This is a state-supplied price sheet for Bid Solicitation #26DPP01192 (T2881) for water damage restoration services on a statewide basis. The document establishes pricing requirements for the South Region, with bidders required to complete the yellow-highlighted cells across three contract years. The price sheet is structured to capture all-inclusive hourly rates for labor personnel, equipment rental costs, and transportation fees.
The contract encompasses labor categories including Project Manager, Supervisor, Water Restoration Technician, Laborer, and Carpenter positions (Foreman, Journeyman, and Apprentice), with separate rates for regular time and overtime work. Equipment pricing covers extraction and drying equipment, power distribution equipment, transportation rental (trailers, trucks, vans), and miscellaneous equipment such as generators, cleaning machines, dehumidifiers, and holding tanks. All labor rates and equipment rentals are priced on an hourly basis across three contract years. The document requires bidders to provide a percentage mark-up for both labor supplies and materials (Line 1) and a percentage mark-up for rental equipment (Line 67). The price sheet prohibits bidders from altering the schedule structure in any manner, ensuring standardized pricing comparison across all responsive bids.
View the file
Other files
| File | Type | Posted |
|---|---|---|
| T2881 Att 4 Procedure for Background Checks.pdf | ||
| T2881 Att 3 Reim~1.xlsx | XLSX spreadsheet | |
| T2881 Bid Amendment 1_1.21.26~1.docx | DOCX document | |
| T2881 - Method of Operation 10.1.2026.docx | DOCX document | |
| T2881 Final PS North 10.1.2026.xlsx | XLSX spreadsheet | |
| First_Knight_OA_Redacted_Signed.pdf | ||
| T2881 Att 1 Combined SSTC 6.3.2025.pdf | ||
| T2881 Final Bid Solicitation 10.1.2026.docx | DOCX document | |
| T2881 Final PS Central 10.1.2026.xlsx | XLSX spreadsheet |
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Sheet1 South Region - State Supplied Price Sheet Bid Solicitation #26DPP01192 - T2881 - Water Damage Restoration Services - Statewide
| Bidder Name: | ||||
| Refer to Bid Solicitation Section 3.23 for Bidder instructions. The Bidder shall provide pricing in the yellow highlighted cells below. The Bidder must not alter the price schedule in any manner. | ||||
| Line No. | Item Description | Unit of Measure | Year 1 | |
| Unit Cost | Year 2 | |||
| Unit Cost | Year 3 |
Unit Cost
| South Region Labor | ||
| 1 | South Region: Percentage Mark-Up for Labor Supplies and Materials | PCNT |
| 2 | South Region: Project Manager - All-Inclusive Hourly Rate - Regular Time |
| As per Bid Solicitation Section 4.6 Personnel Categories and Section 3.23 State-Supplied Price Sheet Instructions | HOURLY | |
| 3 | South Region: Project Manager - All- Inclusive Hourly Rate - Overtime |
| As per Bid Solicitation Section 4.6 Personnel Categories and Section 3.23 State-Supplied Price Sheet Instructions | HOURLY | |
| 4 | South Region: Supervisor -All-Inclusive Hourly Rate - Regular Time |
| As per Bid Solicitation Section 4.6 Personnel Categories and Section 3.23 State-Supplied Price Sheet Instructions | HOURLY | |
| 5 | South Region: Supervisor - All-Inclusive Hourly Rate - Overtime |
| As per Bid Solicitation Section 4.6 Personnel Categories and Section 3.23 State-Supplied Price Sheet Instructions | HOURLY | |
| 6 | South Region: Water Restoration Technician - All-Inclusive Hourly Rate - Regular Time |
| As per Bid Solicitation Section 4.6 Personnel Categories and Section 3.23 State-Supplied Price Sheet Instructions | HOURLY | |
| 7 | South Region: Water Restoration Technician - All-Inclusive Hourly Rate - Overtime |
| As per Bid Solicitation Section 4.6 Personnel Categories and Section 3.23 State-Supplied Price Sheet Instructions | HOURLY | |
| 8 | South Region: Laborer - All-Inclusive Hourly Rate - Regular Time |
| As per Bid Solicitation Section 4.6 Personnel Categories and Section 3.23 State-Supplied Price Sheet Instructions | HOURLY | |
| 9 | South Region: Laborer - All-Inclusive Hourly Rate - Overtime |
| As per Bid Solicitation Section 4.6 Personnel Categories and Section 3.23 State-Supplied Price Sheet Instructions | HOURLY | |
| 10 | South Region: Carpenter Foreman - All-Inclusive Hourly Rate - Regular Time |
