W50S82-21-R-0001.pdf

PDF 585 KB Posted

Attached to
High Expansion Foam Install w/Pumphouse Federal contract opportunity
Solicitation number
W50S8221R0001
Issued by
Department of the Army Maryland Army National Guard

About this file

This Request for Proposal issued by the Maryland Army National Guard seeks a firm fixed-price contract to replace an existing fire alarm system with a new high expansion foam system at two hangars, and construct a new pumphouse. The contractor must provide all labor, materials, equipment, tools, licenses and permits to complete the project within 365 days of notice to proceed. The North American Industry Classification Code is 236220, with a size standard of $39.5 million. The solicitation is set aside 100% for women-owned small businesses. Offerors must perform at least 25% of the contract cost with their own employees in accordance with FAR 52.219-14. Plans and specifications are available only through the Contracting Opportunities website using an MPIN password, which normally takes 7 to 12 business days to obtain. The place of performance is Middle River, Maryland.

View the file

Other files for this federal contract opportunity

Other files attached to High Expansion Foam Install w/Pumphouse, newest first.
File Type Posted
RFI W50S8221R0001 17 Jun 2021.pdf PDF
W50S8221R00010003.pdf PDF
W50S8221R00010002.pdf PDF
RFI W50S8221R0001 16 Jun 2021.pdf PDF
U-3 PWATER MPUtilities-Layout1.pdf PDF
RFI W50S8221R0001 11 Jun 2021.pdf PDF
Vendor sign in sheet.pdf PDF
RFI W50S8221R0001.pdf PDF
Pre-proposal slides.ppt PPT presentation
W50S82-21-R-0001-0001.pdf PDF
WF 113 - Installation Access Application.pdf PDF
Exhibit D_Letter of Commitment.docx DOCX document
EXHIBIT A.doc DOC document
RFI 1.docx DOCX document
EXHIBIT B.doc DOC document
EXHIBIT_C_Reference_Questionnaire_Package.docx DOCX document
Show all 16

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

PJMS 152001 Fire Suppression Installation

The Maryland Air National Guard is seeking services to replace the current f ire suppression system w ith a new high expansion foam system and construct a new pump house and associated w ork. IAW FAR 36.204(f), the disclosure of magnitude for this projects is betw een $1,000,000 and $5,000,000. The project is %100 set aside for w omen ow ned small buisness. The NAICS code for this project is 236220 w ith a size standard of $39.5 million.

Funds are not currently available for this contract. The Government anticipates funds w ill become available but no later than midnight 30 Sep 2021. This action has been identif ied on the National Guard priority list for aw ards and if funds become available and if prices received are w ith in an an aw ardable range. Aw ard w ill be made to the responsible offeror w hos proposal conforms to the request for proposal and is most advantageous to the Government.

MICHAEL DOMBKIEWICZ 410-918-6218

NOTE: In sealed bid solicitations "offer" and "offeror" mean "bid" and "bidder".

10. THE GOVERNMENT REQUIRES PERFORMANCE OF THE WORK DESCRIBED IN THESE DOCUMENTS

NEGOTIATED

18-May-2021

(RFP)

(IFB)

X

CALL:

Fire Suppression Installation

B. TELEPHONE NO. (Include area code) (NO COLLECT CALLS)

See Item 7

2. TYPE OF SOLICITATION

SEALED BID

3. DATE ISSUED

9. FOR INFORMATION A. NAME

SOLICITATION

NSN 7540-01-155-3212 1442-101 STANDARD FORM 1442 (REV. 4-85)

Prescribed by GSA

FAR (48 CFR) 53.236-1(e)

11. The Contractor shall begin performance w ithin _______30 calendar days and complete it w ithin ________365 calendar days after receiving aw ard, X notice to proceed. This performance period is X mandatory, negotiable. (See _________________________FAR 52.211-10

12 A. THE CONTRACTOR MUST FURNISH ANY REQUIRED PERFORMANCE AND PAYMENT BONDS?

(If "YES," indicate within how many calendar days after award in Item 12B.)

X YES NO

13. ADDITIONAL SOLICITATION REQUIREMENTS:

A. Sealed offers in original and __________1 copies to perform the w ork required are due at the place specified in Item 8 by ___________ local time ______________18 Jun 2021 (date). If this is a sealed bid solicitation, offers must be publicly opened at that time.

shall be marked to show the offeror's name and address, the solicitation number, and the date and time offers are due.

B. An offer guarantee X is, is not required.

C. All offers are subject to the (1) w ork requirements, and (2) other provisions and clauses incorporated in the solicitation in full text or by reference.

D. Offers providing less than _______90 calendar days for Government acceptance after the date offers are due w ill not be considered and w ill be rejected.

SOLICITATION, OFFER,

AND AWARD

(Construction, Alteration, or Repair)

1. SOLICITATION NO.

IMPORTANT - The "offer" section on the reverse must be fully completed by offeror.

4. CONTRACT NO.

7. ISSUED BY CODE

USPFO MD 175 MSC

2701 EASTERN BLVD

MIDDLE RIVER MD 21220-2801

W50S82

PAGE OF PAGES

1 OF

CODE

(Title, identifying no., date):

12B. CALENDAR DAYS

02:00 PM (hour)

Sealed envelopes containing offers

5. REQUISITION/PURCHASE REQUEST NO. 6. PROJECT NO.

PJMS 152001

8. ADDRESS OFFER TO (If Other Than Item 7)

FAX:TEL: TEL: FAX:

W50S8221R0001 75

20B. SIGNATURE

(REV. 4-85)STANDARD FORM 1442 BACK

TO SIGN

NSN 7540-01-155-3212

SOLICITATION, OFFER, AND AWARD (Continued) (Construction, Alteration, or Repair)

CODE FACILITY CODE

17. The offeror agrees to perform the w ork required at the prices specif ied below in strict accordance w ith the terms of this solicitation, if this offer is accepted by the Government in w riting w ithin ________ calendar days after the date offers are due.

the minimum requirements stated in Item 13D. Failure to insert any number means the offeror accepts the minimum in Item 13D.)

