(11) Attachment K Project Specifications and Submittals
View the file
Other files for this federal contract opportunity
| File | Type | Posted |
|---|---|---|
| Amendment_0005.pdf | ||
| Amendment_0004.pdf | ||
| Amendment_0003.pdf | ||
| Amendment_0003_attachments.pdf | ||
| Amendment_0002.pdf | ||
| Amendment_0001.pdf | ||
| Revised_Dwg_ES-101_&_ES-108-_Amendment_0001.pdf | ||
| Site_Visit_Notes.pdf | ||
| (12)_Attachment_L_Drawings.pdf | ||
| (10)_Attachment_J_Wage_Determinations.pdf | ||
| (2)_Attachment_B_Short_Form_Badge_Request.pdf | ||
| (6)_Attachment_F_DLA_SP_Camera_Pass_Request_Form.pdf | ||
| (5)_Attachment_E_Deliv_Notification_Form.docm | DOCM document | |
| (7)_Attachment_G_SF24_-_Bid_Bond.pdf | ||
| (8)_Attachment_H_SF25_(Performance_Bond).pdf | ||
| SP3300-17-B-0006.pdf | ||
| (3)_Attachment_C_Long_Form_Badge_Request.pdf | ||
| (4)_Attachment_D_Badge_Renewal.doc | DOC document | |
| (1)_Attachment_A_New_Personnel_Notification_Form.docm | DOCM document | |
| (9)_Attachment_I_SF25A_(Payment_Bond).pdf |
Show all 20
On GovTribe
Work with this file on GovTribe
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Defense Distribution Center, Susquehanna New Cumberland, PA Contract No: W912HP-11-D-0008
United States Army Corps of Engineers Charleston District
Specifications RTA Submission
31 May 2017
Site-Wide Replacement of Utility Poles
Site-Wide Replacement of Utility Poles READY TO ADVERTISE SUBMISSION Defense Distribution Center, Susquehanna, New Cumberland, PA May 31, 2017
PROJECT TABLE OF CONTENTS
DIVISION 01 - GENERAL REQUIREMENTS
00 01 07 SEALS PAGE
01 11 00 SUMMARY OF WORK
01 14 00 WORK RESTRICTIONS
01 32 01.00 10 PROJECT SCHEDULE
01 33 00 SUBMITTAL PROCEDURES
01 35 26 GOVERNMENTAL SAFETY REQUIREMENTS
01 35 40.00 20 ENVIRONMENTAL MANAGEMENT
01 45 00.10 20 QUALITY CONTROL FOR MINOR CONSTRUCTION
01 50 00 TEMPORARY CONSTRUCTION FACILITIES AND CONTROLS
01 57 19 TEMPORARY ENVIRONMENTAL CONTROLS
01 62 35 RECYCLED/RECOVERED/BIOBASED MATERIALS
01 78 00 CLOSEOUT SUBMITTALS
DIVISION 26 - ELECTRICAL
26 00 00 BASIC ELECTRICAL MATERIALS AND METHODS
DIVISION 32 - EXTERIOR IMPROVEMENTS
32 12 16 HOT - MIX ASPHALT (HMA) FOR ROADS
DIVISION 33 - UTILITIES
33 71 01 OVERHEAD TRANSMISSION AND DISTRIBUTION
-- End of Project Table of Contents --
PROJECT TABLE OF CONTENTS Page 1
SECTION 01 11 00 Page 1
SECTION 01 11 00
SUMMARY OF WORK
08/11
Table of Contents
PART 1 GENERAL
REFERENCES ................................................................................................................2 1.1 DEFINITIONS ................................................................................................................2 1.2 SUBMITTALS ................................................................................................................2 1.3 WORK COVERED BY CONTRACT DOCUMENTS ..................................................3 1.4
1.4.1 Project Description
1.4.2 Location
WORK SCHEDULING ..................................................................................................3 1.5 OCCUPANCY OF PREMISES ......................................................................................3 1.6 EXISTING WORK .........................................................................................................4 1.7 ON-SITE PERMITS........................................................................................................4 1.8
1.8.1 Utility Outage Requests and Utility Connection Requests
1.8.2 Digging, Welding, and Burning Permits
LOCATION OF UNDERGROUND UTILITIES ...........................................................4 1.9
1.9.1 Notification Prior to Excavation
CONSTRUCTION CONSTRAINTS..............................................................................5 1.10
1.10.1 Operations Requirements:
1.10.2 Contractor’s Working Hours:
1.10.3 Contractor Request:
1.10.4 Utility/Systems Demo/Install (MV power, LV power, communications, security):
SALVAGE MATERIAL AND EQUIPMENT ...............................................................6 1.11
PART 2 PRODUCTS
PART 3 EXECUTION
SECTION 01 11 00 Page 2
SECTION 01 11 00
SUMMARY OF WORK
GENERAL PART 1
REFERENCES 1.1
The publications listed below form a part of this specification to the extent referenced. The publications are referred to within the text by the basic designation only.
ASTM INTERNATIONAL (ASTM)
ASTM E2114 (2008) Standard Terminology for Sustainability Relative to the Performance of Buildings
GREEN BUILDING INITIATIVE (GBI)
Green Globes (2004) Green Globes(™) US Green Building Rating System
U.S. ENVIRONMENTAL PROTECTION AGENCY (EPA)
Energy Star (1992; R 2006) Energy Star Energy Efficiency Labeling System
U.S. GREEN BUILDING COUNCIL (USGBC)
LEED NC (2009) Leadership in Energy and Environmental Design(tm) New Construction Rating System
DEFINITIONS 1.2
Definitions pertaining to sustainable development are as defined in ASTM E2114, Section 01 57 19, TEMPORARY ENVIRONMENTAL CONTROLS, and as specified.
a. "Environmentally preferable products" have a lesser or reduced effect on the environment in comparison to conventional products and services. This comparison may consider raw materials acquisition, production, manufacturing, packaging, distribution, reuse, operation, maintenance, or disposal of the product.
b. "Indoor environmental quality" is the physical characteristics of the building interior that impact occupants, including air quality, illumination, acoustics, occupant control, thermal comfort, daylighting, and views.
c. "Operational performance" is the functional behavior of the building as a whole or of the building components.
d. "Sustainability" is the balance of environmental, economic, and societal considerations.
