Template Construction Contract - Woodland Park 2024.docx

DOCX document 100 KB Posted

Attached to
Browning Street Improvements
Solicitation number
25.ST.004
Issued by
Weld County, Colorado

About this file

This document is a Construction Agreement template between the City of Woodland Park, Colorado and an unspecified contractor for the Browning Street Improvements project. The project involves road improvements on Browning Avenue from Highway 24 to the street's western dead end, requiring the installation of approximately 1,100 square yards of 4-inch thick asphalt, 6,300 square yards of 1.5-inch mill and overlay, 700 linear feet of curb and gutter, and 9 ADA-compliant pedestrian ramp reconstructions. The contract specifies that the contractor must achieve Substantial Completion within a predetermined number of calendar days after receiving a Notice to Proceed, with specific liquidated damages of $250 per day for delays.

The contract includes comprehensive financial and performance provisions, with the Owner agreeing to pay the full contract price upon satisfactory completion. The payment structure involves monthly progress payments with a 5% retainage, and the contractor is required to provide a Performance Bond for the full contract price. Insurance requirements are detailed, including commercial general liability with $1,000,000 per occurrence, workers' compensation, and comprehensive automobile liability insurance. The contract also includes two-year Project Warranties, requiring the contractor to correct any defects within that period, and mandates that the contractor comply with Colorado state employment authorization laws and maintain independent contractor status.

View the file

Other files

File Type Posted
Bidding - Bid Bond Form Blank - 10%.pdf PDF
Q&A Document 1.pdf PDF
05RF-TECHNICAL SPECIFICATIONS BRWN.doc DOC document
Contract - General Conditions Construction Contract - Woodland Park.pdf PDF
CWP Business License Application_fillable (1).pdf PDF
01F-COVER BRWN.docx DOCX document
Bidding - General Conditions (RFPs) 2024.pdf PDF
02F-INVITATION FOR BIDS BRWN.docx DOCX document
BRWN_20250327_Sealed_F.pdf PDF
03RF-BID PROPOSAL BRWN.docx DOCX document
04RF-MEASUREMENT AND PAYMENT BRWN.doc DOC document
Blank W-9.pdf PDF
Show all 12

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

CONSTRUCTION AGREEMENT

This CONSTRUCTION AGREEMENT (this “Agreement”) is entered into this _____ day of __________________, 2024 by and between the City of Woodland Park, Colorado (hereinafter referred to as the “Owner”) and _______________ (hereinafter referred to as the “Contractor”).

Owner and Contractor, in consideration of the mutual covenants hereinafter set forth, agree as follows:

ARTICLE 1 WORK

1.01 Contractor shall complete all work as specified or indicated in the Contract Documents (defined below). The work is generally described as follows: _____________________.

ARTICLE 2 THE PROJECT

2.01 The project for which the work under the Contract Documents may be the whole or only a part is generally described as follows: __________________________________________ (the “Project”).

ARTICLE 3ENGINEER
3.01____________________ shall serve as construction management engineer who is hereinafter called Engineer and who is to act as Owner’s representative, assume all duties and responsibilities, and have the rights and authority assigned to Engineer in the Contract Documents in connection with the completion of the work in accordance with the Contract Documents.

ARTICLE 4 WORKER WITHOUT AUTHORIZATION EMPLOYMENT

4.01 Contractor shall not knowingly employ or contract with a worker without authorization to perform work under this Agreement. Contractor shall not contract with a subcontractor that fails to certify that the subcontractor does not knowingly employ or contract with workers without authorization to work within the State of Colorado. By entering into this Agreement, Contractor certifies that as of the date of this Agreement it does not knowingly employ or contract with anyone not authorized to perform work within the State of Colorado who will perform work under the public contract for services.

ARTICLE 5 CONTRACT TIMES

5.01 Time is of the Essence

A. All time limits for Milestones, if any, Substantial Completion, and completion and readiness for final payment as stated in the Contract Documents are of the essence of the Contract.

5.02 Days to Achieve Substantial Completion and Final Payment

A. Contractor shall achieve Substantial Completion within _____ calendar days of the issuance by the Owner of a Notice to Proceed and shall finally complete the Work so that it is ready for final payment within _____ calendar days of the issuance by the Owner of a Notice to Proceed.

