W911XK-10-B-0012-0005.pdf

PDF 37 KB Posted

Attached to
FY11 Sault Ste. Marie, MI - Replace Center Observation Deck and Security Fence
Solicitation number
W911XK-10-B-0012
Issued by

View the file

Other files

Show all 20

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

W56MES01758287

AMENDMENT OF SOLICITATION/MODIFICATION OF CONTRACT

Except as provided herein, all terms and conditions of the document referenced in Item 9A or 10A, as heretofore changed, remains unchanged and in full force and effect.

15A. NAME AND TITLE OF SIGNER (Type or print)

30-105-04EXCEPTION TO SF 30

APPROVED BY OIRM 11-84

STANDARD FORM 30 (Rev. 10-83) Prescribed by GSA

FAR (48 CFR) 53.243

FY10 Replace Soo Fence and Center Observation Platform

The purpose of this amendment is to ADD FAR Clause 52.217-7, incorporated in full text in Section 00700. Wage Determination MI4 dated 8/13/10 is DELETED and REPLACED w ith MI4 dated 9/3/10. There are no further changes.

1. CONTRACT ID CODE PAGE OF PAGES

J 1 14

16A. NAME AND TITLE OF CONTRACTING OFFICER (Type or print)

16C. DATE SIGNED

BY 07-Sep-2010

16B. UNITED STATES OF AMERICA15C. DATE SIGNED15B. CONTRACTOR/OFFEROR

(Signature of Contracting Officer)(Signature of person authorized to sign)

8. NAME AND ADDRESS OF CONTRACTOR (No., Street, County, State and Zip Code) X W911XK-10-B-0012

X 9B. DATED (SEE ITEM 11)

07-Aug-2010

10B. DATED (SEE ITEM 13)

9A. AMENDMENT OF SOLICITATION NO.

11. THIS ITEM ONLY APPLIES TO AMENDMENTS OF SOLICITATIONS

X The above numbered solicitation is amended as set forth in Item 14. The hour and date specified for receipt of Offer is extended, X is not extended.

Offer must acknowledge receipt of this amendment prior to the hour and date specified in the solicitation or as amended by one of the following methods:

(a) By completing Items 8 and 15, and returning copies of the amendment; (b) By acknowledging receipt of this amendment on each copy of the offer submitted;

or (c) By separate letter or telegram which includes a reference to the solicitation and amendment numbers. FAILURE OF YOUR ACKNOWLEDGMENT TO BE RECEIVED AT THE PLACE DESIGNATED FOR THE RECEIPT OF OFFERS PRIOR TO THE HOUR AND DATE SPECIFIED MAY RESULT IN

REJECTION OF YOUR OFFER. If by virtue of this amendment you desire to change an offer already submitted, such change may be made by telegram or letter, provided each telegram or letter makes reference to the solicitation and this amendment, and is received prior to the opening hour and date specified.

12. ACCOUNTING AND APPROPRIATION DATA (If required)

13. THIS ITEM APPLIES ONLY TO MODIFICATIONS OF CONTRACTS/ORDERS.

IT MODIFIES THE CONTRACT/ORDER NO. AS DESCRIBED IN ITEM 14.

A. THIS CHANGE ORDER IS ISSUED PURSUANT TO: (Specify authority) THE CHANGES SET FORTH IN ITEM 14 ARE MADE IN THE

CONTRACT ORDER NO. IN ITEM 10A.

B. THE ABOVE NUMBERED CONTRACT/ORDER IS MODIFIED TO REFLECT THE ADMINISTRATIVE CHANGES (such as changes in paying office, appropriation date, etc.) SET FORTH IN ITEM 14, PURSUANT TO THE AUTHORITY OF FAR 43.103(B).

C. THIS SUPPLEMENTAL AGREEMENT IS ENTERED INTO PURSUANT TO AUTHORITY OF:

D. OTHER (Specify type of modification and authority)

E. IMPORTANT: Contractor is not, is required to sign this document and return copies to the issuing office.

14. DESCRIPTION OF AMENDMENT/MODIFICATION (Organized by UCF section headings, including solicitation/contract subject matter where feasible.)

10A. MOD. OF CONTRACT/ORDER NO.