SUBMITTALS 1.3
SECTION 01 11 00 Page 3
Government approval is required for submittals with a "G" designation; submittals not having a "G" designation are for information only. The following shall be submitted in accordance with Section 01 33 00, SUBMITTAL PROCEDURES:
SD-01 Preconstruction Submittals
Construction Sequence; G
WORK COVERED BY CONTRACT DOCUMENTS 1.4
1.4.1 Project Description
Site-Wide Replacement of Utility Poles, which includes but is not limited to the following.
This project includes the replacement of wooden utility poles throughout the Installation, including the associated appurtenances, as shown on the drawings. New wooden poles will be provided and installed with associated appurtenances as shown and specified. Existing cabling will be relocated to the new poles. The project also includes the removal of specifically identified wooden poles as shown on the drawings. Any damage to pavement or grass areas from the removal of any wooded poles or the installation of new wooden poles will be repaired as specified. New pole name tags will be provided and installed on all wooden utility poles throughout the installation.
1.4.2 Location
The work shall be located at Defense Distribution Center, Susquehanna in New Cumberland, PA. Refer to the Contract Drawings for specific location(s) on site for the work.
WORK SCHEDULING 1.5
Normal duty hours for work shall be from 0700 to 1530, Monday through Friday excluding all federal holidays. Requests for work off hours shall require written approval from the Contracting Officer Representative (COR) no less than 15 working days in advance of the proposed work period.
OCCUPANCY OF PREMISES 1.6
All areas of the Installation shall remain occupied for the duration of this construction project.
The utility poles that are to be removed or replaced under the scope of this project are located throughout the Installation. These poles are used to support (MV power, LV power, communications, security, etc.) system conductors and equipment that are critical to the continued operation of the entire Installation. These systems and/or system conductors shall remain energized for the duration of the project with the exception of scheduled outages.
Before work is started, the Contractor shall prepare and submit a Construction Schedule to the COR detailing the sequence of procedures, means of access, space for storage of materials and equipment, and use of approaches, etc. required to successfully execute the work. This
SECTION 01 11 00 Page 4 sequence shall be provided in writing and shall be approved by the COR prior to the start of any work. See Section 01 32 01.00 10, PROJECT SCHEDULE for further details.
EXISTING WORK 1.7
In addition to "FAR 52.236-9, Protection of Existing Vegetation, Structures, Equipment, Utilities, and Improvements":
a. Remove or alter existing work in such a manner as to prevent injury or damage to any portions of the existing work which remain.
b. Repair or replace portions of existing work which have been damaged or altered during construction operations to match existing or adjoining work, as approved by the Contracting Officer. At the completion of operations, existing work shall be in a condition equal to or better than that which existed before new work started.
ON-SITE PERMITS 1.8
1.8.1 Utility Outage Requests and Utility Connection Requests
Work shall be scheduled to keep outages to a minimum.
Requests for utility outages and connections shall be made in writing to the COR at least 30 calendar days in advance of the proposed time. Each request shall state the system involved, area involved, approximate duration of outage, and the nature of work involved.
1.8.2 Digging, Welding, and Burning Permits
ACTIVITY SUBMISSION DATE SUBMISSION FORM
Digging / Excavation 10 working days prior to work Dig Permit COR will supply when requested.
Confined Space Entry Daily (12 hours maximum) Confined Space Entry Permit
Hot Work Daily Hot Work Permit
Issued by Fire Department when requested.
Utility Outage 30 calendar days N/A
Permits shall be posted at a conspicuous location in the construction area. Burning of trash or rubbish is not permitted on project site.
LOCATION OF UNDERGROUND UTILITIES 1.9
Location of the existing utilities indicated is approximate. Contractor is responsible for requesting existing underground utilities to be located prior to beginning work. Contractor is also responsible for verifying the elevations of existing piping, utilities, and any type of
SECTION 01 11 00 Page 5 underground or encased obstruction not indicated to be relocated or removed but indicated or discovered during scanning in locations to be traversed by piping, ducts, and other work to be conducted or installed. Verify elevations before installing new work closer than nearest manhole or other structure at which an adjustment in grade can be made. See Section 01 78 00, CLOSEOUT SUBMITTALS for additional information.
1.9.1 Notification Prior to Excavation
In accordance with the requirements of the Underground Utility Line Protection Act (p.l. 852,
no. 287) as amended by the Act (p.l. 1567, no. 199) of November 30, 2004, the Contractor must contact the PA One Call System at (800) 242-1776 at least three (3) but no more than ten
(10) working days in advance of beginning excavation work. The Contractor must also comply with “Installation SOP 26 - Underground Utility Locating” which is attached.
The Contractor shall make written requests for a Dig Permit to the COR at least 10 working days prior to starting excavation work. Contractor is responsible for maintaining markings provided by both PA One Call and Dig Permit once utilities are marked and throughout construction. Damage to existing marked utilities shall be repaired at the contractor’s expense.
CONSTRUCTION CONSTRAINTS 1.10
The affected systems and/or system conductors shall remain energized for the duration of the project with the exception of scheduled power outages. The following construction phasing requirements and work restrictions are provided by DLA. Contractor shall include a Phasing Schedule for approval by COR prior to start of work. Refer to Section 01 32 01.00 10
PROJECT SCHEDULE.
