W90VN6-16-T-0005-0004.pdf

PDF 304 KB Posted

Attached to
Replace outdated DSL with Fiber and LAN
Solicitation number
W90VN6-16-T-0005
Issued by

About this file

Amendment 0004

View the file

Other files

File Type Posted
W90VN6-16-T-0005-0003.doc DOC document
W90VN6-16-T-0005-0002.doc DOC document
W90VN6-16-T-0005-0001.pdf PDF
W90VN6-16-T-0005.pdf PDF

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

F3J3SG5056A003

AMENDMENT OF SOLICITATION/MODIFICATION OF CONTRACT

Except as provided herein, all terms and conditions of the document referenced in Item 9A or 10A, as heretofore changed, remains unchanged and in full force and effect.

15A. NAME AND TITLE OF SIGNER (Type or print)

30-105-04EXCEPTION TO SF 30

APPROVED BY OIRM 11-84

STANDARD FORM 30 (Rev. 10-83) Prescribed by GSA

FAR (48 CFR) 53.243

A. A. The purpose of this amendment is to change scope and response to received questions.

B. The closing date/time is extended from 31 May 2016, 1300 hours to 7 June 2016, 1300 hours.

C. All other terms and conditions of the solicitation remain the same.

1. CONTRACT ID CODE PAGE OF PAGES

J 1 1 3

16A. NAME AND TITLE OF CONTRACTING OFFICER (Type or print)

16C. DATE SIGNED

BY 24-May-2016

16B. UNITED STATES OF AMERICA15C. DATE SIGNED15B. CONTRACTOR/OFFEROR

(Signature of Contracting Officer)(Signature of person authorized to sign)

8. NAME AND ADDRESS OF CONTRACTOR (No., Street, County, State and Zip Code) X W90VN6-16-T-0005

X 9B. DATED (SEE ITEM 11)

08-Dec-2015

10B. DATED (SEE ITEM 13)

9A. AMENDMENT OF SOLICITATION NO.

11. THIS ITEM ONLY APPLIES TO AMENDMENTS OF SOLICITATIONS

X The above numbered solicitation is amended as set forth in Item 14. The hour and date specified for receipt of Offer X is extended, is not extended.

Offer must acknowledge receipt of this amendment prior to the hour and date specified in the solicitation or as amended by one of the following methods:

(a) By completing Items 8 and 15, and returning copies of the amendment; (b) By acknowledging receipt of this amendment on each copy of the offer submitted;

or (c) By separate letter or telegram which includes a reference to the solicitation and amendment numbers. FAILURE OF YOUR ACKNOWLEDGMENT TO BE RECEIVED AT THE PLACE DESIGNATED FOR THE RECEIPT OF OFFERS PRIOR TO THE HOUR AND DATE SPECIFIED MAY RESULT IN

REJECTION OF YOUR OFFER. If by virtue of this amendment you desire to change an offer already submitted, such change may be made by telegram or letter, provided each telegram or letter makes reference to the solicitation and this amendment, and is received prior to the opening hour and date specified.

12. ACCOUNTING AND APPROPRIATION DATA (If required)

13. THIS ITEM APPLIES ONLY TO MODIFICATIONS OF CONTRACTS/ORDERS.

IT MODIFIES THE CONTRACT/ORDER NO. AS DESCRIBED IN ITEM 14.

A. THIS CHANGE ORDER IS ISSUED PURSUANT TO: (Specify authority) THE CHANGES SET FORTH IN ITEM 14 ARE MADE IN THE

CONTRACT ORDER NO. IN ITEM 10A.

B. THE ABOVE NUMBERED CONTRACT/ORDER IS MODIFIED TO REFLECT THE ADMINISTRATIVE CHANGES (such as changes in paying office, appropriation date, etc.) SET FORTH IN ITEM 14, PURSUANT TO THE AUTHORITY OF FAR 43.103(B).

C. THIS SUPPLEMENTAL AGREEMENT IS ENTERED INTO PURSUANT TO AUTHORITY OF:

D. OTHER (Specify type of modification and authority)

E. IMPORTANT: Contractor is not, is required to sign this document and return copies to the issuing office.

14. DESCRIPTION OF AMENDMENT/MODIFICATION (Organized by UCF section headings, including solicitation/contract subject matter where feasible.)

10A. MOD. OF CONTRACT/ORDER NO.

