F9S3S30162AW01

Statement of Work Project Number VBDZ202106 Relocation and Renovation of the Recruiting Off ice This is a total small business set-aside.

IAW FAR 36.204(c) the magnitude of this project is betw een $25,000 and $100,000 Bid guarantee of 20% or $1M, w hichever is less, is required.

Payment bond or IRLC (Irrevocable Letter of Credit) required.

Site visit w ill be conducted on July 6, 2020 at 9:00am Quotes due July 17, 2020 at 2:00pm and should be emailed to w anda.d.yarbor.mil@mail.mil

WANDA D. YARBOR 518-344-2487

NOTE: In sealed bid solicitations "offer" and "offeror" mean "bid" and "bidder".

10. THE GOVERNMENT REQUIRES PERFORMANCE OF THE WORK DESCRIBED IN THESE DOCUMENTS

NEGOTIATED

25-Jun-2020

(RFP)

(IFB)

X

CALL:

Relocation and Renovation of Recruiting Off ice

B. TELEPHONE NO. (Include area code) (NO COLLECT CALLS)

See Item 7

2. TYPE OF SOLICITATION

SEALED BID

3. DATE ISSUED

9. FOR INFORMATION A. NAME

SOLICITATION

NSN 7540-01-155-3212 1442-101 STANDARD FORM 1442 (REV. 4-85)

Prescribed by GSA

FAR (48 CFR) 53.236-1(e)

11. The Contractor shall begin performance w ithin _______14 calendar days and complete it w ithin ________60 calendar days after receiving aw ard, X notice to proceed. This performance period is mandatory, negotiable. (See _________________________

12 A. THE CONTRACTOR MUST FURNISH ANY REQUIRED PERFORMANCE AND PAYMENT BONDS?

(If "YES," indicate within how many calendar days after award in Item 12B.)

X YES NO

13. ADDITIONAL SOLICITATION REQUIREMENTS:

A. Sealed offers in original and __________1 copies to perform the w ork required are due at the place specif ied in Item 8 by ___________ local time ______________17 Jul 2020 (date). If this is a sealed bid solicitation, offers must be publicly opened at that time.

shall be marked to show the offeror's name and address, the solicitation number, and the date and time offers are due.

B. An offer guarantee X is, is not required.

C. All offers are subject to the (1) w ork requirements, and (2) other provisions and clauses incorporated in the solicitation in full text or by reference.

D. Offers providing less than _______60 calendar days for Government acceptance after the date offers are due w ill not be considered and w ill be rejected.

SOLICITATION, OFFER,

AND AWARD

(Construction, Alteration, or Repair)

1. SOLICITATION NO.

IMPORTANT - The "offer" section on the reverse must be fully completed by offeror.

4. CONTRACT NO.

7. ISSUED BY CODE

USPFO NY 109 MISSION SUPPORT CONTRACTING

1 AIR NATIONAL GUARD RD

SCOTIA NY 12302-9572

W50S8J

PAGE OF PAGES

1 OF

CODE

(Title, identifying no., date):

12B. CALENDAR DAYS

02:00 PM (hour)

Sealed envelopes containing offers

5. REQUISITION/PURCHASE REQUEST NO. 6. PROJECT NO.

VBDZ202106

8. ADDRESS OFFER TO (If Other Than Item 7)

FAX:TEL: TEL: FAX:

W50S8J20R0011 59

20B. SIGNATURE

(REV. 4-85)STANDARD FORM 1442 BACK

TO SIGN

NSN 7540-01-155-3212

SOLICITATION, OFFER, AND AWARD (Continued) (Construction, Alteration, or Repair)

CODE FACILITY CODE

17. The offeror agrees to perform the w ork required at the prices specif ied below in strict accordance w ith the terms of this solicitation, if this offer is accepted by the Government in w riting w ithin ________ calendar days after the date offers are due.

the minimum requirements stated in Item 13D. Failure to insert any number means the offeror accepts the minimum in Item 13D.)

AMOUNTS SEE SCHEDULE OF PRICES

18. The offeror agrees to furnish any required performance and payment bonds.

19. ACKNOWLEDGMENT OF AMENDMENTS

(The offeror acknowledges receipt of amendments to the solicitation -- give number and date of each)

AMENDMENT NO.

DATE

20A. NAME AND TITLE OF PERSON AUTHORIZED TO SIGN

OFFER (Type or print)

AWARD (To be completed by Government)

21. ITEMS ACCEPTED:

22. AMOUNT 23. ACCOUNTING AND APPROPRIATION DATA

24. SUBMIT INVOICES TO ADDRESS SHOWN IN ITEM

(4 copies unless otherwise specified)

CODE

(Insert any number equal to or greater than

20C. OFFER DATE

25. OTHER THAN FULL AND OPEN COMPETITION PURSUANT TO

10 U.S.C. 2304(c) 41 U.S.C. 253(c)

CODE27. PAYMENT WILL BE MADE BY:26. ADMINISTERED BY

(Include ZIP Code)14. NAME AND ADDRESS OF OFFEROR 15. TELEPHONE NO. (Include area code)

See Item 14

(Include only if different than Item 14)16. REMITTANCE ADDRESS

30B. SIGNATURE

29. AWARD (Contractor is not required to sign this document.)

document and return _______ copies to issuing office.) Contractor agrees Your of f er on this solicitation, is hereby accepted as to the items listed. This award con-to f urnish and deliv er all items or perf orm all work, requisitions identif ied summates the contract, which consists of (a) the Gov ernment solicitation and on this f orm and any continuation sheets f or the consideration stated in this y our of f er, and (b) this contract award. No f urther contractual document is contract. The rights and obligations of the parties to this contract shall be necessary .

gov erned by (a) this contract award, (b) the solicitation, and (c) the clauses, representations, certif ications, and specif ications or incorporated by ref er-ence in or attached to this contract.

