Questions_and_Answers_AMENDMENT0006.docx

DOCX document 16 KB Posted

Attached to
Mechnical Maintenance Service Federal contract opportunity
Solicitation number
SP4705-15-R-0004
Issued by
Defense Logistics Agency Headquarters

About this file

Questions and Answers amendent 0006

View the file

Other files for this federal contract opportunity

Other files attached to Mechnical Maintenance Service, newest first.
File Type Posted
AMENDMENT_0010.pdf PDF
Amendment_0009.pdf PDF
AMENDMENT_SP4705-15-R-0004-0008.pdf PDF
AMENDMENT_0007.docx DOCX document
AMENDMENT_SP4705-15-R-0004-0007-2.pdf PDF
AMENDMENT_SP4705-15-R-0004-0006_(2).pdf PDF
Mecahnical_Asset_2014.pdf_AttachmentC19.pdf PDF
Attachement_C_9___Mechanical_Work_Order_Data.pdf PDF
QUESTIONS_SP4705-15-R-0004.docx2.docx DOCX document
AMENDMENT_SP4705-15-R-0004-0005.pdf PDF
SP4705-15-R-0001-0004.pdf PDF
Revised_Attachement_C18_Deduction_Summary_(PRS).docx DOCX document
C-26_Mechanical_PM_Guide_(2).pdf PDF
C-26_Mechanical_PM_Guide_(1).pdf PDF
ATTACHMENT_C.14_ASSET_MECHANICAL.PDF PDF
ATTACHMENT_C.14_ASSET_PIPE_2013.pdf PDF
ATTACHMENT_C.14_ASSET_DIN_2013.pdf PDF
1449.pdf PDF
Mecahnical_Asset_2014.pdf_AttachmentC19.pdf PDF
C-3_Discription_of_facilities_SP4705-15-R-0004.pdf PDF
Sample_IDIQ_SOW_Mechanical.doc DOC document
DCSO-F-Mech-Maint-PWS-01APR15.docx DOCX document
DCSO-F-Mech-Maint-RFP-Cont-01APR15.docx DOCX document
Show all 23

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Questions and Answers SP4705-15-R-0004, Amendment 0006

Question 1. General Intent 1.1, 3rd and 4th paragraphs: The referenced paragraphs refer to a separate IDIQ contract. However the solicitation does not include a copy of this contract nor does the pricing schedule include an IDIQ section for pricing purposes. Please clarify?

Answer: See Paragraph C.1.0 of the PWS, General Intention within the PWS. As for the IDIQ Section, offerors are required to follow the General Proposal Instructions, under Paragraph 2.4, Volume III, Price Proposal.

Question 2. 2.4, For the Sample Project: This is a two part question; the footnote under the Labor Rate Table instructs the contractor to fully burden the hourly rate for both on site and off site personnel. We assume this means to add ALL costs to include overhead and profit. However, on the Sample Project form there does not appear to add overhead and profit on materials and subcontractor costs or other costs. Please clarify? Answer: For the Sample Project, the offerror is responsible for including labor categories needed to complete the services. See Page 14 of General Information for information on Sample Project.

The lead sentence appears to direct the contractor to complete the costing of a Sample Project. However no mention is made of the scope of this project so it is not possible to estimate the costs. Furthermore, in 3.2.3, Price Proposal, once again the Sample Order Pricing is mentioned. Also in the PWS, C.1.0, it is requested again, the pricing of a Sample Project. Please clarify?

Answer: See Attachment C25 for the Sample Project.

Lastly, will the Sample Project be evaluated in our Technical Proposal rating? If so, can you please clarify the evaluation criteria and evaluation weight will be given to the Sample Project completion?

Answer: No, the sample project will not be evaluated in your technical proposal rating.

Question 3. Are the Fire extinguishers excluded from this contract?

Answer: Yes

Question 4. Is the Fire Alarm System (smoke detectors, heat detectors, Manual Pull Stations, Duct Smoke Detectors, Elevator recall, Fire doors, Fire and Smoke Dampers & Horn Strobes) excluded from this contract?

Answer: Yes (fire and smoke dampers are not excluded)

Question 5: If the fire alarm system is part of this contract, can the government please provide quantities for the number of smoke detectors, heat detectors, Manual Pull Stations, Duct Smoke Detectors, Elevator recall, Fire doors, Fire and Smoke Dampers & Horn Strobes.

Answer: N/A