Question No. Question / Comment Government Response

1) If a contractor performs sustainment support for LMP and/or AESIP as a Prime Contractor, will this OCI them out of bidding?

2) If that contractor were to win, would they be OCId out of performing new development/sustainment work?

1. Sustainment offerors are fine, not developers as this could give them unfair advantage.

2. The work in sustainment will be ok, however not for any new development.