5.03 Liquidated Damages

A. Contractor understands and agrees that time is an essential condition of this Agreement. Contractor further understands and agrees that delay in completion of the project will cause Owner to suffer substantial losses and damages which cannot be measured, including without limitation the loss of revenues for services, loss of other revenue incidental to the operation of the facility, additional engineering, legal, accounting and administrative costs, reduced public confidence and adverse public relations which would reduce future revenues, and additional interest and financing costs and charges if the Work is not completed within the times specified above, plus any extensions. The parties also recognize the delays, expense, and difficulties involved in proving in a legal or mediation proceeding the actual loss suffered by Owner if the Work is not completed on time. Accordingly, instead of requiring proof of such losses and damages, Owner and Contractor agree that as liquidated damages for delay (but not as a penalty), Contractor shall pay two hundred fifty dollars ($250.00) for each day that expires after the time specified above for Substantial Completion until the Work is substantially complete.

B. After Substantial Completion, if Contractor shall neglect, refuse, or fail to complete the remaining Work within the contract time or any proper extension thereof granted by Owner, Owner and Contractor agree that as liquidated damages for delay (but not as a penalty) Contractor shall pay two hundred fifty dollars ($250.00) for each day that expires after the time specified above for final completion and readiness for final payment until the Work is finally complete and ready for final payment.

C. Owner shall have the right to deduct the liquidated damages from any money in its hands, otherwise due, or to become due, to Contractor, or to sue for and recover compensation for damages for nonperformance of this Contract.

D. Any liquidated damages payable by Contractor may, at Owner’s election be deducted from any amounts owed to Contractor. In the event no funds are due Contractor at a time when Contractor becomes liable to Owner for liquidated damages, then Contractor agrees to pay all accrued liquidated damages to Owner on the first (1st) day and on the fifteenth (15th) day of each month when Contractor is liable to Owner for liquidated damages. Permitting Contractor to continue and finish the Work or any part thereof after the deadline for completion of the Work shall not act as a waiver of these liquidated damages provisions.

E. The aggregate liability of Contractor to pay liquidated damages pursuant to this Article shall not exceed an amount equal to fifty percent (50%) of the Contract Price. This Article shall not be construed to limit Contractor’s other obligations or liabilities arising under or in connection with this Contract.

F. In the event that this section conflicts with any other provisions regarding liquidated damages within the Contract Documents, this section shall control.

ARTICLE 6 CONTRACT PRICE

6.01 Owner shall pay Contractor ________________ dollars ($ ______) for completion of the Work as full compensation for everything furnished and done by Contractor under this Agreement, including all loss or damage arising out of the work or from the action of the elements; for any unforeseen obstruction or difficulty encountered in the prosecution of the work, including increased prices for or shortages of materials for any reason, including natural disasters; for all risks of every description associated with the work; for all expenses incurred due to the suspension or discontinuation of the work; and for well and faithfully completing the work as provided in this Agreement.

ARTICLE 7 PAYMENT PROCEDURES

7.01 Submittal and Processing of Payments

A. Contractor shall submit Applications for Payment to the Owner on a monthly basis, which shall be processed by the Engineer.

7.02 Progress Payments; Retainage

A. Owner shall make progress payments towards the Contract Price, less five percent (5%) for retainage, on the basis of Contractor’s Applications for Payment, as verified and recommended by Engineer, on or about the twenty-fifth (25th) day of each month during performance of the Work. In the Engineer’s discretion, the Owner may withhold some or all of a progress payment where the Contractor’s Application for Payment does not reflect the actual amount of the Work completed.

7.03 Final Payment

A. Upon final completion and acceptance of the Work as recommended by the Engineer, Owner shall pay the remainder of the Contract Price, including any retainage previously withheld.

ARTICLE 8 PROJECT WARRANTIES

8.01 Contractor’s warranties in respect of the Work (the “Project Warranties”) are as follows: Contractor warrants to Owner that the Work shall be fit for its intended purposes, that materials and equipment furnished under this Agreement shall be of good quality and new, that all Work shall be free from defects and that all Work shall meet all of the requirements of this Agreement. Contractor shall furnish satisfactory evidence that it has met the Project Warranties. The Project Warranties shall commence on the date Contractor achieves final completion of the Work satisfactorily to Owner. If at any time within two (2) years after the date on which the Project Warranties commenced, any portion of the Work is found to be not in accordance with the Project Warranties, Contractor shall correct it promptly after receipt of notice from Owner to do so unless Owner has previously given Contractor a written acceptance of such condition.

