MATOC RFI 4 various.pdf
PDF 191 KB Posted
- Attached to
- OK MATOC
- Solicitation number
- W50S8T-20-B-0001
- Issued by
-
Department of the Army National Guard
About this file
This document contains responses to a request for information (RFI) regarding a project to demolish and construct a loading dock platform. The RFI responses clarify project details such as the requirement to provide a concrete ramp with manual adjustment but no dock leveler. Dock bumpers of an unspecified type will be required, two for each level. The existing ramp is one foot thick concrete with #5 rebar reinforcement and the interior is compacted sand. Any disturbed areas will require sodding with bermuda grass and watering until established. Reinforcement of the loading and unloading pavement area will be #5 rebar at 12-inch spacing according to the project drawings, except for an area addressed in a previous RFI.
View the file
Other files
Show all 16
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
REQUEST FOR INFORMATION
(RFI)
PROJECT TITLE: Demo and Construct Platform B1047 RFI NO: 4
PROJECT NUMBER: YZEU162024
BASE: WRANG
Initials Critical: Yes No
Date Req’d:
DISTRIBUTION/ROUTING
Date Contractor to Contracting Contracting Received Contracting to COR COR Received COR to A & E (if necessary) A & E Received A & E to COR COR Received COR to Contractor & Contracting
SUBJECT: Dock leveler Drawing/Spec Ref:
Information Requested: The following is a list of questions that we need clarification on, so that we can proceed with our bid on this project.
1. In the solicitation for bid under scope of work task list 2.2 (A) Is to provide concrete ramp with manual loading ramp adjustment. In solicitation final design drawings there is no indication of dock leveler, can you verify is there a dock leveler and if so what are the requirements?
2. There is some question as to whether or not dock bumpers would be installed on the new dock. If dock bumpers are required please provide specifications as to what kind?
3. There is a question as to the thickness of the ramp to be removed, also dimensions of any existing foundations that need to be removed and if possible a rebar layout including size and quantity?
4. It appears there will need to be a slope from the ramp to the new chain link fence. Will this area require sod, and if so what are the requirements, such as type of sod and how many days required watering?
5. In the loading and off-loading pavement area it appears to only have four section of pavement near drop inlet area that requires reinforcement steel. If this is accurate please provide rebar size and spacing?
Attachment(s):
POC: Phone: Organization:
Response: There is no dock leveler.
7-8-20
2. 4 Dock bumpers will be required 2 for each level. See att. for type of dock bumpers to be installed.
3. The existing ramp is 1 foot thick concrete on the top and sides, with #5 rebar 12" oc through out, and #5 bars tying the sides and top together. The interior is compacted sand.
4. Any disturbed areas will require to be sodded with bermuda grass, and watered until established.
5. The area south of the ramp is the loading and unloading area, and is to be constructed according to Section B-B on sheet CS-502 with the exception of the rebar being #5 vice #4 @12" oc. also answered in RFI #3.
Attachment(s):