2. AMENDMENT/MODIFICATION NO. 5. PROJECT NO.(If applicable)

6. ISSUED BY

3. EFFECTIVE DATE

07-Sep-2010

CODE

CONTRACTING DIVISION

DETROIT DISTRICT

477 MICHIGAN AVE

RM 700

DETROIT MI 48226-2550

W911XK 7. ADMINISTERED BY (If other than item 6)

4. REQUISITION/PURCHASE REQ. NO.

CODE

See Item 6

FACILITY CODECODE

EMAIL:TEL:

W911XK-10-B-0012

SECTION SF 30 BLOCK 14 CONTINUATION PAGE

SUMMARY OF CHANGES

SECTION 00700 - CONTRACT CLAUSES

The following have been added by full text:

52.217-7 OPTION FOR INCREASED QUANTITY--SEPARATELY PRICED LINE ITEM (MAR 1989)

The Government may require the delivery of the numbered line item, identified in the Schedule as an option item, in the quantity and at the price stated in the Schedule. The Contracting Officer may exercise the option by written notice to the Contractor within 30 days after contract award. Delivery of added items shall continue at the same rate that like items are called for under the contract, unless the parties otherwise agree.

(End of clause)

SECTION 00800 - SPECIAL CONTRACT REQUIREMENTS

The following have been added by full text:

WAGE DET MI 4 UPDATED 9/3/2010

General Decision Number: MI100004 09/03/2010 MI4

Superseded General Decision Number: MI20080004

State: Michigan

Construction Type: Building

Counties: Alger, Chippewa, Delta, Dickinson, Luce, Mackinac, Marquette, Menominee and Schoolcraft Counties in Michigan.

BUILDING CONSTRUCTION PROJECTS (does not include residential construction consisting of single family homes and apartments up to and including 4 stories)

Modification Number Publication Date 0 03/12/2010 1 07/02/2010 2 08/06/2010 3 08/13/2010 4 09/03/2010

ASBE0047-001 07/01/2009

CHIPPEWA, LUCE AND MACKINAC COUNTIES:

Rates Fringes

ASBESTOS WORKER/INSULATOR

Includes the application of all insulating materials, protective coverings, coatings and finishings to all types of mechanical systems..........$ 28.42 15.41

ASBE0127-003 05/31/2009

ALGER, DELTA, DICKINSON, MARQUETTE, MENOMINEE AND SCHOOLCRAFT

COUNTIES:

ASBESTOS WORKER/HEAT & FROST

INSULATOR

Includes the application of all insulating materials; protective coverings, coatings, and finishings to all types of mechanical systems..........$ 27.54 19.38

BOIL0169-001 07/01/2008

Rates Fringes

BOILERMAKER......................$ 31.953 20.869

BRMI0006-001 05/01/2009

Rates Fringes

Bricklayer; plasterer;

marble, terrazzo and tile setter...........................$ 24.88 14.43

CEMENT MASON/CONCRETE FINISHER...$ 24.88 14.43

Pointer, caulker and cleaner.....$ 24.88 14.43

FOOTNOTES: Stacks: Work on industrial and powerhouse stacks shall receive $2.00 per hour above the journeyman bricklayer rate.Industrial: Refinishing work on digesters, tanks, lime kilns, chests, boilers, and boiler tubes shall receive $2.00 per hour above the journeyman bricklayer rate.

CARP1510-001 05/01/2009

ALGER, CHIPPEWA, DELTA, DICKINSON, LUCE, MACKINAC AND MARQUETTE

COUNTIES; MENOMINEE COUNTY (except for that part south of County Road K at Amberg, Wisconsin, starting on the west at the Menominee River and ending on the east at the Bay of Green

Bay); AND SCHOOLCRAFT COUNTIES:

CARPENTER (Includes concrete forms; Does not include drywall finisher)

DRYWALL HANGER; SOFT FLOOR

LAYER.......................$ 26.27 12.18

MILLWRIGHT.......................$ 30.78 12.40

Piledriver.......................$ 26.47 12.18

FOOTNOTES:

Waterfront work on the Great Lakes or connecting water navigable to Lake carriers: $0.20 per hour additional.

Work on industrial construction, defined as industrial manufacturing and processing plants such as ore plants, paper mills, power houses, foundries, saw mills, wood processing plants, or other industrial complexes: $.25 per hour additional.