2. AMENDMENT/MODIFICATION NO. 5. PROJECT NO.(If applicable)

6. ISSUED BY

3. EFFECTIVE DATE

24-May-2016

CODE

411TH CONTRACTING SUPPORT BRIGADE, KOREA

RCO OSAN, UNIT #2039

APO AP 96278-2039

UNITED STATES OF AMERICA (THE)

W90VN6 7. ADMINISTERED BY (If other than item 6)

4. REQUISITION/PURCHASE REQ. NO.

CODE

See Item 6

FACILITY CODECODE

EMAIL:TEL:

W90VN6-16-T-0005

SECTION SF 30 BLOCK 14 CONTINUATION PAGE

SUMMARY OF CHANGES

SECTION SF 1449 - CONTINUATION SHEET

SOLICITATION/CONTRACT FORM

The required response date/time has changed from 31-May-2016 01:00 PM to 07-Jun-2016 01:00 PM.

The following have been added by full text:

QUESTION AND ANSWER

The question (Q) and answer (A) is as follow:

Q1: Is there any racks to install FOPP at TR in the building 433, 434, 708, 712, 733, 769, 775, 738 ?

If not, Shall we install Racks as well for this contract?

A1: Please refer to revised PWS

Q2. We like to know the specification and type for Pig Tail for cable termination. For example) LC/LC, SC/LC

A2: Please refer to revised PWS 2.6.2.5

Q3: No distance is indicated in the drawing from mh712 to B712.

A3: Distance has been added

Q4: Is innerduct size 25mm hdpe ?

A4: Please refer to revised PWS 2.4.3 and 2.5.2

Q5 Installing FOC cable, will this be building to building or M/H(splice point) to building ?

A5: Please refer to revised PWS 2.6.2.2

Q6: In the 4.0 Deliverables on page 14, what is " IPT Minutes" means ?

A6: Initial Planning Team Minutes (IPT)

The following have been modified:

PERFORMANCE WORK STATEMENT

PERFORMANCE WORK STATEMENT

For

Fiber Optic Cable Installation between Core Node at Building 355 and Access Nodes at Buildings 433, 434, 708, 712, 733, 769, 775, and 738

Osan AB, Republic of Korea 25 August 2015

1.0 INTRODUCTION. This Performance Work Statement (PWS) defines the requirements for the contractor to engineer, furnish, install and test (EFI&T) additional cable infrastructure connecting between Core Node at Building 355 and Access Nodes at Buildings 433, 434, 708, 712, 733, 769, 775, and 738 at Osan AB, Republic of Korea

(ROK).

2.0 SPECIFIC TASKS AND REQUIREMENTS.

2.1 General Requirements.

2.1.1 Contractor and all associated sub-contractors employees shall provide all information required for background checks to meet installation access requirements to be accomplished by installation Provost Marshal Office, Director of Emergency Services or Security Office. Contractor workforce must comply with all personal identity verification requirements (FAR clause 52.204-9, Personal Identity Verification of Contractor Personnel) as directed by DOD, HQDA and/or local policy. In addition to the changes otherwise authorized by the changes clause of this contract, should the Force Protection Condition (FPCON) at any individual facility or installation change, the Government may require changes in contractor security matters or processes.

2.1.2 Contractor and all associated sub-contractors employees shall comply with adjudication standards and procedures using the National Crime Information Center Interstate Identification Index (NCIC-III) and Terrorist Screening Database (TSDB) (Army Directive 2014-05/AR 190-13), applicable installation, facility and area commander installation/facility access and local security policies and procedures (provided by government representative), or, at OCONUS locations, in accordance with status of forces agreements and other theater regulations.

2.1.3 The contractor shall provide all equipment, tools, materials, supplies, transportation, labor, supervision, management, and other incidentals necessary to EFI&T the requirements as stated in this PWS. The contractor shall expand the existing manhole and duct system as described in this document. The contractor shall utilize the expanded duct system to connect between Core Node at Building 355 and Access Nodes at Buildings 433, 434, 708, 712, 733, 769, 775, and 738 with 12 strand single mode fiber optic cable (FOC). Install all necessary Fiber Optic Distribution Panels (FODP) to terminate the 12 strand Single mode FOCs. All provided materials shall be new and not refurbished. FODP must be installed in a lockable cabinet (provided by the contractor)and the cabinet may be wall mounted.

2.2 Restoration. The contractor shall restore all work areas affected after installation of the manhole/duct system.

The contractor shall comply with Osan ROK grounds restoration requirements.

