NMWM Vendor Questions

1. How much rooms remains in the existing duct work from 3387 to the site?

A six duct bank (4 open) leaves MH3387 heading south to Tank Destroyer Blvd.

In the Tank Destroyer MH, two ducts (each with inner ducts/pull strings) continue south to

MH3085.

2. How many feet is it between the new stub work and the site?

Approximately 200 Feet

3. How far down does the conduit need in feet?

36 to 48 inches deep concrete encased

4. Has there been any underground surveys between the stub out and the site?

No

5. Are the existing manholes standardized and the same throughout the entire worksite?

No, there are various sizes of maintenance holes & hand holes from MH3387 to MH3085

6. Will there be a floor plan for the building available that will identify the location of the communications room and racks?

The NEC could ask the Gov. rep, Gene Roberts for a floor plan.

7. What is the estimated Period of Performance?

Jun21 to Aug21 (90 days) but could be extended if the NMWM completion date is extended.