A07_Questions_and_Answers.pdf
PDF 93 KB Posted
- Attached to
- RADOME for Satellite Transportable Terminals Federal contract opportunity
- Solicitation number
- W25G1V18R0019
About this file
Questions and Answers
View the file
Other files for this federal contract opportunity
| File | Type | Posted |
|---|---|---|
| A07_Summary_of_Changes_for_STT_RADOME_SOW_02.pdf | ||
| A07_Attachment_I_SOW_STT_Radome_AMENDMENT_02.pdf | ||
| A07_Solicitation_Amendment_0002.pdf | ||
| A07_Questions_and_Answers.pdf | ||
| A07_Attachment_1_SOW_STT_Radome_AMENDED.pdf | ||
| A07_Summary_of_Changes_to_STT_Radome_SOW.pdf | ||
| A07_Solicitation_Amendment_0001.pdf | ||
| A07_Attachment_I_SOW.pdf | ||
| A07_Solicitation_W25G1V18R0019.pdf | ||
| A07_Attachment_V_Past_Performance_questionnaire.pdf | ||
| A07_Attachment_III_KO's_determination_brand_name_connector_REDACTED.pdf | ||
| A07_Attachment_II_Wage_Rate_Requirements_(Construction).pdf | ||
| A07_Attachment_IV_Small_Business_Participation_Plan.pdf |
Show all 13
On GovTribe
Work with this file on GovTribe
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Questions and Answers W25G1V18R0019
Q1. What are the antenna reflector sizes of the STT units that will be used within the radome?
A1. for all STT-167, 185, 202, 208, and Phoenix, the reflector is 2.4 Meter disk
Q2. What are the frequency range (sub-bands) for these antennas?
A2. C-Band: RX: 3.40 - 4.20 GHz TX: 5.85 - 6.65 GHz
X-Band: RX: 7.25 - 7.75 GHz TX: 7.90 - 8.40 GHz
Ku-Band: RX: 10.95 - 12.75GHz TX: 13.75 - 14.50 GHz
Ka-Band: RX: 20.2 - 21.2 GHz TX: 30.0 - 31.0 GHz
Q3. Do you have the electrical requirements for items 3.8.5 through 3.8.11, and 3.8.14 in the A07_Attachment_I_SOW? The SOW requests performance data on the radome, but does not supply any antenna parameters. I would like to understand the requirement thresholds for each characteristic (insertion loss, boresight error, beamwidth error, sidelobe, etc.).
A3. Noted. No additional information should be provided regarding this question. We are requesting the Offeror's radome performance data for comparison reasons.
Q4. The radome requirements clearly specify dielectrc radome and non-metallic components. Would a metal space frame radome be considered if it was shown to have better overall performance?
A4. Based on the unknowns associated with planned and future workload, the Metal Space Frame Type Radome will introduce high risk to asset performance. This is illustrated in the following: Antenna size(s) will vary with 2.4 m as typical diameter; Antenna placement within the RADOME will be at various locations; No fixed vertical offsets from floor level (such as with fixed pedestal mounted earth stations).
Q5. Can the Government please provide guidance as to the desired disposal location/process for the removal of trees.
A5. The trees will be cut to the stump (3ft or less from the ground). The felled trees are to be stacked along the sides of the lines-of-site and left for wildlife habitat.
This area outside of the fence is also a Low Probability section of the UXO area and the contractor will need a UXO Tech III on site for this phase of construction.
Q6. Can the Government please provide guidance where the soil removed for grading and excavating the site is to be placed.
A6. There is currently no dump site on Tobyhanna Army Depot. The contractor must remove all unused soil from the installation and take it to an approved clean fill site off post.