Attachment J Target Project Schedule
Hamilton City Phase 1 Revegetation Assumed Contract Award Date: 8/19/2016
Title
Start, Days from
Contract Award
Finish, Days from Contract Award D u ra ti o n
D ay s
Start Finish
Task 1 Pre Work Submittals
1 Schedule ‐ 31 31 8/19/16 9/19/16
2 Contractor Quality Control Plan ‐ 31 31 8/19/16 9/19/16
3 Environmental Protection Plan ‐ 31 31 8/19/16 9/19/16
4 Accident Prevention Plan ‐ 31 31 8/19/16 9/19/16
5 Performance Work Plan ‐ 45 45 8/19/16 10/3/16
6 Irrigation System Design ‐ 90 90 8/19/16 11/17/16
SWPPP And Associated Documentation ‐ 120 120 8/19/16 12/17/16
Task 2 Planting Development
8 Collect Propagules 31 211 180 9/19/16 3/18/17
9 Plant Propagation 60 278 218 10/18/16 5/24/17
10 Nursery Growing 60 254 194 10/18/16 4/30/17
Task 3 Pre‐Installation Weed Control
Pre Installation Weed Control Spraying 45 194 149 10/3/16 3/1/17
12 Pre‐Installation Mowing 45 194 149 10/3/16 3/1/17
13 Pre‐Installation Road Maintenance 45 194 149 10/3/16 3/1/17
Task 4 Planting Supplies
14 Irrigation Drip Line Procurement 136 376 240 1/2/17 8/30/17
15 Plant Location Flag Procurement 136 376 240 1/2/17 8/30/17
16 Browse Guard Procurement 136 376 240 1/2/17 8/30/17
17 Bamboo Stake Procurement 136 376 240 1/2/17 8/30/17
18 Native Grass Seed procurement 136 376 240 1/2/17 8/30/17
19 Nursery Growing 2017 255 619 364 5/1/17 4/30/18
Option Task 1 Site Prep
20 Facility Set Up 194 224 30 3/1/17 3/31/17
21 BMP Installation 194 424 230 3/1/17 10/17/17
NPDES Monitoring And Reporting And BMP Maintenance 194 376 182 3/1/17 8/30/17
Pre Installation Weed Control Spraying 194 527 333 3/1/17 1/28/18
24 Orchard Removal 194 254 60 3/1/17 4/30/17
Orchard Removal, Soil Disturbance Avoidance Area 194 254 60 3/1/17 4/30/17
26 Soil Prep 225 255 30 4/1/17 5/1/17
27 Road Maintenance 214 499 285 3/21/17 12/31/17
Water Elderberry Transplants 225 468 243 4/1/17 11/30/17
Weed Elderberry Transplants 166 499 333 2/1/17 12/31/17
Option Task 2 Installation
28 Develop Irrigation Water Source 269 301 32 5/15/17 6/16/17
Title
Start, Days from
Contract Award
Finish, Days from Contract Award D u ra ti o n
D
Installing Underground Irrigation Infrastructure 302 347 45 6/17/17 8/1/17
30 Planting Zone Layout 348 408 60 8/2/17 10/1/17
31 Installing Flexible Irrigation Lines 362 422 60 8/16/17 10/15/17
32 Planting Tile Layout 392 469 77 9/15/17 12/1/17
33 Planting Location Layout 422 530 108 10/15/17 1/31/18
34 Plant Delivery 559 619 60 3/1/18 4/30/18
35 Plant Deepot 40 Container Plants 559 619 60 3/1/18 4/30/18
36 Plant Treepot 4 Container Plants 559 619 60 3/1/18 4/30/18
37 Plant Treebands 559 619 60 3/1/18 4/30/18
Irrigation During The Installation Period 559 619 60 3/1/18 4/30/18
39 As Built Plans 603 633 30 4/14/18 5/14/18
Option Task 3 Establishment Season 1
Watering In The First Year Of Establishment 620 773 153 5/1/18 10/1/18
Weeding Of Plant Locations In The First Year Of Establishment 634 833 199 5/15/18 11/30/18
42 1st Herbicide Application, Rows, 531 545 14 2/1/18 2/15/18
43 2nd Herbicide Application, Rows, 620 651 31 5/1/18 6/1/18
44 3rd Herbicide Application, Rows 681 712 31 7/1/18 8/1/18