30A. NAME AND TITLE OF CONTRACTOR OR PERSON AUTHORIZED 31A. NAME OF CONTRACTING OFFICER (Type or print)

30C. DATE

(Type or print)

TEL: EMAIL:

31B. UNITED STATES OF AMERICA 31C. AWARD DATE

BY

CONTRACTING OFFICER WILL COMPLETE ITEM 28 OR 29 AS APPLICABLE

(Contractor is required to sign this28. NEGOTIATED AGREEMENT

(M ust be fully completed by offeror)OFFER

W50S8J20R0011

Section 00 10 00 - Solicitation

ITEM NO SUPPLIES/SERVICES QUANTITY UNIT UNIT PRICE AMOUNT

0001 1 Job

BLDG 1 RECRUITING AREA PROJECT

FFP

BLDG 1 RECRUITING AREA PROJECT #VBDZ202106. The Contractor shall provide all construction services and materials for demolition and construction of new recruiting office spaces located in Building #1 per the SOW, FOB: Destination

PURCHASE REQUEST NUMBER: F9S3S30162AW01

SIGNAL CODE: A

PSC CD: Z2QA

NET AMT

ITEM NO SUPPLIES/SERVICES QUANTITY UNIT UNIT PRICE AMOUNT

0002 1 Each

CMRA

FFP

CMRA Reporting FOB: Destination

SIGNAL CODE: A

PSC CD: Z2QA

NET AMT

DELIVERY INFORMATION

CLIN DELIVERY DATE QUANTITY SHIP TO ADDRESS DODAAC /

CAGE

0001 60 dys. ADC 1 F9S3S3 - 109 CES

1 AIR NATIONAL GUARD ROAD

SCOTIA NY 12302-9752

518-344-2440 FOB: Destination

F9S3S3

0002 30-SEP-2020 1 F9S3S3 - 109 CES

SHAWN RULISON

1 AIR NATIONAL GUARD ROAD

SCOTIA NY 12302-9752

344-2480 FOB: Destination

F9S3S3

Section 00 21 00 - Instructions

EVALUATION FACTORS

EVALUATION FACTORS

Offerors shall submit their quotes electronically to both wanda.d.yarbor.mil@mail.mil and nicholas.b.bastiani.mil@mail.mil. Return a signed copy of page 2 of the solicition with your quote.

BASIS OF AWARD

Quotes will be evaluated using Simplified Acquisition Procedures IAW FAR Part 13. The Government intends to make an award to the responsible small business whose quote represents the best value based on the following factors:

TECHNICAL, PAST PERFORMANCE AND PRICE

Evaluation will be conducted as follows:

The contracting officer will evaluate all technically acceptable quotes to determine whether the lowest priced of the quotations having the highest past performance rating possible represents the best value when compared to any lower priced quotation or offer. Any quote that is determined technically unacceptable shall not be evaluated in terms of price or past performance.

TECHNICAL:

In order to be considered technically acceptable, the contractor must submit the following:

1) A completed and signed 1442, Solicitation, Offer and Award (to include acknowledgement of all amendments, if applicable) and provide a price for all line items, to include any $0 line items, if applicable.

2) A fully executed bid bond IAW the instructions contained within the solicitation.

3) A summary of no more than two pages on how you intend to complete this project to include a list of the manufacturer, part number, and specification of the materials intended to be used on this project. Include a list of any subcontactors you plan to use (if applicable).

PAST PERFORMANCE:

Submit two (2) project references with the same or similar scope to include contact information.

Past Performance will be evaluated based on this information, information contained in Contractor Performance Assessment Reporting System (CPARS) and/or the contracting officer’s knowledge or personal experience Lacking that information, the contracting officer may use any other reasonable basis to determine past performance rating.

PRICE:

Price will be evaluated based on the total price of all line items combined

Section 00 73 00 - Supplementary Conditions

Section 01 00 00 - General Requirements

GENERAL REQUIREMENTS

1. INSURANCE - MINIMUM AMOUNTS

1.1. Reference Contract Clause titled, “Insurance -Work on a Government Installation (FAR 52.228-5). Kinds and minimum amounts are as follows:

KIND AMOUNTS

Workmen’s Compensation $100,000 (see paragraph 1.2, below)

Comprehensive General Liability $500,000 per occurrence for bodily injury

Comprehensive Automobile Liability $200,000 per person and $500,000 per accident for bodily injury and $20,000 for property damage

1.2. Except in states with exclusive or monopolistic funds that do not permit workers’ compensation to be written by private carriers.

1.3. NOTE: Before commencing work under this contract, the Contractor shall certify to the Contracting

Officer, in writing, that the required insurance has been obtained. The policies referenced in the certification (s) shall contain an endorsement to the effect that any cancellation or any material change adversely affecting the Government’s interest shall not be effective (1) for such period as the laws of the state in which this contract is to be performed prescribe or (2) until 30 days after the insurer or the Contractor gives written notice to the Contracting Officer, whichever period is longer. The Contractor shall maintain a copy of proofs of required insurance, and shall make copies available to the Contracting Officer upon request. The Contractor shall maintain a copy of all subcontractors’ proofs of required insurance, and shall make copies available to the Contracting Officer upon request.

