.222-50 Combating Trafficking in Persons JAN 2019 52.222-54 Employment Eligibility Verification OCT 2015 52.222-55 Minimum Wages Under Executive Order 13658 DEC 2015 52.222-62 Paid Sick Leave Under Executive Order 13706 JAN 2017 52.223-2 Affirmative Procurement of Biobased Products Under Service and Construction Contracts

SEP 2013

52.223-3 Hazardous Material Identification And Material Safety Data JAN 1997 52.223-5 Pollution Prevention and Right-to-Know Information MAY 2011 52.223-6 Drug-Free Workplace MAY 2001 52.223-17 Affirmative Procurement of EPA-Designated Items in Service and Construction Contracts

AUG 2018

52.223-18 Encouraging Contractor Policies To Ban Text Messaging While Driving

AUG 2011

52.225-9 Buy American--Construction Materials MAY 2014 52.225-13 Restrictions on Certain Foreign Purchases JUN 2008 52.227-1 Authorization and Consent DEC 2007 52.227-2 Notice And Assistance Regarding Patent And Copyright

Infringement

DEC 2007

52.227-4 Patent Indemnity-Construction Contracts DEC 2007 52.228-5 Insurance - Work On A Government Installation JAN 1997 52.228-11 Pledges Of Assets AUG 2018 52.228-12 Prospective Subcontractor Requests for Bonds MAY 2014 52.228-14 Irrevocable Letter of Credit NOV 2014 52.228-15 Performance and Payment Bonds--Construction OCT 2010 52.229-3 Federal, State And Local Taxes FEB 2013 52.232-17 Interest MAY 2014 52.232-23 Assignment Of Claims MAY 2014 52.232-27 Prompt Payment for Construction Contracts JAN 2017 52.232-33 Payment by Electronic Funds Transfer--System for Award

Management

OCT 2018

52.232-39 Unenforceability of Unauthorized Obligations JUN 2013 52.232-40 Providing Accelerated Payments to Small Business

Subcontractors

DEC 2013

52.233-1 Disputes MAY 2014 52.233-1 Alt I Disputes (May 2014) - Alternate I DEC 1991 52.233-3 Protest After Award AUG 1996 52.233-4 Applicable Law for Breach of Contract Claim OCT 2004 52.236-2 Differing Site Conditions APR 1984 52.236-3 Site Investigation and Conditions Affecting the Work APR 1984 52.236-5 Material and Workmanship APR 1984 52.236-6 Superintendence by the Contractor APR 1984 52.236-7 Permits and Responsibilities NOV 1991 52.236-8 Other Contracts APR 1984 52.236-9 Protection of Existing Vegetation, Structures, Equipment, Utilities, and Improvements

APR 1984

52.236-10 Operations and Storage Areas APR 1984 52.236-11 Use and Possession Prior to Completion APR 1984 52.236-12 Cleaning Up APR 1984 52.236-13 Accident Prevention NOV 1991 52.236-14 Availability and Use of Utility Services APR 1984 52.236-15 Schedules for Construction Contracts APR 1984

52.236-17 Layout of Work APR 1984 52.236-21 Specifications and Drawings for Construction FEB 1997 52.236-26 Preconstruction Conference FEB 1995 52.242-13 Bankruptcy JUL 1995 52.243-4 Changes JUN 2007 52.244-2 Subcontracts OCT 2010 52.244-6 Subcontracts for Commercial Items JAN 2019 52.246-21 Warranty of Construction MAR 1994 52.248-3 Value Engineering-Construction OCT 2015 52.249-2 Alt I Termination for Convenience of the Government (Fixed-

Price) (Apr 2012) - Alternate I

SEP 1996

52.249-10 Default (Fixed-Price Construction) APR 1984 52.253-1 Computer Generated Forms JAN 1991 252.201-7000 Contracting Officer's Representative DEC 1991 252.203-7000 Requirements Relating to Compensation of Former DoD

Officials

SEP 2011

252.203-7001 Prohibition On Persons Convicted of Fraud or Other Defense- Contract-Related Felonies

DEC 2008

252.203-7002 Requirement to Inform Employees of Whistleblower Rights SEP 2013 252.204-7000 Disclosure Of Information OCT 2016 252.204-7003 Control Of Government Personnel Work Product APR 1992 252.204-7012 Safeguarding Covered Defense Information and Cyber

Incident Reporting

OCT 2016

252.204-7015 Notice of Authorized Disclosure of Information for Litigation Support

MAY 2016

252.209-7004 Subcontracting With Firms That Are Owned or Controlled By The Government of a Country that is a State Sponsor of Terrorism

MAY 2019

252.223-7004 Drug Free Work Force SEP 1988 252.223-7006 Prohibition On Storage, Treatment, and Disposal of Toxic or

Hazardous Materials

SEP 2014

252.223-7008 Prohibition of Hexavalent Chromium JUN 2013 252.225-7012 Preference For Certain Domestic Commodities DEC 2017 252.225-7048 Export-Controlled Items JUN 2013 252.227-7033 Rights in Shop Drawings APR 1966 252.232-7010 Levies on Contract Payments DEC 2006 252.236-7000 Modification Proposals-Price Breakdown DEC 1991 252.243-7001 Pricing Of Contract Modifications DEC 1991 252.243-7002 Requests for Equitable Adjustment DEC 2012 252.247-7022 Representation of Extent of Transportation by Sea. JUN 2019 252.247-7023 Transportation of Supplies by Sea FEB 2019

52.219-28 POST-AWARD SMALL BUSINESS PROGRAM REREPRESENTATION (JULY 2013)

(a) Definitions. As used in this clause--

Long-term contract means a contract of more than five years in duration, including options. However, the term does not include contracts that exceed five years in duration because the period of performance has been extended for a cumulative period not to exceed six months under the clause at 52.217-8, Option to Extend Services, or other appropriate authority.

