This document is an amendment to a solicitation for an electric power resiliency project at two buildings located at the Defense Logistics Agency Distribution San Joaquin facility. The amendment provides revised specifications for the solar PV systems to be installed on Building 57 and 58. It clarifies that the buildings are separately metered with two utility distribution meters required. The amendment also answers contractor questions to confirm separate metering and clarify that the walk pad layout will be designed by the contractor. The original solicitation sought construction services to design and install a 500KW solar photovoltaic system on Building 57 and a 300KW system on Building 58, with the generated power interconnected to each building's existing electric service and used to offset retail electricity consumption. Accompanying documents included the scope of work, specifications, drawings, submittal registers, and requirements for pre-construction meetings and initial and final submittals.

View the file

Other files

Show all 18

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

AMENDMENT OF SOLICITATION/MODIFICATION OF CONTRACT

1. CONTRACT ID CODE

2. AMENDMENT/MODIFICAITON NO. 3. EFFECTIVE DATE 4. REQUISITION/PURCHASE REQ. NO. 5. PROJECT NO. (If applicble)

7. ADMINISTERED BY (If other than Item 6) CODE

STANDARD FORM 30 (REV. 10-83)

Prescribed by GSA FAR (48 CFR) 53.243

FACILITY CODE

9A. AMENDMENT OF SOLICIATION NO.

9B. DATED (SEE ITEM 11)

10A. MODIFICATION OF CONTRACT/ORDER NO.

10B. DATED (SEE ITEM 11)

11. THIS ITEM ONLY APPLIES TO AMENDMENTS OF SOLICITATIONS

The above numbered solicitation is amended as set forth in Item 14. The hour and date specified for receipt of Offers is extended, is not extended.

Offers must acknowledge receipt of this amendment prior to the hour and date specified in the solicitation or as amended, by one of the following methods:

(a)By completing items 8 and 15, and returning copies of the amendment; (b) By acknowledging receipt of this amendment on each copy of the offer submitted;

or (c) By separate letter or telegram which includes a reference to the solicitation and amendment numbers. FAILURE OF YOUR ACKNOWLEDGMENT TO BE RECEIVED AT THE PLACE DESIGNATED FOR THE RECEIPT OF OFFERS PRIOR TO THE HOUR AND DATE SPECIFIED MAY RESULT IN REJECTION OF YOUR OFFER. If by virtue of this amendment your desire to change an offer already submitted, such change may be made by telegram or letter, provided each telegram or letter makes reference to the solicitation and this amendment, and is received prior to the opening hour and date specified.

12. ACCOUNTING AND APPROPIRATION DATA (If required)

13. THIS ITEM ONLY APPLIES TO MODIFICATION OF CONTRACTS/ORDERS.

IT MODIFIES THE CONTRACT/ORDER NO. AS DESCRIBED IN ITEM 14.

CHECK ONE A. THIS CHANGE ORDER IS ISSUED PURSUANT TO: (Specify authority) THE CHANGES SET FORTH IN ITEM 14 ARE MADE IN THE CONTRACT ORDER

NO. IN ITEM 10A.

B. THE ABOVE NUMBERED CONTRACT/ORDER IS MODIFIED TO REFLECT THE ADMINISTRATIVE CHANGES (such as changes in paying office, appropriation date, etc.) SET FORTH IN ITEM 14, PURSUANT TO THE AUTHORITY OF FAR 43.103(b).

C. THIS SUPPLEMENTAL AGREEMENT IS ENTERED INTO PURSUANT TO AUTHORITY OF:

D. OTHER (Specify type of modification and authority)

E. IMPORTANT: Contractor is not, is required to sign this document and return copies to the issuing office.

Except as provided herein, all terms and conditions of the document referenced in Item 9A or 10A, as heretofore changed, remains unchanged and in full force and effect.