ELEC0158-001 06/02/2008

MENOMINEE COUNTY (Townships of Ingallston, Melon and Menominee)

Rates Fringes

ELECTRICIAN......................$ 27.27 7.62+26.25%

FOOTNOTE: Work 40 or more ft. above the floor or ground, if not working on approved equipment, for the time when work is performed; also, work in tunnels under construction and where gas accumulaton rquires the use of protective equipmnet: 20% of the regular straight time rate of pay, additional.

ELEC0219-001 05/31/2010

DICKINSON COUNTY:

Rates Fringes

ELECTRICIAN (Does not include low-voltage work) Electrical contracts of $90,000 or less.............$ 26.24 16.59 Electrical Contracts over $90,000.....................$ 28.44 16.65

FOOTNOTES: All industrial work over 30 ft. above the ground, unless on solid flooring or grating permanently attached in place: 10% per hour additional.Over 60 ft.: 20% per hour additional.Over 90 ft.: 30% per hour additional.Work performed within 3 ft. of an unguarded opening at the above-mentioned heights to receive the above-mentioned premiums.Work in underground mines, except mine shaft work:

10% per hour additional.

ELEC0979-001 06/01/2009

DELTA COUNTY; MENOMINEE COUNTY (does not include the townships of Ingallston, Melon and Menominee); AND SCHOOLCRAFT COUNTY:

ELECTRICIAN......................$ 29.69 13.45+4%

FOOTNOTES: Work on chimneys, stacks, or towers where the worker is required to work at a distance of twenty-five

(25) feet but less than fifty (50) feet from the ground or floor to the working area (catwalks are not to be considered as a permanent floor): 10% additional.Work as defined above over fifty (50) feet but less than seventy-five (75) feet from the ground or floor: 20% additional.Work as defined above over seventy-five (75) feet but less than one hundred (100) feet from the ground or floor: 30% additional.Work as defined above over one hundred (100 feet from the ground or floor: to be paid at the double time rate.

ELEC1070-002 06/01/2009

Rates Fringes

ELECTRICIAN

Contracts $130,000 and under.......................$ 27.33 15.99+1% Contracts over $130,000.....$ 29.33 16.05+1%

ELEV0085-005 01/01/2010

Rates Fringes

ELEVATOR MECHANIC................$ 42.73 20.035

FOOTNOTE: Vacation Pay: 8% with 5 or more years of service, 6% for 6 months to 5 years service. Paid Holidays: New Years Day, Memorial Day, Independence Day, Labor Day, Veterans Day,Thanksgiving Day and Friday after, and Christmas Day.

ENGI0324-009 05/01/2010

Rates Fringes

OPERATOR: Power Equipment (Including underground work) Crane operator, main boom & jib 120' or longer........$ 26.78 18.65

Crane operator, main boom & jib 140' or longer........$ 27.03 18.65 Crane operator, main boom & jib 220' or longer........$ 27.28 18.65

GROUP 1.....................$ 26.28 18.65

GROUP 2.....................$ 23.03 18.65

GROUP 3.....................$ 22.45 18.65

GROUP 4.....................$ 21.51 18.65

Mechanic with truck and tools.......................$ 27.78 18.65

FOOTNOTES: Swing boom truck operator over 15 tons:$.50 per hour additional. Hydraulic crane operator 75 tons and under:$.75 per hour additional. Hydraulic crane operator over 75 tons:$1.00 per hour additional. Lattice boom crane operator:$1.50 per hour additional. Crusher pits, shafts and tunnel workers:$2.00 per hour additional. Premium rate:

main boom and jib 300 feet or longer is $1.50 per hour above the 220 ft. boom and jib rate. Premium rate: main boom and jib 400 feet or longer is $3.00 per hour above the 220 ft. boom and jib rate.

POWER EQUIPMENT OPERATOR CLASSIFICATIONS

GROUP 1: Regular equipment operator , backhoe, crane, dozer, front end loader, job mechanic, pumpcrete and squeezecrete, welder, concrete pump, excavator, milling and pulverizing machines,scraper (self-propelled and tractor drawn), welder

GROUP 2: Air track drill, boom truck (non-swing), concrete mixer, material hoist and tugger, pump 6" and over, beltcrete, sweeping machine, trencher, winches, well points and freeze systems

GROUP 3: Air compressor, conveyor, concrete saw, farm tractor (without attachments), fork truck, generator, guard post driver, mulching machine, pumps under 6-in., welding machine and grease person

GROUP 4: Oiler, fire tender, heater operator, brock concrete breaker, elevators (other than passenger), end dumps and skid steer.