AMOUNTS SEE SCHEDULE OF PRICES

18. The offeror agrees to furnish any required performance and payment bonds.

19. ACKNOWLEDGMENT OF AMENDMENTS

(The offeror acknowledges receipt of amendments to the solicitation -- give number and date of each)

AMENDMENT NO.

DATE

20A. NAME AND TITLE OF PERSON AUTHORIZED TO SIGN

OFFER (Type or print)

AWARD (To be completed by Government)

21. ITEMS ACCEPTED:

22. AMOUNT 23. ACCOUNTING AND APPROPRIATION DATA

24. SUBMIT INVOICES TO ADDRESS SHOWN IN ITEM

(4 copies unless otherwise specified)

CODE

(Insert any number equal to or greater than

20C. OFFER DATE

25. OTHER THAN FULL AND OPEN COMPETITION PURSUANT TO

10 U.S.C. 2304(c) 41 U.S.C. 253(c)

CODE27. PAYMENT WILL BE MADE BY:26. ADMINISTERED BY

(Include ZIP Code)14. NAME AND ADDRESS OF OFFEROR 15. TELEPHONE NO. (Include area code)

See Item 14

(Include only if different than Item 14)16. REMITTANCE ADDRESS

30B. SIGNATURE

29. AWARD (Contractor is not required to sign this document.)

document and return _______ copies to issuing office.) Contractor agrees Your of f er on this solicitation, is hereby accepted as to the items listed. This award con-to f urnish and deliv er all items or perf orm all work, requisitions identif ied summates the contract, which consists of (a) the Gov ernment solicitation and on this f orm and any continuation sheets f or the consideration stated in this y our of f er, and (b) this contract award. No f urther contractual document is contract. The rights and obligations of the parties to this contract shall be necessary .

gov erned by (a) this contract award, (b) the solicitation, and (c) the clauses, representations, certif ications, and specif ications or incorporated by ref er-ence in or attached to this contract.

30A. NAME AND TITLE OF CONTRACTOR OR PERSON AUTHORIZED 31A. NAME OF CONTRACTING OFFICER (Type or print)

30C. DATE

(Type or print)

TEL: EMAIL:

31B. UNITED STATES OF AMERICA 31C. AWARD DATE

BY

CONTRACTING OFFICER WILL COMPLETE ITEM 28 OR 29 AS APPLICABLE

(Contractor is required to sign this28. NEGOTIATED AGREEMENT

(M ust be fully completed by offeror)OFFER

W50S8221R0001

Section 00 10 00 - Solicitation

TABLE OF CONTENTS

TABLE OF CONTENTS

SOLICITATION, OFFER, AND AWARD SF 1442 and SF 1442 BACK

SECTION 00 01 10 - PRICING SCHEDULE, NOTES

SECTION 00 21 00 - INSTRUCTIONS, CONDITIONS AND NOTICES TO OFFERORS

SECTION 00 21 16 – PROPOSAL PREPARTION INSTRUCTIONS

SECTION 00 22 16 – BASIS FOR AWARD

SECTION 00 45 00 – REPRESENTATIONS & CERTIFICATIONS

SECTION 00 70 00 - CONTRACT CLAUSES

SECTION 01 00 00 – Wage Determination

EXHIBIT A - Performance Relevancy Questionnaire EXHIBIT B - Subcontractor Information and Consent Form EXHIBIT C - Reference Questionnaire package EXHIBIT D- Letter of Commitment

Attachments:

B3 Drawings Project Specification Book

SECTION 00010 NOTES

NOTES

1. Instructions for the preparation of proposals are located in Sections 00 01 00, 00 21 00,00 21 16, and 00 22 16.

2. Offeror’s attention is invited to the insurance requirement contained in this solicitation (FAR Clause 52.228-5 Insurance – Work on a Government Installation). Certification of the required coverage for the prime contractor shall be furnished prior to beginning work on this contract, and the Contracting Officer may request evidence of the required insurance at any time during the life the contract.

3. Reference DFARS Provision 252.236-7008, Contract Prices – Bidding Schedules. The term “Bidding Schedule” shall also be construed to mean “Offer Schedule” or “Schedule”. The terms “bid” and “offer”, and “bidder” and “offeror” shall be construed as having the same meaning in this solicitation and resulting contract.

ITEM NO SUPPLIES/SERVICES QUANTITY UNIT UNIT PRICE AMOUNT

0001 1 Job Fire Suppression Installation

FFP

Vendor to provide all labor, materials, and supervision to install fire suppression systems at Hangar 2050 and Hangar 2070, and incidental related work.

FOB: Destination

SIGNAL CODE: A

PSC CD: N012

NET AMT

ITEM NO SUPPLIES/SERVICES QUANTITY UNIT UNIT PRICE AMOUNT

0002 1 Job New Pump House

FFP

Vendor to provide all labor, materials, supervision, and incidental related work to construct a new pump house.

FOB: Destination

SIGNAL CODE: A

PSC CD: Y1NZ

NET AMT

DELIVERY INFORMATION

CLIN DELIVERY DATE QUANTITY SHIP TO ADDRESS DODAAC /

CAGE

0001 365 dys. ANP 1 F7U3MB 175TH CIVIL ENGINEERING

SQUADRON

DEJUAN SAUNDERS, MAJ

2701 EASTERN BLVD

BALTIMORE MD 21220

410.918.6538 FOB: Destination

F7U3MB

0002 365 dys. ANP 1 (SAME AS PREVIOUS LOCATION)

FOB: Destination

F7U3MB

Section 00 21 00 - Instructions

INSTRUCTIONS TO OFFERORS

1. SCOPE

1.1. You are invited to submit a proposal in response to our Request for Proposal (RFP) W50S8221R0001 for Project No. PJMS 152001 at the Maryland Air National Guard. As a result of this solicitation, the Government intends to award a single Firm Fixed Price (FFP) contract to the responsible offeror whose proposal represents the best value after evaluation in accordance with the factors and subfactors in the solicitation.