2.2.1 All wall penetrations shall be restored to support the required fire ratings of NFPA-70 110.31(accessible at building 949 room 203) and ANSI/TIA/EIA-569B Annex A(accessible at building 949 room 203).

2.2.2 All trenches for conduits shall be a minimum of 24” deep at the top of the conduit.

2.2.3 At the completion of the project, all disturbed earth shall be restored to original grade and original condition.

2.2.4 At the completion of the project, all disturbed paved surfaces shall be restored to original grade and original condition.

2.2.5 All residues from this project shall be disposed of off base and IAW of Osan AB, ROK environmental laws and regulations.

2.3 Outside Plant General Requirements. The contractor shall engineer, furnish and install manhole/duct infrastructure as defined herein and shall document their installation with photos upon project completion IAW the distribution list. If required, the contractor shall pump out any manholes.

2.3.1 All information provided in this PWS will need to be verified at the pre-proposal/site survey. Distances provided are approximations and should NOT be used for ordering materials or determining duct lengths.

2.3.2 The contractor shall complete and process all permits as required to complete installation.

2.3.3 The Contractor shall be responsible for any required trenching and/or boring necessary to lay the duct system.

Contractor is also responsible for backfilling ditch lines and compaction of fill materials. It is expected that crossing of paved surfaces will be performed by road cuts, concrete T cap and resurfacing with appropriate matching road material. Boring may be considered at the Contractor’s discretion. Ducts will be encased or otherwise appropriately protected when placed under paved surfaces.

2.3.4 The contractor shall coordinate with base agencies to ensure flags/temporary markings are placed over existing base infrastructure prior to digging or directional drilling and will take precautions to protect existing infrastructure.

Contractor will be responsible for costs associated with repair of any damages caused during installation when the infrastructure is clearly flagged.

2.3.5 The contractor shall comply with all ANSI/TIA/EIA and base installation standards. The contractor shall label all equipment and cables they install in accordance with ANSI/TIA/EIA-606-A (sample Label accessible at building 949 room 203)

2.3.6 Base personnel will accompany contractor during walk through/site-survey to answer questions and provide access into buildings and manholes/hand-holes.

2.4 General Installation Requirements.

2.4.1 Route. The contractor shall utilize the expanded duct system to connect between Core Node at Building 355 and Access Nodes at Buildings 433, 434, 708, 712, 733, 769, 775, and 738 with 12 strand single mode fiber optic cable (FOC). Install all necessary Fiber Optic Distribution Panels (FODP) to terminate the 12 strand single mode FOCs. New duct/path will be required between HH739-B769 (Est. 75’), MH12-MH12.1 (Est. 130’), MH12-12A (Est. 135’), MH 12A-B733 (Est.160’), MH9-B755 (Est. 150’), MH11-B738 (Est. 40’) and HH428-B434 (Est. 220’).

If contractor proposes additional ducting/cable path it must be approved by 51 CS.

2.4.2 Manholes and Handholes. Contractor must use existing manholes and hand-holes.

2.4.3 Underground Conduit Systems. A (2) way, 4” schedule 40 PVC duct configuration will be used for new duct installation. The ducts shall be corrosion resistant and 4-inch inside diameter (I.D.) round or metric equivalent. The ducts shall be made of EPC-40 Polyvinyl Chloride (PVC) (Schedule 40) IAW NEMA TC-2(accessible at www.NEMA.org); or EPC-80-PVC (Schedule 80) IAW NEMA TC-2; or high density polyethylene (HDPE) SDR