2. Reserved.

3. SCHEDULING

3.1. Normal base work hours for the Contractor will be between the hours of 7:00 AM through 4:30 PM, excluding Saturdays, Sundays, and Federal Holidays. If the Contractor desires to work during periods other than above, he must notify the Contracting Officer’s Representative (COR) five (5) working days in advance of his intention to work during other periods to allow assignment of additional inspection forces. When the COR determines that they are reasonably available, he may authorize the Contractor to perform work during periods other than normal duty hours/days. However, if inspectors are required to perform in excess of their normal duty hours/days solely for the benefit of the Contractor, the actual cost of the inspection, at overtime rates, will be charged to the Contractor and will be deducted from the final payment of the Contract amount.

3.2. The following Federal legal Holidays are observed by this base:

New Year’s Day 1 January Martin Luther King’s Birthday Third Monday of January President’s Day Third Monday of February Memorial Day Last Monday of May Independence Day 4 July Labor Day First Monday in September Columbus Day Second Monday in October Veteran’s Day 11 November

Thanksgiving Day Fourth Thursday in November Christmas Day 25 December

3.3. NOTE: Any of the above holidays falling on a Saturday will be observed the preceding Friday; holidays falling on a Sunday will be observed on the following Monday.

3.4. Prior to commencing work on the job initially, resumption of work after prolonged interruption (7 calendar days or more), commencement of any warranty work, and upon completion of warranty work, the contractor must notify the Contracting Officer (or the Contracting Officer’s Representative). When relocating to new sites, returning to sites for follow-up work on a phased work plan, notification to the Contracting Officer’s Representative is sufficient. Notification should be by personal contact; however, advance notification may be by telephone, or in writing, and should be accomplished sufficiently in advance to allow scheduling of inspection forces. The purpose of the above precautions is to ensure construction inspection and recording of work proceedings.

3.5. The organization of the specifications into divisions, sections, and articles, and the arrangement of the drawings shall not control the Contractor in dividing the work among subcontractors or in establishing the extent of the work to be performed by any trade.

4. INVOICING AND PAYMENT

4.1. Properly prepared invoices, bearing the contract number, shall be emailed to the Contracting Officer at wanda.d.yarbor.mil@mail.mil or nicholas.b.bastiani.mil@mail.mil on designated invoice forms provided at the pre-construction meeting PRIOR to uploading in Wide Area Workflow (WAWF) the DFAS paying system.

This submission will be for review prior to submitting an electronic invoice through Wide Area Workflow (WAWF). See end of this Section for important information and codes needed. Payment will be made by in accordance with FAR Clause 52.232-5 Fixed-Price Construction Contracts and FAR Clause 52.232-27, Prompt Payment for Construction Contracts, All payments will be made by electronic transfer of funds (EFT).

4.2. To meet compliance with DFARS 252.232-7003, Electronic Submission of Payment Requests, you shall submit your request for payment (invoice) through WAWF. For more information on the WAWF system, including how to register, visit https://wawf.eb.mil. Payment will be made by paying office specified in the contract award in accordance with the clauses Payments under Fixed-Price Construction Contracts, FAR 52.232-5, and Prompt Payment for Construction Contracts, FAR 52.232-27.

4.3. The Government will make payment through WAWF upon satisfactory completion of work AND receipt of a proper certification for payment. Do not input invoice into WAWF until the pre-approval of invoice is received from the contracting officer. This will lessen the need for rejections in WAWF Payment may be withheld unless all contractual requirements including but not limited to: RECEIPT OF PROPER WEEKLY PAYROLLS IAW DAVIS BACON REQUIREMENTS, Small Business Subcontracting Reports, have been timely received.

4.4. All requests for payments through WAWF must include a Subcontractor Payment Register pursuant to

FAR Clause 52.232-5 and a contractor’s certification that reads as follows:

I hereby certify, to the best of my knowledge and belief that – The amounts requested are only for performance in accordance with the specifications, terms and conditions of the contract; All payments due to subcontractors and suppliers from previous payments received under the contract have been made, and timely payments will be made from the proceeds of the payment covered by this certification, in accordance with subcontract agreements and requirements of Chapter 39 of Title 31, United States Code; This request for progress payments does not include any amounts which the prime contractor intends to withhold or retain from subcontractor or supplier in accordance with the terms and conditions of the subcontract; and This certification is not to be construed as final acceptance of a subcontractor’s performance.

4.5. The Government will make payment upon satisfactory completion of work AND receipt of a proper certification for payment. Payment may be withheld unless all contractual requirements, including but not limited to: RECEIPT OF PROPER WEEKLY PAYROLLS IAW CONSTRUCTION WAGE REQUIREMENTS FAR 52.222-6. Payrolls shall indicate CLIN to which they are applicable.

4.6. A release of claims is required for all final payment requests and shall be submitted by the contractor with the final invoice.

5. CONTRACT ADMINISTRATION

5.1. The contracting office of the 109th Airlift Wing is the office having administrative jurisdiction over this contract for all matters. A list of the names and telephone numbers of the Government team comprising the contract administrator, Contracting Officer’s Representative (COR), consultant, and point of contact at the project site will be provided at the post-award/pre-construction conference.

5.2. All correspondence shall be addressed to the Contracting Officer. A copy of all correspondence shall be furnished to the contracting officer’s representative. Enclosures attached to or transmitted with the correspondence shall also be furnished with an original and one copy. Each letter shall make reference to the contract name, contract number, project number, and project title, and shall have only one subject. For tracking purposes, a sequential numbering system should be used for all correspondence.