1.10.1 Operations Requirements:
The Contractor shall adhere to the following operational requirements and constraints:
1.10.2 Contractor’s Working Hours:
Comply with the following working hour requirements:
a. Normal Working Hours: 0700 thru 1530.
b. Refer to Section 01 14 00 WORK RESTRICTIONS for additional information.
1.10.3 Contractor Request:
Procedure for Contractor requests necessary for construction activities shall be as follows:
a. Barricading work area must be scheduled and pre-approved by the Government through the COR. All requests shall be submitted 24 hours in advance to setting up a barricade/caution tape.
SECTION 01 11 00 Page 6
b. Small incidental (daily) stored materiel moves (for construction access) must be requested 24 hours in advance of construction activities through the COR.
1.10.4 Utility/Systems Demo/Install (MV power, LV power, communications, security):
a. Any work that will require de-energization of power (MV or LV) or result in an interruption to electric, communications, or security systems will need to be coordinated/scheduled through the COR.
b. Requests for utility outages and connections shall be made in writing to the COR at least 30 calendar days in advance of the proposed time.
c. Utility outages/service switchovers shall generally be scheduled to occur outside of normal working hours. Local systems outages/service switchovers may possibly be scheduled during the week outside or normal working hours. Systems outages/service switchovers that will affect multiple systems and/or multiple buildings will likely be required to occur on Sundays. The maximum duration of any Sunday outage shall be limited to 8 hours.
d. Government shall receive a (48) hour notice prior to any traffic pattern changes being implemented.
SALVAGE MATERIAL AND EQUIPMENT 1.11
Materials and equipment to be salvaged as identified by the contract documents shall remain the property of the Government. The salvaged property shall be segregated, itemized, delivered, and off-loaded at the Government designated storage area located on the Defense Distribution Center Susquehanna site.
Contractor shall maintain property control records for material or equipment designated as salvage. Contractor's system of property control may be used if approved by the Contracting Officer. Contractor shall be responsible for storage and protection of salvaged materials and equipment until receipt and acceptance of salvage material by the COR. Salvaged material under the Contractor’s control that is damaged prior to turnover to the Government shall be replaced by the Contractor at Contractor’s expense. Salvage material shall be documented on Form DD 250 and DD250C (continuation if necessary). A copy of this form is attached and shall be made electronically available by the COR. Instructions for the proper preparation of this form can be found at the following link, Part 4:
http://farsite.hill.af.mil/reghtml/regs/far2afmcfars/fardfars/dfars/DFARSApxF.htm
PRODUCTS PART 2
Not Used
EXECUTION PART 3
Not used
-- End of Section --
SECTION 01 11 00 Page 7
SECTION 01 11 00 Page 8
SECTION 01 11 00 Page 9
SECTION 01 11 00 Page 10
SECTION 01 11 00 Page 11
SECTION 01 14 00 Page 1
SECTION 01 14 00
WORK RESTRICTIONS
11/11
TABLE OF CONTENTS
GENERAL .....................................................................................................................2 PART 1
1.1 REFERENCES
1.2 SUBMITTALS
1.3 SPECIAL SCHEDULING REQUIREMENTS
1.3.1 Materials, Equipment, and Personnel
1.3.2 Active facility
1.3.3 Construction Interruptions
1.3.4 Scheduling Interruptions
1.4 CONTRACTOR ACCESS AND USE OF PREMISES
1.4.1 Activity Regulations
1.4.2 Working Hours
1.4.3 Work Outside Regular Hours
1.4.4 Occupied and Existing Buildings
1.4.5 Utility Cutovers and Interruptions
PRODUCTS ...................................................................................................................8 PART 2 EXECUTION .................................................................................................................8 PART 3
SECTION 01 14 00 Page 2
SECTION 01 14 00
WORK RESTRICTIONS
GENERAL PART 1
1.1 REFERENCES
The publications listed below form a part of this section to the extent referenced. The publications are referred to within the text by the basic designation only.
Defense Logistics Agency
DLA Physical Security Manual – DLAM 5200.08-V1 and DLAM 5200.08-V2
Defense Distribution Center Susquehanna – Installation Access Policy
Defense Distribution Center Susquehanna – Image Capturing Device Policy
1.2 SUBMITTALS
Government approval is required for submittals with a "G" designation; submittals not having a "G" designation are for information only. The following shall be submitted in accordance with Section 01 33 00, SUBMITTAL PROCEDURES:
SD-01 Preconstruction Submittals
List of Contact Personnel; G Contractor and Visitor Badge Request Form – (Short Form); G DDSP Security Information Form – (Long Form); G Camera Pass Request Form; G
1.3 SPECIAL SCHEDULING REQUIREMENTS
1.3.1 Materials, Equipment, and Personnel
Have materials, equipment, and personnel required to perform the work at the site prior to the commencement of the work.
1.3.2 Active facility
The activity at the facility under construction will remain in operation during the entire construction period. The Contractor must conduct his operations so as to cause the least possible interference with normal operations of the activity.
1.3.3 Construction Interruptions
SECTION 01 14 00 Page 3
Permission to interrupt any active roads, railroads, and/or parking areas must be requested in writing a minimum of 15 working days prior to the desired date of interruption. In addition, work that will impact existing employee workspaces or material storage areas, etc. shall require a minimum additional advance notification not less than (15) working days in advance of the proposed activities. Coordinate all activities through the Contracting Officer Representative (COR).
1.3.4 Scheduling Interruptions
The work under this Contract requires special attention to the scheduling and conduct of the work in connection with existing operations. Identify on the Project Schedule each factor which constitutes a potential interruption to operations. The COR and Contractor shall work with operations personnel to coordinate these interruptions and to affect minimal impact to the mission.