11. The ducts shall be appropriately labeled indicating the composition material. Ducts shall have a sleeve or bell end type coupling and shall be watertight when assembled. Installation of underground conduits/ducts, shall be IAW RUS Bulletin 1751F-643(accessible at www.rd.usda.gov); RUS Bulletin 1753F-151(accessible at www.rd.usda.gov); and T.O 31W3-10-22(accessible at building 949 room 328. Ducts across roads, sidewalks, parking areas, or areas to be paved, etc. shall be installed a minimum of 36" below grade. In manholes with knockouts, ducts shall start at the bottom knockout, allowing for upward expansion in the manholes. All ducts not installed across roads, sidewalks, parking areas, or areas to be paved, etc. shall have a minimum of 24 inches ground cover, where possible. The Contractor shall provide other protective measures, concrete cap, etc., in those areas where the minimum ground cover cannot be achieved. Grading of ducts shall be accomplished IAW RUS Bulletin 1751F-643(accessible at www.rd.usda.gov). All bends between handholes shall be a minimum 40-foot radius with the sum of bends in all directions not exceeding a total of 90 degrees. Only one 90-degree bend shall be allowed between handholes. Ducts shall have bell ends and enter a handhole perpendicular to the surface of the wall through which it is entering. All ducts/innerducts entering handholes must be sealed. Universal duct plugs or removable putty sealants may be used. Upon completion of conduit sections, a test mandrel ¼” (6.4mm) smaller than the inside diameter of the conduit shall be pulled through the ducts to ensure proper alignment. In addition, all ducts shall be cleared of loose materials such as concrete, mud, dirt, stones, etc. All vacant ducts/innerducts shall be provided with a waterproof corrosion resistant pull rope for future cable installation. The pull rope shall extend into the handhole and be secured to the cable rack or pulling iron, etc. When communications ducts cross either power duct or buried power cable, maintain a minimum separation of 3 inches of concrete or 12 inches of well-tamped earth between the two or 12 inches of well tamped earth when parallel; for pipes (e.g., gas, water, oil) maintain 6 inches when crossing or 12 inches when parallel. Along the length of the duct run, if the ducts are installed by trenching, spacers shall be placed at an interval of four (4) spacers per 20 feet and cable warning tape shall be buried one (1) foot below the surface and shall follow the duct route. The tape shall be a minimum of three inches wide and orange in color with the appropriate warning message. The distances given for duct installation in the following paragraphs are for estimating purposes only and are not to be used by the Contractor to order material.

2.4.4 Conduit Bends or Sweeps. Where a bend or sweep is placed in Schedule 40 nonmetallic duct bank between manholes, the duct bank must be encased in concrete with a minimum compressive strength of 17,225 kilopascal (kPa) [2500 pounds per square inch (psi)]. Inspection of Conduit Bends or Sweeps must be inspected by a Government appointed official from the Quality Insurance Office while the trench or hole is still exposed prior to back filling.

2.4.5 Labeling. The contractor shall label all equipment and cables they install in accordance with ANSI/TIA/EIA- 606-A (accessible at building 949 room 203) and as directed by the 51 Communication Squadron.(Sample Label available at building 949 room 203)

2.5 Manhole /Handhole /Conduit Installation.

2.5.1 General Installation Description. The proposed route and the distances shown on Figure 1 is approximate.

The exact locations of new conduit and duct runs will be approved by the 51 Communication Squadron prior to installation. It is understood that there may be numerous below ground and above ground obstructions and paved surfaces that may be encountered. The exact route will be subject to approval of the 51 Comm Squadron after digging permit is issued and obstructions are identified and located. The contractor is free to propose changes to the route.

2.5.2 Ducts and Inner Ducts

Ducts and Inner-ducts from Core Node at Building 355 to Access Nodes at Buildings B433, B434, B712, B733, B708, B738, B769 and B775 are as follows:

1. Install new duct as well as 2-4’’, SCHD 40 PVC conduits from B434 to HH428. Install (3), 3-cell (total of 9 cells) geotextile inner ducts from B434 to HH428(Est. 220’)

2. Install (3), 3-cell (total of 9 cells) geotextile innerducts from HH202-2 to B433.

3. Install new duct as well as 2-4’’, SCHD 40 PVC conduits from B769 to HH739. Install (3), 3-cell (total of

9 cells) geotextile inner ducts from B769 to HH739. (Est. 75’)

4. Install new duct as well as 2-4’’, SCHD 40 PVC conduits from MH12 to MH12-1. Install (3), 3-cell (total of 9 cells) geotextile Inner ducts from MH12 to MH12-1.(Est. 135’)

5. Install new duct as well as 2-4’’, SCHD 40 PVC conduits from MH-9 to B775. Install (3), 3-cell (total of 9 cells) geotextile innerducts from MH-9 to B775. (Est. 150’)

6. Install new duct as well as 2-4’’, SCHD 40 PVC conduits from MH-11 to B738. Install (3), 3-cell (total of 9 cells) geotextile innerducts from MH-11 to B738. (Est. 40’)

7. Install (3), 3-cell (total of 9 cells) geotextile innerducts from MH12-1 to B708.

8. Install new duct as well as 2-4’’, SCHD 40 PVC conduits from MH12-A to B733. Install (3), 3-cell (total of

9 cells) geotextile innerducts from MH12-A to B733. (Est. 160’)

