UNITED STATES ARMY GARRISON DAEGU

OFFICE OF DIRECTORATE OF PUBLIC WORKS

ENGINEERING DIVISION

DESIGN AND TECHNICAL REVIEW BR

UNIT #15746

APO AP 96218-5746

IMDA-PWF 27 July 2020

SPECIFICATIONS

FOR

REPAIR GAS DEFICIENCIES FROM

GAS SAFETY INSPECTION REPORTS

USAG DAEGU

PROJECT NO. J1-00505-0J

TABLE OF CONTENTS

1. Technical Provisions - I: Statement of Work

2. Technical Provisions - II: Technical Detail Specifications

3. Technical Provisions - III: Special Conditions

4. Appendix "A": List of Applicable Contract Drawings

TECHNICAL PROVISIONS - I

STATEMENT OF WORK

PROJECT NO TITLE LOCATION

J1-00505-0J Repair Gas Deficiencies from Gas Safety Inspection Reports USAG Daegu

DESCRIPTION: The work to be performed shall be in accordance with all drawings and specifications provided under this contract.

a. Work by Contractor:

(1) The contractor shall provide all labor, tools, equipment, supplies and any other resources necessary to accomplish the scope of work contained herein as indicated in the drawings and specifications.

(2) The contractor shall repair gas deficiencies from gas safety inspection reports, USAG Daegu in accordance with the specifications and drawings.

b. Work by In-House Labor: Not applicable to this project.

c. Work by Troop Labor: Not applicable to this project.

(3) Performance Period: Shall be 120 calendar days after Notice to Proceed (NTP) is issued.

PRINCIPAL FEATURES: This project shall include the following:

General Services:

The contractor shall submit completed material lists and shop drawings to DPW, Engineering Division, Design and Technical Review Branch.

Schedule #I, Repair (K): All work shall be in accordance with the attached drawings and specifications.

A. Mechanical Work

Above-ground

1. Remove rust from flanges of gas meter and piping, and then apply paint.

2. Find and eliminate corrosion causes of gas equipment and piping.

3. Repair gas and carbon monoxide (co) leak.

4. Install gas leak alarm and shutoff system.

TP I-1

5. Replace gas leak detectors.

6. Reinforce fixation of gas meters with bands and protective structures.

7. Reinforce fixation of riser pipe supports.

8. Reinforce supports for smokestacks.

9. Install new dampers in smokestacks.

10. Install ventilation system in mechanical rooms and regulator boxes.

11. Apply insulating materials between gas piping and its fixture.

12. Apply heat-resistant silicon on smokestacks.

13. Plug or cap holes on pipes and smokestacks.

14. Install regulator vent caps.

15. Supply power to abnormal pressure annunciator in governor house.

16. Supply power to alarm and controller of gas leak alarm & shutoff system.

17. Replace defective pressure gauges.

18. Remove foreign materials in regulator boxes

19. Install protection guards for riser pipes to avoid vehicle collisions.

20. Adjust height of gas piping in contact with floor.

21. Separate welded gas piping and regulator boxes.

22. Reflect correction of deficiencies to as-built drawings.

23. Refer to gas safety diagnosis reports for more details.

24. The contractor shall be responsible for ensuring that above-ground gas distribution system is fully operational and functional.

Underground

1. Verify and repair pipe coating damage.

2. Repair valve boxes inundated with water.

TP I-2

3. Replace defective valve rods.

4. Install new valve rods and handles.

5. Replace damaged or incorrect gas pipeline marks.

6. Install new gas pipeline marks.

7. Replace unmarked valve covers.

8. Adjust valve buried depth.

9. Verify existence of valve boxes that are in as-built drawings but do not really exist.

10. Verify existence of valve boxes that are not in as-built drawings but really exist.

11. Reflect correction of deficiencies to as-built drawings.

12. Refer to gas safety diagnosis reports for more details.

13. The contractor shall be responsible for ensuring that underground gas distribution system is fully operational and functional.