1.2. This solicitation is set-aside 100% for Women Owned Small Business.

2. NOTICE OF PRE-PROPOSAL CONFERENCE

2.1. A pre-proposal conference will be conducted on 15 June 2020 at 9:00 AM EST for the purposes of briefing on the proposal requirements and answering questions regarding this solicitation. This conference will be held at Building 2100, 175th Civil Engineering Squadron.

Interested Contractors are highly encouraged to attend the pre-proposal conference. The site visit will be held following the conference.

2.2. Due to security conditions, all offerors must register to attend this conference and site visit.

Email the WF 113 Base access form for all attendees to 175.wg.msc@us.af.mil.

2.3. This information must be provided in advance, not later than 5 business days prior to the meeting, in order to ensure access to the military base and conference site and ensure adequate seating for the conference attendees. Even if you have access to the base you must register to ensure adequate seating. The furnishing of the above information is voluntary; however, your failure to furnish all or part of the requested information may result in the Government’s denial of your access to the pre-proposal conference. This information will be provided to the Base Security Forces who will authorize your entrance to the site.

2.4. Visitors must pick up their passes at the Installation’s Main Entry Gate prior to arrival.

You will be required to present the following information upon arrival: (1) Vehicle Registration,

(2) Valid Driver’s License, (3) Proof of Insurance for Vehicle, and/or (4) Safety Inspection and Car Rental agreement if applicable. Any of the above information furnished by you is protected under the Privacy Act and shall not be released unless permitted by law and/or you have consented to such. Escorts will be provided after inspection.

2.5. Information provided at this conference or site visit shall not qualify the terms and conditions of the solicitation and specifications. Terms of the solicitation and specifications remain unchanged unless the solicitation is amended in writing. If an amendment is issued, normal procedures relating to the acknowledgment and receipt of solicitation amendments shall apply.

2.6. A record of the conference shall be made and furnished to all prospective offerors via posting to https://beta.sam.gov. The record will include minutes of the meeting, including questions (on a non-attribution basis) and answers.

3. FORMAL COMMUNICATION, OFFEROR EXPLANATIONS

3.1. Submit all questions via email to the contracting office at the address shown below. Do NOT contact the A-E or Engineering personnel directly. Doing so will only delay the response to your question.

Subject Line: Reference No. W50S8221R0001 Email: 175.wg.msc@us.af.mil

INQUIRIES SHALL BE SUBMITTED VIA EMAIL AND INCLUDE THE FOLLOWING

INFORMATION:

Date of Proposal Inquiry:

From: ______________________________

Company Name: ___________________________

Phone Number: ____________________________

Email address: _____________________________

Proposal Inquiry: Be specific as to part of solicitation you are questioning. Include paragraph number.

3.2. Any explanation desired by an offeror regarding the meaning or interpretation of the solicitation, or proposals, drawings, specifications, etc. must be requested in writing and with sufficient time allowed for a reply to reach offerors before the submission of their offer.

3.3. The Contracting Officer reserves the right to address questions received after the fifth day prior to solicitation closing with those offers deemed compliant and/or in the competitive range after closing. All questions and requests for information (RFI) must be received NOT LATER THAN the fifth business day prior to closing and will be posted not later than two business days prior to closing. The contracting officer reserves the right to address questions received after the fifth business day prior to closing. OFFERORS ARE STRONGLY ENCOURAGED TO SUBMIT

QUESTIONS EARLY IN THIS PROCESS.

3.4. Any interpretations made will be in the form of an amendment of the solicitation, drawings, specifications, etc., and will be furnished to all prospective offerors via posting to https://beta.sam.gov.

3.4.1. Receipt by the offeror must be acknowledged in the space provided on the SF 1442 in section 19, Acknowledgement of Amendments, or by returning a signed copy of the amendment by the time set for receipt of proposals. Explanations or instructions given in a form other than an amendment to the solicitation shall not be binding. Questions (on a non-attribution basis) and answers shall be furnished to all prospective offerors via the website.

3.4.2. For security reasons, all technical and engineering data related to this solicitation will be distributed using the Contracting Opportunities (https://beta.sam.gov) system. Contracting Opportunities is a web-based dissemination tool designed to safeguard acquisition-related information for all Federal agencies. Plans and specifications are locked on Contracting Opportunities and require Contractors to request explicit access from the Contracting Officer OR export controlled access through DLA. See the instructions on Contracting Opportunities regarding registration as interested bidders/offerors must register with Contracting Opportunities before accessing the system.

3.4.2.2. Interested offerors must be registered in the System for Award Management (SAM). To register go to: www.sam.gov. You will need your DUNS number to register. Instructions for registering are on the web page.

4. AMENDMENTS PRIOR TO DATE SET FOR RECEIPT OF PROPOSALS

4.1. The right is reserved, as the interest of the Government may require, to revise or amend, the specifications or drawings or both prior to and/or after the date set for receipt of proposals as necessary. Such amendments, if any, will be announced by an amendment or amendments to this Request for Proposal. All information relating to this RFP, including pertinent changes/amendments and information prior to the date set for receipt of proposals will be posted at https://beta.sam.gov.

4.2. Offerors are strongly cautioned to check this site frequently and to refresh their web page to ensure they have the lasted information.

5. HAND CARRIED PROPOSALS/INVITATIONS

5.1. A bid repository is provided for hand carried proposals and is located at: Building 4200, Maryland Air National Guard HQ, Room 205.