9. Install (3), 3-cell (total of 9 cells) geotextile innerducts from MH12 to MH712.

10. Install (3), 3-cell (total of 9 cells) geotextile innerducts from MH712 to B712.

11. Install new duct as well as 2-4’’, SCHD 40 PVC conduits from MH12 to MH12-A. Install (3), 3-cell (total of 9 cells) geotextile innerducts from MH12 to MH12-A. (Est. 135’)

2.6 Cable Installation.

2.6.1 Assumptions:

At HH431; there is an existing 144 strands single mode FOC from Building 355. Out of the 144 strands, 60 strands (strand numbers 85 to 144) is not assigned to any buildings. The 60 strands are left dark in a splice case in HH431.

At MH712; there is an existing 288 strands single mode FOC from Building 355. Out of the 288 strands, 84 strands (strand numbers 205 to 288) is not assigned to any buildings. The 84 strands is left dark in a splice case at MH712.

Contractor shall verify the above assumptions and inform the 51st Communication Squadron in case it is different or incorrect.

2.6.2 Fiber Optic Distribution Panels

2.6.2.1 Install FODPs in an enclosed lockable cabinet in the communications rooms or designated locations in buildings 433, 434, 708, 712, 733, 769, 775, and 738 to receive the 12-strand single mode FOC’s. (locations will be identified during survey)

2.6.2.2 Fiber Cable Installation. The following fiber optic cables shall be installed through the existing man-hole duct system and the new man-hole duct system installed above.

1. Install 24 strands single mode FOC from HH431, to HH412, to HH425, and then to MH1-14-1. Splice the 24-strands to strand numbers from 85 to 109 at HH431. Splice the fiber at MH1-14-1 to a new splice case for branching off to B434 and B433.

2. Install 12 strands single mode FOC from MH 1-14-1, to MH1-14, to MH1-13, to MH1-12, to HH202-2, and then to B433. Splice the fiber at MH1-14-1 to strand numbers from 1 to 12 of the new splice case installed above.

Terminate the new 12 strands cable at B433 using the FODP installed above. Test the new 12 strands cable between Core Node at Building 355 and Access Node at Building 433.

3. Install 12 strands single mode FOC from MH 1-14-1, to HH428, and then to B434. Splice the fiber at MH1-14-1 to strand numbers from 13 to 24 of the new splice case installed above. Terminate the new 12 strands cable at B434 using the FODP installed above. Test the new 12 strands cable between Core Node at Building 355 and Access Node at Building 434.

4. Install 12 strands single mode FOC from MH712 to B712. Splice the fiber at MH712 to strand numbers from 205 to 216 of the existing splice case. Terminate the new 12 strands cable at B712 using the FODP installed above. Test the new 12 strands cable between Core Node at Building 355 and Access Node at Building 712.

5. Install 12 strands single mode FOC from MH712, to MH12, to MH12-1, and then to B708. Splice the fiber at MH712 to strand numbers from 217 to 228 of the existing splice case. Terminate the new 12 strands cable at B708 using the FODP installed above. Test the new 12 strands cable between Core Node at Building 355 and Access Node at Building 708.

6. Install 12 strands single mode FOC from MH712, to MH12, to MH12-A. and then to B733. Splice the fiber at MH712 to strand numbers from 229 to 240 of the existing splice case. Terminate the new 12 strands cable at B733 using the FODP installed above. Test the new 12 strands cable between Core Node at Building 355 and Access Node at Building 733.

7. Install 36 strands single mode FOC from MH712, to MH-12, and then to MH11. Splice the 36 strands to strand numbers from 241 to 276 at MH712. Splice the fiber at MH11 to a new splice case for branching off the fiber to B775, B769, and B738.

8. Install 12 strands single mode FOC from MH11 to B738. Splice the fiber at MH11 to strand numbers from 241 to 252 of the new splice case installed above. Terminate the new 12 strands cable at B738 using the FODP installed above. Test the new 12 strands cable between Core Node at Building 355 and Access Node at Building 738.

9. Install 12 strands single mode FOC from MH11, to MH10, to MH9, and then to B775. Splice the fiber at MH11 to strand numbers from 253 to 264 of the new splice case installed above. Terminate the new 12 strands cable at B775 using the FODP installed above. Test the new 12 strands cable between Core Node at Building 355 and Access Node at Building 775.