1.4 CONTRACTOR ACCESS AND USE OF PREMISES
1.4.1 Activity Regulations
Ensure that Contractor personnel employed on the activity become familiar with and obey activity regulations including Safety, Fire, Traffic and Security Regulations. Keep within the limits of the work and avenues of ingress and egress. To minimize traffic congestion, delivery of materials should be outside of peak traffic hours (0630 to 0800 and after 1530) unless otherwise approved by the Contracting Officer. Wear Hard Hats, Safety Shoes, Reflective Vests, and Eye Protection at all times in designated areas. Do not enter any restricted areas unless required to do so and until cleared for such entry. All Contractor equipment and vehicles must be properly identified with their company name and company logo.
1.4.1.1 Subcontractors and Personnel Company Contacts
Provide a list of contact personnel for the Contractor and subcontractors including addresses and telephone numbers for use in the event of an emergency by the Contracting Officer Representative. As changes occur and additional information becomes available, correct and change the information contained in previous lists.
1.4.1.2 Identification Badges and Installation Access
Contractor ID Badges a.
All badges are the property of the United States government. Badges must be displayed at all times while on the installation unless prohibited by safety concerns. Badges will not be photographed or copied and will not be displayed off the installation. Any lost or stolen badges will be reported to the COR and Installation Security immediately. The Contractor
SECTION 01 14 00 Page 4 will ensure that all badges are returned to the Pass and ID office upon the termination of the contract or individual employees.
All persons, with the exception of delivery truck drivers and persons possessing valid Government Common Access Cards (CACs), entering the Installation must obtain an Identification Badge from Security, Pass and ID. All contractors will receive a badge for the duration of the contract. The construction contractor shall follow the below procedures to obtain and renew Identification Badges for all direct hire and subcontractor employees and visitors:
(1) Complete a Contractor and Visitor Badge Request (noted as Attachment D) for short term passes less than 30 days or DDSP Security Information (noted as Attachment B) for long term passes more than 30 days. Example copies of these passes are provided at the end of this section.
(2) Submit completed Badge Request forms to the Contracting Officer Representative a minimum of 2 working days prior to arrival on-site.
(3) Electronic copies of these forms are available from the COR and must be used for badge requests. Badge request forms contain Personally Identifiable Information (PII) and must therefore be transmitted over the Internet encrypted. Encrypted forms require a password for access to the form. The COR will provide the password with the encrypted form when the form is delivered for use.
Installation Access b.
(1) Obtaining Contractor ID Badge
Contractor personnel shall enter the Installation at Post #3 off of Old Depot Road and go to the Pass & ID Building located just inside the Installation Entrance.
Personnel shall acquire their ID Badges at the Pass & ID Building. The hours of operation for Pass and ID is 0700 to 1500. Contractor personnel that have not submitted either the Contractor and Visitor Badge Request From or the DDSP Security Information Form (described above) through the COR will not be issued ID Badges or granted access to the Installation.
(2) Privately Owned Vehicles (POVs)
POVs transporting Contractor personnel may enter the Installation via Post 3 off Old Depot Road, provided they are not transporting tools, equipment, or supplies.
All persons in Contractor vehicles are required to show ID Badges at the ID Check Stations. All vehicles entering the Installation at Post 3 are subject to random vehicle search procedures.
(3) Contractor and Construction Vehicles
SECTION 01 14 00 Page 5
Contractors driving any form of vehicle designed to carry tools, equipment, supplies, or materials necessary for the work are required to enter the installation via Post 4 off of Old York Road (at Normandy Drive). All persons in Contractor vehicles are required to show ID Badges at the Vehicle Search Area. All vehicles entering the Installation at Post 4 are subject to vehicle search procedures.
Construction Deliveries c.
Deliver equipment and materials to the site in an undamaged condition. Material that is deemed to be damaged or defective by the Contracting Officer Representative from manufacturing, during shipment, or while on-site shall be replaced at the Contractor's expense. Equipment and materials that are deemed to be damaged or defective shall be removed and properly disposed of by the Contractor. New equipment and materials shall be utilized to replace rejected materials or equipment.
Contractors shall receive material and equipment at their own facility and transport this equipment to the Installation and project site themselves. Government is not responsible for damage to material and equipment shipped directly to the Installation. Contractor must be present to accept shipment of material directly to the Installation. Material that is shipped to the main warehouse (Building 2001) can easily be lost in the midst of the large volume of material constantly moving through the receiving warehouse. Material that is shipped to the Installation and subsequently lost shall be replaced at the Contractors expense.
All contractor deliveries shall enter the Installation at Post 4. To avoid delays at Post 4, deliveries should be scheduled to arrive after 0800 whenever possible. The Construction Contractor shall follow the following procedure for all deliveries (including pick-ups at the construction site):
(1) After being processed by DLA Police in the Post 4 Vehicle Search Area, Delivery Vehicles are directed to proceed onto the Installation and into the vehicle holding area where they must wait for an authorized member of the Construction Contractor to escort them from Post 4 to the construction site. The Construction Contractor’s Site Supervisor is responsible for coordinating all material deliveries and providing all required vehicle escorts. Upon completion of material delivery, the Construction Contractor is responsible for escorting the delivery vehicle back to Post 4 to exit the Installation.
Delivery Escort Authorization d.
Personnel that intend to escort deliveries arriving at Gate 4 to the construction site will require special annotation on their contractor badges to enable this activity. Contractors may provide up to 2 names of persons authorized to escort their deliveries on the depot.
If the contractor intends to use subcontractors, each sub-contractor is authorized to have
SECTION 01 14 00 Page 6 one (1) person designated as an escort for their deliveries. To obtain this authorization, place a stamp (electronically added) to the top of either the Contractor or Visitor Badge Request for short term passes or DDSP Security Information for long term passes with the words: “Authorization Request for Construction Delivery Escort”. This stamp should be displayed prominently on the top of the sheet to assure that security personnel do not miss this annotation.