TP I-3

TECHNICAL PROVISIONS - II

TECHNICAL DETAIL SPECIFICATIONS

GENERAL: The specifications are from the "Standard Technical Specifications for O&MA Projects, Korea", dated 30 October 2015, issued by the Department of the Army, Installation Management Command. The most current specifications are available (for referral purposes only) on the USFK’s Web Page http://www.usfk.mil/Resources/Contracting-with-USFK. The electronic version of the specifications are Acrobat® PDF format and can be read with the Acrobat Reader® software.

TP II – 1

TECHNICAL PROVISIONS - III

SPECIAL CONDITIONS

1. GENERAL: In addition to the requirements specified under "GENERAL PROVISIONS" for the Fixed Price Construction Contract for this project, the Contractor shall comply with the following "SPECIAL CONDITIONS" which is incorporated in to the contract.

2. WORK HOURS: The work will be accomplished from 0730 hours through 1730 hours (Monday through Saturday) except for Korean Legal Holidays. Any proposed change in working hours must be approved by the Contracting Officer (KO) and Contracting Officer's Representative (COR).

3. NOTIFICATION OF INSPECTION SECTION: The contractor shall also give the project inspector seven (7) working days notice prior to each concrete placement, field test, weld application, protective coating application, or any other work deemed by the Government to require inspection.

4. COORDINATION: The contractor shall coordinate his work with all others (subcontractor and government agencies) involved in this project and shall cooperate with all other contractors and government agencies so as to facilitate the general progress of the work. Before proceeding with any work, the contractor and/or subcontractor shall consult applicable drawings and specifications for each trade involved.

5. CONSTRUCTION: The contractor shall submit a request for the construction permit at least ten (10) working days prior to the starting of work. The request shall be submitted to the COR for approval.

6. MATERIALS COMPLIANCE: The contractor shall make certain all materials used meet the requirements of the contract and proof thereof upon request of the COR. Materials not meeting the requirements of the contract shall not be brought to the job site. All materials shall be new and the standard products of a manufacturer regularly engaged in the manufacturing of such materials.

7. HOISTING AND MOVING EQUIPMENT: The Contractor and each subcontractor shall provide and be responsible for all cranes, lifts, and other equipment necessary for proper and efficient movement of materials. The equipment shall be provided with proper guys, bracing, safety devices, and any other items, as required by law.

8. EQUIPMENT: All contractor equipment shall be subject to functional and safety inspection by the COR. Equipment not completely safe or functional shall be repaired and accepted by the government before work is started.

TP III - 1

9. RECORD DRAWINGS: During performance of work, the contractor shall accurately record and delineate on a set of full-size blue line prints of contract drawings any changes in such work which constitute any change from the original contract drawings. The set of drawings (one original and one blue line print), thus corrected and changed, usually referred to as “As-Built Drawings”, shall be delivered to the COR at the final acceptance/inspection of the completed work by the Government.

10. US ORIGIN MATERIALS: If applicable, all US Origin Materials will be ordered immediately after Notice to Proceed.

11. RELEASE OF FACILITIES WITH U.S. ORIGIN MATERIALS: If applicable, Building/facility will not be released to the contractor by the COR until all U.S. origin building construction supplies are available or due within such a time frame that there will be no delay in project completion.

12. UTILITY CUTOVERS AND INTERRUPTIONS: Make utility cutovers and interruptions after normal working hours or on Saturdays, Sundays, and U. S. Government holidays. Conform to procedures required in the paragraph "Work Outside Regular Hours." Ensure that new utility lines are complete, except for the connection, before interrupting existing service. Interruption to water, sanitary sewer, storm sewer, telephone service, electric service, air conditioning, heating, fire alarm, compressed air, shall be considered utility cutovers pursuant to the paragraph entitled "Work Outside Regular Hours." Such interruption shall be limited to 4 hours. This time includes for deactivation and reactivation.

13. WORK OUTSIDE REGULAR HOURS: Work outside regular working hours requires Contracting Officer approval. Make request fourteen (14) calendar days prior to such work to allow arrangements to be made by the Government for inspecting the work in progress, giving the specific dates, hours, location, type of work to be performed, contract number and project title. Based on the justification provided, the Contracting Officer may approve work outside regular hours. During the period of darkness, associated level of work shall be lighted in a manner approved by the Contracting Officer. Make utility cutovers after normal working hours on Saturdays, Sundays, and U. S. Government holidays unless directed otherwise.