45 4th Herbicide Application, Rows 773 818 45 10/1/18 11/15/18
1st Herbicide Application, Middles, Grasslands 545 573 28 2/15/18 3/15/18
2nd Herbicide Application, Middles, Grasslands 620 634 14 5/1/18 5/15/18
Road Maintenance During First Establishment Year 500 864 364 1/1/18 12/31/18
49 Infrastructure Maintenance 500 864 364 1/1/18 12/31/18
NPDES Monitoring And Reporting And BMP Maintenance 500 864 364 1/1/18 12/31/18
51 Records And Reports 500 864 364 1/1/18 12/31/18
52 Water Elderberry Transplants 590 833 243 4/1/18 11/30/18
53 Weed Elderberry Transplants 531 833 302 2/1/18 11/30/18
Native Grass Seed Procurement, 2017 651 864 213 6/1/18 12/31/18
Option Task 4 Establishment Season 2
Watering In The Second Year Of Establishment 955 1,198 243 4/1/19 11/30/19
Weeding Of Plant Locations In The Second Year Of Establishment 955 1,198 243 4/1/19 11/30/19
Spot Spraying In The Second Year Of Establishment 1,091 1,137 46 8/15/19 9/30/19
58 1st Herbicide Application, Rows 896 938 42 2/1/19 3/15/19
Title
Start, Days from
Contract Award
Finish, Days from Contract Award D u ra ti o n
D
59 2nd Herbicide Application, Rows 1,016 1,046 30 6/1/19 7/1/19
60 3rd Herbicide Application, Rows 1,152 1,213 61 10/15/19 12/15/19
1st Herbicide Application, Middles, Grasslands 896 938 42 2/1/19 3/15/19
2nd Herbicide Application, Middles, Grasslands 1,016 1,046 30 6/1/19 7/1/19
Road Maintenance During The Second Establishment Year 865 1,229 364 1/1/19 12/31/19
Infrastructure Maintenance During The Second Year Of Establishment 865 1,229 364 1/1/19 12/31/19
NPDES Monitoring And Reporting And BMP Maintenance 865 1,229 364 1/1/19 12/31/19
66 Records And Reports 865 1,229 364 1/1/19 12/31/19
Water Elderberry Transplants 955 1,198 243 4/1/19 11/30/19
Weed Elderberry Transplants 865 1,229 364 1/1/19 12/31/19
Native Grass Seed Procurement, 2018 865 1,169 304 1/1/19 11/1/19
Option Task 5 Native Grass Installation
68 Pre‐Seeding Herbicide Application 1,169 1,244 75 11/1/19 1/15/20
2nd Pre‐Seeding Herbicide Application 1,183 1,260 77 11/15/19 1/31/20
70 Drill Seeding Native Grass Seed 1,183 1,260 77 11/15/19 1/31/20
Option Task 6 Establishment Season 3
Watering In The Third Year Of Establishment 1,321 1,535 214 4/1/20 11/1/20
Spot Spraying In The Third Year Of Establishment 1,321 1,535 214 4/1/20 11/1/20
73 1stHerbicideApplication,,Rows 1,290 1,304 14 3/1/20 3/15/20
Optional1stMowing,Middles,Grass lands 1,321 1,351 30 4/1/20 5/1/20
1stHerbicideApplication,Middles,G rasslands 1,290 1,304 14 3/1/20 3/15/20
2ndHerbicideApplication,Middles, Grasslands 1,351 1,365 14 5/1/20 5/15/20
77 Reseeding 804 864 60 11/1/18 12/31/18
Road maintenance during the Third Establishment Year 1,230 1,595 365 1/1/20 12/31/20
Infrastructure maintenance during the Third Establishment Year 1,230 1,595 365 1/1/20 12/31/20
NPDES monitoring and reporting and BMP maintenance 1,230 1,595 365 1/1/20 12/31/20
81 Well Abandonment 1,535 1,595 60 11/1/20 12/31/20
Title
Start, Days from
Contract Award
Finish, Days from Contract Award D u ra ti o n
D
82 Staging area removal 1,504 1,595 91 10/1/20 12/31/20
83 Site Clean up 1,504 1,595 91 10/1/20 12/31/20
84 Records and Reports 1,230 1,595 365 1/1/20 12/31/20