5.2. Hand carried proposals must be deposited in the repository prior to the time established for receipt of proposals.

5.3. Offerors are cautioned that approval to enter the base must be obtained prior to the closing date for receipt of proposals. Follow the procedures outlined above in paragraph 2.1.2 for entry. Delays are probable at the entry point and should be accounted for. Late receipt of proposals due to base entry delays may not be deemed excusable and the Contracting Officer may declare the proposal late and remove it from consideration.

6. WAGE DETERMINATION

6.1. The Construction Wage Rate Requirements formerly known as Davis Bacon Wage Rates are applicable to this project. Current prevailing wage determination(s) at time of issuance of solicitation are General Decision Number: MD20210030 01/15/2021 for Baltimore County, MD.

In the event the current prevailing Wage Determination is changed by the Department of Labor prior to the closing date of the solicitation, the most current wage determination is in effect. Should the wage rate change after closing, but prior to award, the updated Wage Determination will be incorporated by amendment and issued to all offerors that have not been eliminated from the competition. If applicable, these offerors/contractors will be given a reasonable opportunity to provide revised proposals solely to amend proposals due to Wage Determination changes. If the wage determination modification does not change any affected wage rates, then the provisions of FAR 22.404-5(c)(4) will apply.

6.2. Applicable wage rates can be found at https://beta.sam.gov/wage-determination/MD20210030/2/document.

7. PROPOSAL EXPENSES AND PRE-CONTRACT COSTS

This RFP does not commit the Government to pay costs incurred in preparation and submission of initial and subsequent proposals or for other costs incurred prior to award of a formal contract.

8. REMOVAL OF SECTIONS AT TIME OF AWARD

Sections 00 21 00, 00 21 16, 00 22 16, 00 45 00 and all exhibits will be physically removed as a result of an award, but will be deemed to be incorporated by reference in that award.

9. DISPOSITION OF UNSUCCESSFUL PROPOSALS

In compliance with FAR Subpart 4.8, the Government will retain one copy of all unsuccessful proposals. The Government will destroy extra copies of unsuccessful proposals. No destruction certificate will be provided.

10. INFORMATION REGARDING AVAILABILITY OF UTILITY SERVICES

It has been determined that all reasonable amounts of utilities, where/if physically available, used in connection with this project will be furnished to contractor without cost. The offerors will take this into consideration when computing its offer. (FAR Clause 52.236-14, Availability and Use of Utility Services)

11. BID BONDS

An Original Bid bond is required with submission of the proposal. The bid bond is due on the date as stated on the SF1442 block 13. The bid bond must be on a SF24 form. Rejection of a bid bond shall be in accordance with FAR 28.101-4 Noncompliance with bid guarantee requirements.

12. EXCEPTIONS

If the offeror takes exception to any of the requirements specified in this solicitation, the offeror shall clearly identify each such exception and include a complete explanation of why the exception was taken and what benefit accrues to the Government. All exceptions to the solicitation requirements (Sections 00 10 00 through 01 00 00) and supporting rationale shall be included in an addendum to the proposal and clearly labeled "Exceptions". An addendum is only required if the offeror takes exception to any requirement in the solicitation. (The Addendum does not have a page limitation, but shall only include information relevant to exceptions taken to the solicitation requirements.) The Government will assume an offeror takes no exceptions to any solicitation requirement if the offeror does not submit an Addendum identifying exceptions. Offerors are advised that solicitation requirements are not necessarily negotiable and such exceptions may render an offeror’ s proposal unacceptable and ineligible for award.

13. CLAUSES

13.1. Clauses and provisions from the Federal Acquisition Regulation (FAR) and supplements thereto are incorporated in this document by reference and in full text. Those incorporated by reference have the same force and effect as if they were given in full text.

13.2. Clauses and provisions in this document may not appear in consecutive order.

14. BRAND NAME REQUIREMENTS

Vendor shall ensure fire suppression system must connect and operate with current installed Monaco Fire System.

CLAUSES INCORPORATED BY REFERENCE

52.204-7 System for Award Management OCT 2018 52.204-16 Commercial and Government Entity Code Reporting AUG 2020 52.211-6 Brand Name or Equal AUG 1999 52.215-1 Instructions to Offerors--Competitive Acquisition JAN 2017 52.222-5 Construction Wage Rate Requirements--Secondary Site of the

Work

MAY 2014

252.204-7008 Compliance With Safeguarding Covered Defense Information Controls

OCT 2016

252.215-7008 Only One Offer JUL 2019

CLAUSES INCORPORATED BY FULL TEXT

52.216-1 TYPE OF CONTRACT (APR 1984)

The Government contemplates award of a firm fixed priced contract resulting from this solicitation.

(End of provision)

52.222-23 NOTICE OF REQUIREMENT FOR AFFIRMATIVE ACTION TO ENSURE EQUAL

EMPLOYMENT OPPORTUNITY FOR CONSTRUCTION (FEB 1999)

(a) The offeror's attention is called to the Equal Opportunity clause and the Affirmative Action Compliance Requirements for Construction clause of this solicitation.

(b) The goals for minority and female participation, expressed in percentage terms for the Contractor's aggregate workforce in each trade on all construction work in the covered area, are as follows:

Goals for minority participation for each trade

Goals for female participation for each trade

23% 6.9%

These goals are applicable to all the Contractor's construction work performed in the covered area. If the Contractor performs construction work in a geographical area located outside of the covered area, the Contractor shall apply the goals established for the geographical area where the work is actually performed. Goals are published periodically in the Federal Register in notice form, and these notices may be obtained from any Office of Federal Contract Compliance Programs office.

