Statement of Work (SOW)

Bldg 620 Retrofit Channel/Infiltration Swale

Project Description: The project purpose is to retrofit an existing concrete channel that runs between Bldgs 619, 620, and 622 with an infiltration swale and provide other landscaping improvements to promote storm water infiltration, improve water quality, and prevent flooding and runoff.

1. General:

1.1 Description of Services: The Contractor shall provide all personnel, equipment, supplies, facilities, transportation, tools, materials, supervision, and other items necessary to retrofit an existing concrete channel that runs between Buildings 619, 620, and 622 on the Presidio of Monterey. This includes, but is not limited to: removing the existing concrete v-ditch, installing a cobble-lined infiltration swale with surrounding native riparian vegetation and improving the existing outdoor gathering area with permeable paving, vegetation, and seating areas. The contractor shall perform to the standards in this contract and all work shall be in compliance with the current editions of all applicable codes and standards.

1.2 Background: The existing concrete channel that runs between Bldgs 619, 620, and 622 does not effectively capture and divert storm water runoff, and instead collects and pools near the sidewalk around Bldg 620. During heavy rain events, the sidewalk becomes flooded, creating a nuisance for the building’s occupants. It also presents a hazard as people may be forced to walk in the street instead of the sidewalk.

1.3 Objectives: The primary objectives of this requirement are to mitigate sidewalk flooding at Bldg 620, and to reduce the quantity of stormwater runoff and provide water quality benefits in compliance with the NPDES General Permit for Phase II Small Municipal Separate Storm Sewer Systems (MS4).

2. Scope of Work:

2.1 The contractor shall provide labor, material, equipment, transportation, and project management to execute and complete the subject project. Work requirements include, but are not limited to, the following:

General

a. Contractor shall be responsible to provide necessary geotechnical engineering and survey data, and coordinate and provide design and engineering services for removal and disposal of the existing concrete channel, and installation of the swale, surrounding landscaping, and seating areas.

b. Photo authorization is needed if photos/videos will be taken of the project site. Refer to Command Policy #21, Technical Exhibit 8.

(Revised by Amendment 0001)

c. Field verify all measurements.

d. Provide survey data of alignment and elevation to design engineers.

e. Provide a site design by a registered professional engineer for review and approval by the Government prior to commencing demolition or new work.

f. Properly dispose of any or all excess fill and other construction debris off post.

g. Maintain compliance with all environmental stipulations (See Section 5).

h. Contractor must notify PG&E, DigAlert, and POM DPW (831-242-7768) for utility clearance at least two weeks prior to construction.

i. Minimize the amount of excavation taking place on this project.

Demolition

j. Obtain utility clearance.

k. Remove the existing concrete v-ditch (approx. 320 LF) that runs along the south end of Building 620.

l. Dispose of all debris off post.

New Work (Contingent upon Government approval of design)

m. Conduct site visits to obtain field measurements.

n. Design a cobble-lined infiltration swale with underground overflow pipe, rain gardens, and seating areas based on concepts provided in Exhibits 2, 3, and 4 with the following design and sizing assumptions for the swale:

Design Parameter Value Drainage Area to Project 80,000 SF Bioswale Area 1,950 SF NRCS Hydrologic Soil Group D Assumed Infiltration Rate 0.25 in/hr Composite Runoff Coefficient (C)

0.23

Area-weighted Abstraction 0.19 in Assumed Ponding Depth 6 in Assumed Soil Media Depth 12 in Design Runoff Volume 2,715 CF Design Storm Depth 2 in

Design must be approved by a registered professional engineer. Provide the design and plans to the Government for review and approval prior to commencing installation of swale. Site design will be based on field measurements and other data collected during site visits. The swale and surrounding landscaping shall be designed to slow runoff and allow for maximum infiltration.

o. Swale will tie into Presidio of Monterey’s existing storm water conveyance system.

p. Tie the downspout on the southeast corner of Building 620 into the new swale.

q. Upon Government approval of the design, install swale, surrounding landscaping, and seating area per design.

r. Restore disturbed area where v-ditch was removed to original habitat with Government-approved hydroseed mix. Area must be stabilized with 70% coverage prior to project completion date.

s. Dispose of all construction debris off post.

2.2 The contractor shall provide at a minimum the following technical submittals for review by the Government. Allow two weeks for review.

a. Project schedule

b. Geotechnical data

c. Project site plans/design

d. Erosion control measures

e. Proposed vegetation & hydroseed mix

2.3 Contractor shall meet with DPW POC and COR weekly to update on construction progress.

2.4 Upon completion of the project, Contractor shall provide manufacturer’s warranty for any installed parts and systems, as well as contractor warranty on labor and workmanship.