14. WINTERIZATION: The contractor may be required to perform the work during the winter season, which may cause the contractor additional cost. These additional incurred costs are contractor’s responsibility. The Contractor shall reflect these costs in the preparation of their proposal.

15. SAFETY: The safety plan must be approved before any work can be performed on this contract.

Hard hats, suitable work boots and other necessary personnel protective gear per safety regulations are mandatory. Contractors are required to get a written permission from safety office (POC: Mr. To, Pong Uk, DSN: 768-8971) and Fire and Emergency Service (POC: Fire Communication office, DSN: 768- 4120) prior to entering confined spaces (i.e. manholes). Contractors should be properly trained and equipped with PPEs, calibrated air monitoring instrument, to work at confined spaces to insure compliance with OSHA (Occupational Safety and Health Administration) 29 CFR 1910.146.

16. SECURITY: All prime contractor and subcontractor personnel will be required to obtain a station pass from the Base Security Office. It is the prime contractor’s responsibility to provide information to security regarding all prime and subcontractor personnel and a list of all vehicles that will be driven on the site.

TP III – 2

17. WARRANTY: The contractor shall be responsible for resolution on any defect/ failure on the contract during the one (1) year warranty period. The contractor shall provide services or/and repair and replacement to the satisfaction of the government. The one (1) year warranty starts the day after final inspection approval from the authorized government personnel.

18. ANTITERRORISM/OPRATIONS SECURITY REQUIREMENTS.

18.1. AT Level 1 Training: This standard language is for contractor employees with an area of performance within an Army controlled installation, facility or area. All contractor employees, to include subcontractor employees, requiring access Army installations, facilities and controlled access areas shall complete AT Level I awareness training within 30 calendar days after contract start date or effective date of incorporation of this requirement into the contract, whichever is applicable and annually thereafter.

The contractor shall submit certificates of completion for each affected contractor employee and subcontractor employee, to the COR or to the contracting officer, if a COR is not assigned, within 05 calendar days after completion of training by all employees and subcontractor personnel. AT level I awareness training is available at the following website: http://jko.jten.mil.

18.2. Access and General Protection/Security Policy and Procedures. This standard language is for contractor employees with an area of performance within an Army controlled installation, facility or area.

All contractor employees, to include subcontractor employees, requiring access Army installations, facilities and controlled access areas shall complete AT Level I awareness training within 30 calendar days after contract start date or effective date of incorporation of this requirement into the contract, whichever is applicable and annually thereafter. The contractor shall submit certificates of completion for each affected contractor employee and subcontractor employee, to the COR or to the contracting officer, if a COR is not assigned, within 05 calendar days after completion of training by all employees and subcontractor personnel. AT level I awareness training is available at the following website:

http://jko.jten.mil

18.3. For contractors that do not require CAC, but require access to a DoD facility or installation.

Contractor and all associated sub-contractors employees shall comply with adjudication standards and procedures using the National Crime Information Center Interstate Identification Index (NCIC-III) and Terrorist Screening Database (TSDB) (Army Directive 2014-05/AR 190-13), applicable installation, facility and area commander installation/facility access and local security policies and procedures (provided by government representative), or, at OCONUS locations, in accordance with status of forces agreements and other theater regulations.

18.4. iWATCH TRAINING. This standard language is for contractor employees with an area of performance within an Army controlled installation, facility or area. The contractor and all associated sub-contractors shall brief all employees on the local iWATCH program (training standards provided by the requiring activity ATO). This locally developed training will be used to inform employees of the types of behavior to watch for and instruct employees to report suspicious activity to the COR. This training shall be completed within 30 calendar days of contract award and within 05 calendar days of new employees commencing performance with the results reported to the COR NLT 30 calendar days after contract award.

