W911QY19R0010, Attachment 5 Building 1, Cafeteria Expansion
INSPECTION LOG 15 MAR 2019
# Inspection item Scheduled
Date Review Date
Comments Open Closed COR
COR/COTR
Electrical Mechanical
Wall framing Fire stopping
Removal of old material to source Panels Conduit Outlets
Removal of old material to source New piping and venting
Design of new Fire Alarm Wiring, connections
Removal of old material to source Panels Conduit Outlets
Removal of old material to source New piping and venting
FINAL ELECTRICAL
FINAL PLUMBING
DEMOLITION ‐ Review at completion
ROUGH FIRE PROTECTION / ALARM
ROUGH FRAMING
ROUGH ELECTRICAL
ROUGH PLUMBING
Contract #W911QY Building 1, Cafeteria Expansion
INSPECTION LOG 20‐Dec‐18
Removal of old material to source Mounting of equipment
Final device and system testing
FINAL HVAC
FINAL FIRE PROTECTION / ALARM