W16H1F210301EM PR 77716732 Statement of Work SOW.docx

DOCX document 34 KB Posted

Attached to
SPANCO CRANE RAILS & WELD JIBS
Solicitation number
W911PT-22-Q-0041
Issued by

View the file

Other files

File Type Posted
W16H1F210301E5 PR 77716463 Statement of Work SOW.docx DOCX document
W911PT-22-Q-0041-U00001.pdf PDF
PR 73007674 W16H1F11170048 Statement of Work SOW.docx DOCX document
W911PT-22-Q-0041.pdf PDF
WD 15-4143 rev 20.txt TXT text file
W911PT-22-Q-0041.pdf PDF
75409180 (SOW).docx DOCX document

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

STATEMENT OF WORK (SOW)

FOR

INSTALL ANTI-COLLISON SYSTEM ON THREE (3) CRANES BLDG 135

AT

Watervliet Arsenal Building 135

W16H1F210301EM / PR 77716732

Support Division (TAWV-ODR)

PART 1 GENERAL

1.01 Overview.

A. This Statement of Work (SOW) defines the effort required for the Installation of anti-collision systems provided by the Watervliet Arsenal on three (3) cranes (B109, B271 & B330) in bldg. 135

1.02 Hours of Operation.

1.03 General Requirements.

A. Work will be performed at the Watervliet arsenal facility, bldg. 135.

B. The contractor shall supply all tools, materials, supplies, equipment, labor, temporary utilities and supervision necessary for the complete execution of the requirements within the contract documents and requirements of this SOW.

C. The contractor shall, prior to submitting a proposal, review (i) all contract documents, and (ii) the project work site, and shall provide written notice to Contracting Specialist detailing any discrepancies that are found between the contract documents and the project work site.

1.04 Safety Requirements.

1.05 Period of Performance.

A. The contractor shall be required to (i) commence work under this contract within 7 calendar days after the date the contractor receives notice to proceed, (ii) prosecute the work diligently, and (iii) complete the entire work ready for use not later than [30] calendar days after notice to proceed was given. The time stated for completion shall include final cleanup of the premises.

1.06 Project Schedule.

1.07 Permits.

1.08 Equipment Identification.

1.09 Applicable Documents.

1.010 Submittals.

PART 2 PRODUCTS

2.01 General.

PART 3 ITEMS OF WORK

A. General.

The contractor shall coordinate with WVA personnel to gain access

Install anti-collision systems provided by WVA on three cranes B109, B271 and B330 located in Bldg 135

1. Install four (4) Magnetek LG2-H-4-25 Laserguard Systems on referenced cranes per manufacturer’s installation instructions.

1. Two (2) to be installed on B330 and one (1) each to be installed on B109 and B271

1. Settings for distance and slow down directions will be determined at time of installation.

1. Equipment furnished shall, except as otherwise noted, comply in all respects with the requirements of the following standards:

*CMAACrane Manufacturer’s Association of America
Specifications for Top Running Bridge & Gantry Type Multiple

Girder Electric Overhead Traveling Cranes - No. 70 (2010)

*ANSI/ASME

American National Standards Institute/American Society of Mechanical Engineers ANSI/ASME B30.2 - 201 Overhead and Gantry Cranes (Top Running Bridge, Single or Multiple Girder, Top Running Trolley Hoist) OSHA Occupational Safety and Health Administration Part 1910.179 – Overhead and Gantry Cranes

NEMANational Electric Manufacturer’s Association
NECNational Electric Code – 2014

*Compliance to this standard is limited to the extent such standard is incorporated into and made mandatory by OSHA regulations.

WARRANTY

Upon final acceptance of the systems, a Standard Commercial Warranty shall commence for duration of One Year, to include as a minimum, parts and labor for the duration of the warranty, at no cost to the Government. The one year period shall commence from the date of notification by the Contracting Officer of the final acceptance. Final acceptance is defined as the act of an authorized representative of the Government, by which the Government assumes ownership of existing supplies/equipment and/or approves specific services rendered, as partial or complete performance of the contract (i.e. testing, training, and delivery of all required technical documentation).

PART 1 CLOSEOUT REQUIREMENTS

1.01 Cleanup of Work Site.

1.02 Final Repairs and Restoration to Work Site.

PART 2 APPENDICES

A. Consolidated List of Submittals B. Quality Assurance Surveillance Plan (QASP)

APPENDIX A: Consolidated List of Submittals

Line
Item Submitted
Submittal Needed By
Submittal Reviewed By (Office)
1
Safety Data Sheets for Hazardous Materials (SDS)
NLT 7 Calendar Days After Award
Safety Office
2
Signed Contractor Asbestos Notification Form
NLT 7 Calendar Days After Award
Environmental Office
3
Signed Lockout/Tagout (LOTO) Notification Acknowledgement Record
NLT 7 Calendar Days After Award
Safety Office
4
Project Schedule
NLT 7 Calendar Days After Award
COR
5
Contractor Safety Plan (1.05.A.)
NLT 7 Calendar Days After Award
COR

APPENDIX B: Quality Assurance Surveillance Plan (QASP)

PURPOSE

This Quality Assurance Surveillance Plan (QASP) will be used as a guide to Government Quality Assurance Personnel (QAP). It provides a systematic method to evaluate the services the contractor is required to furnish.

SURVEILLANCE PROCEDURES

Timeliness: Progress is maintained to assure compliance with completion time.

Quality: Conformance with statement of work and industry standards.

Tasks: Performed according to statement of work requirements.

Problem Resolution: Contractor submits deliverables in accordance with the contract and resolves any deficiencies identified by the government in the final submission. Following final submission, contractor resolves any additional deficiencies identified by the government and resubmits and or corrects within one week.

Delivery: Contractor submits each deliverable in accordance with the statement of work and terms of the contract.

PERFORMANCE AREAS

Management Responsiveness: Evaluate the adequacy of the contractor’s responsiveness and their ability to keep the government informed of work progress and provides for early problem identification and effective corrective action plans.

Schedule Control: Evaluate the contractor’s adherence to completion schedule.

Performance: The contractor will be evaluated as to the workmanship and adherence to the statement of work.

EVALUATION CRITERIA

(Outstanding). Indicates performance clearly exceeds contractual requirements. The area of evaluation contains few minor problems for which corrective actions appear highly effective.

(Satisfactory). Indicates performance clearly meets contractual requirements. The area of evaluation contains some minor problems for which the corrective actions appear satisfactory.

(Unsatisfactory). Indicates the contractor failed to satisfy contractual requirements and recovery is not likely in a timely manner. The area of evaluation contains serious problems for which the corrective actions were ineffective.

DOCUMENTATION

Documentation used to perform surveillance will consist of random government inspections and inspection records, as well as the evaluation of final work product delivery by the project COR/COTR.

RATING

Contractor will be given an overall rating of Outstanding, Satisfactory, or Unsatisfactory by the Government Technical point of contact or Contracting Specialist Representative, if appointed, 3 using the above evaluation criteria.