Crane Operator with main boom and jib 300' or longer shall be paid an additional one dollar and fifty cents ($1.50) per hour above the 220' of boom and jib wage rate.

Crane Operator with main boom and jib 400' or longer shall be paid an additional one dollar and fifty cents ($1.50) per hour above the 300 foot of boom wage rate ($3.00)

ENGI0325-006 10/01/2009

ALGER, BARAGA, CHIPPEWA, DELTA, DICKINSON, GOGEBIC, HOUGHTON,

IRON, KEWEENAW, LUCE, MACKINAC, MARQUETTE, MENOMINEE,

ONTONAGON, SCHOOLCRAFT

Power equipment operators -hazardous waste removal:

LEVEL A:

Crane operator, mechanic, dragline operator, boom truck operator and concrete pump with boom operator, power shovel operator...................$ 31.09 17.80 Engineer when operating crane with boom and jib or leads 140' or longer....$ 32.77 17.80 Engineer when operating crane with boom and jib or leads 220' or longer....$ 33.07 17.80

GROUP 1....................$ 30.12 17.80

GROUP 2....................$ 25.72 17.80

LEVEL B AND C:

Crane operator, mechanic, dragline operator, boom truck operator and concrete pump with boom operator, power shovel operators..................$ 30.14 17.80 Engineer when operating crane with boom and jib or leads 140' or longer....$ 31.71 17.80 Engineer when operating crane with boom and jib or leads 220' or longer....$ 32.03 17.80

GROUP 1....................$ 29.17 17.80

GROUP 2....................$ 24.78 17.80

LEVEL D WHEN CAPPING

LANDFILL:

Crane operator, mechanic, dragline operator, boom truck operator and concrete pump with boom operator, power shovel operators..................$ 28.59 17.80 Engineer when operating crane with boom and jib or leads 140' or longer....$ 30.27 17.80 Engineer when operating crane with boom and jib or leads 220' or longer....$ 30.57 17.80

GROUP 1....................$ 27.62 17.80

GROUP 2....................$ 23.23 17.80

LEVEL D:

Crane operator, mechanic, dragline operator, boom truck operator and concrete pump with boom operator, power shovel operators..................$ 28.84 17.80 Engineer when operating crane with boom and jib or leads 140' or longer....$ 30.52 17.80 Engineer when operating crane with boom and jib or leads 220' or longer....$ 30.82 17.80

GROUP 1....................$ 27.87 17.80

GROUP 2....................$ 23.48 17.80

HAZARDOUS WASTE REMOVAL CLASSIFICATIONS

GROUP 1: Backhoe, batch plant operator, clamshell, concrete breaker when attached to hoe, concrete cleaning decontamination machine operator, concrete pump, concrete paver, crusher, dozer, elevating grader, endloader, farm tractor (90 h.p. and higher), gradall, grader, heavy equipment robotics operator, loader, pug mill, pumpcrete machines, pump trucks, roller, scraper (self- propelled or tractor drawn), side boom tractor, slip form paver, slop paver, trencher, ultra high pressure waterjet cutting tool system operator, vactors, vacuum blasting machine operator, vertical lifting hoist, vibrating compaction equipment (self-propelled), well drilling rig, slope paver, hydro excavator

GROUP 2: Air compressor, concrete breaker when not attached to hoe, elevator, end dumps, equipment decontamination operator, farm tractor (less than 90 h.p), forklift, generator, heater, mulcher, pigs (portable reagent storage tanks), power screens, pumps (water), stationary compressed air plant, sweeper, welding machine and water wagon

ENGI0326-019 05/01/2010

Rates Fringes

OPERATOR: Power Equipment (Steel Erection) Compressor, welder and forklift....................$ 23.43 18.65 Crane operator, main boom & jib 120' or longer........$ 27.18 18.65 Crane operator, main boom & jib 140' or longer........$ 27.43 18.65 Crane operator, main boom & jib 220' or longer........$ 27.68 18.65 Mechanic with truck and tools.......................$ 28.18 18.65 Oiler and fireman...........$ 22.13 18.65 Operator....................$ 26.68 18.65

Crane Operator with main boom and jib 300' or longer shall be paid an additional one dollar and fifty cents ($1.50) per hour above the 220' of boom and jib wage rate.