| As per Bid Solicitation Section 4.6 Personnel Categories and Section 3.23 State-Supplied Price Sheet Instructions | HOURLY | |
| 11 | South Region: Carpenter Foreman - All-Inclusive Hourly Rate - Overtime |
| As per Bid Solicitation Section 4.6 Personnel Categories and Section 3.23 State-Supplied Price Sheet Instructions | HOURLY | |
| 12 | South Region: Carpenter Journeyman -All-Inclusive Hourly Rate - Regular Time |
| As per Bid Solicitation Section 4.6 Personnel Categories and Section 3.23 State-Supplied Price Sheet Instructions | HOURLY | |
| 13 | South Region: Carpenter Journeyman - All-Inclusive Hourly Rate - Overtime |
| As per Bid Solicitation Section 4.6 Personnel Categories and Section 3.23 State-Supplied Price Sheet Instructions | HOURLY | |
| 14 | South Region: Carpenter Apprentice - All-Inclusive Hourly Rate - Regular Time |
| As per Bid Solicitation Section 4.6 Personnel Categories and Section 3.23 State-Supplied Price Sheet Instructions | HOURLY | |
| 15 | South Region: Carpenter Apprentice - All-Inclusive Hourly Rate - Overtime |
| As per Bid Solicitation Section 4.6 Personnel Categories and Section 3.23 State-Supplied Price Sheet Instructions | HOURLY | |||||
| $ 10.00 | . | |||||
| South Region Equipment | ||||||
| Extraction, Drying, Air Filtration & Cooling Equipment | Unit of Measure | Year 1 Unit Cost | Year 2 Unit Cost | Year 3 Unit Cost | ||
| 16 | Air Mover/Carpert Blowers | HOURLY | ||||
| 17 | Dehumidifier (200 cfm refrigerant) | HOURLY | ||||
| 18 | Dehumidifier (3,500 cfm dessicant) | HOURLY | ||||
| 19 | Dehumidifier (4,500 - 5,000 cfm dessicant) | HOURLY | ||||
| 20 | Dehumidifier (9,000 - 10,000 cfm dessicant) | HOURLY | ||||
| 21 | Dehumidifier (15,000 cfm dessicant) | HOURLY | ||||
| 22 | Dehumidifier (DX Unit 20/30 ton) | HOURLY | ||||
| 23 | Dehumidifier (DX Unit 60 ton) | HOURLY | ||||
| 24 | Extraction Unit (Portable) | HOURLY | ||||
| 25 | Extraction Unit (Trailer) | HOURLY | ||||
| 26 | HEPA Filtration Unit (Air Scrubber) | HOURLY | ||||
| 27 | Inject-dry Unit | HOURLY | ||||
| Power and Distribution Equipment Rental | Unit of Measure | Year 1 Unit Cost | Year 2 Unit Cost | Year 3 Unit Cost | ||
| 28 | Electrical Distribution Panel (120 AMPS) | HOURLY | ||||
| 29 | Generator (Portable) | HOURLY | ||||
| 30 | 60 KW Generator (with enviro fuel tank) | HOURLY | ||||
| 31 | 75 KW Generator (with enviro fuel tank) | HOURLY | ||||
| 32 | 125 KW Generator (with enviro fuel tank) | HOURLY | ||||
| 33 | 200 KW Generator (with enviro fuel tank) | HOURLY | ||||
| 34 | 500 KW Generator (with enviro fuel tank) | HOURLY | ||||
| 35 | 1,000 KW Generator (with enviro fuel tank) | HOURLY | ||||
| 36 | Air Compressor | HOURLY | ||||
| 37 | Carpet Cleaning Machine | HOURLY | ||||
| 38 | Carpet Tilt/Demolition | HOURLY | ||||
| 39 | Saw - Demo | HOURLY | ||||
| 40 | Saw - Power Miter | HOURLY | ||||
| Transportation Rental Fee | Unit of Measure | Year 1 Unit Cost | Year 2 Unit Cost | Year 3 Unit Cost | ||
| 41 | Trailer, Enclosed (12-16 feet) | HOURLY | ||||
| 42 | Trailer, Flat Bed | HOURLY | ||||
| 43 | Trailer, Freezer | HOURLY | ||||
| 44 | Truck, Moving | HOURLY | ||||
| 45 | Truck, Pickup | HOURLY | ||||
| 46 | Van, Box (12 -16 feet) | HOURLY | ||||
| 47 | Van, Box (17-20 feet) | HOURLY | ||||
| 48 | Van, Passenger (up to 10 people) | HOURLY | ||||
| 49 | Vehicle Pickup, SUV or car | HOURLY | ||||
| 50 | Truck and Driver for water disposal | HOURLY | ||||
| Miscellaneous Equipment | Unit of Measure | Year 1 Unit Cost | Year 2 Unit Cost | Year 3 Unit Cost | ||
| 51 | Bobcat, Small | HOURLY | ||||
| 52 | Floor Cleaning System (walk behind) | HOURLY | ||||
| 53 | Light, Tower Mobile (400 W diesel) | HOURLY | ||||
| 54 | Oven, Convection Convection Drying (ULT) | HOURLY | ||||
| 55 | Oven, Vacuum (large) | HOURLY | ||||
| 56 | Ozone Generator | HOURLY | ||||
| 57 | Pump, Sump/Flood | HOURLY | ||||
| 58 | Scaffolding Section | HOURLY | ||||
| 59 | Sprayer, Airless H.P. | HOURLY | ||||
| 60 | Steam Cleaner | HOURLY | ||||
| 61 | Vacuum, HEPA | HOURLY | ||||
| 62 | Vacuum, Upright | HOURLY | ||||
| 63 | Vacuum, Wet/Dry | HOURLY | ||||
| 64 | Washer, High Pressure (hot) | HOURLY | ||||
| 65 | Portable Holding Tank (550 gallon) | HOURLY | ||||
| 66 | Portable Holding Tank (1,000 gallon) | HOURLY | ||||
| 67 | South Region - Rental Equipment: All Inclusive Percentage Mark-Up for Rental Equipment | PCNT |
Sheet2