2.5 Attachments

a. Technical Exhibit 1 – Project Boundary

b. Technical Exhibit 2 – Concept Plan 1

c. Technical Exhibit 3 – Concept Plan 2

d. Technical Exhibit 4 – Low Impact Development (LID) BMP #10 – Concrete Channel

Retrofit to Cobble Lined Conveyance

e. Technical Exhibit 5 – Presidio of Monterey Storm Drain Network Map 1

f. Technical Exhibit 6 – Presidio of Monterey Storm Drain Network Map 2

g. Technical Exhibit 7 – Presidio of Monterey Existing Water Line Near Building 620

h. Technical Exhibit 8 – Command Policy #21-Photo Authorization

i. Technical Exhibit 9 – Environmental Requirements of the Final Programmatic

Environmental Assessment for the Presidio of Monterey Integrated Water Sustainability Concept Plan, November 2018

3. Period of Performance (POP):

The Period of Performance (POP) will commence upon issue of the Notice to Proceed (NTP) and shall be finished no later than twelve months following NTP. This includes time to develop submittals and receive Government approval, lead and delivery time for material, project execution, cleanup after the project is complete, and demobilization.

4. General Information:

4.1 Federal Observed Holidays: The Contractor will not be required to perform repairs or construction work on Federal Holidays. Below is the observed holiday’s schedule:

New Year’s Day 1st day of January Martin Luther King, Jr. Day 3rd Monday of January

President’s Day 3rd Monday of February Memorial Day Last Monday of May Independence Day 4th day of July Labor Day 1st Monday of September Columbus Day 2nd Monday of October Veteran’s Day 11th day of November Thanksgiving Day 4th Thursday of November Christmas Day 25th day of December

4.2 Hours of Operation: The Contractor is responsible for conducting business, between the hours 0800 – 1630, Monday through Friday, except Federal Holidays or when the Government facility is closed due to local or national emergencies, administrative closings, or similar Government directed facility closings. The contractor must at all times maintain an adequate workforce for the uninterrupted performance of all tasks defined within this PWS when the Government facility is not closed.

4.3 Place of Performance: The work to be performed shall be at Building 620, Presidio of Monterey, California.

4.4 Quality Control Plan (QCP): The Contractor shall develop and maintain an effective QCP to ensure services are performed in accordance with this PWS.

4.5 Security Requirements: The Contractor shall submit a list of employees to the DPW POC for security access processing and approval. The list shall contain the employee’s full name, state driver’s license number, social security number, and date of birth. Contractor personnel shall be prepared to be searched by the installation security guard force.

4.6 Acceptance and Warranty: The contractor shall coordinate with the Contracting Officer’s Representative (COR) for final close-out inspection and/or acceptance at each phase of the project. The project may only be officially accepted by the COR. The contractor shall provide warranty manuals/documents (if applicable) to the COR within 30 days following the acceptance of the project. The manuals/documents shall be submitted to the COR.

4.7 Safety Requirements: No person shall be subjected to work in an unsafe or dangerous environment. Contractor safety will be governed by AR 385-10, paragraphs 3-5, 3-8, and Chapter 4. AR 385-10 may be made available through the COR.

4.8 Environmental Protection Plan (EPP): Not applicable to this project.

4.9 AT Level I Training. All contractor employees, to include subcontractor employees, requiring access to Army installations, facilities and controlled access areas shall complete AT Level I awareness training NLT 15 calendar days after contract award start date or effective date of incorporation of this requirement into the contract, whichever is applicable. The contractor shall submit certificates of completion for each affected contractor employee and subcontractor employee to the IGSATR or to the Inter-Governmental Services Agreement Manager (IGSAM), within 5 calendar days after completion of training by all employees and subcontractor personnel. AT Level I awareness training is available at the following website: http//jko.jten.mil.

4.10 Access and General Protection/Security Policy and Procedure. Contractor and all associated subcontractor employees shall provide all information required for background checks to meet installation access requirements to be accomplished by the installation Provost Marshall, Director of Emergency Services or Security Office. Contractor workforce shall comply with all personal identity verification requirements (FAR clause 52.204-9, Personal Identity Verification of Contractor Personnel) as directed by DoD, HQDA and/or local policy. In addition to the changes otherwise authorized by the changes clause of this contract, should the Force Protection Condition (FPCON) at any individual facility or installation change, the Government may require changes in contractor security matters or processes

4.11 For Contractors that do not require CAC, but require access to a DoD Facility or Installation. Contractor and all associated subcontractor employees shall comply with adjudication standards and procedures using the National Crime Information Center Interstate Identification Index (NCIC-III) and Terrorist Screening Data Base (TSDB) (Army Directive 2014-05/AR 190-13), applicable installation, facility and area commander installation/facility access and local security policies and procedures (provided by government representative), or at OCONUS locations, in accordance with status of forces agreement and other regulations.

