This solicitation seeks fixed-price construction bids for a road rehabilitation project at Fort Hood, Texas. The work includes demolishing an existing asphalt pavement and constructing a new road structure with 3 inches of Type C and 4 inches of Type B hot-mix asphalt over 12 inches of aggregate base course. Additional signs and pavement markings will also be installed. The estimated value is $1-5 million. Bids are due on March 25, 2021 with contract completion in 210 days. The project is 100% set aside for small businesses. Interested parties must be registered in SAM and ensure their information is current. Drawings can be requested from the contracting officer.

View the file

Other files

Show all 16

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

0011575152 AD213050P

AMENDMENT OF SOLICITATION/MODIFICATION OF CONTRACT

Except as provided herein, all terms and conditions of the document referenced in Item 9A or 10A, as heretofore changed, remains unchanged and in full force and effect.

15A. NAME AND TITLE OF SIGNER (Type or print)

30-105-04EXCEPTION TO SF 30

APPROVED BY OIRM 11-84

STANDARD FORM 30 (Rev. 10-83) Prescribed by GSA

FAR (48 CFR) 53.243

A. This amendment is issued to provide Responses to Industry.

B. This amendment is issued to provide Revised Draw ings (Technical Exhibit G) and Revised Specifications (Technical Exhibit F).

C. This amendment is issued to provide additional Technical Exhibits C (Construction Suvey & Staking), D (Hot-Mix Asphalt Paving), and E (TXDOT Standard Specifications).

D. This amendment is to change the Bid Opening Date and Time to 25 March 2021 at 2:00 P.M.

E. This amendment is to update the Project Synopsis.

F. All other terms and conditions remain unchanged.

1. CONTRACT ID CODE PAGE OF PAGES

J 1 11

16A. NAME AND TITLE OF CONTRACTING OFFICER (Type or print)

16C. DATE SIGNED

BY 10-Mar-2021

16B. UNITED STATES OF AMERICA15C. DATE SIGNED15B. CONTRACTOR/OFFEROR

(Signature of Contracting Officer)(Signature of person authorized to sign)

8. NAME AND ADDRESS OF CONTRACTOR (No., Street, County, State and Zip Code) X W9115121B0002

X 9B. DATED (SEE ITEM 11)

01-Feb-2021

10B. DATED (SEE ITEM 13)

9A. AMENDMENT OF SOLICITATION NO.

11. THIS ITEM ONLY APPLIES TO AMENDMENTS OF SOLICITATIONS

X The above numbered solicitation is amended as set forth in Item 14. The hour and date specified for receipt of Offer X is extended, is not extended.

Offer must acknowledge receipt of this amendment prior to the hour and date specified in the solicitation or as amended by one of the following methods:

(a) By completing Items 8 and 15, and returning copies of the amendment; (b) By acknowledging receipt of this amendment on each copy of the offer submitted;

or (c) By separate letter or telegram which includes a reference to the solicitation and amendment numbers. FAILURE OF YOUR ACKNOWLEDGMENT TO BE RECEIVED AT THE PLACE DESIGNATED FOR THE RECEIPT OF OFFERS PRIOR TO THE HOUR AND DATE SPECIFIED MAY RESULT IN

REJECTION OF YOUR OFFER. If by virtue of this amendment you desire to change an offer already submitted, such change may be made by telegram or letter, provided each telegram or letter makes reference to the solicitation and this amendment, and is received prior to the opening hour and date specified.

12. ACCOUNTING AND APPROPRIATION DATA (If required)

13. THIS ITEM APPLIES ONLY TO MODIFICATIONS OF CONTRACTS/ORDERS.

IT MODIFIES THE CONTRACT/ORDER NO. AS DESCRIBED IN ITEM 14.

A. THIS CHANGE ORDER IS ISSUED PURSUANT TO: (Specify authority) THE CHANGES SET FORTH IN ITEM 14 ARE MADE IN THE

CONTRACT ORDER NO. IN ITEM 10A.

B. THE ABOVE NUMBERED CONTRACT/ORDER IS MODIFIED TO REFLECT THE ADMINISTRATIVE CHANGES (such as changes in paying office, appropriation date, etc.) SET FORTH IN ITEM 14, PURSUANT TO THE AUTHORITY OF FAR 43.103(B).

