This Statement of Work (SOW) details interior painting and repairs for a U.S. Embassy residential property located at Oom Jochem 225 in Pretoria, South Africa. The project requires comprehensive interior maintenance including painting walls, ceilings, wet areas, steelwork, and doors, with specific paint specification requirements such as low VOC, lead-free, and stain-resistant products. Additional scope includes maintenance tasks like replacing door handles, drawer runners, shower components, toilet seats, and addressing various minor repairs and finishing details.
The project is expected to take three weeks, with strict safety and operational guidelines for the contractor. Key requirements include submitting detailed safety plans, using certified personal protective equipment, conducting safety briefings, and following extensive safety protocols for tasks like fall protection, scaffolding, chemical handling, and welding. The contractor must provide insurance, undergo security vetting, and will be subject to inspection by the U.S. Embassy's Post Occupational Safety & Health Officers (POSHOs). A 12-month workmanship guarantee is required, and the contractor will be responsible for maintaining a clean work environment and addressing any post-installation touch-ups needed.
View the file
Other files
| File | Type | Posted |
|---|---|---|
| SOW 225 Oom Jochem - Exterior painting and repairs. V1.pdf | ||
| NDAA_Certificate_for vendor compliance.pdf |
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
CONTRACTOR SIGNATURE___________________________________________________________
US Embassy Statement of Work – GOP Residential, Preparing residence for Occupation.
Interior painting and repairs.
Oom Jochem 225
P a g e 1 | 10
Embassy of the United States of America
Pretoria, South Africa.
STATEMENT of WORK
Maintenance and repair.
Project: Exterior painting and repairs.
Interior painting and repairs.
Oom Jochem 225
P a g e 2 | 10
Project title: Oom Jochem 225 - Interior painting and repairs.
1. General
(a) Work Required: The work required under this contract consists of furnishing all professional services, labor, materials, equipment, required insurance, permits, and any other items, accessories, and services necessary to complete the maintenance bid documents specified herein. All work shall be in accordance with this statement of work, available information, and local regulations.
(b) Project Description: The U.S. Government requests painting and general maintenance repairs /make ready work bid documentation for the interior only of the residence, to reflect items/ tasks as listed in lower section of the SOW. Work to be done is in preparation of the residence for occupation.
Proposals to include:
- Tasks described under section 6: Project requirements.
o ALL interior surfaces previously painted or treated.
o General, Maintenance, repairs and upkeep of buildings.
o ALL BUILDINGS.
(c) Proposal Submission: The requested services and costs shall be addressed in the consultant's proposal for each category of services. In addition, the proposal shall include a schedule presenting the time required to perform the services, and detailed lump sum fee for the services to be performed.
(d) Access:
All contractor employees are required to be vetted before allowing access to work site within an U.S. Government property.
This vetting procedure includes providing, to the P.O.C. copies of I.D’s, P.O.C. will submit to the security office for temporary clearance.
Access Clearances issued will be valid only for the discussed times with P.O.C.
All service dates are to be indicated on the access control sheets upon site visits/ meetings.
Site visits, original ID’s must be taken with for access confirmation. Not certified, original only.
2. Definitions.
(a) Whenever the term "Owner" is used herein, it shall refer to the U.S. Embassy in Pretoria.
(b) Whenever the term “P.O.C.” is used herein, it shall refer to the project manager, “Point of contact”.
(c) Whenever the term “Contractor” is used herein, it shall refer to vendor.
3. Site Familiarization: Site meeting/ visit and brief held:
The Contractor shall be familiar with the nature of the work, the general and local conditions, and all matters which may in any way affect the work under this contract. A site visit will be arranged to discuss the scope of work and requirements from the owner.
The Contractor shall notify the P.O.C. in writing of any additional information needed.
4. Suggested Modifications.
Any suggestions for modification of the requested scope believed to be appropriate to improve the outcome of the project are welcome and will be reviewed for acceptance.
Interior painting and repairs.
Oom Jochem 225
P a g e 3 | 10
5. Deliverables for quotation/ proposal submission
- If new to the U.S.G. projects submission, a company profile, to include indications of previous and similar work completed.
- Should detail all Tasks listed below.
- Quotation/ costs to be separated between Labour and material.
- Expected work plan/ time frame.
Before commencement of work:
- Safety plan will be required before work commences.
CONTRACTOR/COMPANY: ________________________________________
➢ Contractor to confirm measurements before quoting. NO COST ADJUSTMENTS WILL BE APPROVED DUE TO INCORRECT
MEASUREMENTS.
STANDARD PREPARATION AND WORK TO BE DONE.
Cost Labour Cost Material
1. Interior walls. R R
2. Interior ceilings. R R
3. Wet areas. R R
4. Steelwork. R R
5. Doors. R R
6. Maintenance. R R
7. Final make ready/ finishing. R R
R R
Sub Total R R
VAT (if applicable) R R
TOTAL AMOUNT QUOTED R
Contractor concerns and notes:
Interior painting and repairs.