4.12 iWATCH Training. The contractor and all associated subcontractor shall brief all employees on the local iWATCH program (training standards provided by the requiring activity ATO). This locally developed training will be used to inform employees of the types of behavior to watch for and instruct employees to report suspicious activity to the COR. This training shall be completed NLT 30 calendar days of contract award and NLT 5 calendar days of new employees commencing performance. The results shall be reported to the COR on/or before the timelines stipulated.

4.13 OPSEC Training. Per AR 530-1 Operations Security, the contractor employees must complete Level I OPSEC Awareness training. New employees shall complete training with 30 calendar days after their report of duty date and annually thereafter.

5. Environmental Stipulations

Contractor must abide by the following environmental stipulations:

a. Project must operate in full compliance with the most recent Federal, State, and local environmental laws, regulations, and programs.

b. Project must comply with all environmental requirements listed in the Final Programmatic Environmental Assessment for the Presidio of Monterey Integrated Water Sustainability Concept Plan, November 2018 (see Technical Exhibit 9; only yellow highlighted portions are applicable), in addition to the requirements listed below.

c. All areas where soil disturbance occurs shall be restored to its original condition or better and any vegetation or hydroseed mixtures shall be approved by DPW Natural Resource Manager (April Andujar, 831-242-6736).

d. Portable generators must be certified under the Portable Equipment RegistrationProgram (PERP) via the California Air Resources Board.

e. A professional archaeologist (per qualifications at 36 CFR 61) shall monitor ground disturbance associated with this project.

f. Proposed work may proceed in accordance with the “Programmatic Agreement Among the US Army, the Advisory Council on Historic Preservation (ACHP) and the California State Historic Preservation Officer (SHPO) Regarding Routine Maintenance of Historic Properties at the Presidio of Monterey” (PA) provided the channel retrofit is within the footprint of the existing channel.

g. Ensure all equipment and vehicles are kept on hardscape. Staging areas must be on DPW Environmental-approved hardscaped areas.

h. In accordance with the Phase II Municipal Separate Storm Sewer Systems (MS4) General Permit, Best Management Practices (BMPs) are required to be used to minimize erosion from the project site and to prevent any illicit discharges to the MS4 during construction.

BMPs must be implemented and followed according to the latest California Stormwater Quality Association (CASQA) Construction BMP Handbook. Any illicit discharges to the MS4 must be reported immediately to Erika Marx at 831-242-7925.

i. Migratory Bird Treaty Act: If work is performed during the migratory bird nesting season (1 February to 31 August), a biological survey for nesting migratory birds must be conducted by a qualified biologist no more than 10 days prior to the start of work.

j. All plants must be native to the region. Final selection of plants must be approved by the Presidio Natural Resource Program Manager.

Technical Exhibit 1 – Project Boundary

Technical Exhibit 2 – Concept Plan 1

Technical Exhibit 3 – Concept Plan 2

Technical Exhibit 4 – Low Impact Development (LID) BMP #10 – Concrete Channel Retrofit to Cobble Lined Conveyance

Technical Exhibit 5 – Presidio of Monterey Storm Drain Network Map 1

Technical Exhibit 6 – Presidio of Monterey Storm Drain Network Map 2

Technical Exhibit 7 – Presidio of Monterey Existing Water Line Near Building 620

Technical Exhibit 8 – Command Policy #21-Photo Authorization

Technical Exhibit 9 – Environmental Requirements of the Final Programmatic Environmental Assessment for the Presidio of Monterey Integrated Water Sustainability Concept Plan, November 2018

Presidio of Monterey

Integrated Water Sustainability Concept Plan 6 Programmatic Environmental Assessment

Table ES-1 Summary of Environmental Consequences

Resource Impact Alternative 1, Proposed Action Alternative 2, No

Action Alternative 3, Full Implementation

Measures Incorporated into the Proposed Action

Mitigation Measures

Air Quality

Short-term emissions of various air pollutants, fugitive dust, and greenhouse gases during construction.

Less than Significant No Impact Less than Significant Air Quality Measure 1:

Compliance with Standard MBARD Emission Control Measures. Construction activity would be required to comply with the following standard MBARD emission control measures to reduce fugitive dust and construction related emissions of PM10:

• Water all active construction areas as required with acceptable non-potable water sources to the extent feasible, with frequency based on the type of operation, soil, and wind exposure, and minimized to prevent wasteful use of water.

• Prohibit all grading activities during periods of high wind (over 15 mph)

• Apply chemical soil stabilizers on inactive construction areas (disturbed lands within Construction Projects that are unused for at least four consecutive days)

• Apply non-toxic binders (e.g., latex acrylic copolymer) to exposed

None required.

erika.r.marx.civ Highlight

Executive Summary

Programmatic Environmental Assessment 7

Resource Impact Alternative 1, Proposed Action Alternative 2, No

Action Alternative 3, Full Implementation

Measures Incorporated into the Proposed Action

Mitigation Measures areas after cut and fill operations and hydro seed area

• Haul trucks shall maintain at least 2'0" of freeboard

• Cover all trucks hauling dirt, sand, or loose materials

• Plant vegetative ground cover in disturbed areas as soon as possible with POM approved plants

• Cover inactive storage piles

• Install wheel washers at the entrance to construction sites for all exiting trucks

• Sweep streets if visible soil material is carried out from the construction site.