C. THIS SUPPLEMENTAL AGREEMENT IS ENTERED INTO PURSUANT TO AUTHORITY OF:

D. OTHER (Specify type of modification and authority)

E. IMPORTANT: Contractor is not, is required to sign this document and return copies to the issuing office.

14. DESCRIPTION OF AMENDMENT/MODIFICATION (Organized by UCF section headings, including solicitation/contract subject matter where feasible.)

10A. MOD. OF CONTRACT/ORDER NO.

2. AMENDMENT/MODIFICATION NO. 5. PROJECT NO.(If applicable)

6. ISSUED BY

3. EFFECTIVE DATE

10-Mar-2021

CODE

MICC - FORT HOOD

36000 DARNALL LOOP, ROOM 1300B

FORT HOOD TX 76544-5025

W91151 7. ADMINISTERED BY (If other than item 6)

4. REQUISITION/PURCHASE REQ. NO.

CODE

See Item 6

FACILITY CODECODE

EMAIL:TEL:

W9115121B0002

SECTION SF 30 BLOCK 14 CONTINUATION PAGE

SUMMARY OF CHANGES

SECTION 00010 - SOLICITATION CONTRACT FORM

The required response date/time has changed from 11-Mar-2021 02:00 PM to 25-Mar-2021 02:00 PM.

TABLE OF CONTENTS

The Table of Contents has changed from:

Exhibit/Attachment Table of Contents

DOCUMENT TYPE DESCRIPTION PAGES DATE

Exhibit A Technical Exhibit A -

Specifications

3173 25-MAR-2019

Exhibit B Technical Exhibit B - Drawings

38 12-NOV-2020

Attachment 1 Attachment 1 - Appendix A

139 02-JUL-2018

to:

Exhibit/Attachment Table of Contents

DOCUMENT TYPE DESCRIPTION PAGES DATE

Exhibit A Technical Exhibit A -

Specifications

3173 25-MAR-2019

Exhibit B Technical Exhibit B - Drawings

38 12-NOV-2020

Exhibit C Technical Exhibit C - Construction Surveying & Staking

10 04-MAR-2021

Exhibit D Technical Exhibit D - Hot-Mix Asphalt Paving

31 04-MAR-2021

Exhibit E Technical Exhibit E - TXDOT Standard Specifications

59 01-NOV-2014

Exhibit F Technical Exhibit F - Revised Specifications

3424 11-JAN-2016

Exhibit G Technical Exhibit G - Revised Drawings

38 04-MAR-2021

Attachment 1 Attachment 1 - Appendix A

139 02-JUL-2018

The following have been added by full text:

RESPONSE TO INDUSTRY QUESTIONS

Solicitation 21-B-0002

North Clarke Road C Reconstruction

RFIs Contractor submitted after Site Visit on 22 February 2021

1. Is there a way to get clarification of the Type “C” HMAC and Type “B” HMAC? The specs 32 16 12 HMAC for Roads covers SuperPave and Marshall mix designs. On the drawings it states the HMAC placed and compacted to a minimum of 93% of Maximum Theoretical (Rice) Density Method.

For this project, the following HMAC is required:

1. TxDOT Item 341, Type “C” and Type “B”.

a. TxDOT 341 will be used for the required material testing within and for the JMF development and placement requirements only.

b. Placement acceptance testing, pay factors and schedule will follow 32 12 16.16 (Note: An error was made by the author in the original question, calling for specification “32 16 12”.

The correct specification is 32 12 16.16).

c. RAS is prohibited from being used within the type “C” mix.

d. RAS is allowed for use within the type “B” mix, within the limitations imposed by TxDOT item 341.

e. RAP is allowable within the limitations prescribed by TxDOT item 341.

f. The SGC Ndes for type “B” and Type “C” mixes shall be 50-gyrations.

g. The binder for the mix design shall be PG70-22. Recycled content or additives within the mix shall not be used if detrimental to the performance of the mix with PG70-22 binder.

Note: see revised specification 32 12 16.16.

2. What PG Binder will be used for the mixes? It states 70-10 for the PG Binder but should it be 70-22?

The required binder shall be PG70-22.

Note: see revised specification 32 12 16.16.