Crane Operator with main boom and jib 400' or longer shall be paid an additional one dollar and fifty cents ($1.50) per hour above the 300 foot of boom wage rate ($3.00)

* IRON0008-008 06/07/2010

Rates Fringes

Ironworker - pre-engineered metal building erector...........$ 23.70 6.95

IRONWORKER

Contracts $10,000,000 or greater.....................$ 24.93 21.47 Contracts less than $10,000,000.................$ 21.84 21.47

LABO0005-004 10/01/2008

Rates Fringes

Laborers - hazardous waste abatement:

Work performed inside the building and up to and including 5 ft. outside the building:

Level A, B or C............$ 22.18 10.35 Work performed in conjunction with site preparation not requiring the use of personal protective equipment;

Also, Level D..............$ 21.18 10.35 Work performed over 5 ft.

outside the building:

Work performed in conjunction with site preparation not requiring the use of personal protective equipment;

Also, Level D..............$ 19.44 9.80 Level A, B or C............$ 20.44 9.80

LABO0259-009 08/01/2010

Rates Fringes

Asbestos Laborer Includes removing and disposing of all insulation materials from walls, ceilings, floors, columns, and all other non-mechanical surfaces; and removal of insulating materials from mechanical systems that are to be demolished;

loading/unloading of bagged and tagged materials at the disposal site (includes lead paint abatement clean-up).........$ 25.09 11.94

LABO0334-013 07/01/2010

Rates Fringes

Landscape Laborer

GROUP 1.....................$ 19.08 6.25

GROUP 2.....................$ 14.88 6.25

LANDSCAPE LABORER CLASSIFICATIONS

GROUP 1: Landscape specialist, including air, gas and diesel equipment operator and lawn sprinkler installer

GROUP 2: Landscape laborer: small power tool operator, material mover, truck driver and lawn sprinkler installer tender

LABO1329-001 05/01/2010

Rates Fringes

Laborers:

Commercial Construction

GROUP 1....................$ 19.58 11.54

GROUP 2....................$ 19.98 11.54

GROUP 3....................$ 20.33 11.54

GROUP 4....................$ 17.63 11.54

GROUP 5....................$ 21.63 11.54

Industrial Construction

GROUP 1....................$ 21.24 11.54

GROUP 2....................$ 21.64 11.54

GROUP 3....................$ 21.99 11.54

GROUP 4....................$ 17.83 11.54

GROUP 5....................$ 23.29 11.54

FOOTNOTE: Work on waterfront work (working over water) on the Great Lakes or connecting waters navigable to lake carriers: $0.75 per hour additional.

LABORER CLASSIFICATIONS

GROUP 1: All construction laborers on building and heavy construction work, storm and sanitary sewers, tool crib attendant, rodman, oxi-gun operator, workers using propane or acetylene cutting torch, motor-driven buggies, chipping hammers, tamping machines, green cutting (whether run by air, electric or gas), sandblasters, mason tenders, Mortar mixer, material mixer (whether done by hand or machine), vibrator operator, concrete mixer, laborer with concrete crew, mixer to pour, including pour from trucks

GROUP 2: Cement gun nozzle operator, blaster, miner, driller, buster operator, layer of all non-metallic pipe

GROUP 3: Caisson worker and airtrack

GROUP 4: Watchman, Fire watch and Hole watch

GROUP 5: Digester, tanks & kilns

PAIN1011-001 06/01/2010

Rates Fringes

Drywall Finisher and foam applicator.......................$ 25.78 9.17

PAINTER

Work on iron ore processing plants, water tanks, petroleum tanks, chemical tanks or vessels, towers, bridges, radio and television towers, church steeples, blast furnaces, smoke stacks, flag poles, aircraft hangers, power plants, heating plants, water treatment plants and buildings affixed to or included in an industrial complex and paper mills.....$ 19.61 8.92 Work on multiple housing units and all housing units over 4 stories, offices, stores , banks, commercial garages, gas stations, restaurants, motels, hotels, theaters, depots, churches, commercial warehouses, marinas, schools, dormatories, funeral homes and all other like structures..................$ 14.02 8.92

FOOTNOTES: High pay (bridges, overpasses, watertowers): 30 to 80 ft.: $.65 per hour additional. 80 ft. and over: $1.30 per hour additional.