6. PAPERLESS CONTRACTING

6.1. The National Guard is fully committed to the Federal Government’s electronic commerce and paperless contracting initiatives. As such, it is anticipated that to the maximum extent possible to include but not limited to correspondence, modification distribution, etc., to include specifications and drawings, will be issued using electronic methods, i.e., electronic mail (e-mail). Contractors shall have and maintain capability to receive documents in this manner.

6.2. Additionally, it is anticipated that within the life of this contract, other electronic processes will be enacted.

These include, but are not limited to, electronic bidding/offers, change order proposals, and electronic invoicing.

When implemented by the Contracting Officer, contractors shall participate fully in any of these new requirements at no additional cost to the Government.

7. TELEPHONE COMMUNICATIONS SECURITY MONITORING

All communications with DOD organizations are subject to communications security (COMSEC) review. Contractor personnel must be aware that telephone communications networks are continually subject to intercept by unfriendly intelligence organizations. The DOD has authorized the military departments to conduct COMSEC monitoring and recording of telephone calls originating from, or terminating at, DOD organizations. Therefore, civilian contractor personnel are advised that any time they place a call to, or receive a call from, a DOD organization, they are subject to COMSEC procedures. The contractor shall assume the responsibility for ensuring wide and frequent dissemination of the above information to all employees dealing with DOD information.

8. UTILITY SERVICES

The Contracting Officer has determined that Government-operated utilities are adequate and will be furnished to the contractor without charge where existing outlets are available. The contractor is responsible for installing temporary service outlets, as necessary, at its expense in accordance with the clause entitled “Availability and Use of Utility Services” (FAR Clause 52.236-14). The following utilities will be available: Reasonable amounts of water and electricity.

9. PREPARATION OF MATERIAL APPROVAL SUBMITTALS

The contractor shall submit all materials and articles requiring approval, as required by the Material and Workmanship Clause, FAR 52.236-5. Submittals shall be made using AF Form 3000, or approved equal.

Submittals shall be processed in accordance with the procedures in Section 01 33 00, Submittals. Submittals shall be given a distinct identification system by CLIN if multiple CLINS are applicable. Individual submittal documents shall not be comprised of items for more than one CLIN. Address for delivery of submittals will be provided at the post award/pre-construction conference. The contractor is reminded that an individual within the company who has authority to make the certification must sign the certification on the AF Form 3000.

10. WORK PROGRESS AND PREPARATION OF PROGRESS SCHEDULES AND REPORTS

10.1. A weekly meeting may be held with the Contractor, COR and Contracting Officer (KO), if necessary, to discuss work progress, problems and potential change orders. The Contractor shall attend these meetings at no additional cost to the Government. Prior to beginning work on specific work elements of a project, the contractor shall confer with the COR and agree on a sequence of procedures and means of access to premises and buildings;

space for storage of materials and equipment; delivery of materials; and use of approaches, use of corridors, stairways and similar means of passage.

10.1.1. In accordance with FAR Clause 52.236-15, “Schedules for Construction Contracts”, the contractor shall within five days after work commences on the contract, or another period of time determined by the KO, prepare and submit to the KO for approval three copies of a practicable schedule showing the order in which the contractor proposes to perform the work, and the dates on which the Contractor contemplates starting and completing features of work. A composite schedule for the overall contract shall also be provided. The schedule shall be on an AF Form 3064, Contract Progress Schedule, or an approved computer generated format similar to the AF Form 3064. The work shall be scheduled so that, upon the start of construction, work progresses in a continuous and diligent manner. A schedule which does not reflect steady and reasonable progress throughout the construction period will be rejected. Both the Contractor and the COR are required to provide monthly progress reports covering the period from notice to proceed through final inspection. Unless agreement cannot be made on the applicable percentage of progress a joint report will be submitted to the Contracting Officer. This reports shall be submitted on the NGB Contract Progress Report form (similar to an AF Form 3065), or an approved computer generated similar format. These reports shall track progress by CLIN, if contract contains multiple CLINs, multiple AF Form 3064 and NG Contract Progress Reports will also be required for payment purposes.

10.2. Additionally, for projects exceeding $1M, the contractor shall provide a project plan in a commercially available network scheduling software that meets requirements of the specification to define work tasks and track progress. At least five days prior to work initiation, the contractor shall provide the Contracting Officer a hardcopy CPM and a formatted diskette or CD copy, or e-mail file copy, of the plan that shall include definition of rescues. No work may start until the Contracting Officer approves the plan in writing.

10.3. The Contractor shall prepare a work progress schedule required for completion of each of the various divisions of work. Updated plans and Form 3064 showing work progress (hardcopy and formatted diskette or CD, or e-mail file copy), unless otherwise directed by the Contracting Officer, shall be provided bi-weekly. If there are possible deviations from the original plan, those must be noted and approved by the Contracting Officer before work changes are implemented. The schedule shall be submitted to the Contracting Officer, in the number of copies as directed. Reference Contract Clause FAR 52.236-15, “Schedules for Construction Contracts”. The reports contemplated by the clause herein titled “Schedules for Construction Contracts” shall be accomplished on and in accordance with instructions pertaining to AF Form 3064, “Contract Progress Schedule” and a National Guard Contract Progress Report”.

11. NOTICE OF COMPLETION OF CONSTRUCTION/PRE-FINAL AND FINAL INSPECTION

11.1. The contractor shall conduct a pre-final inspection in the presence of the Contracting Officer’s Representative (COR) prior to the date scheduled for Final Inspection. Any discrepancies noted shall be corrected prior to Final Inspection.