15C. DATE SIGNED

15A. NAME AND TITLE OF SIGNER (Type or print)

16C. DATE SIGNED

16A. NAME AND TITLE OF CONTRACTING OFFICER (Type or print)

14. DESCRIPTION OF AMENDMENT/MODIFICATION (Organized by UCF section headings, including solicitation/contract subject matter where feasible.)

PAGE OF PAGES

6. ISSUED BY CODE

8. NAME AND ADDRESS OF CONTRACTOR (No., street, county, State and ZIP Code) (X)

CODE

15B. CONTRACTOR/OFFEROR

(Signature of person authorized to sign)

16B. UNITED STATES OF AMERICA

(Signature of Contracting Officer)

NSN 7540-01-152-8070

Previous edition unusable

SP3300-22-B-0001

Electric Power Resiliency - Bldgs. 57 and 58

Amendment 0002

Amendment 0002 is incorporated into this Invitation For Bid (IFB) for the project “Electric Power Resiliency - Bldgs. 57 and 58”, DLA Distribution San Joaquin and shall become part of any resulting Contract issued.

Amendment 0002 is being issued to provide a revised Attachment 3 and to answer late Vendor questions.

See revised Attachment 3 Specifications Solar PV Bldg.57-58 Rev2.0 attached.

Answers to vendor questions are listed below.

Vendor Question:

Question 1: The specifications for this project state this as the requirement for PV module warranty: "The power warranty must be minimum of 98% output of nameplate KW rating for first five years, and not more than 0.25%/yr depreciation for next 20 years amounting to minimum 92% efficiency at the end of 25 years. The product workmanship material and manufacturing defect warranty shall be a minimum of 25 year" We couldn't find a module that fits the warranty, especially the underlined part about the module holding 98% output for five years. I think it could be an error in the spec because it's usually 98% of nameplate kW rating for the first year then 0.25% degradation after that, leading to 92% power output at year 25. Do you know if this was a typo?

Answer 1: Yes, it is a typo. The correct specifications are - 98% of nameplate KW rating for the first year then 0.25% degradation after that, leading to 92% power output at year 25.

Question 2: Can you provide the walk pad layout that is called out in the scope of work “Install 30” wide, skid proof, weatherproof trak III walkway protection pad”?

Answer 2: Walk pad layout will be decided by the contractor during design phase based on solar panel layout to ensure adequate maintenance space for the solar panels and existing equipment on the roof.

Question 3: Are building 57 and 58 separately metered, with 2 separate utility retail distribution meters and service points?

Answer 3: Yes, Utility retail distribution meter will be required with each electrical panel i.e.

MSB-1 and MSB-2 in WHSE 57 and BDS in WHSE 58.

Question 4: Are building 57 and 58 separately metered. or does this large facility only have a single utility retail distribution service point with one 1 meter for the entire facility?

Answer 4: See response to Question 3.

Question 5: Are building 57 and 58 separately metered, or does the utility serve this customer from a customer owned substation breaker and take transmission service?

Answer 5: Building 57 and 58 are separately metered. See response to Question 3.

All other terms and conditions remain unchanged.

END OF AMENDMENT 0002

Amendment 0005
Amendment 0004
Amendment 0003
Amendment 0002
Amendment 0001
Amendment 0001
Amendment 0001
Amendment 0001

Amendment 0005 wording

IDCode:
Page: 1
Pages: 2
AmendNo: 0002
EffDate: 9-Jun-2022
ReqNo: N/A
ProjNo: P.2022.00456
IssCode: SP3300
IssuedBy: DLA DISTRIBUTION

ACQUISITION OPERATIONS J7-AB

5404 J AVENUE BUILDING 404

NEW CUMBERLAND PA 17070-5059

AdmCode: SP3300
AdminBy:
ContName:
ContStrt:
ContCnty:
ContSt:
ContZIP:
Code:
FacCode:
SolChgYs: Yes
SolChgNo: Off
SolAmdNo: SP3300-22-B-0001
AmendDate: 17-May-2022
ModNo:
ModDate: 05 JUL 20