PLUM0111-002 07/01/2010

PLUMBER/PIPEFITTER (Includes HVAC piping).....................$ 29.49 19.12

FOOTNOTES: Welders working on Chrome Moly or PP Stamp work:

$.50 per hour additional. Workers working in a confined space as defined in Title 29 Code of Federal Regulations 1910.146, and required to wear a selfcontained breathing apparatus: $1.00 per hour additional. Workers working with or around hazardous materials as specified in Title 29 Code of Federal Regulations 1926.62, and required to wear protective rubber gloves, boots and a self contained breathing apparatus or a complete hazardous materials protective bodysuit (Level B or more protective): $1.00 per hour additional.

ROOF0149-014 05/01/2009

Rates Fringes

ROOFER, Including Built Up, Composition and Single Ply Roofs............................$ 16.16 9.65 Slater...........................$ 18.31 9.65

SFMI0669-005 04/01/2010

Rates Fringes

SPRINKLER FITTER.................$ 30.96 16.35

SHEE0007-006 06/01/2008

Rates Fringes

SHEET METAL WORKER (Includes HVAC duct work)..................$ 27.96 17.04

SUMI2001-001 08/10/2001

Rates Fringes

Power Equipment Operator

EXCAVATOR...................$ 17.62 3.28

TEAM0328-001 05/01/2003

Rates Fringes

TRUCK DRIVER

GROUP 1.....................$ 19.62 3.76/hr.+ a GROUP 2.....................$ 19.77 3.76/hr.+ a GROUP 3.....................$ 19.83 3.76/hr.+ a GROUP 4.....................$ 19.98 3.76/hr.+ a

FOOTNOTE:

a. $17.80 per day

PAID HOLIDAYS: Memorial Day, Fourth of July, Labor Day and Thanksgiving Day, if the regular work day immediately preceding or following the holiday is either worked or an excused absence.

TRUCK DRIVER CLASSIFICATIONS

GROUP 1: All other trucks

GROUP 2: Heavy duty, double axle and semi trucks

GROUP 3: Truck repair and maintenance

GROUP 4: Euclid type equipment

WELDERS - Receive rate prescribed for craft performing operation to which welding is incidental.

Unlisted classifications needed for work not included within the scope of the classifications listed may be added after award only as provided in the labor standards contract clauses (29CFR 5.5 (a) (1) (ii)).

In the listing above, the "SU" designation means that rates listed under the identifier do not reflect collectively bargained wage and fringe benefit rates. Other designations indicate unions whose rates have been determined to be prevailing.

WAGE DETERMINATION APPEALS PROCESS

1.) Has there been an initial decision in the matter? This can be:

* an existing published wage determination

* a survey underlying a wage determination

* a Wage and Hour Division letter setting forth a position on a wage determination matter

* a conformance (additional classification and rate) ruling

On survey related matters, initial contact, including requests for summaries of surveys, should be with the Wage and Hour Regional Office for the area in which the survey was conducted because those Regional Offices have responsibility for the Davis-Bacon survey program. If the response from this initial contact is not satisfactory, then the process described in 2.)

and 3.) should be followed.

With regard to any other matter not yet ripe for the formal process described here, initial contact should be with the Branch of Construction Wage Determinations. Write to:

Branch of Construction Wage Determinations Wage and Hour Division U.S. Department of Labor 200 Constitution Avenue, N.W.

Washington, DC 20210

2.) If the answer to the question in 1.) is yes, then an interested party (those affected by the action) can request review and reconsideration from the Wage and Hour Administrator (See 29 CFR Part 1.8 and 29 CFR Part 7). Write to:

Wage and Hour Administrator U.S. Department of Labor 200 Constitution Avenue, N.W.

Washington, DC 20210

The request should be accompanied by a full statement of the interested party's position and by any information (wage payment data, project description, area practice material, etc.) that the requestor considers relevant to the issue.

3.) If the decision of the Administrator is not favorable, an interested party may appeal directly to the Administrative Review Board (formerly the Wage Appeals Board). Write to:

Administrative Review Board U.S. Department of Labor 200 Constitution Avenue, N.W.

Washington, DC 20210

4.) All decisions by the Administrative Review Board are final.

END OF GENERAL DECISION

The following have been deleted:

WAGE DET MI 4

(End of Summary of Changes)

File details come from the government source that posted it. Updated .