3. Can RAS be used in the B mix?

Refer to RFI #1 response for clarification on RAS and RAP use.

4. Are we installing a taper on the edges of the HMAC or will it be vertical with a compacted shoulder up? Plans have two different installs. Pg. C300 and C502

Install Tapered as depicted on sheet C-502, “Condition 4” Total HMAC Thickness 5” or Greater.

5. Sheet G-003 Note 18 states “project crosses waters of the US in two locations any work done within the streams must comply with Nationwide Permit #14”. What does complying with nationwide permit #14 until for the contractor?

For this project, NO WORK are required on the streams.

6. Sheet G-003 traffic control note one specifies the traffic control plan should be submitted at least 45 days prior to construction. Will the contractor get additional days to the contract duration for this submittal and review process that could take over 60 days?

No. Per drawing G-006 “Traffic Control Concept”, the Government recommend at total road closure for which provided that conceptual plan. Therefore, if the contractor submits a TTC Plan diligently, 45 days should be sufficient for the Government review and notification to the end-users. The Government will evaluate any delays related to this matter accordingly.

7. Sheet G-003 Site Prep Note 7 says subgrade preparation should extend 24” beyond the pavement edge. Sheet C- 300 Note 7 says subgrade prep should extend 12” beyond the pavement edge. How far past edge of pavement should the subgrade prep extend?

12 inches from the tapered edge of the pavement. Refer to revised drawing sheet C-300.

8. Sheet C-300 Detail B shows an overall HMAC width of 28 ft. Does this 28 ft include the two 9” tapered shoulders shown on Sheet C-502 Condition 4 Detail or do these 9” tapers need to be added to the total HMAC? This would result in a HMAC surface 29.5’ wide.

The roadway and shoulders width extend 29’-6” feet wide, including the tapers.

9. If total HMAC width including the tapers from C-502 Condition 4 detail is extended 9” on each side, are the base and subgrade width to be widened by 9” on each side as well? This would result in base and subgrade surfaces at 31.5’ wide.

Correct.

10. 32 11 16, 32 11 23, and 32 11 24 could all be applicable to this project. Which base specifications are we being held to?

For this project, the following base material is required:

1. TxDOT Item 247, Type A, Grade 1-2.

a. TxDOT Item 247 will be used for the required material testing submittals and placement requirements.

b. TxDOT Item 247 will be used for placement methods.

c. Testing schedule for placement shall follow sheet G-003.

11. Sheets G-003 and C-300 have notes directing base to meet TxDOT Type A Grade 1-2 requirements. Specifications 32 11 16, 32 11 23, and/or 32 11 24 are all standard COE/DPW specs with gradations that do not match TxDOT and refer to LA Abrasion vs wetball. Please provide one clear and concise specification on the base material.

See response to RFI #10 for clarification.

12. Sheets G-003 and C-300 note base should be compacted to 95%. 32 11 16, 32 11 23, and/or 32 11 24 says base should be compacted to 100%. What is the required compaction?

The compaction requirement shall follow sheets G-003 and C-300. Specifications 32 11 XX shall be replaced with TxDOT item 247 for material, testing and placement requirements. The testing schedule shall follow sheet G-003.

13. Sheet G-003 Testing Schedule does not match with 32 11 16, 32 11 23, and/or 32 11 24. Please provide one clear and concise testing schedule.

See response to RFI #12 for clarification.

14. 32 12 16 contains pay scales based on HMAC compaction effort. Will DPW be basing payment on this scale or just paying 100% for everything equal to or greater than 93% compaction as suggested in the plans?

Specification 32 12 16 and plans have been revised. Compact according to revised specification 32 12 16.16.

The “93% compaction” notes have been removed in lieu of the revised specification 32 12 16. Pay factors will be used in this contract according to revised specification 32 12 16.16.

15. Sheet C-300 calls for TxDOT Type C and Type B HMAC mixes. 32 12 16 talks about Marshall method with options for Contractor to design per outdated literature or either utilizing crack-inducing gyrations. Please provide one clear and concise HMAC spec.

See response to RFI #1 for clarification.

16. Specification 32 16 12 HMAC for Roads covers SuperPave and Marshall mix designs. On the drawings it states the HMAC placed and compacted to a min. of 93% of Max. Theoretical (Rice) Density Method. Which design method for the TY B and TY C HMAC should be used?