• Where feasible, use construction equipment that conforms to MBARD’s Tier 3 or Tier 4 standards

• Whenever feasible, construction equipment shall use alternative fuels such as compressed natural gas, propane, electricity, or biodiesel

• If any trees or vegetation are disposed of via wood chipping, the operator shall

8 Programmatic Environmental Assessment

Resource Impact Alternative 1, Proposed Action Alternative 2, No

Action Alternative 3, Full Implementation

Measures Incorporated into the Proposed Action

Mitigation Measures contact MBARD’s Engineering Division at

(831) 647-9411 to discuss if a Portable Registration is necessary for the wood chipper being utilized for the project

Biological Resources

Ground disturbance could result in impacts to Yadon’s piperia, nesting bird, and native tree communities.

Less than Significant No Impact Less than Significant Bio Measure 1: Avoidance and Minimization Measures for impacts to Yadon’s piperia (USFWS 2013)

1. Yadon’s piperia Surveys.

Surveys for Yadon’s piperia shall be conducted during the growing season, between December and March. All individuals identified shall be documented, photographed, and flagged or fenced to maximize avoidance and accurately determine the number of individuals affected.

2. Yadon’s piperia Protection.

A biological monitor shall be onsite during all construction activities in or adjacent to Yadon’s piperia habitat.

Construction activities occurring in occupied Yadon’s piperia habitat shall be limited to the minimum area required, None required.

Programmatic Environmental Assessment 9

Resource Impact Alternative 1, Proposed Action Alternative 2, No

Action Alternative 3, Full Implementation

Measures Incorporated into the Proposed Action

Mitigation Measures and shall occur in existing access roads and disturbed areas to the maximum extent possible.

Construction shall be restricted to the dormant season (August to November) to the extent possible. Only the equipment absolutely necessary to accomplish work shall be allowed in occupied habitat. Staging areas, spoils piles, equipment, and vehicle parking shall be located in designated areas outside of occupied habitat. The boundaries of Yadon’s piperia habitat shall be clearly marked with fencing to prevent additional ground disturbance or impacts.

3. Worker Environmental Awareness Program (WEAP). Prior to initiation of construction activities (including staging and mobilization), all personnel associated with project construction shall attend WEAP training, conducted by a qualified biologist, to aid workers in recognizing special status resources that may occur in the

10 Programmatic Environmental Assessment

Resource Impact Alternative 1, Proposed Action Alternative 2, No

Action Alternative 3, Full Implementation

Measures Incorporated into the Proposed Action

Mitigation Measures project area, including Yadon’s piperia. The specifics of this program shall include identification of the sensitive species and habitats, a description of the regulatory status and general ecological characteristics of sensitive resources, review of the limits of construction and mitigation measures required to reduce impacts to biological resources in the work area, and penalties for non-compliance. A fact sheet conveying this information shall also be prepared for distribution to all contractors, their employees, and other personnel involved with construction of the project.

All personnel shall sign a form, provided by the trainer, documenting they have attended the WEAP training and understand the information presented to them.

4. Pesticide Use. Use of broad-spectrum insecticide and/or herbicide shall not occur during the growing season of Yadon’s piperia (December to August), and

Programmatic Environmental Assessment 11

Resource Impact Alternative 1, Proposed Action Alternative 2, No

Action Alternative 3, Full Implementation

Measures Incorporated into the Proposed Action

Mitigation Measures individuals shall be covered by a qualified biologist during the growing season (December to August) as necessary prior to treatment.

5. Relocation. If individuals of Yadon’s piperia cannot be avoided by construction, they shall be salvaged and either donated (upon approval of FWS) for academic research, or transplanted to protected areas. Ideal transplant areas shall be in suitable habitat, but outside of known locations of extant population to avoid disturbing extant individuals. The guidelines recommended by USFWS for transplantation include the following:

• Individuals shall be relocated during the dormant season (fall/winter)

• Yadon’s piperia tubers will be collected by sieving dirt or using a tree spade

• Local soil will be transplanted with tubers to ensure necessary mycorrhizal fungi are

12 Programmatic Environmental Assessment

Resource Impact Alternative 1, Proposed Action Alternative 2, No

Action Alternative 3, Full Implementation

Measures Incorporated into the Proposed Action

Mitigation Measures present

• If necessary, tubers will be stored in trays in the field or in a lathe house to prevent herbivory

• Non-native invasive species will be removed (non-chemical) from the transplant area prior to transplantation