1.4.1.3 Photographs
Cameras may be possessed and operated by authorized persons only. To obtain a Camera Pass, the Contractor must provide the following information to the COR:
Camera Pass Request Form (attached) shall be provided to the contractor by the COR. a.
MATOC contractors shall use the long form and request a camera pass for the duration to the end of the current option year. Indicate on the request form that the contractor will be under contract with us for numerous ongoing projects.
The COR will validate the Contractor’s request information and forward the Camera Pass Request Form to Installation Security. If approved, the COR will notify the Contractor that a Camera Pass can be obtained at the Pass & ID Building. Camera Pass requests shall be kept to a minimum and limited to Prime Contractor personnel only. A Camera Pass must be in the possession of the person taking the photographs at all times and presented whenever requested by Government personnel. Failure to maintain or loss of Camera Passes must be reported to COR for action. Installation Security will be notified as necessary by the COR. Personnel found to be in the possession of photographic equipment without the proper documentation will have their equipment confiscated, contents reviewed and returned upon their departure of the Installation or other arrangements will be made.
Only Digital Still Cameras should be used. Cell phones and tablets are NOT authorized b.
under any circumstances for taking photographs.
All images captured on digital cameras must be reviewed by Installation Security prior to removing the Camera from the Installation. Cameras must be brought to the Public Safety Facility, Building 911, on J Avenue at the end of each work day and surrendered to Installation Security Staff for review. Any images found to contain images of unauthorized items or areas will be deleted prior to return to Contractor personnel.
Do not take pictures of Contractor or Government Employee ID Badges, identification c.
signs, certain stored materials (as clarified by the COR), security hardware, fire suppression systems, utilities fixtures, or other areas, facilities, or improvements unless images of such are specifically required by the project.
1.4.1.4 Employee List
SECTION 01 14 00 Page 7
The Contractor must provide to the Contracting Officer, in writing, the names of two designated representatives authorized to request personnel and vehicle passes for employees and subcontractor's employees prior to commencement of work under this contract
1.4.1.5 Radioactive Materials and Equipment
All testing equipment, containing a radioactive source, must be operated in accordance with an approved radioactive equipment plan. This plan must be submitted to the Contracting Officer and approved prior to bringing the equipment unto the Installation. A different radioactive equipment plan will be required for each different type of equipment, type of radioactive source, or size of radioactive source. A data sheet of for each piece of new radioactive equipment must be submitted to the Contracting Officer. The data sheet must contain the following information:
Name of equipment. a.
Name and address of equipment manufacturer. b.
Type and size of radiation source. c.
The location of the installed radioactive equipment (i.e. building no., floor, code/shop d.
area).
1.4.2 Working Hours
Regular working hours must consist of an 8-1/2 hour period, between 0700 and 1530, Monday through Friday, excluding Government holidays.
1.4.3 Work Outside Regular Hours
Work outside regular working hours requires Contracting Officer Representative approval.
Make application 30 calendar days prior to such work to allow arrangements to be made by the Government for inspecting the work in progress, giving the specific dates, hours, location, type of work to be performed, contract number and project title. Based on the justification provided, the Contracting Officer may approve work outside regular hours.
During periods of darkness, the different parts of the work must be lighted in a manner approved by the Contracting Officer Representative. The Contractor shall coordinate its efforts to make all utility cutovers outside of normal working hours to the greatest extent possible to minimize impact to existing operations, unless directed otherwise.
1.4.4 Occupied and Existing Buildings
The Contractor may be working around existing buildings which are occupied. Do not enter the buildings without prior approval of the Contracting Officer Representative.
SECTION 01 14 00 Page 8
The existing buildings and their contents must be kept secure at all times. The Contractor shall provide temporary closures as required to maintain security as directed by the Contracting Officer Representative.
The Contractor shall provide dust covers or protective enclosures to protect existing work that remains and Government material located in the work area during the construction period.
1.4.5 Utility Cutovers and Interruptions
1.4.5.1 Make utility cutovers and interruptions outside of normal working hours to minimize impact on existing operations, unless directed otherwise. Conform to procedures required in the paragraph 1.4.3 entitled Work Outside Regular Hours.
1.4.5.2 Ensure that new utility lines are complete, except for the connection, before interrupting existing service.
1.4.5.3 Interruption to the MV electric system, LV electric systems, communications systems, and/or security systems shall be considered utility cutovers pursuant to the paragraph 1.4.3 entitled Work Outside Regular Hours.
1.4.5.4 Operation of Station Utilities: The Contractor shall be responsible for the operation of control devices in the Installation Utilities System (electrical) unless indicated otherwise in the contract documents. The Government will provide supervision and direct which control devices to operate. The Contractor shall not operate control devices except when the COR is present. The Contractor shall notify the COR a minimum of 5 working days prior to the need of when such operation is required.
PRODUCTS PART 2
Not Used
EXECUTION PART 3
Not Used
-- End of Section –
SECTION 01 14 00 Page 9
AUTHORIZATION REQUEST FOR CONSTRUCTION DELIVERY ESCORT
This electronic stamp is to be provided Only for Escort Requests. See paragraph 14.1.2.d above.
SECTION 01 14 00 Page 10
AUTHORIZATION REQUEST FOR CONSTRUCTION DELIVERY ESCORT
This electronic stamp is to be provided Only for Escort Requests. See paragraph 14.1.2.d above.