11.2. The contractor shall request scheduling of a final inspection in writing to the Contracting Officer at least five (5) working days prior to the desired date or as otherwise negotiated with the Contracting Officer.

11.3. Civil Engineering personnel and the Contracting Officer will perform the Final Inspection in the presence of the contractor, and any discrepancies noted shall be corrected within the time specified by the Contracting Officer.

11.4. Final Inspection shall not constitute acceptance of a project unless so stipulated by issuance of a separate acceptance notice.

11.5. The contractor is cautioned to ensure they have completed adequate Quality Control reviews prior to scheduling pre-final or final inspections. In the event the Contracting Officer finds that the project is not ready for the applicable inspection, (too many discrepancies) the contractor may be held liable for the costs of a repeat inspection. If the inspection involves A/E personnel these costs may include additional labor, travel and miscellaneous expenses.

12. DESIGNATION OF TECHNICAL REPRESENTATIVE

The Contracting Officer will appoint a qualified Contracting Officer’s Representative (COR) for the purposes of technically administering the contract; however, all matters concerning this contract or any work ordered placed against this contract must first be approved by the Contracting Officer. This in no way authorizes anyone other than the Contracting Officer to commit the Government to changes in terms of the contract.

13. CONTRACTOR STAFF AND EMPLOYEES

13.1. Prior to commencing on-site construction, the contractor shall provide the Contracting Officer with a telephone number and FAX number at which the contractor or his representative may be contacted at any time during regular working hours and an emergency number at which the contractor may be contacted in situations requiring immediate attention.

13.2. Supervision. The Government shall not exercise any supervision or control over the contractor employees performing services under this contract; such employees shall be accountable not to the Government, but solely to the contractor, who in turn is responsible to the Government.

13.3. Contractor’s Employees. All work under this contract shall be performed in a skillful and workmanlike manner. The Contracting Officer may, in writing, require the contractor to remove from the job site, any employee the Contracting Officer deems incompetent, careless or otherwise objectionable.

14. CONTRACTOR OFFICE AND STORAGE

14.1. Parking of contractor vehicles shall be restricted to the contractor’s designed on-site area or the work area. The company name shall be prominently displayed on all construction vehicles parked on the job site.

14.2. Security of material storage areas on the job site shall be the responsibility of the contractor. The area shall be kept neat and orderly and free of debris.

15. RECORD DRAWINGS

During construction of a project and on the job site, the contractor shall maintain a completed record of all changes and corrections from the layout shown on the drawings, if applicable. The contractor shall enter such changes and corrections on contract or record drawings promptly, and submit the “red line” drawings to the Contracting Officer upon completion of the project. The record drawings shall indicate all changes and corrections concerning the actual locations of all sub-surface utility lines. In order for the location of these lines and appurtenances to be determined in the event the surface opening or indictors become covered or obscured, the record drawings shall show, by offset dimensions to two permanently fixed surface features, the end of the each run including each change in direction.

Valves splice boxes, and similar appurtenances shall be located by dimensioning along the utility run from a reference point. The average depth below the surface of each run shall also be recorded. The Government does not guarantee the accuracy of existing record drawings; it is the contractor’s responsibility to verify all as-built conditions.

16. VERIFICATION OF DIMENSIONS

The contractor shall be responsible for the coordination and proper relation of all aspects of the work. He/she shall field verify all dimensions and advise the Contracting Officer of any discrepancies prior to proceeding with any phase of the work. Where exact locations are not given for the positioning of equipment and devices, they shall be positioned to permit easy access for maintenance and for removal and replacement of component parts.

17. SECURITY REQUIREMENTS

17.1. The contractor shall comply with all security regulations imposed by the base/post commander and/or agency occupying the space where work is to be performed. Any necessary security clearances shall be obtained prior to commencement of work.

17.2. It is expected that new security requirements to satisfy contractor personal identification requirements in Homeland Security Presidential Directive (HSPD-12), ''Policy for a Common Identification Standard for Federal Employees and Contractors,'' and Federal Information Processing Standards Publication (FIPS PUB) Number 201, ''Personal Identity Verification (PIV) of Federal Employees and Contractors” are incorporated in the life of this contract. Contractor shall comply with all requirements, at no additional cost to the Government.

17.3. The contractor shall ensure that all parts of the facility where work is being performed are adequately protected against vandalism and theft.

17.4. Contractors shall follow instructions provided by the Security Forces for access to the Stratton ANGB.

If a gate pass is not granted to a contractor allowing the delivery of goods, execution of warranty support, or performance of services please contact the contracting officer. Be sure that all of your employees have the proper ID (drivers license, state ID, immigration card, U.S. Passport, etc.). If they do not have the proper ID, they will be turned away.

17.5. The Prime Contractor and all of its subcontractors will be required to wear orange or lime colored safety vests while performing work on the installation.

17.6. U.S. Government will not be held liable for any delays or breach of contract caused by refusal of the

Security Forces to allow entry.

17.7. All prospective contractors MUST be U.S. citizens or MUST have established and maintain legal residence in the U.S., and are authorized by the US government to work in the United States (i.e. Green card, worker authorization, etc.). All prospective contractors MUST have at least one form of U.S. government issued photo identification (drivers license, U.S. passport, U.S. work visa, etc.) for entry to the installation. Security Forces will review any questionable identification documents for determination as to whether or not said identification is authorized for access to the installation.