• Transplant areas shall be chosen based on habitat characteristics such as the presence of indicator species, soils, and hydrology

• Transplanted individuals will be monitored during annual surveys

Bio Measure 2: Avoid, minimize, and mitigate impacts to other special status species (POM

INRMP)

1. Nesting Bird Protection - For projects that may result in tree felling or removal of trees or vegetation that may contain a nesting bird, construction activities should occur outside of the nesting season, if feasible, generally between September 1 and January

31. This includes the NP

Programmatic Environmental Assessment 13

Resource Impact Alternative 1, Proposed Action Alternative 2, No

Action Alternative 3, Full Implementation

Measures Incorporated into the Proposed Action

Mitigation Measures

Storage Tank Retrofit and Building 622 Parking Lot Bioswale projects, and any activities occurring in the two conservation areas:

Huckleberry Hill Nature Preserve or the Monterey pine forest. Additionally, all Concepts have some potential to support nesting birds in undeveloped areas, and landscaped areas containing natural or ornamental trees and shrubs. If construction activities must occur during the nesting season (generally February 1 to August 31), surveys for nesting birds covered under the Migratory Bird Treaty Act shall be conducted by a Directorate of Public Works Environmental Division- (DPWE) approved biologist no more than 14 days prior to vegetation removal. The surveys shall include the entire disturbance area plus a 500-foot buffer around the site, as feasible. If active nests are found, all construction work shall be conducted outside a buffer zone from the nest to be

14 Programmatic Environmental Assessment

Resource Impact Alternative 1, Proposed Action Alternative 2, No

Action Alternative 3, Full Implementation

Measures Incorporated into the Proposed Action

Mitigation Measures determined by the approved biologist and DPWE. Typical buffer distances consist of up to 250 feet for non-raptor bird species and up to 500 feet for raptor species. Larger buffers may be required based upon the species, status of the nest, and type of construction activities occurring near the nest.

The buffer area(s) shall be closed to all construction personnel and equipment until the adults and young no longer rely on the nest site. A DPWE-approved biologist shall confirm that breeding/nesting is completed and young have fledged the nest prior to removal of the buffer.

Bio Measure 3: Avoid, minimize, and mitigate impacts to Monterey pine and native tree communities (USFWS 2013)

1. Tree Protection - To reduce impacts to Yadon’s piperia habitat, construction designs will incorporate selective Monterey pine tree removal as a first choice as opposed to complete clear-cutting the forest in erika.r.marx.civ Highlight

Programmatic Environmental Assessment 15

Resource Impact Alternative 1, Proposed Action Alternative 2, No

Action Alternative 3, Full Implementation

Measures Incorporated into the Proposed Action

Mitigation Measures undeveloped areas.

2. Bark Beetle Prevention - Prior to the start of construction, all Monterey pine trees that are within 100 feet of the project area and scheduled to be preserved shall be treated for bark beetle using standard practices recommended by the certified arborist and in accordance with the

INRMP.

3. Invasive Weed Prevention

- Plant species used for landscaping shall not include invasive or noxious species. If invasive species such as French broom, pampas grass (Cortaderia spp.), or ice plant (Carpobrotus edulis) are discovered in area proposed for disturbance they shall be removed. If disturbed areas require hydroseeding, a mix of locally native species will be used. All equipment, including clothes and shoes, shall be free of seeds prior to entering the work area. All invasive plant seeds shall be contained (in plastic bags) erika.r.marx.civ Highlight

16 Programmatic Environmental Assessment

Resource Impact Alternative 1, Proposed Action Alternative 2, No

Action Alternative 3, Full Implementation

Measures Incorporated into the Proposed Action

Mitigation Measures and taken to an appropriate disposal facility.

4. Avoid negative impacts to protected trees (including Monterey pine, coast live oak, Monterey cypress, and horticultural trees) to the maxim extent feasible, by installing temporary fencing around all trees identified for preservation prior to work. Generally fencing shall be located at the edge of the root zone, located out a distance 15 times the DBH in all directions. Fencing shall be rigidly supported and maintained during the project. Fenced areas shall not be used for material stockpile, or equipment.

5. Ensure that no irrigation, trenching, compaction, or other soil condition altering activities occur within the drip line of naturally occurring Monterey pine, coast live oak trees, Monterey cypress, and horticultural trees unless necessary or unavoidable.

Such activities can compromise the health and structural stability of the tree, and can create a

Programmatic Environmental Assessment 17

Resource Impact Alternative 1, Proposed Action Alternative 2, No

Action Alternative 3, Full Implementation

Measures Incorporated into the Proposed Action

Mitigation Measures safety hazard. If unavoidable, the proponent shall coordinate the activity with an ISA-certified arborist and Presidio of Monterey Environmental Division.

6. Tree replacement will be per the POM INRMP as assessed by the POM Natural Resource Manager.

Cultural Resources

Ground disturbance within or near archaeological resources.