SECTION 01 14 00 Page 11
SECTION 01 14 00 Page 12
SECTION 01 32 01.00 10 Page 1
SECTION 01 32 01.00 10
PROJECT SCHEDULE
02/15
TABLE OF CONTENTS
GENERAL ................................................. 3 PART 1
1.1 REFERENCES
1.2 SUBMITTALS
1.3 PROJECT SCHEDULER QUALIFICATIONS
PRODUCTS ................................................ 4 PART 2
2.1 SOFTWARE
...................................................................................... 4 2.1.1 Government Default Software
EXECUTION ............................................... 4 PART 3
3.1 GENERAL REQUIREMENTS
3.2 BASIS FOR PAYMENT AND COST LOADING
3.2.1 Activity Cost Loading
3.2.2 Withholdings / Payment Rejection
3.3 PROJECT SCHEDULE DETAILED REQUIREMENTS
3.3.1 Level of Detail Required
3.3.2 Activity Durations
3.3.3 Procurement Activities
3.3.4 Mandatory Tasks
3.3.5 Government Activities
3.3.6 Standard Activity Coding Dictionary
3.3.7 Contract Milestones and Constraints
3.3.8 Calendars
3.3.9 Open Ended Logic
3.3.10 Default Progress Data Disallowed
3.3.11 Out-of-Sequence Progress
3.3.12 Added and Deleted Activities
3.3.13 Original Durations
SECTION 01 32 01.00 10 Page 2
3.3.14 Leads, Lags, and Start to Finish Relationships
3.3.15 Retained Logic
3.3.16 Percent Complete
3.3.17 Remaining Duration
3.3.18 Cost Loading of Closeout Activities
3.3.19 Anticipated Adverse Weather
3.3.20 Early Completion Schedule and the Right to Finish Early
3.4 PROJECT SCHEDULE SUBMISSIONS
3.4.1 Preliminary Project Schedule Submission
3.4.2 Initial Project Schedule Submission
3.4.3 Periodic Schedule Updates
3.5 SUBMISSION REQUIREMENTS
3.5.1 Data CD/DVDs
3.5.2 Schedule Reports
3.5.3 Network Diagram
3.6 PERIODIC SCHEDULE UPDATE
3.6.1 Periodic Schedule Update Meetings
3.6.2 Update Submission Following Progress Meeting
3.7 WEEKLY PROGRESS MEETINGS
3.8 REQUESTS FOR TIME EXTENSIONS
3.8.1 Justification of Delay
3.8.2 Time Impact Analysis (Prospective Analysis)
3.8.3 Time Extension
3.8.4 Impact to Early Completion Schedule
3.9 FAILURE TO ACHIEVE PROGRESS
3.9.1 Artificially Improving Progress
3.9.2 Failure to Perform
3.9.3 Recovery Schedule
3.10 DIRECTED CHANGES
SECTION 01 32 01.00 10 Page 3
SECTION 01 32 01.00 10
PROJECT SCHEDULE
GENERAL PART 1
1.1 REFERENCES
The publications listed below form a part of this specification to the extent referenced. The publications are referred to within the text by the basic designation only.
AACE INTERNATIONAL (AACE)
AACE 52R-06 (2006) Time Impact Analysis - As Applied in Construction
U.S. ARMY CORPS OF ENGINEERS (USACE)
ER 1-1-11 (1995) Administration -- Progress, Schedules, and Network Analysis Systems
1.2 SUBMITTALS
Government approval is required for submittals with a "G" designation; submittals not having a "G" designation are information only. Submit the following in accordance with Section 01 33 00 SUBMITTAL PROCEDURES:
SD-01 Preconstruction Submittals
Project Scheduler Qualifications; G Preliminary Project Schedule; G Initial Project Schedule; G Periodic Schedule Update; G Scheduling/Leveling Report, G
1.3 PROJECT SCHEDULER QUALIFICATIONS
Designate an authorized representative to be responsible for the preparation of the schedule and all required updating and production of reports. The authorized representative must have a minimum of 2-years experience scheduling construction projects similar in size and nature to this project with scheduling software that meets the requirements of this specification. Representative must have a comprehensive knowledge of CPM scheduling principles and application.
SECTION 01 32 01.00 10 Page 4
PRODUCTS PART 2
2.1 SOFTWARE
The scheduling software utilized to produce and update the schedules required herein must be capable of meeting all requirements of this specification.
2.1.1 Government Default Software
The Government intends to use Microsoft Project 2010.
2.1.1.1 Microsoft Project
Provide the "mpp" export file in a version of Project importable by the Government’s system.
EXECUTION PART 3
3.1 GENERAL REQUIREMENTS
Prepare for approval a Project Schedule, as specified herein, pursuant to FAR Clause 52.236-15, SCHEDULE FOR CONSTRUCTION CONTRACTS. Show in the schedule the proposed sequence to perform the work and dates contemplated for starting and completing all schedule activities. The scheduling of the entire project is required. The scheduling of construction design and construction is the responsibility of the Contractor. Contractor management personnel must actively participate in its development. Subcontractors and suppliers, Designers, Subcontractors, and suppliers working on the project must also contribute in developing and maintaining an accurate Project Schedule. Provide a schedule that is a forward planning as well as a project monitoring tool. Use the Critical Path Method (CPM) of network calculation to generate all Project Schedules. Prepare each Project Schedule using the Precedence Diagram Method (PDM).
3.2 BASIS FOR PAYMENT AND COST LOADING
The schedule is the basis for determining contract earnings during each update period and therefore the amount of each progress payment. The aggregate value of all activities coded to a contract CLIN must equal the value of the CLIN.
3.2.1 Activity Cost Loading
Activity cost loading must be reasonable and without front-end loading. Provide additional documentation to demonstrate reasonableness if requested by the Contracting Officer.
3.2.2 Withholdings / Payment Rejection
SECTION 01 32 01.00 10 Page 5
Failure to meet the requirements of this specification may result in the disapproval of the preliminary, initial or periodic schedule updates and subsequent rejection of payment requests until compliance is met.