See response to RFI #1 for clarification.

17. It states to use a 70-10 PG binder for the HMAC. Should it be a 70-22?

See response to RFI #1 for clarification.

18. Can RAS be used in the TY B HMAC?

See response to RFI #1 for clarification.

19. Sheet C-300 detail B shows a vertical hot mix edge with the base extending 1 foot past the edge of hot mix.

Sheet C-502 is a detail sheet with tapered edges. Are we installing a taper and if so what condition should we follow?

Yes, the tapered edge shall be included and the HMAC Type “B” layer surface should 29.5 ft. The aggregate Base surface layer should be 31.5 feet wide respectively. Refer to revised drawing sheet C-300.

20. Plans show to compact the subgrade 12 inches in depth. Is this correct?

Compacting of subgrade to 12-inches refers to new pavement areas in the widening areas, as indicated on the plans notes.

This project is intended for pavement reconstruction and do not include new pavement widening areas; the subgrade shall be tested and worked as indicated on note 5, Sheet G-003, Sheet C-300, and Sheet C-501.

21. The amount of aggregate base that will be needed for this project?

The Contractor (s) shall calculate as part of their estimating process.

22. Can a second site visit be permitted? This request is being made due to the Disaster in Texas last week that affected my business and employees. I am sure that all businesses were affected as well.

A second site visit will not be scheduled.

23. Can the RFB Bid opening date of Mar 11, 2021 02:00 pm CST be changed?

Bid Opening is rescheduled for March 25, 2021

24. Will Instruction to Offerors “draft progress schedule that demonstrates the offeror's understanding of the work requirements, phasing of work between buildings, and estimated time frames for ordering and installing equipment”, be removed?

Yes, this paragraph will be removed from the Instructions to Offerors.

25. Will Instruction to Offerors, “will relevant work experience within the last 10 years”, be removed?

Yes, this paragraph will be removed from the Instruction to Offerors.

26. In review of the certifications and training identified in Technical Exhibit A Specifications, specifically AT Level I Training, OPSEC Training on page 33, Proof of qualification for Crane Operators page 54,could you please advise as to what page is the Technical Exhibit A Specification that the Government specifically wants the submitter to be considered technically capable?

This paragraph will be removed from the Instructions to Offerors.

27. How are you going to evaluate experience, schedule, and subcontracting IAW FAR Part 14?

This is a FAR Part 14 construction project with Bid Submittals there will be no evaluation of experience, schedule and subcontracting.

28. Is this RFB meant to be an RFP?

It is an IFB.

29. Will the Government be adding FAR Clause 52.236-1 Performance of Work by the Contractor to the solicitation? If so, what is the percentage of work that needs to be performed by the Prime Contractor in accordance with this clause, if added?

FAR Clause 52.236-1 Performance of Work by the Contractor will not be added to the Solicitation.

30. Which FAR Clause, does the Government consider this project to operate under? # 3 at 85% or # 4 at 75% of the amount paid by the Government for contract performance, excluding the cost of materials, to subcontractors that are not similarly situated entities.

FAR Clause 52.219-14 (Dev) Limitations on Subcontracting (Deviation 2020-0008) will be removed from the Solicitation.

The following have been modified:

PROJECT SYNOPSIS

PROJECT SYNOPSIS

North Clarke Road C Reconstruction

Project No. AD213050P

DESCRIPTION OF WORK:

The work shall be located at northwest boundary of main cantonment, on N Clarke Road from the intersection with W Tank Destroyer Blvd. at south to the Portland Cement Concrete (PCC) tank crossing near the intersection with Turkey Run Rd at north, Fort Hood Texas. The exact location will be shown by the Contracting Officer.

Total road is considered and areas will be occupied during performance of work under this Contract.

The purpose of this project is to perform road rehabilitation as included but not limited to: the demolition and disposal of the existing asphaltic concrete pavement, excavate to construct a new road structure consisting of a new 3 in. Surface Course Type “C” of Hot- Mix Asphaltic Concrete (HMAC) over a 4 in. Type “B” HMAC Base Course over a 12 in. Aggregate Base Course. Additional traffic signs, Thermoplastic reflective pavement markings & symbols with reflectorized pavement markers (RPMs) are to be installed within the project’s limits.