Less than Significant with Mitigation

No Impact Impacts unknown until further analyses has been completed

Cultural Measure 1: Cultural Resources Measures in Accordance with the POM ICRMP, Section 106 of the NHPA, and NAGPRA

1. The ICRMP for POM (POM 2004) identifies standard operating procedures (SOP) to protect cultural resources and comply with applicable federal laws. In accordance with SOPs #1 and #5, all Concepts would be subject to a Phase I cultural resources investigation that would identify additional requirements, including addressing impacts to known and newly identified cultural resources, on a project by project basis. If

18 Programmatic Environmental Assessment

Resource Impact Alternative 1, Proposed Action Alternative 2, No

Action Alternative 3, Full Implementation

Measures Incorporated into the Proposed Action

Mitigation Measures cultural resources are identified in an area of potential effect (APE) and determined eligible or potentially eligible for listing in the National Register of Historic Places (NRHP), the Cultural Resources Manager (CRM) and project manager may develop a plan for avoidance of the resource. Compliance with Section 106 of the NHPA will be required for all projects that do not comply with the terms of the "Programmatic Agreement Among the U.S. Army, the Advisory Council on Historic Preservation and the California State Historic Preservation Officer Regarding Routine Maintenance of Historic Properties at the Presidio of Monterey, Monterey County, California."

Compliance with Section 106 of the NHPA requires consultation with the California State Historic Preservation Officer (SHPO), Native Americans, the Alliance of Monterey Area Preservationists and

Programmatic Environmental Assessment 19

Resource Impact Alternative 1, Proposed Action Alternative 2, No

Action Alternative 3, Full Implementation

Measures Incorporated into the Proposed Action

Mitigation Measures interested stakeholders. If it is determined that there will be an adverse effect to cultural resources, consultation with the Advisory Council on Historic Preservation and development of a Memorandum of Agreement will also be required.

2. A qualified archaeologist (per 36 CFR 61) will be required on site to monitor excavations associated with the Water Tank Retrofit.

23.If cultural resources are inadvertently discovered, work shall be halted within 30-meters (100-feet) of the find until it can be evaluated by a qualified professional archaeologist (per 36 CFR 61 Appendix A) and the U.S. Army Cultural Resources Manager. Inadvertent discoveries will require implementation of procedures set forth in the Presidio of Monterey's Integrated Cultural Resources Management Plan (ICRMP) and Army Regulation (AR 200-1), erika.r.marx.civ Highlight

20 Programmatic Environmental Assessment

Resource Impact Alternative 1, Proposed Action Alternative 2, No

Action Alternative 3, Full Implementation

Measures Incorporated into the Proposed Action

Mitigation Measures which includes consultation procedures and planning requirements per Section 106 of the National Historic Preservation Act (NHPA) (54 U.S.C. 306108 et seq.;

36 CFR Part 800). Any construction that would take place in the POM Historic District or El Castillo, including all or portions of Concepts 1, 5, 8, 9, 10, 11, would be monitored by an archaeologist and Native American monitor.

34.An inadvertent discovery of human remains, funerary objects, sacred objects, or objects of cultural patrimony will require implementation of procedures set forth in the Presidio's ICRMP, AR 200- 1, and the Native American Graves Protection and Repatriation Act

(NAGPRA; 25 U.S.C. 3001

et seq.; 43 CFR 10). An inadvertent discovery of NAGPRA items requires that all construction activities stop within 30-meters of the find for 30 days and the U.S. Army Cultural Resources Manager will coordinate

Programmatic Environmental Assessment 21

Resource Impact Alternative 1, Proposed Action Alternative 2, No

Action Alternative 3, Full Implementation

Measures Incorporated into the Proposed Action

Mitigation Measures with the appropriate Native American tribes in accordance with Section 3 of NAGPRA.

45. If avoidance is not feasible, consult with the ACHP, SHPO, Native Americans, the Alliance of Monterey Area Preservationists and the public as required to comply with the NHPA per

36 CFR 800.

Geology and Soils

Short-term erosion and slope destabilization during construction due to ground disturbance and excavation.

Less than Significant with Mitigation

No Impact Less than Significant with Mitigation

Geology and Soils Measure 1: The California Stormwater Construction General Permit requires the use of specific BMPs for projects that disturb one acre or more to achieve strict compliance with federal technology-based and water quality-based standards. For each Construction Project that disturbs one acre or more, Permit Registration Documents would be prepared for submission to the State Water Resources Control Board (SWRCB) and would include a Notice of Intent, Risk Assessment, site map, Stormwater Pollution Prevention Plan (SWPPP), a signed certification statement, post-construction

Mitigation Measure GS–1: For Projects and Concepts located in undeveloped areas or on steep slopes but that disturb less than one acre, BMPs shall be implemented prior to construction to address the control of pollutant discharges. The BMPs would include but would not be limited to the following:

• Schedule construction sequences to minimize land disturbance during rainy and dry seasons

• Provide soil stabilization to steep slope areas

• Provide sediment controls to intercept and slow down stormwater flows and capture entrained sediment, such as sandbags, silt fences, earthen erika.r.marx.civ Highlight

22 Programmatic Environmental Assessment

Resource Impact Alternative 1, Proposed Action Alternative 2, No

Action Alternative 3, Full Implementation

Measures Incorporated into the Proposed Action

Mitigation Measures documentation, and payment of fees. The findings of the Risk Assessment would determine the hazards associated with the site conditions and establish the specific compliance conditions of the permit. A SWPPP is required to be developed prior to construction of projects that disturb one acre or more to address the control of pollutant discharges using BMPs selected for the specific project and to address stormwater monitoring. The BMPs would include but not be limited to the following:

• Schedule construction sequences to minimize land disturbance during rainy and dry seasons

• Provide soil stabilization to steep slope areas

• Provide sediment controls to intercept and slow down stormwater flows

• Cover stockpiled soil

• Use dust suppressants, such as watering soils and unpaved roadways

• Preserve existing vegetation where no construction activities are berms, fiber rolls, sediment traps, erosion control blankets, check dams in medium-sized channels, or straw bale dikes in smaller drain channels

• Cover stockpiled soil

• Use dust suppressants, such as watering soils and unpaved roadways

• Preserve existing vegetation where no construction activities are planned and wherever possible

• Replant/revegetate all exposed disturbed areas with POM approved seed immediately upon completion of construction with POM approved plants

Following the completion of each Project or Concept located in an undeveloped area or on steep slopes but that disturbs less than one acre, post-construction BMPs and long-term maintenance plans shall be implemented.

Mitigation Measure GS-2:

Modified hillslopes associated with the Building 622 Parking Lot Bioswale Project shall be constructed to ensure stable post-construction conditions. Soil stabilization may include, but is not limited to:

Programmatic Environmental Assessment 23

Resource Impact Alternative 1, Proposed Action Alternative 2, No

Action Alternative 3, Full Implementation

Measures Incorporated into the Proposed Action

Mitigation Measures planned and wherever possible

• Replant/revegetate all exposed disturbed areas immediately upon completion of construction with POM approved plants.

Following the completion of each Construction Project that disturbs one acre or more, the site must meet the conditions for Termination of Coverage by certifying the site has been stabilized and there is no potential for construction-related stormwater discharges. On September 2, 2012, the new post-construction standards went into effect, and post-construction BMPs and long-term maintenance plans are required.

• Reinforcement measures, such as anchors or micropiles, to increase the shear strength of the hillslope

• Surface stabilization, such as shotcrete, to increase the surface strength of the hillslope

• Drainage mechanisms to reduce the water pressure in the vicinity of the hillslope and to prevent over-saturation of soils

• Geometry modifications to reduce the angle of the hillslope and minimize the potential for landslide

Long-term geology and soil impacts related to potential erosion and sedimentation

Beneficial Effect No Impact Beneficial Effect None identified. None identified.

Hazards and Hazardous Materials

Potential to generate or uncover hazardous materials through modifications to existing pipes (NP

Less than Significant No Impact Less than Significant Hazardous Materials Measure 1: Spill Contingency Plan. A spill contingency and containment plan would be prepared and implemented in the event that

None required.

24 Programmatic Environmental Assessment

Resource Impact Alternative 1, Proposed Action Alternative 2, No

Action Alternative 3, Full Implementation

Measures Incorporated into the Proposed Action

Mitigation Measures

Storage Tank Retrofit and some Concepts) or installation of a chlorine disinfection system (Concept 2).

hazardous materials are accidentally spilled during construction. Engineering controls that may be used during construction to protect water resources may include, but would not be limited to:

hay bales and silt fencing. In addition, inspection and monitoring for compliance with the permit requirements would be implemented.

Potential to encounter Munitions and Explosives of Concern (MEC)

Less than Significant No Impact Less than Significant Hazardous Materials Measure 2: In the event the that MEC is suspected or encountered, there shall be no attempt to disturb, remove, or destroy it, but shall cease any intrusive or ground-disturbing activities being conducted at the project and immediately notify the POM police or fire department so that appropriate personnel can be dispatched to address such MEC.

Land Use

None of the improvements would alter or conflict with existing land use.

No Impact No Impact No Impact None identified. None required.