TP III – 3

19. ENVIRONMENTAL MANAGEMENT SYSTEM (EMS): Recycling all eligible material, including glass, paper (including magazines), plastic, aluminum, and cardboard to the maximum extent practicable;

Reducing the amount of hazardous material and/or solvent used by purchasing fewer hazardous materials and by increasing the use of products with recycled content;

Reducing the amount of solid waste from construction and demolition debris, and scrap metal sent to municipal and rubble landfills by reducing, reusing, and recycling;

Conserving energy and water usage by turning off lights and equipment when not in use and using only the necessary amount of water needed to complete the required tasks. Continuous conservation of our natural resources is a must;

20. CONTAMINATION FIND CLAUSE: When contaminated soil is encountered during excavation work, contractor shall report the findings to the Environmental Office immediately and contractor will segregate contaminated soil from clean soil.

21. INADVERDENT FIND CLAUSE: When potential cultural or historic items are inadvertently found during construction activities, contractor shall cease activities in the vicinity of the discovery and report the findings to the Environmental Office immediately. (Reference: USFK Reg 201-1, Environmental Governing Standard (EGS) Ch. 12, Para 12-3 J)

22. FUEL TANK AND LINES: If applicable, when underground piping associated with POL storage containers shall be tested for integrity and leaks at the time of installation, modification, construction, relocation, or replacement. New underground piping must be protected against corrosion IAW recognized industry standards. (Reference: USFK Reg 201-1, Environmental Governing Standard (EGS) Ch. 9, Para 9-3.b. (5))

23. Non-PCB TRANSFORMER CERTIFICATION: If applicable, before contractor replace/install any transformer at USAG Daegu, contractor shall submit two copies of non-PCB transformer certification to COR for each to be installed transformer. New transformer will be installed after COR's approval for non-PCB transformer certification for each to be installed transformer.

24. CONTRACTING MANPOWER REPORTING

24.1 (CMR) Requirement: The Office of the Assistant Secretary of the Army (Manpower & Reserve Affairs) operates and maintains a secure Army data collection site where the Contractor will report ALL Contractor manpower (including sub-contractor manpower) required for performance of this contract. The Contractor is required to completely fill in all the CMR information in the format using the following web address: https://cmra.army.mil. However, before the Contractor can begin reporting CMR data in this website, he or she must first register as a User. In order to register, the Contractor must have a Cage Code.

24.2 How to Obtain Cage Code for Korean Company: If you are a Korean company needing a Cage Code, at Telephone #82-2-2079-4639, FAX 82-2-773-7587, EMAIL CAGEKR@dapa.go.kr , Address:

The Standard Planning Team of the Standard Management Bureau Defense Acquisition Program Division (23 Yongsangogyogil), #2-15 Yongsan 2 ga dong, Yongsan-gu, Seoul (140-841), Republic of Korea.

TP III – 4

신청 절차

1. 방위사업청 국방전자조달 홈페이지 (www.d2b.go.kr)에 접속 합니다.

2. 방위사업청 국방전자조달 홈페이지 메인화면의 민원서비스 – 나토 생산자 (Ncage) 부호 신청을 클릭

합니다. 로긴(Login) 없이 접속 가능

3. 나토생산자부호 (Ncage) 부여요청을 위한 Login 화면에서 회원가입을 합니다.

*유의사항: 아이디와 비밀번호는 요청및 결과확인용으로 가능하며 국방전달조달 메뉴에 있는 기타

다른 업무에는 사용할 수 없습니다.

4. 회원가입시 번호 부여 대상이 회사인 경우에는 사업자등록증번호, 개인일 경우에는 DUNS번호를

기입합니다.

5. 가입한 아이디와 비밀번호로 로긴하여 접속 후 온라인 나토생산자부호 요청서에 해당업체에 대한

정보를 기록합니다.

6. 회사인 경우에는 사업자등록증, 개인일 경우에는 DUNSNUMBER 부여결과서를 스캔하여 EDM에 jpg

파일로 첨부합니다.

7. 등록한 후 재 조회를 하여 업체자료가 정상적으로 신청이 되었는지 확인합니다.

8. 신청서의 접수 및 진도는 요청서 상단의 진행 상태를 확인 합니다.