17.8. All prospective contractors/contractor employees, once it has been established that they maintain the appropriate credential as described in one above, are subject to a Criminal History Check.

17.9. Note: For the purposes of Contracting services, it is implied that, that any and all parties agree to a

Criminal History Background Check once entered into any contract. Any documents that are provided and found fraudulent to include, but not limited to driver’s licenses, contracting licenses, etc., will result in an arrest and potential termination for default from the contract. All contractors are subject to search in order to obtain entry onto the installation and while working on the installation. Any refusal to submit to a search of their person or vehicle will be deemed as a violent act of aggression against the installation and will be cause for dismissal from the installation and revocation of future privileges and installation access.

17.10 The contractor shall comply with all applicable installation/facility access and local security policies and procedures, which may be obtained from the Contracting Officer’s Representative (COR). The contractor shall also provide all information required for background checks to meet installation access requirements to be accomplished by the local installation’s Security Forces, Director of Emergency Services or local Security Office. The contractor shall ensure compliance with all personal identity verification requirements as directed by DoD, HAF and/or local policy. Should the Force Protection Condition (FPCON) change, the Government may require changes in contractor security matters or processes.

17.11 Contractor and all associated sub-contractors employees shall comply with adjudication standards and procedures using the National Crime Information Center Interstate Identification Index (NCIC-III) and Terrorist Screening Database (TSDB) (AFI 31-101 and AFI 10-245), applicable installation, facility and area commander installation/facility access and local security policies and procedures (provided by government representative), or, at OCONUS locations, in accordance with status of forces agreements and other theater regulations.

17.12 The use and possession of controlled substances to include marijuana (medical or recreational use) on the installation is in violation of Title 10 US Code 912a. Art 112a. Contractors are notified this policy is strictly enforced and violators will be denied entry. Personnel caught on the installation can be prosecuted.

18. REGULATIONS

18.1. The contractor shall comply with all applicable Federal, State, Local, DOD, National Guard Bureau, Army and Air Force regulations pertaining to safety, traffic control and fire prevention.

19. TRANSPORTATION, HANDLING AND STORAGE

19.1. The contractor shall coordinate with suppliers and shippers to ensure that incoming materials are properly identified with the contractor’s name, contract number and project title. The contractor shall designate an authorized individual to be available to receive shipment. The Government will not provide storage other than that available at the project site.

19.2. Storage of supplies, materials and equipment on the project site shall be accomplished in such a manner so as to prevent mechanical and climatic damage and loss due to vandalism or theft. Equipment temporarily removed in the performance of work and stored on the job site shall be stored and protected in accordance with previous paragraphs, and shall be replaced in a condition compatible with its original state. Security for equipment and material removed from the job site for temporary storage until reuse shall be the responsibility of the contractor.

20. CLEANUP AND DISPOSAL OF DEBRIS AND FILL MATERIALS

20.1. At the end of each workday, the contractor shall clean up the work and storage areas and stack all materials in a manner approved by the Contracting Officer or his designated representative. Upon completion of a project, the contractor shall ensure that all dirt, trash, and debris resulting from the construction operations are removed from the work area. Unless directed otherwise in the contract or by the Contracting Officer, disposal of debris shall be made at the contractor’s expense and shall be delivered to a state approved disposal site located off base. Debris shall not be left in such a manner that wind or other weather conditions can cause the debris to be scattered outside the work area (i.e., on nearby runways, ramps or taxiways).

20.2. The hauling and disposal of excess fill material including rock, gravel, sod, broken concrete or asphalt, plaster, etc., shall be the responsibility of the contractor. Disposal shall be in accordance with applicable state and local regulations.

21. ENVIRONMENTAL IMPACT

All waste materials generated by any work under the contract performed on a Government installation shall at all times be handled, transported, stored, and disposed of by the contractor and by his subcontractors in accordance with all applicable Federal, state, and local laws, ordinances, regulations, court orders, and other types of rulings having the effect of the law. Should the United States Government be held liable for any neglect or improper actions by the contractor or any subcontractor regarding removal or disposal of any hazardous waste, the contractor shall reimburse the Government for all such liability.

22. HAZARDOUS MATERIALS

22.1. Any material suspected of being hazardous that is encountered during performance of a project shall immediately be brought to the attention of the Contracting Officer, at which time a determination will be made as to whether hazardous material testing shall be performed. If the Contracting Officer directs the contractor to perform tests, and/or the material is found to be of a hazardous nature requiring additional protective measures, a contract modification may be required, subject to equitable adjustment under the terms of the contract.

22.2. The contractor is advised that friable and/or non-friable asbestos-containing material may be encountered in project areas. Friable asbestos-containing material is any material that contains more than one percent asbestos by weight, and that hand pressure can crumble, pulverize or reduce to powder when dry. Non-friable asbestos-containing materials are materials in which asbestos fibers are bound by a matrix material, saturation, impregnation or coating. Non-friable asbestos-containing materials do not normally release airborne asbestos fiber during routine handling and end-use. However, excessive fiber concentrations may be produced during uncontrolled abrading, sanding, drilling, cutting, machining, removal, demolition, or other similar activities.

29 CFR 1910.1001 shall be referenced in the event asbestos-containing materials are encountered. Friable asbestos-containing materials are not authorized for use in new construction or maintenance projects.

23. POLLUTION ABATEMENT

23.1. All work shall be performed in a manner minimizing pollution of air, water and land as required.

23.2. Transporting materials to or from the site shall be accomplished in a manner preventing materials or particles from becoming airborne. Earth materials shall be wetted or otherwise protected. Gravel, sand and concrete shall be contained within vehicles to prevent spillage. Tarpaulins must be fastened over load before entering surrounding streets. Removal of any materials dropped or blown off vehicles shall be the responsibility of the contractor.