(c) The Contractor's compliance with Executive Order 11246, as amended, and the regulations in 41 CFR 60-4 shall be based on (1) its implementation of the Equal Opportunity clause, (2) specific affirmative action obligations required by the clause entitled "Affirmative Action Compliance Requirements for Construction,'' and (3) its efforts to meet the goals. The hours of minority and female employment and training must be substantially uniform throughout the length of the contract, and in each trade. The Contractor shall make a good faith effort to employ minorities and women evenly on each of its projects. The transfer of minority or female employees or trainees from Contractor to Contractor, or from project to project, for the sole purpose of meeting the Contractor's goals shall be a violation of the contract, Executive Order 11246, as amended, and the regulations in 41 CFR 60-4. Compliance with the goals will be measured against the total work hours performed.

(d) The Contractor shall provide written notification to the Deputy Assistant Secretary for Federal Contract Compliance, U.S. Department of Labor, within 10 working days following award of any construction subcontract in excess of $10,000 at any tier for construction work under the contract resulting from this solicitation. The notification shall list the --

(1) Name, address, and telephone number of the subcontractor;

(2) Employer's identification number of the subcontractor;

(3) Estimated dollar amount of the subcontract;

(4) Estimated starting and completion dates of the subcontract; and

(5) Geographical area in which the subcontract is to be performed.

(e) As used in this Notice, and in any contract resulting from this solicitation, the "covered area" is Baltimore County, Middle River, MD 21220

52.225-10 NOTICE OF BUY AMERICAN REQUIREMENT--CONSTRUCTION MATERIALS (MAY 2014)

(a) Definitions. “Commercially available off-the-shelf (COTS) item,” “construction material,” “domestic construction material,” and “foreign construction material,” as used in this provision, are defined in the clause of this solicitation entitled “Buy American --Construction Materials” (Federal Acquisition Regulation (FAR) clause 52.225-9).

(b) Requests for determinations of inapplicability. An offeror requesting a determination regarding the inapplicability of the Buy American statute should submit the request to the Contracting Officer in time to allow a determination before submission of offers. The offeror shall include the information and applicable supporting data required by paragraphs (c) and (d) of the clause at FAR 52.225-9 in the request. If an offeror has not requested a determination regarding the inapplicability of the Buy American statute before submitting its offer, or has not received a response to a previous request, the offeror shall include the information and supporting data in the offer.

(c) Evaluation of offers. (1) The Government will evaluate an offer requesting exception to the requirements of the Buy American statute, based on claimed unreasonable cost of domestic construction material, by adding to the offered price the appropriate percentage of the cost of such foreign construction material, as specified in paragraph (b)(3)(i) of the clause at FAR 52.225-9.

(2) If evaluation results in a tie between an offeror that requested the substitution of foreign construction material based on unreasonable cost and an offeror that did not request an exception, the Contracting Officer will award to the offeror that did not request an exception based on unreasonable cost.

(d) Alternate offers.

(1) When an offer includes foreign construction material not listed by the Government in this solicitation in paragraph (b)(2) of the clause at FAR 52.225-9, the offeror also may submit an alternate offer based on use of equivalent domestic construction material.

(2) If an alternate offer is submitted, the offeror shall submit a separate Standard Form 1442 for the alternate offer, and a separate price comparison table prepared in accordance with paragraphs (c) and (d) of the clause at FAR 52.225-9 for the offer that is based on the use of any foreign construction material for which the Government has not yet determined an exception applies.

(3) If the Government determines that a particular exception requested in accordance with paragraph (c) of the clause at FAR 52.225-9 does not apply, the Government will evaluate only those offers based on use of the equivalent domestic construction material, and the offeror shall be required to furnish such domestic construction material. An offer based on use of the foreign construction material for which an exception was requested--

(i) Will be rejected as nonresponsive if this acquisition is conducted by sealed bidding; or

(ii) May be accepted if revised during negotiations.

52.228-1 BID GUARANTEE (SEP 1996)

(a) Failure to furnish a bid guarantee in the proper form and amount, by the time set for opening of bids, may be cause for rejection of the bid.

(b) The bidder shall furnish a bid guarantee in the form of a firm commitment, e.g., bid bond supported by good and sufficient surety or sureties acceptable to the Government, postal money order, certified check, cashier's check, irrevocable letter of credit, or, under Treasury Department regulations, certain bonds or notes of the United States.

The Contracting Officer will return bid guarantees, other than bid bonds, (1) to unsuccessful bidders as soon as practicable after the opening of bids, and (2) to the successful bidder upon execution of contractual documents and bonds (including any necessary coinsurance or reinsurance agreements), as required by the bid as accepted.-

(c) The amount of the bid guarantee shall be 20 percent of the bid price or $3,000,000.00, whichever is less.-

(d) If the successful bidder, upon acceptance of its bid by the Government within the period specified for acceptance, fails to execute all contractual documents or furnish executed bond(s) within 10 days after receipt of the forms by the bidder, the Contracting Officer may terminate the contract for default.-

(e) In the event the contract is terminated for default, the bidder is liable for any cost of acquiring the work that exceeds the amount of its bid, and the bid guarantee is available to offset the difference.

52.233-2 SERVICE OF PROTEST (SEP 2006)

(a) Protests, as defined in section 33.101 of the Federal Acquisition Regulation, that are filed directly with an agency, and copies of any protests that are filed with the Government Accountability Office (GAO), shall be served on the Contracting Officer (addressed as follows) by obtaining written and dated acknowledgment of receipt from SMSgt Michael Dombkiewicz, 2701 Eastern Blvd, Middle River, MD 21220

(b) The copy of any protest shall be received in the office designated above within one day of filing a protest with the GAO.

52.236-27 SITE VISIT (CONSTRUCTION) (FEB 1995)

(a) The clauses at 52.236-2, Differing Site Conditions, and 52.236-3, Site Investigations and Conditions Affecting the Work, will be included in any contract awarded as a result of this solicitation. Accordingly, offerors or quoters are urged and expected to inspect the site where the work will be performed.

(b)(1) Vendor to submit WF 113 to 175.wg.msc@us.af.mil with subject title – “Site Visit for W50S8221R0001.

(2) WF 113 must be submitted a minimum 3 business days prior to the site visit. Failure to submit documentation on time or incomplete documentation may result in denied access. Failure to arrive on time may result in vendor not getting escort to the site visit. Allow time for traffic at the gate and inspections.

(3) There will only be one site visit. All requests for another site visit due to the above paragraph (b)(2) or subcontractors not available on the day of the site visits will be denied.

52.252-1 SOLICITATION PROVISIONS INCORPORATED BY REFERENCE (FEB 1998)

This solicitation incorporates one or more solicitation provisions by reference, with the same force and effect as if they were given in full text. Upon request, the Contracting Officer will make their full text available. The offeror is cautioned that the listed provisions may include blocks that must be completed by the offeror and submitted with its quotation or offer. In lieu of submitting the full text of those provisions, the offeror may identify the provision by paragraph identifier and provide the appropriate information with its quotation or offer. Also, the full text of a solicitation provision may be accessed electronically at this/these address(es):

https://www.acquisition.gov/

52.252-5 AUTHORIZED DEVIATIONS IN PROVISIONS (NOV 2020)

(a) The use in this solicitation or contract of any Federal Acquisition Regulation (48 CFR Chapter 1) clause with an authorized deviation is indicated by the addition of "(DEVIATION)" after the date of the clause.

(b) The use in this solicitation or contract of any Defense Federal Acquisitions Regulation Supplement (48 CFR Chapter 2) clause with an authorized deviation is indicated by the addition of "(DEVIATION)" after the name of the regulation.

Section 00 21 16 - Instructions to Proposers

PROPOSAL PREPARATOIN INSTRUCT

A. PROPOSAL SUBMISSION (Section 00 21 16)

1. INTRODUCTION. The instructions prescribe the format of proposals, and describe the approach for the development and presentation of the proposal data. They are designed to ensure the submission of necessary information to provide for the understanding and comprehensive evaluation of proposals. Carefully review this section prior to commencing proposal preparation. All solicitation amendments must be acknowledged in accordance with Section 00 21 00, FAR Provision 52.215-1, and Instructions to Offerors – Competitive Acquisition.

Offerors are cautioned to strictly comply with all instructions within this solicitation to ensure submission of a complete proposal. Failure to furnish a complete proposal, at the time of proposal submission, may result in the proposal being unacceptable to the Government and eliminated from consideration for award.

Prospective offerors shall submit the following volumes in two separate packages. The RFP shall provide the Government address and receipt date for proposal submitted.

2. PROPOSAL SUBMISSION REQUIREMENTS.

Volume 1, (Part 1) Technical Capability Proposal

Factor 1 – Experience and Capability (limit to 15 pages) Factor 2 – Past Performance – limited to 3 projects within the past 5 years (limit to 3 pages per project or CPARS Print out or attached Past Performance Questionnaire)

Volume 2, Price Proposal

Forward Pricing Schedule, pro forma documents, in original and (1) hard copy, in accordance with instructions contained herein.

3. Proposal Files

Purpose: These instructions prescribe the format of proposals, and describe the approach for the development and presentation of the proposed data. The proposal shall include all of the information requested in the specific instructions. Failure to include all information requested may adversely affect the evaluation.

A proposal that merely reiterates or promises to accomplish the requirements of the RFP will be considered unacceptable. A proposal that is orderly and sufficiently documented will be easy for the Government to understand and will enable the Government to perform a thorough and fair evaluation.

Offerors are cautioned to submit enough information to enable the evaluation committee to fully ascertain each offeror’ s capability to perform all of the requirements contemplated by this solicitation. All commitments made in the proposal may become a part of the resultant contract. The data submitted with each proposal should be complete and concise, but not overly elaborate. Excessive reliance on promotional brochures is discouraged.

Written proposals shall be prepared on standard 8.5 x 11 inch paper (charts may be landscaped but must be on 8.5 x 11 inch paper) and shall be in a legible font size (10 min.). All pages of each proposal shall be appropriately numbered, and identified with the RFP number. For ease of reference, consecutive page numbering with tabs is required. Type size for graphics, charts, diagrams and tables shall be of an appropriate font and size for the application, and must be clearly readable without magnification assistance to the normal eye. Text lines shall be no less than single-space. To the maximum extent practicable, proposal submission shall be double sided. Where page limits exist, a page is defined as one single side of a page. Double sided pages count as 2 pages. Unless otherwise stated, tabs, indexes and dividers do not count in the page count.

Binding: Elaborate format and binding are neither necessary nor desirable. All binders will be capable of lying flat when opened. Three ring binders are preferred. The cover and spine of each binder will clearly identify the offeror’ s name, Project number, RFP number, RFP title and copy number, (e.g. copy 2 of 3). The original for each volume will be clearly identified on the cover and the spine. All binders will allow for easy removal and replacement of pages.

Indexing: Each binder will contain a “Table of Contents” for that volume. The “Table of Contents” will identify major areas, paragraphs and subparagraphs by number and title, as well as by page number and volume locations.

Tab indexing will be used to identify sections as appropriate.

Electronic Copy: Provide one (1) electronic copy of all of the Volume 1 and 2 proposal information. Electronic copies shall be submitted on CD/DVD saved in Microsoft Word format or Adobe Acrobat. (“Read Only” files are acceptable). All disks shall be virus checked prior to submission.

If revised proposals are requested, all proposal revisions shall be submitted on colored paper as page changes with each page identified by date and page number. Revised pages shall be printed on one side and punched with a 3-hole punch along the left margin. The number of revised copies to be submitted is the same as the initial proposal in accordance with FAR 15.306 (a). Requests for such information do not constitute discussions.