ARTICLE 9 INSURANCE

9.01 Insurance Requirements. Contractor shall not commence work under this Agreement until Contractor has obtained all insurance required under this Article and the insurance has been approved by the City Administrator or his designee. The City of Woodland Park shall be named as an additional insured. Certificates of insurance shall be issued prior to execution of the Notice to Proceed. Additionally, Contractor shall not allow any approved subcontractor to commence work on his or her subcontract until all similar insurance required of subcontractor has been so obtained and approved. The following insurance shall be required:

A. Commercial General Liability Insurance: At a minimum, combined single limits of $1,000,000 per occurrence and $1,000,000 for general aggregate for bodily injury and property damage, which coverage shall include products/completed operations, independent contractors, and contractual liability each at $1,000,000 per occurrence.

B. Workers’ Compensation and Employer’s Liability: Workers’ compensation insurance for all of Contractor’s employees engaged in work at the site of the project including occupational disease coverage in accordance with scope and limits as required by the State of Colorado.

C. Comprehensive Automobile Liability Insurance: Liability insurance with minimum combined single limits for bodily injury of not less than One Hundred Thousand Dollars ($100,000.00) each person and each accident and for property damage of not less than Fifty Thousand Dollars ($50,000.00) each accident with respect to each of the Contractor’s owned, hired and non-owned vehicles assigned or used in performance of the Services. The policy shall contain a severability of interests provision. Such insurance coverage must extend to all levels of subcontractors. Such coverage must include all automotive equipment used in the performance of the Agreement, both on the work site and off the work site, and such coverage shall include non-ownership and hired cars coverage. Such insurance shall be endorsed to name the Owner as Certificate Holder and name the Owner, and its elected officials, officers, employees, and agents as additional insured parties.

ARTICLE 10 CONTRACTOR’S REPRESENTATIONS

10.01 In order to induce Owner to enter into this Agreement, Contractor makes the following representations:

A. Contractor has examined and carefully studied the Contract Documents and the other related data identified in the Bidding Documents.

B. Contractor has visited the Site and become familiar with and is satisfied as to the general, local, and Site conditions that may affect cost, progress, and performance of the Work.

C. Contractor is familiar with and is satisfied as to all federal, state, and local laws and regulations that may affect cost, progress, and performance of the Work.

D. Contractor has obtained and carefully studied (or assumes responsibility for having done so) any examinations, investigations, explorations, tests, studies, and data concerning conditions at or contiguous to the Site which may affect cost, progress, or performance of the Work or which relate to any aspect of the means, methods, techniques, sequences, and procedures of construction to be employed by Contractor, including applying the specific means, methods, techniques, sequences, and procedures of construction, if any, expressly required by the Contract Documents to be employed by Contractor, and safety precautions and programs incident thereto.

E. Contractor does not consider that any further examinations, investigations, explorations, tests, studies, or data are necessary for the performance of the Work at the Contract Price, within the Contract Times, and in accordance with the other terms and conditions of the Contract Documents.

F. Contractor is aware of the general nature of work to be performed by Owner and others at the Site that relates to the Work as indicated in the Contract Documents.

G. Contractor has correlated the information known to Contractor, information and observations obtained from visits to the Site, reports and drawings identified in the Contract Documents, and all additional examinations, investigations, explorations, tests, studies, and data with the Contract Documents.

H. Contractor has given Engineer written notice of all conflicts, errors, ambiguities, or discrepancies that Contractor has discovered in the Contract Documents, and the written resolution thereof by Engineer is acceptable to Contractor.

I. The Contract Documents are generally sufficient to indicate and convey understanding of all terms and conditions for performance and furnishing of the Work.

J. Contractor warrants and guarantees to Owner and Engineer that all Work will be in accordance with the Contract Documents and will not be defective within two (2) years of Substantial Completion.

K. Contractor is organized, validly existing and in good standing under the laws of the State of Colorado and has all requisite power to own its properties and assets and carry on its business as now conducted or proposed to be conducted.