In the event that the Contracting Officer directs schedule revisions and those revisions have not been included in subsequent Project Schedule revisions or updates, the Contracting Officer may withhold 10 percent of pay request amount from each payment period until such revisions to the project schedule have been made.
3.3 PROJECT SCHEDULE DETAILED REQUIREMENTS
3.3.1 Level of Detail Required
Develop the Project Schedule to the appropriate level of detail to address major milestones and to allow for satisfactory project planning and execution. Failure to develop the Project Schedule to an appropriate level of detail will result in its disapproval. The Contracting Officer will consider, but is not limited to, the following characteristics and requirements to determine appropriate level of detail:
3.3.2 Activity Durations
Reasonable activity durations are those that allow the progress of ongoing activities to be accurately determined between update periods. Less than 2 percent of all non-procurement activities may have Original Durations (OD) greater than 20 work days or 30 calendar days.
3.3.3 Procurement Activities
Include activities associated with the critical submittals and their approvals, procurement, fabrication, and delivery of long lead materials, equipment, fabricated assemblies, and supplies. Long lead procurement activities are those with an anticipated procurement sequence of over 90 calendar days.
3.3.4 Mandatory Tasks
Include the following activities/tasks, as applicable, in the initial project schedule and all updates.
Submission, review and acceptance of SD-01 Preconstruction Submittals (individual a.
activity for each).
Submission of electrical systems layout drawings. b.
Long procurement activities c.
Submission and approval of O & M manuals. d.
SECTION 01 32 01.00 10 Page 6
Submission and approval of as-built drawings. e.
Submission and approval of DD1354 data and installed equipment lists. f.
Performance Verification testing. g.
Other systems testing, if required. h.
Contractor's pre-final inspection. i.
Correction of punch list from Contractor's pre-final inspection. j.
Government's pre-final inspection. k.
Correction of punch list from Government's pre-final inspection. l.
Final inspection m.
3.3.5 Government Activities
Show Government and other agency activities that could impact progress. These activities include, but are not limited to: environmental permit approvals by State regulators, inspections, utility tie-in, Government Furnished Equipment (GFE) and Notice to Proceed (NTP) for phasing requirements.
3.3.6 Standard Activity Coding Dictionary
Use the activity coding structure defined in the Standard Data Exchange Format (SDEF) in ER 1-1-11. This exact structure is mandatory. Develop and assign all Activity Codes to activities as detailed herein. A template SDEF compatible schedule backup file is available on the QCS web site: http://rms.usace.army.mil.
The SDEF format is as follows:
Field Activity Code Length Description
1 WRKP 3 Workers per day
2 RESP 4 Responsible party
3 AREA 4 Area of work
4 MODF 6 Modification Number
SECTION 01 32 01.00 10 Page 7
Field Activity Code Length Description
5 BIDI 6 Bid Item (CLIN)
6 PHAS 2 Phase of work
7 CATW 1 Category of work
8 FOW 20 Feature of work*
*Some systems require that FEATURE OF WORK values be placed in several activity code fields. The notation shown is for Primavera P6. Refer to the specific software guidelines with respect to the FEATURE OF WORK field requirements.
3.3.6.1 Workers Per Day (WRKP)
Assign Workers per Day for all field construction or direct work activities, if directed by the Contracting Officer. Workers per day is based on the average number of workers expected each day to perform a task for the duration of that activity.
3.3.6.2 Responsible Party Coding (RESP)
Assign responsibility code for all activities to the Prime Contractor, Subcontractor(s) or Government agency(ies) responsible for performing the activity.
Activities coded with a Government Responsibility code include, but are not limited to: a.
Government approvals, Government design reviews, environmental permit approvals by State regulators, Government Furnished Property/Equipment (GFP) and Notice to Proceed (NTP) for phasing requirements.
Activities cannot have more than one Responsibility Code. Examples of acceptable b.
activity code values are: DOR (for the designer of record); ELEC (for the electrical subcontractor); MECH (for the mechanical subcontractor); and GOVT (for USACE).
3.3.6.3 Area of Work Coding (AREA)
Assign Work Area code to activities based upon the work area in which the activity occurs.
Define work areas based on resource constraints or space constraints that would preclude a resource, such as a particular trade or craft work crew from working in more than one work area at a time due to restraints on resources or space. Examples of Work Area Coding include different areas within a floor of a building, different floors within a building, and different buildings within a complex of buildings. Activities cannot have more than one Work Area Code.
SECTION 01 32 01.00 10 Page 8
Not all activities are required to be Work Area coded. A lack of Work Area coding indicates the activity is not resource or space constrained.
3.3.6.4 Modification Number (MODF)
Assign a Modification Number Code to any activity or sequence of activities added to the schedule as a result of a Contract Modification, when approved by Contracting Officer. Key all Code values to the Government's modification numbering system. An activity can have only one Modification Number Code.
3.3.6.5 Bid Item Coding (BIDI)
Assign a Bid Item Code to all activities using the Contract Line Item Schedule (CLIN) to which the activity belongs, even when an activity is not cost loaded. An activity can have only one BIDI Code.
3.3.6.6 Phase of Work Coding (PHAS)
Assign Phase of Work Code to all activities. Examples of phase of work are procurement phase, and construction phase. Each activity can have only one Phase of Work code.
Code proposed fast track design and construction phases proposed to allow filtering and a.
organizing the schedule by fast track design and construction packages.
If the contract specifies phasing with separately defined performance periods, identify a b.
Phase Code to allow filtering and organizing the schedule accordingly.
3.3.6.7 Category of Work Coding (CATW)
Assign a Category of Work Code to all activities. Category of Work Codes include, but are not limited to permits, construction submittals, construction submittal, procurement, fabrication, weather sensitive installation, non-weather sensitive installation, start-up, and testing activities. Each activity can have no more than one Category of Work Code.