The offeror shall be held responsible for the validity of all information supplied in his/her proposal, including that provided by potential subcontractors. Should subsequent investigation disclose that the facts and conditions were not as stated, the proposal may be rejected.

Section 00 22 16 - Supplementary Instructions to Proposers

EVALUATION CRITERIA

B. BASIS FOR AWARD (Section 00 22 16)

The award will be made to the lowest priced technically acceptable proposal. Proposals will be evaluated for technical acceptability, but will not be ranked using the non-price Factors (and Sub-factors). In order for an Offeror to be considered for award, the proposal must receive an “Acceptable” rating in every non-price Factor. A proposal receiving a rating of “Unacceptable” in any non-price Factor will not be eligible for award.

To arrive at a Best Value decision, this acquisition will utilize the FAR Part 15.101-2 lowest price technically proposal with the lowest price. When using the lowest price technically acceptable process, the following apply:

(1) The evaluation factors and significant sub-factors that establish the requirements of acceptability shall be set forth in the solicitation. Solicitations shall specify that award will be made on the basis of the lowest evaluated price of proposals meeting or exceeding the acceptability standards for non-cost factors.

If the contracting officer documents the file pursuant to 15.304(c) (3) (iii), past performance need not be an evaluation factor in lowest price technically acceptable source selections. If the contracting officer elects to consider past performance as an evaluation factor, it shall be evaluated in accordance with

15.305. However, the comparative assessment in 15.305(a) (2) (i) does not apply. If the contracting officer determines that a small business’ past performance is not acceptable, the matter shall be referred to the Small Business Administration for a Certificate of Competency determination, in accordance with the procedures contained in subpart 19.6 and 15 U.S.C. 637(b)(7)).

(2) Tradeoffs are not permitted.

(3) Proposals are evaluated for acceptability but not ranked using the non-cost/price factors.

(4) Exchanges may occur (see FAR 15.306 –Exchange with offerors after receipt of proposal).

The source selection process will be conducted in accordance with FAR Subpart 15.3, Source Selection procedures.

Offers will be evaluated using the criteria listed in “Evaluation Factors for Award.” Noncompliance with the RFP requirements may raise serious questions regarding an offeror’s technical ability, pricing, and may be grounds to eliminate the proposal from consideration for contract award. Failure to include all information requested may adversely affect the evaluation. A proposal that merely reiterates or promises to accomplish the requirements of the RFP will be considered unacceptable. A proposal that is orderly and sufficiently documented will be easy for the Government to understand and will enable the Government to perform a thorough and fair evaluation.

The Contracting Officer will begin the evaluation process by conducting a proposal compliance review for all timely-received proposals for determination of basic proposal adequacy prior to providing the proposals to the evaluators. Failure to provide a complete proposal may result in the proposal being removed from further consideration for award. Failure to address any factor Technical and Price or any technical subfactor shall be grounds for elimination from evaluation and consideration for award.

Offerors must ensure that no pricing information is displayed in Volume 1, Technical Proposal.

The Government intends to evaluate proposals and award a contract without discussions with offerors (except clarifications as described in FAR 15.306(a)). The Government reserves the right to conduct discussions if the Contracting Officer, in his/her sole discretion, later determines them to be necessary or appropriate. Further, the Government reserves the right to create or not to create a competitive range.

ENFORCEABILITY OF PROPOSAL: The proposal must set forth full, accurate and complete information as required by this solicitation. By submission of the offer, the Offeror agrees that all items proposed (if applicable e.g., key personnel, subcontractors, etc.) will be utilized for the duration of the contract and any substitutions shall require prior Contracting Officer's approval.

B. FACTORS TO BE EVALUATED

The following Technical evaluation factors will be used to evaluate each proposal. Award will be made to the offeror whose proposal is most advantageous to the Government based upon an integrated assessment of the evaluation factors and sub-factors described below.

FACTOR 1: EXPERIENCE AND CAPABILITY:

Sub-factor 1: Experience shall include projects 10,000 square feet or more and include projects comprised of constructing and connecting pump houses to existing or new fire suppression systems and/or high expansion foam systems, or have constructed aircraft hangers to include such systems. The contractor shall have mechanical and hydrology engineering experience for Pump House construction. Offerors experience shall be a minimum of 2 projects within the past 5 years.

Sub-factor 2: Possess mass notification system qualifications to install and program addressable and nonaddressable fire notification system outlined in PJMS 152001.

Sub-factor 3: Qualified and competent key personnel with the required experience listed below for installation of High Expansion Foam (HEF) systems, fire protection, hydrology engineering, and construction related to a pump house.

FACTOR 2: PAST PERFORMANCE

a) Experience with Respect to Installing and testing HEF system

b) Previous experience related to construction of pump house or similar projects.

A detailed explanation of the criteria for the evaluation is set forth in the “Evaluation Approach”, Paragraph C of this section. An offer which fails to provide information in any of the specified areas may be deemed incomplete, and eliminated from the competition and ineligible for further consideration.

COST/PRICE: The resulting award will be a firm fixed price contract type. Price Reasonableness will be utilized in the evaluation of the Firm-Fixed price effort but will not be rated.

C. EVALUATION APPROACH

All proposals shall be subject to evaluation by the Source Selection Evaluation Board (SSEB). All ratings will be conducted at the Factor level.

1. The overarching evaluation approach for all factors and follows:

a. Adequacy of Response. The proposal will be evaluated to determine whether the offeror’ s methods and approach have adequately and completely considered, defined, and satisfied the requirements specified in the RFP. The proposal will be evaluated to determine the extent to which each requirement has been addressed in the proposal in accordance with the proposal submission section of the RFP.

b. Feasibility of Approach. The proposal will be evaluated to determine the extent to which proposed approach is workable and the end results achievable. The proposal will be evaluated to determine the extent to which successful performance is contingent upon proven devices and techniques. The proposal will be evaluated to determine the extent to which the offeror is expected to be able to successfully complete the proposed task and technical requirements within the required schedule.