10. Install 12 strands single mode FOC from MH11, to MH10, to MH9, HH766, HH768, HH739, and then to B769.

Splice the fiber at MH11 to strand numbers from 265 to 276 of the new splice case installed above. Terminate the new 12 strands cable at B769 using the FODP installed above. Test the new 12 strands cable between Core Node at Building 355 and Access Node at Building 769.

2.6.2.3 A 50 foot maintenance loop shall be provided in every third manholes.

2.6.2.4 A 30 foot maintenance loop shall be provided in the building entrance facilities where the FOC will connect to a FODP.

2.6.2.5 The contractor will utilize ST Connector/Pigtails at each location. The connector must meet ANSI/TIA/EIA standards.

2.6.2.6 All strands of the final installation shall be tested from its core node at Building 355 to each access nodes at buildings 433, 434, 708, 712, 733, 769, 775, and 738 for proper signal attenuation end to end. Those test results will be provided to the government and will be subject to a random 10% test.

3.0 MANAGEMENT.

3.1 The contractor shall provide a complete milestone schedule that denotes major activities to include time-phased start and completion dates for this project and sub-projects associated with the installation of the components and systems.

3.2 The contractor shall remain in compliance with all Osan AB security and safety laws, regulations, policies, and requirements.

3.3 At day’s end, the contractor shall remove all debris and surplus materials from the work place. Equipment and materials required to complete the work effort may remain on site as long as they are organized/stored in a manner that does not cause a safety hazard.

3.4 Environmental Management: The Contractor shall comply, and their subcontractors, shall comply, with the most stringent environmental and local laws and regulations; and Air Force policies, instructions, and plans. The federal Government is not exempt from compliance with environmental regulations. The Contractor shall maintain an awareness of changing environmental regulatory requirements to avoid environmental deficiencies for activities on Osan AB. The Prime Contractor shall ensure their sub contractors comply with these specifications.

4.0 DELIVERABLES.

4.1 The contractor shall provide two sets of in-place drawings upon project completion in accordance with (IAW) the distribution list. Soft copies will be electronic markups in Adobe PDF format.

4.2 All deliverables are subject to Government acceptance and approval. They shall meet professional standards and the requirements set forth in the basic contract and this PWS. All deliverables shall be produced using recommended software tools/versions as accepted by the Government. The contractor shall deliver the required numbers and type of copies IAW the distribution list set forth below.

DOCUMENTS BASE

IPT Minutes *1 EM per attendee Red Line Drawings *2 CD, Test Report *2 CD, *CD = Compact Disc *PC = Paper Copy *EM=Email

5.0 CONTRACTOR EVALUATION FACTORS

5.1 The contractor shall be required to possess, at a minimum: A comprehensive knowledge of telecommunications principles such as switching, traffic, signaling, inside plant and networking; as well as knowledge of the operational, capabilities, and limitations of electronic telecommunications equipment and systems to diagnose problems and determine corrective action. Building Instruction Consulting Service International(BICSI) Telecommunications Installer Certification or International equivalent.

5.2 A knowledge of Local Area Network (LAN) principles to the facility to include hubs, switches, routers, cabling connectivity and installation. A knowledge of maintenance management practices, telephone fundamentals, electronic principles, including theory of solid-state components, digital techniques, and copper and fiber –optic modems, multiplexers, line drivers and associated hardware. Skill in the routine repair, disassembly, modification, assembly, testing, installation, and maintenance of telecommunications systems cables, equipment and accessories.

Ability to apply knowledge of wire color-codes, layout sheets, wiring diagrams and schematics. Skill in identifying and locating equipment and components in order to perform cleaning, disassembling and assembling tasks to repair and/or test. BICSI Telecommunications Engineer Certification or International equivalent.

5.3 A comprehensive knowledge of Telecommunications Circuit Flow – Circuit Troubleshooting (Voice / Video / Data). A comprehensive knowledge of ISP cable plant – Horizontal/Vertical. A comprehensive knowledge of OSI Model - Layer 1 architecture. A working knowledge of the publications listed in Part 5 of this document.

5.4 Extensive experience (minimum 5 years) in engineering, management and coordination of all communication systems requirements as assigned. NEC / Professional Engineer or International equivalent.

6.0 TESTING.

6.1 The contractor shall perform testing and inspections of all systems solutions to ensure the technical adequacy and accuracy of all work, including reports and other documents required in support of that work. The contractor shall conduct on-site testing IAW OEM’s installation manuals, practices and the appropriate vendor’s test procedures. The contractor shall participate with the government in testing the complete communications system.

When any contractor provided system, subsystem, component or requirement test fails to meet the requirements of the test, Government acceptance and payment will be withheld until such time as the cause of the failure is corrected to the Government’s satisfaction. After appropriate corrective action has been taken, all tests, including those previously completed, related to the failed test(s) and the corrective action shall be repeated and successfully completed prior to Government acceptance.

6.2 The contractor shall furnish all test equipment and personnel required to conduct all required testing. The contractor shall document all test results in “Test Report(s)” and submit to the Government. During any testing phase, the Government reserves the right to perform any of the contractor performed inspections and tests to assure solutions conform to prescribed requirements. The contractor shall provide on-site support during the acceptance testing. The Test Report(s) shall be provided to the Government no later than 10 days after test(s) have been completed.

6.3 In-progress Tests.

6.3.1 Excavations. All excavations shall be inspected for compliance with applicable installation and safety directives, and installation plan procedures. After material is placed, the contractor shall inspect and document the installation prior to backfilling. In addition, the designated government representative shall be allowed to inspect the installation prior to backfilling.

6.3.2 Fiber Optic Tests. All strands of all fiber optic cables shall be tested. As a minimum, the following tests shall be performed.

6.3.2.1 Optical Attenuation. End to end attenuation tests shall be conducted on all fiber optic cable strands. Tests shall be accomplished to ensure the installed cable is within the specified parameters. The bi-directional optical power meter method or equivalent shall be used to perform this test.

6.3.2.2 Distance. Test to determine the installed cable length between fiber optic distribution panels.

7.0 WARRANTY.

7.1 The Contractor shall provide a one year workmanship warranty and the materials warranty for all materials installed.

8.0 PERFORMANCE.

8.1 Period of Performance. Installation shall be completed by 30 June 2016

8.2 Place of Performance. The place of performance is Osan AB, ROK.

8.3 Hours of Work. Contractor shall work during normal operating hours of 8:00 AM – 5:00 PM, Monday through Friday, excluding observed Korean National holidays and United States Federal holidays.

8.3.1. U.S. FEDERAL HOLIDAYS

New Year’s Day - 1 January Martin Luther King Day - 3rd Monday in January Washington’s Birthday - 3rd Monday in February Memorial Day - last Monday in May Independence Day - 4 July Labor Day - 1st Monday in September Columbus Day - 2nd Monday in October Veteran’s Day - 11 November Thanksgiving Day - 4th Thursday in November Christmas Day - 25 December

8.3.2. K.N. holidays

New Year’s Day - 1, 2 January Lunar New year - 3 days Independence Movement Day – 1st March Labor Day – 1st May Children’s Day – 5th May Buddha’s Birthday – 12th May Memorial Day – 6th June

Constitution Day – 17th July Liberation Day – 15th August Chu Sok – 3 days National Foundation Day – 3rd Oct Christmas – 25th December

9.0 GOVERNMENT FURNISHED EQUIPMENT/INFORMATION/ACCESS/STANDARDS.

9.1 The contractor shall specifically identify in their proposal any government resources required during the performance of this Performance Work Statement.

9.2 Government applicable documents and standards. The following documents are hereby incorporated by reference. The contractor shall comply with these documents during the performance of this Performance Work Statement.

OSHA CFR 29 Part 1910-268 - (1988) Telecommunications Accessible at www.osha.gov

REA TE&CM 701/PC-5A - Rural Electrification Administration (REA) REA TE&CM 643 Form 515C - Rural Electrification Administration (REA)

Accessible at www.etler.com NEMA TC 2-1998 – Electrical Polyvinyl Chloride (PVC) Tubing and Conduit ANSI/TIA/EIA-568-B – (2001) Commercial Building Telecommunications (568B-1, 568B-2, 568B-3) Cabling Standard ANSI/TIA/EIA-569-B – (2009) Commercial Building Standard for Telecommunications Pathways and Spaces ANSI/TIA/EIA-606-A – (2002) Administration Standard for the Telecommunications Infrastructure of Commercial Buildings ANSI/TIA/EIA-607-(1994) Commercial Building Grounding and Bonding Requirements for Telecommunications