This segment of Clarke Road will not include the development of a bike lane. The details associated are described on plans and specifications.

The following drawings are included as part of this Solicitation:

G-001 Cover Sheet (Revised) G-002 Index and Legends G-003 General Notes (Revised) G-004 Signage Schedule G-005 Location Map – General G-006 Traffic Map - Conceptual G-007 Key Plan G-008 Suggested Construction Phasing Plan G-009 Haul Route and Staging Area G-010 Project Alignment Data LB-001 Geotechnical Boring Log C-100 Project Control Data C-101 to C-104 Site Plan - Existing Conditions C-105 to C-108 Site Plan - Demolition Plan C-109 to C-112 Site Plan - Proposed Improvements C-300 Typical Cross Sections (Revised) C-501 Pavement Details I (Revised) C-502 Pavement Details II C-503 Typical Pavement Markings Details C-504 Details – Raised Markers Reflectorized C-505 Details – Traffic Signs C-506 Details Traffic Signs Slip Base Breakaway Mounting C-507 to C-512 Work Zone Barricade & Construction Details

C-513 Traffic Control Plan Detail (Road Closure w Detours)

One set of solicitation documents, including plans, specifications, and miscellaneous data, will be furnished to the contractor in Adobe PDF format. After award, one set of Adobe PDF contract drawings and PDF specifications, and one set of MicroStation® format drawings (if available) will be furnished to the Contractor on CD. Reference publications will not be furnished. Contractor shall immediately check furnished drawings and notify the Government of any discrepancies.

- A Temporary Traffic Control Plan (TTCP) will be required for this project.

- A project construction sign will not be required for this project.

PERFORMANCE PERIOD: Barring any contingencies that arise during construction, the Government requires this project be completed within 210 calendar days. Completion is defined as completion of all contractual obligations.

*****************************END OF SCOPE***********************************

SECTION 00100 - BIDDING SCHEDULE/INSTRUCTIONS TO BIDDERS

INSTRUCTIONS TO OFFERORS

Any bids received in response to this solicitation SHALL carry a 120 day acceptance period before prices need to be verified, extended or re-negotiated.

1. Submission of Bids Bidders are required to provide a CD copy of their bid documents with their IFB submission.

2. Public Bid Openings Please refer to Block 13A of the 1442. Anyone wishing to attend the bid opening MUST notify the Contracting Officer (orlando.guerrero4.civ@mail.mil) and Contract Specialist (lisa.d.lewis2.civ@mail.mil) by email no later than 18 March 2021 at 2:00 P.M CST with a firm commitment to attend.

MAILING ADDRESS

ATTN: Lisa Lewis (Contracting Section) Mission and Installation Contracting Command-Fort Hood 36000 Darnall Loop, Room 1300B Fort Hood, Texas 76544-5095

PUBLIC BID OPENING

Shoemaker Center Bldg 36000 Darnall Loop Conference Room 2809 located inside Room 2801 Fort Hood, TX 76544 25 March 2021 at 2:00 P.M.

COVID-19 precautions will be enforced during bid openings.

3. Pre-Bid and Pre-Construction Conferences

The Contracting Officer will conduct a pre-bid/pre-proposal conference in conjunction with the site visit. All potential bidders/offerors attending the site visit are highly encouraged to attend the pre-bid/pre-proposal conference. Information on the scheduled Site Visit is located in FAR 52.236-3 SITE VISIT (CONSTRUCTION) (FEB 1995) of this solicitation. Space limitations dictate that no more than two representatives from each company attend. The Contracting Officer will review solicitation submittal requirements, and other administrative matters critical for successful and timely performance of the work.

The Contractor shall attend a Government coordinated preconstruction conference within 10 calendar days of contract award. As a minimum, the conference shall be attended by the contractor’s appointed project manager, the superintendent, the QCM, and administrative personnel responsible for preparation of contract documents, certified payroll records and invoices. The contractor shall deliver letter appointments of its key personnel that include each individual’s duties, roles and responsibilities.

COVID-19 precautions will be enforced during all visits/meetings/conferences.

4. Amendments to Solicitations

(a) If this solicitation is amended, then all terms and conditions which are not modified remain unchanged. (b) Offerors shall acknowledge receipt of any amendment to this solicitation (1) by signing and returning the amendment, or (2) by identifying the amendment number and date in the space provided for this purpose on the form for submitting a quote. The Government must receive the acknowledgment by the date and time specified for receipt of bids indicated in Block 13 of the SF1442.

52.252-3 ALTERATIONS IN SOLICITATION (APR 1984)

Portions of this solicitation are altered as follows:

Amendment 01:

A. Due to inclement weather, Fort Hood was closed on 11 February 2021, therefore the site visit that was scheduled for 11 February 2021 at 10:00 AM has been rescheduled.

B. The purpose of this amendment is to change the Site Visit Date and Time to 19 February 2021 at 2:00 P.M.

C. The purpose of this amendment is to change the Request for Information (RFI) questions due from Contractor Date and Time to 25 February 2021 at 2:00 P.M.

D. The purpose of this amendment is to change the Bid Opening Date, Time, and Room Number to 11 March 2021 at 2:00 P.M. in Conference Room 2809 which is located inside Room 2801.

E. All other terms and conditions remain unchanged.

Amendment 02:

A. Due to inclement weather, Fort Hood was closed on 19 February 2021, therefore the site visit that was scheduled for 19 February 2021 at 2:00 PM has been rescheduled.

B. The purpose of this amendment is to change the Site Visit Date and Time to 22 February 2021 at 2:00 P.M.

C. The purpose of this amendment is to change the Request for Information (RFI) questions due from Contractor Date and Time to 26 February 2021 at 2:00 P.M.

D. All other terms and conditions remain unchanged.

Amendment 03:

A. This amendment is issued to provide Responses to Industry.

B. This amendment is issued to provide Revised Drawings (Technical Exhibit G) and Revised Specifications (Technical Exhibit F).

C. This amendment is issued to provide additional Technical Exhibits C (Construction Suvey & Staking), D (Hot- Mix Asphalt Paving), and E (TXDOT Standard Specifications).

D. This amendment is to change the Bid Opening Date and Time to 25 March 2021 at 2:00 P.M.

E. This amendment is to update the Project Synopsis.

F. All other terms and conditions remain unchanged.

(End of provision)

SECTION 00700 - CONTRACT CLAUSES

252.236-7001 CONTRACT DRAWINGS AND SPECIFICATIONS (AUG 2000)

(a) The Government will provide to the Contractor, without charge, one set of contract drawings and specifications, except publications incorporated into the technical provisions by reference, in electronic or paper media as chosen by the Contracting Officer.

(b) The Contractor shall--

(1) Check all drawings furnished immediately upon receipt;

(2) Compare all drawings and verify the figures before laying out the work;

(3) Promptly notify the Contracting Officer of any discrepancies;

(4) Be responsible for any errors that might have been avoided by complying with this paragraph (b); and

(5) Reproduce and print contract drawings and specifications as needed.

(c) In general--

(1) Large-scale drawings shall govern small-scale drawings; and

(2) The Contractor shall follow figures marked on drawings in preference to scale measurements.

(d) Omissions from the drawings or specifications or the misdescription of details of work that are manifestly necessary to carry out the intent of the drawings and specifications, or that are customarily performed, shall not relieve the Contractor from performing such omitted or misdescribed details of the work. The Contractor shall perform such details as if fully and correctly set forth and described in the drawings and specifications.

(e) The work shall conform to the specifications and the contract drawings identified on the following index of drawings:

Title File Drawing No.

Technical Exhibit A Specifications W91151-21-B-0002 Technical Exhibit B Drawings W91151-21-B-0002 Technical Exhibit C Construction Surveying & Staking W91151-21-B-0002 Technical Exhibit D Hot-Mix Asphalt Paving W91151-21-B-0002 Technical Exhibit E TXDOT Standard Specifications W91151-21-B-0002 Technical Exhibit F Revised Specifications W91151-21-B-0002 Technical Exhibit G Revised Drawings W91151-21-B-0002

Attachment 1 Appendix A W91151-21-B-0002

(End of clause)

The following have been deleted:

52.219-14 (Dev) Limitations on Subcontracting (DEVIATION 2020-O0008) MAR 2020

(End of Summary of Changes)