23.3. Burning of any material is strictly prohibited.

23.4. Stream beds, lakes, drainage ways, sanitary and storm sewers, etc., shall not be polluted by fuels, oils, bitumen, acids or other harmful materials. Grading shall be accomplished to prevent surface drainage from the construction site containing harmful amounts of sediment from draining onto adjacent areas.

23.5. Flushing of concrete trucks is restricted to the location specifically designed for this purpose by the

Contracting Officer’s Representative.

23.6. Excess mortar, plaster or drywall materials shall not be disposed of on Government property. Water utilized for plastering or drywall equipment shall be disposed of in accordance with the instructions of the COR, and under no circumstances shall water be disposed of in areas which are planted or scheduled to be planted.

24. COORDINATION WITH GOVERNMENT ACTIVITIES

24.1. If it becomes necessary to interrupt work activities in buildings and/or areas for construction purposes, permission to do so must be requested in writing to the Contracting Officer within 5 working days prior to commencing work on the planned interruption and shall be subject to Civil Engineering approval. Written requests for street closing shall be submitted for approval of the Civil Engineer within 7 working days prior to closing the street.

24.2. Work in connection with this contract which requires utility outages, including electrical, water, gas, steam, etc., which will close down or limit (as determined by the Contracting Officer) normal activities in the building, construction area or other affected areas, shall be performed by the contractor at a time other than the regular work period of the organization occupying the facility. Work required by the contractor on a non-standard basis or at premium pay shall be done at no additional cost to the Government. Request for utility outages shall be submitted to the Civil Engineer, in writing within 7 working days prior to commencing work and shall be subject to his/her approval.

24.3. Any temporary construction for facilities used by the contractor for preventing interruption of normal work activity or loss of utility services shall be subject to Contracting Officer’s approval.

25. UNAUTHORIZED PERSONNEL

The contractor shall inform all personnel working under his jurisdiction (including subcontractor and visiting supplier personnel) that access to areas outside of the immediate work area; excluding direct haul and access routes, contracting and Civil Engineering offices, and points of supply and storage; is prohibited. Circulation of said personnel will be limited to official business only. Persons in violation of the above will be apprehended and appropriately disciplined.

26. PERFORMANCE EVALUATION OF CONTRACTOR

26.1. As a minimum, the contractor’s performance will be evaluated upon final inspection. Any specific requirements for contract quality control and quality assurance by the Government personnel will be defined in the specifications. The contractor will be rated as outstanding, satisfactory or unsatisfactory in the areas of contract quality control, timely performance, effectiveness of management, compliance with labor standards, and compliance with safety standards. The contractor will be notified of any unsatisfactory rating, either in an individual element or in the overall rating, prior to completing the evaluation, and all contractor comments will be made a part of the official record. Performance evaluation reports will be available to all DoD Contracting Officers for their future use.

26.2 Past Performance evaluations will be posted via https://www.cpars.gov. It is the responsibility of the contractor to request access to this site.

27. SAFETY ASSURANCE

27.1. Compliance with Regulations. All work including the handling of hazardous materials or the disturbance or dismantling of structures containing hazardous materials shall comply with the applicable requirements of 29 CFR 1910/1926. Work involving the disturbance or dismantling of asbestos or asbestos-containing materials; the demolition of structures containing asbestos; and/or disposal and removal of asbestos, shall also comply with the requirements of 40 CFR, Part 61, Subpart A. All work shall comply with applicable state and municipal safety and health requirements. Where there is a conflict between applicable regulations, the most stringent shall apply. The Safety Manual is available at the following web site:

http://www.usace.army.mil/SafetyandOccupationalHealth/SafetyandHealthRequirementsManual.aspx

27.2. Contractor Responsibility. The contractor shall assume full responsibility and liability for compliance with all applicable regulations pertaining to the health and safety of personnel during the execution of work. The Government shall not be held liable for any actions on the part of the contractor, his employees or subcontractors, which result in illness, injury or death.

28. PRE-CONSTRUCTION CONFERENCE

Before work commences on this contract, the Contracting Officer will conduct a conference to acquaint the contractor with Government policies and procedures that are to be observed during the execution of the work and to develop mutual understanding relative to the administration of the contract. Contractors and/or major subcontractors shall attend this meeting at no additional cost to the Government.

29. MILITARY REAL PROPERTY DATA – DD FORM 1354

29.1. Contractors shall furnish real property data to the Government for each new construction and/or renovation project awarded, unless otherwise notified. The real property data shall be furnished via DD Form 1354, Transfer and Acceptance of Military Real Property, or in a format prescribed on the DD Form 1354. The Contractor is responsible for accuracy of data current up to the time of submission.

29.2. For major renovation and/or complex projects, or those expected to exceed 12 months, the

Contractor shall furnish real property data no less than on a quarterly basis. Frequency of submission shall be standard throughout the duration of the project. Contractors are advised to record information on the DD Form 1354 (or approved facsimile) as the project progresses, due to the volume of data required to be furnished. Upon completion of the project, the Contractor shall furnish a final, comprehensive DD Form 1354.

29.3. DD Form 1354 accounts for five percent (5%) of the total contract amount and therefore, 5% must be shown on the AF Form 3065 or similar breakdown of costs submitted for payment purposes. Upon acceptance of data by the real property specialist, the contractor may invoice for submission of real property data.