Accessible at building 949 room 203 BICSI TDM Manual - (1998) Building Industries Consulting Services International Telecommunications Distribution Methods (TDM) Manual Accessible at www.BICSI.org RUS Bulletin 1751F-640 - Design of Buried Plant-Physical Consideration RUS Bulletin 1751F-641 - Construction of Buried Plant RUS Bulletin 1751F-643 - Underground Plant Design RUS Bulletin 1751F-644 - Underground Plant Construction Telecommunications Engineering Shield Continuity and Construction Manual (TE&CM) 451.2 RUS Bulletin 345-65 (PE-33) - RUS Specification for Shield Bonding Connectors RUS Bulletin 345-54 (PE-52) - RUS Specification for Telephone Cable Splicing Connectors RUS Bulletin 345-72 (PE-74) - RUS Specification for Filled Splice Closures RUS Bulletin 345-150 (515a) - Specifications and Drawings for Construction of Direct Buried Plant RUS Bulletin 345-152 (515d) - Specifications and Drawings for Underground Cable Installation

Accessible at www.rd.usda.gov Electronics Industry Alliance EIA-310-D - Cabinets, Racks, Panels, and Associated Equipment

Accessible at HIS.com ANSI/TIA/EIA-758 - Outside Plant Telecommunication Cabling Standard ANSI/TIA/EIA-606 - Administration Standard for Commercial Telecommunication Standard

Accessible at building 949 room 203 National Electrical Manufacturers Association (NEMA) TC 2-1998 - Electrical Polyvinyl Chloride (PVC) Tubing and Conduit NFPA 70 - (2000) National Electric Code FGDC-STD-001-1998 - Content Standard for Digital Geospatial Metadata

Accessible at www.fgdc.gov

The contractor shall obtain and comply with any other applicable manuals not identified above that would be required to meet industry standards.

10.0 SECURITY. There are security requirements for performance of this contract. Escorts may be required as some work will be performed in secured facilities. It is the Government’s responsibility to provide escorts. To ensure performance starts as soon as possible, the contractor will ensure that all personnel and vehicles meet the requirements for installation entry IAW: 51FW 31-113. Chapter 4(accessible at building 949 room 203) The Contractor will provide the necessary information and documentation to ensure compliance 30 days prior to performance of work.

11.0 POINTS OF CONTACT:

Name: TSgt Brandon Ancheta Project Manager

51 CS/SCXP

Unit 949

APO, AP 96278

DSN: (315) 784-5520

Comm: 0505-784-5520 E-mail: michael.coon.1@us.af.mil

Name: Gary McCrary Plans Director

51 CS/SCXP

Unit 949

APO, AP 96278

DSN: (315) 784-5520

Comm: 0505-784-5520 E-mail: gary.mccrary.1@us.af.mil

W90VN6-16-T-0005 Page

MH

B712

MH

MH

12-1

B708

MH

12-A

B733

MH

B738

MH

MH

B775

HH

HH

HH

B769

DSLAM Cable Route (Part-2 (ITN355 To EBNs)

Drawing NOT to Scale

150'

195'

170'

175'

135'

140'

310'

170'

0'

110'

280'

80'

360'

Notes:

1. Required new 2-4'’ ducts and (3), 3-cell (total of 9) new geotextile Inner ducts in one if the new 4'’ duct.

2. Distances provided on this drawing is approximate and are subject to verify.

3. Need (3), 3-cell (total of 9) new geotextile Inner ducts in existing vacant 4'’ duct.

4. Existing vacant duct/innerduct, may use to pull new cable.

12-St to B712

3-Cable 12-St to B733 12-St to B708 1, 36-St

Splice

288L8.3F Strands 1 to 204 is assigned to various buildings

84-St (205-288 of 288 ) Not Assigned

36-St

12-S t

12-St t o B708

12-St to B775

-S t t o

B7

12-St to B769

12-St to B769

Splice

12-St to B7775

12-St to B769 12-St t o B775

12-St t o B769

-S t to

B

HH

B421

HH

HH

MH

1-14-1

HH

B434

MH

1-14

MH

1-13

MH

1-12

B

HH

202-2

215'

310'

210'

5'

285'

395' 85'

25'

Existing FOC from B355

Splice

144L8.3F

FO B355-B935, 1-48

FO B355-B502, 49-60

FO B355-B503, 61-72

FO B355-B472, 73-84

60 (of 144 ) Not Assigned

Splice

-S t

-S t

-S t

12-St

12-St

12-St

12-St 12-St

12-St

-S t

12-St t o B733

12-St to B733

Figure 1: Path with ducting information

130’

WW90VN6-16-T

T-0005