2. Technical. The term “technical,” as used herein, refers to non-price factors. The purpose of the technical factor is to assess whether the offeror’s proposal will satisfy the Government’s minimum requirements. Some of the aspects affecting an offeror’ s ability to meet the solicitation requirements will include technical approach, key personnel and qualifications, facilities, and others. Once the minimum requirements are established, the team shall evaluate the offeror’ s proposal against these requirements to determine whether the proposal is acceptable or unacceptable, using the ratings and descriptions outlined in Table C-1.

FACTOR 1. EXPERIENCE AND CAPABILITY PROPOSAL

Sub-factor 1: Experience shall include projects 10,000 square feet or more and include projects comprised of constructing and connecting pump houses to existing or new fire suppression systems and/or high expansion foam systems, or have constructed aircraft hangers to include such systems. The contractor shall have mechanical and hydrology engineering experience for Pump House construction. Offerors experience shall be a minimum of 2 projects within the past 5 years.

Sub-factor 2: Possess mass notification system qualifications to install and program addressable and nonaddressable fire notification system outlined in PJMS 152001.

Sub-factor 3: Proposal shall include, as a minimum, the following key personnel: Project Manager, Site Superintendent(s), Site Safety Health Officer (SSHO), Quality Control Manager (on site), Safety Representative, and Fire Protection Specialist. The qualifications for key personnel shall include the following:

Project Manager – The project manager must have a minimum of 5 years managing a multi-disciplined construction project comparable to the work requirements of this solicitation. The information must demonstrate experience on managing the administration (i.e. submittals, RFIs, progress meetings) of the project.

Site Superintendent -The site superintendent must have a minimum of 10 years of experience in construction with at least 5 of those years as a superintendent on projects similar in size and complexity.

The individual shall have experience with the requirements of EM 385-1-1 and provide certificate of training for the EM 385-1-1 40 hour training course.

Site Safety Health Officer (SSHO) - Provide an SSHO that meets the requirements of EM 385-1-1 Section 1 and provide certificate of training for the EM 385-1-1 40 hour training course. The SSHO must ensure that the requirements of 29 CFR 1926.16 are met for the project. Provide a Safety oversight team that includes a minimum of one (1) person at each project site to function as the SSHO.

Quality Control Manager (QCM) - The QCM shall meet minimum requirement in specification Section 01 45 00.00 10/ 3.4.3 Experience Matrix. This person shall also have the Construction Quality Management (CQM) for Contractors course. If the CQC System Manager does not have a current certification, they shall obtain the CQM for Contractors course certification within 90 days of award.

This course is periodically offered by the Naval Facilities Engineering Command and the Army Corps of Engineers.

Fire Protection Specialist – The fire protection specialist shall be a registered professional engineer who has passed the fire protection engineering written examination administered by the National Council of Examiners for Engineering and Surveys (NCEES). This person shall have a minimum of 10 years of experience with at least 5 years working with HEF systems.

Table C-1. Technical Acceptable/Unacceptable Rating Method Adjectival Rating Description

Acceptable Proposal meets the requirements of the solicitation Unacceptable Proposal does not meet the requirements of the solicitation

FACTOR 2. PAST PERFORMANCE

The Government will evaluate the extent of related experience, and determine to what degree the offeror has the experience and capability to manage a complex multi-disciplined construction project comparable to the work requirements of this solicitation. Acceptable past performance are projects 10,000 square feet or more and include projects comprised of constructing and connect pump houses to existing or new fire suppression systems and/or high expansion foam systems, or have constructed aircraft hangers to include such systems. Work can be either federal, state or private. Offeror shall provide at least 3 examples within the past 5 years. The Government has the right to use all means at its disposal to determine relevance (i.e. CPARS, FAPIIS, and attached Questionnaire).

Past Performance Evaluation Ratings Rating Definition

Acceptable Based on the offeror’s performance record, the Government has a reasonable expectation that the offeror will successfully perform the required effort, or the offeror’s performance record is unknown.

Unacceptable Based on the offeror’s performance record, the Government does not have a reasonable expectation that the offeror will be able to successfully perform the required effort.

COST/PRICE: This contract is a firm fixed price contract. Price is not rated.

The purpose of the price/cost evaluation is to determine whether an offeror’ s proposed prices/costs for the project are determined to be fair and reasonable in comparison to the competition, the current market conditions and/or recent prices for the same or similar requirements. Reasonableness of an offeror’s proposal is evaluated through cost or price analysis techniques as described in FAR Subpart 15.305(a) (1) and (4).

The RFP requires firm-fixed prices for the individual contract line items. The Government will use a price reasonableness approach to determine that the proposed prices offered are fair and reasonable and that a “buy-in” or unbalanced pricing between CLINS or Options is not occurring.

The Government will examine price proposals for artificially low unit prices. Offers found to be unreasonably high, unrealistically low (an indication of a “buy-in”), or unbalanced, may be considered unacceptable and may be rejected on that basis.

The Government reserves the right to obtain additional information concerning the price (cost) as necessary to obtain a better understanding of the price proposed. No proposal revisions will be allowed under these conditions.

Request for such information is for clarification purposes only. This does not constitute and shall not be construed as discussions. If a minor clerical error has occurred, the offeror may be given an opportunity to correct the minor error within the constraints of the "clarifications" process. The Contracting Officer in his/her sole discretion may later determine discussions to be necessary or appropriate.

In the event the Government does not award a contract pursuant to this solicitation within 90 calendar days after receipt of proposals and award will be made without discussions, the following will apply: The Government reserves the right to allow offerors to make an adjustment in their price proposals to accommodate cost changes caused by fluctuating construction material market conditions.

This is the start of the file's text. The full file is on GovTribe.