*진행상태: 신청완료, 접수완료, 작업완료등 빨간색으로 변경

*처리소요기간: 1일-2일 *비용: 무료

Once the CAGE code is issued for your company, your company is ready to do CMR registration. For CMR registration, please follow the instruction in the solicitation/contract titled ―Accounting for Contract Services.

After your company‘s CMR registration application is reviewed by U.S Department of Army. You will receive e- mail notification within 2 to 3 working days whether your CMR registration application is approved or not. If it is disapproved, please read carefully the comments provided by DA and correct registration application as commented. After your company‘s CMR registration is approved, your company is ready to do CMR report. There will be short lesson giving how you report CMR on the web site.

TP III – 5

24.3 CMR Reporting: The information required to be reported in the CMR website includes: (1) Contracting Office, Contracting Officer, Contracting Officer’s Technical Representative (COTR) or Contracting Officer’s Representative (COR); (2) Contract Number, including Task and Delivery Order Number(s); (3) Beginning and Ending dates covered by reporting period; (4) Contractor Name, Address, Phone Number, E-Mail Address, Identity of Contractor Employee entering data; (5) Estimated Direct Labor Hours (including sub-Contractors’ hours); (7) Total Payments (including sub-Contractors’ payments); (8) Predominant Federal Service Code (FSC) reflecting services provided by Contractor (and separate Predominant FSC for each sub-Contractor if different); (9) Estimated data collection cost; (10) Organizational Title associated with the Unit Identification Code (UIC) for the Army Requiring Activity reporting this information (the Army Requiring Activity (RA) is responsible for providing the Contractor with its UIC for purposes of reporting this information); (11) Locations where Contractor and sub- Contractors perform the work (specified by zip code in the United States and nearest City and Country when in an overseas location, using standardized nomenclature provided on website); (12) Presence of Deployment or Contingency Contract language; and (13) Number of Contractor and sub-Contractor employees deployed in theater this reporting period (by Country).

As part of its submission in response to a solicitation or a modification request which includes a contract line item number (CLIN) for this CMR reporting requirement, the Contractor shall also provide the estimated total cost (if any) incurred to comply with this reporting requirement on the associated CMR CLIN. Reporting period will be the period of performance not to exceed 12 months ending September 30 of each Government fiscal year and must be reported by 31 October of each calendar year. Contractors may use a direct XML data transfer to the database server or fill in the fields on the website. The XML direct transfer is a format for transferring files from a Contractor’s systems to the secure website without the need for separate data entries for each required data element at the website. The specific formats for the XML direct transfer may be downloaded from the website.

CMR reporting is a requirement mandated by the Department of Army. Failure of the Contractor to comply with this requirement will be noted as Past Performance information about the Contractor to be used on future procurements for the same or similar services.

TP III – 6

APPENDIX "A"

LIST OF APPLICABLE CONTRACT DRAWINGS

GENERAL: The work shall conform to the standard detail drawings (dated 30 November 2015, issued by the Department of the Army, Installation Management Agency, Korea Region Office and located USFK’s Web Page http://www.usfk.mil/Resources/Contracting-with-USFK), all of which form a part of the specifications.

Drawing No. Ref. No. Sheet No. Description Date

D-20-19 R-1 1 of 1 Title Sheet 21 Jul 20

“ M-1 1 of 8 General Notes and Scope of Work “

“ M-2 2 of 8 Site Layout Plan for Above-Ground Gas Line Repair Work (Cp. Carroll) – 1 “

“ M-3 3 of 8 Site Layout Plan for Above-Ground Gas Line Repair Work (Cp. Carroll) – 2 “

“ M-4 4 of 8 Site Layout Plan for Above-Ground Gas Line Repair Work (Cp. Walker) “

“ M-5 5 of 8 Site Layout Plan for Above-Ground Gas Line Repair Work (Cp. Henry) “

“ M-6 6 of 8 Site Layout Plan for Underground Gas Line Repair Work (Cp. Carroll) “

“ M-7 7 of 8 Site Layout Plan for Underground Gas Line Repair Work (Cp. Walker) “

“ M-8 8 of 8 Site Layout Plan for Underground Gas Line Repair Work (Cp. Henry) “