29.4. Contractors should contact the COR with questions pertaining to the DD Form 1354. For construction data assistance, Contractors may consult the COR assigned to the project.

30. TIME EXTENSIONS FOR UNUSUALLY SEVERE WEATHER

30.1. This Paragraph specifies the procedure for the determination of time extensions for unusually severe weather. In order for the Contracting Officer to award a time extension under this clause, the following conditions must be satisfied:

30.1.1. The weather experienced at the project site during the contract period must be found to be unusually severe, that is, more severe than the adverse weather anticipated for the project location during any given month.

30.1.2. The unusually severe weather must actually cause a delay to the completion of the project. The delay must be beyond the control and without the fault or negligence of the contractor.

30.1.3. Weather delays will be based on National Oceanic and Atmospheric Administration

(NOAA) or similar data for the project location and will constitute the base line for monthly weather time evaluations. The contractor’s progress schedule must reflect consideration of these anticipated adverse weather delays in all weather dependent activities.

PARTIAL PAYMENTS ARE AUTHORIZED FOR THIS ORDER

WIDE AREA WORKFLOW STATEMENT (FEB 2006)

IAW 252.232-7003, all invoices must be submitted via WAWF. It is mandatory that you use this E-Invoicing system to ensure timely payment of your invoice.

The web site for this system is https://wawf.eb.mil. There are no charges to use WAWF. All questions relating to system setup and vendor training can be directed to the help desk at Ogden. Their number is 1-866-618-5988.

Failure to include email address will delay payment. The Government is not responsible for delays caused by improper submission and notification in WAWF.

The paying office DoDAAC and mailing address can be located on the front of your award. You can easily track your payment information on the DFAS website at http://myinvoice.csd.disa.mil/index.html. Your purchase order/contract number or invoice number will be required to inquire status of your payment.

CLAUSES INCORPORATED BY REFERENCE

52.203-5 Covenant Against Contingent Fees MAY 2014 52.203-7 Anti-Kickback Procedures JUN 2020 52.203-17 Contractor Employee Whistleblower Rights and Requirement

To Inform Employees of Whistleblower Rights

JUN 2020

52.204-24 Representation Regarding Certain Telecommunications and Video Surveillance Services or Equipment.

DEC 2019

52.204-26 Covered Telecommunications Equipment or Services-- Representation.

DEC 2019

52.211-10 Commencement, Prosecution, and Completion of Work APR 1984 52.216-24 Limitation Of Government Liability APR 1984 52.219-6 Notice Of Total Small Business Set-Aside MAR 2020 52.222-3 Convict Labor JUN 2003 52.222-6 Construction Wage Rate Requirements AUG 2018 52.222-7 Withholding of Funds MAY 2014 52.222-8 Payrolls and Basic Records AUG 2018 52.222-10 Compliance with Copeland Act Requirements FEB 1988 52.222-12 Contract Termination-Debarment MAY 2014 52.222-13 Compliance With Construction Wage Rate Requirements and

Related Regulations

MAY 2014

52.222-14 Disputes Concerning Labor Standards FEB 1988 52.222-15 Certification of Eligibility MAY 2014 52.222-50 Combating Trafficking in Persons JAN 2019 52.222-55 Minimum Wages Under Executive Order 13658 DEC 2015 52.223-5 Pollution Prevention and Right-to-Know Information MAY 2011 52.223-18 Encouraging Contractor Policies To Ban Text Messaging

While Driving

JUN 2020

52.225-13 Restrictions on Certain Foreign Purchases JUN 2008 52.225-25 Prohibition on Contracting with Entities Engaging in Certain

Activities or Transactions Relating to Iran-- Representation and Certifications.

JUN 2020

52.228-5 Insurance - Work On A Government Installation JAN 1997 52.232-5 Payments under Fixed-Price Construction Contracts MAY 2014 52.232-18 Availability Of Funds APR 1984 52.232-27 Prompt Payment for Construction Contracts JAN 2017 52.232-33 Payment by Electronic Funds Transfer--System for Award

Management

OCT 2018

52.233-2 Service Of Protest SEP 2006 52.233-3 Protest After Award AUG 1996 52.236-2 Differing Site Conditions APR 1984 52.236-3 Site Investigation and Conditions Affecting the Work APR 1984 52.236-5 Material and Workmanship APR 1984 52.236-6 Superintendence by the Contractor APR 1984

52.236-7 Permits and Responsibilities NOV 1991 52.236-9 Protection of Existing Vegetation, Structures, Equipment, Utilities, and Improvements

APR 1984

52.236-11 Use and Possession Prior to Completion APR 1984 52.236-12 Cleaning Up APR 1984 52.236-14 Availability and Use of Utility Services APR 1984 52.236-28 Preparation of Proposals--Construction OCT 1997 52.237-2 Protection Of Government Buildings, Equipment, And

Vegetation

APR 1984

52.243-5 Changes and Changed Conditions APR 1984 52.244-6 Subcontracts for Commercial Items JUN 2020 52.246-21 Warranty of Construction MAR 1994 52.249-2 Termination For Convenience Of The Government (Fixed-

Price)

APR 2012

52.253-1 Computer Generated Forms JAN 1991 252.203-7000 Requirements Relating to Compensation of Former DoD

Officials

SEP 2011

252.203-7002 Requirement to Inform Employees of Whistleblower Rights SEP 2013 252.203-7005 Representation Relating to Compensation of Former DoD

Officials

NOV 2011

252.204-7003 Control Of…