Noise

Short-term adverse noise impacts

Less than Significant with Mitigation

No Impact Less than Significant with Mitigation

None identified. Mitigation Measure N-1: The following construction-related erika.r.marx.civ Highlight

Programmatic Environmental Assessment 25

Resource Impact Alternative 1, Proposed Action Alternative 2, No

Action Alternative 3, Full Implementation

Measures Incorporated into the Proposed Action

Mitigation Measures during construction would include noise from large equipment at each of the construction Projects and Concepts.

noise measures shall be implemented for all Projects and Concepts:

• The construction contractor shall ensure that all equipment has the manufacturers’ recommended noise abatement measures, such as mufflers, engine enclosures, and engine vibration isolators, intact and operational. Further, all construction equipment shall be inspected at periodic intervals to ensure proper maintenance and presence of noise control devices.

• Construction activities shall be limited to daytime hours (8:00 a.m. to 5:00 p.m.). In addition, the POM currently promotes quiet hours during the normal workweek for some Construction Projects.

This could include quiet hours between 6:00 a.m. and 10:00 a.m. on specific workdays, if requested by affected staff.

Local neighborhoods shall be notified of the project, and signage should be posted that provides a phone number to call to register complaints about construction-related noise problems.

Operational noise Less than Significant No Impact Less than Significant None identified. None required.

26 Programmatic Environmental Assessment

Resource Impact Alternative 1, Proposed Action Alternative 2, No

Action Alternative 3, Full Implementation

Measures Incorporated into the Proposed Action

Mitigation Measures would not be expected to measurably change from baseline conditions.

Public Health and Safety

Adverse effects to public health and safety could occur if treated greywater and stormwater does not meet appropriate water quality standards.

Less than Significant with Mitigation

No Impact Less than Significant with Mitigation

None identified. Mitigation Measure PHS-1:

Treated water shall meet the higher of NSF 350 or CA Title 22 standards (or most recent higher standard) for recycled water systems.

Utilities

The improvements to stormwater infrastructure on the POM would result in long-term benefits to both on-site and downstream stormwater facilities as the quantity of stormwater runoff would be reduced, which would reduce future demands on existing stormwater conveyance capacity.

Beneficial Effect No Impact Beneficial Effect None identified. None required.

Visual Resources

Short-term visual impacts during construction; no

Less than Significant No Impact Less than Significant None identified. None required.

Programmatic Environmental Assessment 27

Resource Impact Alternative 1, Proposed Action Alternative 2, No

Action Alternative 3, Full Implementation

Measures Incorporated into the Proposed Action

Mitigation Measures long-term adverse effects on visual resources.

Long term visual effects from bioswale projects and concepts would improve the visual character of the surrounding areas.

Beneficial Effect No Impact Beneficial Effect None identified. None identified.

Water Resources

Construction activities would result in ground disturbance that could lead to erosion and subsequent sedimentation of downstream waterbodies following a storm event.

Less than Significant with Mitigation

No Impact Less than Significant with Mitigation

Stormwater Measure 1:

Compliance with General Permit for Stormwater Discharges Associated with Construction and Land Disturbance Activities (Order No. 2010-0014-DWQ).

In compliance with the General Permit for Stormwater Discharges Associated with Construction and Land Disturbance Activities (Order No. 2012- 0006-DWQ), appropriate Best Management Practices (BMP) would be implemented during construction that would minimize impacts on water quality. BMPs may include, but would not be limited to:

scheduling construction to avoid the rainy season;

applying mulch, soil binders, or hydroseeding; installing earth dikes, berms, check

Mitigation Measure GS-1 (refer to Geology and Soils above)

28 Programmatic Environmental Assessment

Resource Impact Alternative 1, Proposed Action Alternative 2, No

Action Alternative 3, Full Implementation

Measures Incorporated into the Proposed Action

Mitigation Measures dams, straw bales, or other velocity dissipation devices;

protecting storm drain inlets with gravel bags, fiber bags, fiber rolls, or other filtration devices; stabilizing streambanks and hillslopes;

installing silt fences; installing sediment basins; or increasing the frequency of street sweeping.

Implementation of one or more of these BMPs or other similar BMPs would ensure that there is minimal suspended sediment in runoff that discharges into storm drains and eventually to the Monterey Bay. For Construction Projects and Concepts that would disturb more than one acre of land, a stormwater pollution prevention plan (SWPPP) and coverage under the California stormwater construction general permit would be required.

Adverse effects to water quality could occur if treated greywater and stormwater does not meet appropriate water quality standards.

Less than Significant with Mitigation

No Impact Less than Significant with Mitigation

None identified. Mitigation Measure PHS-1:

(refer to Public Health and Safety above).

Programmatic Environmental Assessment 29

Resource Impact Alternative 1, Proposed Action Alternative 2, No

Action Alternative 3, Full Implementation

Measures Incorporated into the Proposed Action

Mitigation Measures

Long-term benefits to water quality would occur through a reduction in the amount of runoff and biofiltration of stormwater runoff.

Beneficial Effect No Impact Beneficial Effect None required. None required.

Long-term benefits to water supply would occur through a reduction in potable water use.

Beneficial Effect No Impact Beneficial Effect None required. None required.