3.3.6.8 Feature of Work Coding (FOW)
Assign a Feature of Work Code to appropriate activities based on the Definable Feature of Work to which the activity belongs based on the approved QC plan.
Definable Feature of Work is defined in Section 01 45 00.10 20 QUALITY CONTROL FOR MINOR CONSTRUCTION. An activity can have only one Feature of Work Code.
3.3.7 Contract Milestones and Constraints
SECTION 01 32 01.00 10 Page 9
Milestone activities are to be used for significant project events including, but not limited to, project phasing, project start and end activities, or interim completion dates. The use of artificial float constraints such as "zero free float" or "zero total float" are prohibited.
Mandatory constraints that ignore or effect network logic are prohibited. No constrained dates are allowed in the schedule other than those specified herein. Submit additional constraints to the Contracting Officer for approval on a case by case basis.
3.3.7.1 Project Start Date Milestone and Constraint
The first activity in the project schedule must be a start milestone titled "NTP Acknowledged," which must have a "Start On" constraint date equal to the date that the NTP is acknowledged.
3.3.7.2 End Project Finish Milestone and Constraint
The last activity in the schedule must be a finish milestone titled "End Project."
Constrain the project schedule to the Contract Completion Date in such a way that if the schedule calculates an early finish, then the float calculation for "End Project" milestone reflects positive float on the longest path. If the project schedule calculates a late finish, then the "End Project" milestone float calculation reflects negative float on the longest path.
The Government is under no obligation to accelerate Government activities to support a Contractor's early completion.
3.3.7.3 Interim Completion Dates and Constraints
Constrain contractually specified interim completion dates to show negative float when the calculated late finish date of the last activity in that phase is later than the specified interim completion date.
1. 3.3.8.3.1 Start Phase
Use a start milestone as the first activity for a project phase. Call the start milestone "Start Phase X" where "X" refers to the phase of work.
2. 3.3.8.3.2 End Phase
Use a finish milestone as the last activity for a project phase. Call the finish milestone "End Phase X" where "X" refers to the phase of work.
3.3.8 Calendars
Schedule activities on a Calendar to which the activity logically belongs. Develop calendars to accommodate any contract defined work period such as a 7-day calendar for Government
SECTION 01 32 01.00 10 Page 10
Acceptance activities, concrete cure times, etc. Develop the default Calendar to match the physical work plan with non-work periods identified including weekends and holidays.
Develop Seasonal Calendar(s) and assign to seasonally affected activities as applicable.
If an activity is weather sensitive it should be assigned to a calendar showing non-work days on a monthly basis, with the non-work days selected at random across the weeks of the calendar, using the anticipated days provided in the contract clause TIME EXTENSIONS FOR UNUSUALLY SEVERE WEATHER. Assign non-work days over a seven-day week as weather records are compiled on seven-day weeks, which may cause some of the weather related non-work days to fall on weekends.
3.3.9 Open Ended Logic
Only two open ended activities are allowed: the first activity "NTP Acknowledged" may have no predecessor logic, and the last activity -"End Project" may have no successor logic.
Predecessor open ended logic may be allowed in a time impact analyses upon the Contracting Officer's approval.
3.3.10 Default Progress Data Disallowed
Actual Start and Finish dates must not automatically update with default mechanisms included in the scheduling software. Updating of the percent complete and the remaining duration of any activity must be independent functions. Disable program features that calculate one of these parameters from the other. Activity Actual Start (AS) and Actual Finish (AF) dates assigned during the updating process must match those dates provided in the Contractor Quality Control Reports. Failure to document the AS and AF dates in the Daily Quality Control report will result in disapproval of the Contractor's schedule.
3.3.11 Out-of-Sequence Progress
Activities that have progressed before all preceding logic has been satisfied (Out-of- Sequence Progress) will be allowed only on a case-by-case basis subject to approval by the Contracting Officer. Propose logic corrections to eliminate out of sequence progress or justify not changing the sequencing for approval prior to submitting an updated project schedule. Address out of sequence progress or logic changes in the Narrative Report and in the periodic schedule update meetings.
3.3.12 Added and Deleted Activities
Do not delete activities from the project schedule or add new activities to the schedule without approval from the Contracting Officer. Activity ID and description changes are considered new activities and cannot be changed without Contracting Officer approval.
3.3.13 Original Durations
SECTION 01 32 01.00 10 Page 11
Activity Original Durations (OD) must be reasonable to perform the work item. OD changes are prohibited unless justification is provided and approved by the Contracting Officer.
3.3.14 Leads, Lags, and Start to Finish Relationships
Lags must be reasonable as determined by the Government and not used in place of realistic original durations, must not be in place to artificially absorb float, or to replace proper schedule logic.
Leads (negative lags) are prohibited. a.
Start to Finish (SF) relationships are prohibited. b.
3.3.15 Retained Logic
Schedule calculations must retain the logic between predecessors and successors ("retained logic" mode) even when the successor activity(s) starts and the predecessor activity(s) has not finished (out-of-sequence progress). Software features that in effect sever the tie between predecessor and successor activities when the successor has started and the predecessor logic is not satisfied ("progress override") are not allowed.
3.3.16 Percent Complete
Update the percent complete for each activity started, based on the realistic assessment of earned value. Activities which are complete but for remaining minor punch list work and which do not restrain the initiation of successor activities may be declared 100 percent complete to allow for proper schedule management.
3.3.17 Remaining Duration
Update the remaining duration for each activity based on the number of estimated work days it will take to complete the activity. Remaining duration may not mathematically correlate with percentage found under paragraph entitled Percent Complete.
3.3.18 Cost Loading of Closeout Activities
Cost load the "Correction of punch list from Government pre-final inspection" activity(ies) not less than 1 percent of…