Small business concern means a concern, including its affiliates, that is independently owned and operated, not dominant in the field of operation in which it is bidding on Government contracts, and qualified as a small business under the criteria in 13 CFR part 121 and the size standard in paragraph (c) of this clause. Such a concern is ``not dominant in its field of operation'' when it does not exercise a controlling or major influence on a national basis in a kind of business activity in which a number of business concerns are primarily engaged. In determining whether dominance exists, consideration shall be given to all appropriate factors, including volume of business, number of employees, financial resources, competitive status or position, ownership or control of materials, processes, patents, license agreements, facilities, sales territory, and nature of business activity.

(b) If the Contractor represented that it was a small business concern prior to award of this contract, the Contractor shall rerepresent its size status according to paragraph (e) of this clause or, if applicable, paragraph (g) of this clause, upon the occurrence of any of the following:

(1) Within 30 days after execution of a novation agreement or within 30 days after modification of the contract to include this clause, if the novation agreement was executed prior to inclusion of this clause in the contract.

(2) Within 30 days after a merger or acquisition that does not require a novation or within 30 days after modification of the contract to include this clause, if the merger or acquisition occurred prior to inclusion of this clause in the contract.

(3) For long-term contracts--

(i) Within 60 to 120 days prior to the end of the fifth year of the contract; and

(ii) Within 60 to 120 days prior to the date specified in the contract for exercising any option thereafter.

(c) The Contractor shall rerepresent its size status in accordance with the size standard in effect at the time of this rerepresentation that corresponds to the North American Industry Classification System (NAICS) code assigned to this contract. The small business size standard corresponding to this NAICS code can be found at http://www.sba.gov/content/table-small-business-size-standards.

(d) The small business size standard for a Contractor providing a product which it does not manufacture itself, for a contract other than a construction or service contract, is 500 employees.

(e) Except as provided in paragraph (g) of this clause, the Contractor shall make the representation required by paragraph (b) of this clause by validating or updating all its representations in the Representations and Certifications section of the System for Award Management (SAM) and its other data in SAM, as necessary, to ensure that they reflect the Contractor's current status. The Contractor shall notify the contracting office in writing within the timeframes specified in paragraph (b) of this clause that the data have been validated or updated, and provide the date of the validation or update.

(f) If the Contractor represented that it was other than a small business concern prior to award of this contract, the Contractor may, but is not required to, take the actions required by paragraphs (e) or (g) of this clause.

(g) If the Contractor does not have representations and certifications in SAM, or does not have a representation in SAM for the NAICS code applicable to this contract, the Contractor is required to complete the following rerepresentation and submit it to the contracting office, along with the contract number and the date on which the rerepresentation was completed:

The Contractor represents that it ( ) is, ( ) is not a small business concern under NAICS Code 237990- assigned to contract number W9124N-19-C-00XX.

(Contractor to sign and date and insert authorized signer's name and title).

52.222-35 EQUAL OPPORTUNITY FOR VETERANS (OCT 2015)

``Active duty wartime or campaign badge veteran,'' ``Armed Forces service medal veteran,'' ``disabled veteran,'' ``protected veteran,'' ``qualified disabled veteran,'' and ``recently separated veteran'' have the meanings given at FAR 22.1301.

(b) Equal opportunity clause. The Contractor shall abide by the requirements of the equal opportunity clause at 41 CFR 60-300.5(a), as of March 24, 2014. This clause prohibits discrimination against qualified protected veterans, and requires affirmative action by the Contractor to employ and advance in employment qualified protected veterans.

(c) Subcontracts. The Contractor shall insert the terms of this clause in subcontracts of $150,000 or more unless exempted by rules, regulations, or orders of the Secretary of Labor. The Contractor shall act as specified by the Director, Office of Federal Contract Compliance Programs, to enforce the terms, including action for noncompliance. Such necessary changes in language may be made as shall be appropriate to identify properly the parties and their undertakings.

52.222-36 EQUAL OPPORTUNITY FOR WORKERS WITH DISABILITIES (JUL 2014)

(a) Equal opportunity clause. The Contractor shall abide by the requirements of the equal opportunity clause at 41 CFR 60-741.5(a), as of March 24, 2014. This clause prohibits discrimination against qualified individuals on the basis of disability, and requires affirmative action by the Contractor to employ and advance in employment qualified individuals with disabilities.

(b) Subcontracts. The Contractor shall include the terms of this clause in every subcontract or purchase order in excess of $15,000 unless exempted by rules, regulations, or orders of the Secretary, so that such provisions will be binding upon each subcontractor or vendor.