ARTICLE 11 CONTRACT DOCUMENTS

11.01 Contents

A. The Contract Documents consist of the following:

1. This Agreement;

2. Bidding Documents;

3. General Conditions;

4. Supplementary Conditions;

5. Technical Specifications;

6. Measurement and Payment Provisions;

7. Construction Plans;

8. Labor & Materials Payment Bond;

9. Performance Bond;

10. ________________________;

11. ________________________; and

12. Any written amendments or work change orders which may be delivered or issued on or after the Effective Date of the Agreement and are not attached hereto.

B. There are no Contract Documents other than those listed above in this Article.

C. The Contract Documents may only be amended, modified, or supplemented by written agreement signed by both parties.

ARTICLE 12 PERFORMANCE BOND

A. To secure performance of Contractor’s obligations under this Agreement, the Contractor shall provide the Owner with a Performance Bond in the amount of the full contract price. Prior to execution of this Agreement, the Contractor shall provide the form of the Performance Bond to the City for its review and approval. The City shall be authorized to draw upon the Performance Bond to correct any default by Builder under this Agreement, which default shall be determined and substantiated by an Affidavit of Default signed by the Engineer. The Performance Bond shall be held by the City through the two (2) year Project Warranties period specified in this Agreement.

ARTICLE 13 MISCELLANEOUS

13.01 Indemnification

A. The Contractor agrees to indemnify, save, and hold harmless the Owner, its officers, employees, and agents from any and all liability, loss, costs, charges, obligations, expenses, attorney’s fees, litigation, judgments, damages, claims, and demands of any kind arising from or out of any negligent act, error, omission or other tortious conduct of the Contractor, its officers, subcontractors, employees, or agents in the performance or non-performance of its obligations under this Agreement.

13.02 Assignment of Contract

A. No assignment by a party hereto of any rights under or interests in the Contract will be binding on another party hereto without the written consent of the party sought to be bound; and, specifically but without limitation, moneys that may become due and moneys that are due may not be assigned without such consent (except to the extent that the effect of this restriction may be limited by law), and unless specifically stated to the contrary in any written consent to an assignment, no assignment will release or discharge the assignor from any duty or responsibility under the Contract Documents.

13.03 Successors and Assigns

A. Owner and Contractor each binds itself, its partners, successors, assigns, and legal representatives to the other party hereto, its partners, successors, assigns, and legal representatives in respect to all covenants, agreements, and obligations contained in the Contract Documents.

13.04 Severability

A. Any provision or part of the Contract Documents held to be void or unenforceable by any court of competent jurisdiction shall be deemed stricken, and all remaining provisions shall continue to be valid and binding upon Owner and Contractor, who agree that the Contract Documents shall be reformed to replace such stricken provision or part thereof with a valid and enforceable provision that comes as close as possible to expressing the intention of the stricken provision.

13.05 Independent Contractor

The Contractor shall perform the Services as an independent contractor and shall not be deemed by virtue of this Agreement to have entered into any partnership, joint venture, employer/employee relationship with the Owner other than as a contracting party and independent contractor/ The Owner shall not be obligated to secure, and shall not provide, any insurance coverage or employment benefits of any kind or type to or for the Contractor or the Contractor’s employees, sub-consultants, contractors, agents, or representatives, including coverage benefits related but not limited to: local, state, or federal income or other tax contributions; insurance contributions (e.g., FICA); workers' compensation; disability, injury, or health; professional liability insurance, errors, and omissions insurance; or retirement account contributions.

13.06 No Waiver of Governmental Immunity

Nothing herein is intended as nor shall it be construed as a waiver of the protections and immunities afforded the Owner pursuant to the Colorado Governmental Immunity Act, Sections 24-10-101, et seq., Colorado Revised Statutes, or pursuant to any other applicable laws.

[The remainder of this page is intentionally left blank.]

IN WITNESS WHEREOF, Owner and Contractor have signed and executed this Agreement in duplicate on the date first written above. One counterpart each has been delivered to Owner and Contractor. All portions of the Contract Documents have been signed or identified by Owner and Contractor or on their behalf.

CITY OF WOODLAND PARK

Name:
Title:

ATTEST:

CONTRACTOR

Name:
Title:

ATTEST: