PR 73007674 W16H1F11170048 Statement of Work SOW.docx
DOCX document 42 KB Posted
- Attached to
- SPANCO CRANE RAILS & WELD JIBS Federal contract opportunity
- Solicitation number
- W911PT-22-Q-0041
View the file
Other files for this federal contract opportunity
| File | Type | Posted |
|---|---|---|
| W911PT-22-Q-0041-U00001.pdf | ||
| W16H1F210301E5 PR 77716463 Statement of Work SOW.docx | DOCX document | |
| W16H1F210301EM PR 77716732 Statement of Work SOW.docx | DOCX document | |
| W911PT-22-Q-0041.pdf | ||
| WD 15-4143 rev 20.txt | TXT text file | |
| 75409180 (SOW).docx | DOCX document | |
| W911PT-22-Q-0041.pdf |
On GovTribe
Work with this file on GovTribe
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
STATEMENT OF WORK (SOW)
FOR
WELD STOPS ON FIVE (5) JIBS AND PEDESTAL CRANES
AT
Watervliet Arsenal Buildings 35 and 110
PR 73007674 / W16H1F11170048
Manufacturing Support Division
(TAWV-ODR)
PART 1 GENERAL
1.01 Overview.
A. This Statement of Work (SOW) defines the effort required to Weld stops on five (5) Jibs and Pedestal Cranes.
1.02 Hours of Operation.
A. Normal duty hours are 7:00 AM through 4:00 PM, Monday through Thursday, and 7:00 AM through 3:00 PM on select Fridays (the arsenal is closed every-other Friday). Federal holidays are non-work days. If a federal holiday falls on a Saturday or Sunday, the preceding Friday or following Monday is a work holiday.
1.03 General Requirements.
A. The contractor shall perform all work in strict conformance with Watervliet Arsenal Instructions for Contractors (WAIC). The contractor shall read and understand this document prior to submitting a proposal. The WAIC is publically available at:
http://www.wva.army.mil/Documents/Contracting/WAIC.pdf B. The contractor shall supply all tools, materials, supplies, equipment, labor, temporary utilities and supervision necessary for the complete execution of the requirements within the contract documents and requirements of this SOW.
C. The contractor shall, prior to submitting a proposal, review (i) all contract documents, and (ii) the project work site, and shall provide written notice to Contracting Specialist detailing any discrepancies that are found between the contract documents and the project work site.
D. The contractor shall notify the Contracting Specialist a minimum of two (2) business days before the contractor starts work. The contractor shall notify the COR a minimum of seven (7) business days before the shutdown of a utility or building service.
E. The contactor shall clean all work areas, at the end of each workday, to remove all tools, equipment, debris, materials and all waste from the work site.
F. The COR will update the CMRA.
1.04 Safety Requirements.
A. General.
1. The contractor shall be responsible for complying with all DOD, Army, Federal and State health and safety requirements that are applicable to this project, and shall use all means and precautions available to ensure the safety of the occupants and protection to the existing buildings and structures.
B. Existing Conditions.
1. The contractor shall inspect the project work site prior to starting work, and shall request a copy of the asbestos building inspection records to verify the location and description of known asbestos-containing materials. The contractor shall sign the “Asbestos Notification Acknowledgement Record” and submit this form to the Project COR prior to starting project work.
C. Contractor Safety Plan.
1. The contractor shall submit a safety plan, which is specific to the work activity being performed under the scope of this project for Government review and approval.
1.05 Period of Performance.
A. The contractor shall be required to (i) commence work under this contract within 7 calendar days after the date the contractor receives notice to proceed, (ii) prosecute the work diligently, and (iii) complete the entire work ready for use not later than [30] calendar days after notice to proceed was given. The time stated for completion shall include final cleanup of the premises.
1.06 Project Schedule.
A. The contractor shall create a project schedule and submit for Government review and approval. The project schedule shall detail the phases of work and the overall timeline for the execution of the work. The contractor shall include delivery dates, appropriate milestones, and shall clearly detail any requirements for work performed outside of regular hours of operation.
1.07 Permits.
A. The Contractor shall obtain the following WVA Permits from the Contracting Officer’s Representative (COR), IAW the Watervliet Arsenal Information for Contractors (WAIC). The Project COR will provide the Permit forms and the direction necessary to complete each Permit.
1. Hot Work (Flame) Permit
1.08 Equipment Identification.
A. The contractor shall create and affix a label to all large equipment, dumpsters, and other mobilized property, which is weather-resistant (laminated, or within a see-thru label hanger), securely affixed to the equipment or visible through a window, and which clearly displays the General Contractor’s:
1. Company name
2. POC name (first, last)
3. POC phone number
4. Project Number (see title page of SOW)
1.09 Applicable Documents.
A. Watervliet Arsenal Instructions for Contractors (WAIC).
B. NFPA 70 – National Electric Code (NEC).
1. (2014; AMD 1 2013; Errata 1 2013; AMD 2 2013; Errata 2 2013; AMD 3 2014; Errata 3-4 2014; AMD 4-6 2014).
C. UFGS Section 22 00 00 – Plumbing
1.010 Submittals.
A. The contractor shall e-mail all submittals to the Contracting Specialist for review and approval. All submittals require government approval unless otherwise explicitly stated.
B. The contractor shall reference APPENDIX A “Consolidated List of Submittals” for complete list of required submittals.
PART 2 PRODUCTS
2.01 General.
A. Unless otherwise stated, all materials for this project shall be new. All products shall not contain any asbestos, mercury, chromium/lead paint, Class I Freon and Polychlorinated Biphenyls (PCB), and shall state such on the manufacturer’s original packaging.
B. All work shall be in strict accordance with product manufacturer’s instructions and specifications, including but not limited to manufacturer guidance for storage, staging, application, installation and disposal of the product.
C. All construction materials shall meet the applicable requirements of the DoD Green Procurement Program, specifically recycled content products, environmentally preferable products and services, biobased products, energy-and water-efficient products, alternate fuel vehicles and alternative fuels, products using renewable energy, and alternatives to hazardous or toxic chemicals as found at <http://www.acq.osd.mil/dpap/cpic/cp/docs/USA001967-08-DPAP.pdf>.
2.02 Products and Materials.
A. N/A
PART 3 ITEMS OF WORK
A. General.
Weld stops on five (5) Jibs and Pedestal Cranes.
1. Two (2) stops on Jib J165. One (1) stop on Jib J435. One (1) stop on Pedestal JP330. One (1) stop on Pedestal JP460 and One (1) stop on Pedestal JP130.
PART 4 CLOSEOUT REQUIREMENTS
4.01 Cleanup of Work Site.
A. The contactor shall clean all work areas and remove all tools, equipment, debris, materials and all waste from the premises.
B. The contractor shall remove all debris from any remote holding locations, to include any excavation and concrete equipment chute cleanout debris.
C. The contractor shall remove their equipment from Watervliet Arsenal premises within five (5) working days after completion of project work.
4.02 Final Repairs and Restoration to Work Site.
A. The contractor shall repair any items, building surfaces, equipment or miscellaneous items which were damaged during the execution of this SOW.
PART 5 APPENDICES
A. Consolidated List of Submittals B. Quality Assurance Surveillance Plan (QASP)
APPENDIX A: Consolidated List of Submittals
| Line |
| Item Submitted |
| Submittal Needed By |
| Submittal Reviewed By (Office) |
| 1 |
| Safety Data Sheets for Hazardous Materials (SDS) |
| NLT 7 Calendar Days After Award |
| Safety Office |
| 2 |
| Signed Contractor Asbestos Notification Form |
| NLT 7 Calendar Days After Award |
| Environmental Office |
| 3 |
| Signed Lockout/Tagout (LOTO) Notification Acknowledgement Record |
| NLT 7 Calendar Days After Award |
| Safety Office |
| 4 |
| Project Schedule |
| NLT 7 Calendar Days After Award |
| COR |
| 5 |
| Contractor Safety Plan (1.05.A.) |
| NLT 7 Calendar Days After Award |
| COR |
| 6 |
| Coupling Product Data |
| NLT 7 Calendar Days After Award |
| COR |
| 7 |
| Reducing Tee Product Data |
| NLT 7 Calendar Days After Project Commencement |
| COR |
APPENDIX B: Quality Assurance Surveillance Plan (QASP)
PURPOSE
This Quality Assurance Surveillance Plan (QASP) will be used as a guide to Government Quality Assurance Personnel (QAP). It provides a systematic method to evaluate the services the contractor is required to furnish.
SURVEILLANCE PROCEDURES
Timeliness: Progress is maintained to assure compliance with completion time.
Quality: Conformance with statement of work and industry standards.
Tasks: Performed according to statement of work requirements.
Problem Resolution: Contractor submits deliverables in accordance with the contract and resolves any deficiencies identified by the government in the final submission. Following final submission, contractor resolves any additional deficiencies identified by the government and resubmits and or corrects within one week.
Delivery: Contractor submits each deliverable in accordance with the statement of work and terms of the contract.
PERFORMANCE AREAS
Management Responsiveness: Evaluate the adequacy of the contractor’s responsiveness and their ability to keep the government informed of work progress and provides for early problem identification and effective corrective action plans.
Schedule Control: Evaluate the contractor’s adherence to completion schedule.
Performance: The contractor will be evaluated as to the workmanship and adherence to the statement of work.
EVALUATION CRITERIA
(Outstanding). Indicates performance clearly exceeds contractual requirements. The area of evaluation contains few minor problems for which corrective actions appear highly effective.
(Satisfactory). Indicates performance clearly meets contractual requirements. The area of evaluation contains some minor problems for which the corrective actions appear satisfactory.
(Unsatisfactory). Indicates the contractor failed to satisfy contractual requirements and recovery is not likely in a timely manner. The area of evaluation contains serious problems for which the corrective actions were ineffective.
DOCUMENTATION
Documentation used to perform surveillance will consist of random government inspections and inspection records, as well as the evaluation of final work product delivery by the project COR/COTR.
RATING
Contractor will be given an overall rating of Outstanding, Satisfactory or Unsatisfactory by the Government Technical point of contact or Contracting Specialist Representative, if appointed, three using the above evaluation criteria.