Oom Jochem 225
P a g e 4 | 10
6. Project requirements: ALL BUILDINGS.
TASK # 1: Painting- Interior walls.
• All interior walls. To include inside cupboards and back walls.
o Including windowsills and entry steps.
• Remove all nails, screws etc. prepare walls and paint.
• Multiple visible cracks throughout the residence, open, strengthen, and close before painting.
Paint Specifications to meet the following criteria (use only reputable Paint Manufacturers) Suggested Dulux, or of similar product quality, warranty, and specifications.
- Mid to low sheen.
- Low VOC (Volatile Organic Compounds)
- Lead & odor free.
- Non-Flammable.
- Stain Resistant, exceptional scrub ability and washable.
- Product: Luxurious Silk Salisbury Stone 645YY 83/062.
TASK # 2: Painting- Interior ceilings:
• All interior ceilings.
Paint Specifications to meet the following criteria (use only reputable Paint Manufacturers).
- Exceptional White Matt Acrylic PVA.
- Low VOC (Volatile Organic Compounds)
- Lead & odor free.
- Non-Flammable.
- Stain Resistant, exceptional scrub ability and washable.
- Product: Bergmaster Craftsman Nukote White Acrylic/ Dulux trade pro 65, or of similar product quality, warranty, and specifications.
TASK # 3: Painting- Wet areas (Kitchen, laundry, bathrooms, etc.):
• All interior ceilings.
• All walls that are not tiled.
Paint Specifications to meet the following criteria (use only reputable Paint Manufacturers).
- Mid to low sheen.
- Low VOC (Volatile Organic Compounds).
- Lead & odor free.
- Non-Flammable.
- Stain Resistant, exceptional scrub ability and washable.
- Product: Luxurious Silk, bathroom specific or exterior rated paint to be used.
TASK # 4: Painting- Steelwork:
• Re-paint all painted steel work, frames and grills as required.
• All frames need to be cleaned and touched up if required.
• Where applicable, reglue loose wires to frames and touch up.
TASK # 5: painting- Doors/ Wood:
• Prepare & paint all interior and exterior doors and doorframes previously painted. All doors and door frames white.
• All wood skirting. (Varnish).
• All knotty pine ceiling. (Varnish).
Interior painting and repairs.
Oom Jochem 225
P a g e 5 | 10
TASK # 6: Maintenance- miscellaneous building expenses:
• Ensure all door, drawer & cabinet handles are present & secured, lockable where applicable.
• Ensure all shelves are positioned, secured and clean.
• Replace drawer runners in kitchen with soft close runners.
• Inspect doors, handles, striker plates, keyhole covers, gates and locks for proper alignment and functionality.
o Replace all door handle sets throughout the property. 10 x Doors. Stainless handles to be used with existing thumb turn locksets. Align all.
o Typical door handle set or similar in quality: https://www.builders.co.za/Doors-and-Windows/Door-
Accessories/Door-Handles/Dortello-Bodo-Tube-Lever-Handle-with-Keyhole-
Escutcheon/p/000000000000422632
• Test all windows, window handles and stays for proper functionality, adjust as required.
• Inspect sliding doors, reposition, and secure rails and castors.
• Curtain rails, blind brackets etc. to be removed before painting and re-installed. Inspect integrity of all curtain rails.
Securely fasten rails with appropriately sized nail anchors to walls at specified height.
• Kitchen: Remove cabinet backboard below sink, plaster, seal and paint.
• General reseal, surrounding all water sources, sinks, basins, showers and bathtubs.
• Replace shower door seals.
• Replace shower arms and roses, type and quality: or similar quality and warranty.
o GROHE G-27541001 TEMPESTA COSMOPOLITAN 200mm SHOWER ROSE CP o HANSGROHE RAINDANCE 27413000 SHOWER ARM & FLANGE 390mm LONG (90 DEGREE
• Replace toilet seats.
• Replace pull out seals and pop-up seals for basins and sinks.
• Replace bathtub in bathroom 1.
• Replace doorframe bedroom 3.
• Remove exhaust pipe and vent cover in laundry, will no longer be used. Non vented dryers to be installed.
• Tile garage floor: PC sum @ estimate R 350.00 sqm.
• Replace domestic quarters bedroom window, too high and too small for emergency egress.
TASK # 7: Final make ready and finishing:
• Contractor to return for any touch up paint/ minor snag needed after residence is furnished and on final occupancy phases.
• Removing all paint marks new or old from windows, floors, fixtures, fittings, doors, furniture, appliances, and work tops (do not make use of abrasive or harmful materials and chemicals to clean off excess paint and spills). Use scraper blades to remove paint on windows, work tops, floors and surfaces that have been affected, ensure that no fittings and fixtures are damaged or scratched during the cleaning process.
• As discussed on site meeting, attention to detail is essential and the contractor will be required to complete small detail finishing which might not have been seen on the site meeting.
General:
• Remove all redundant and unused equipment, nails, hooks, wiring, antennas, dishes, mounting fixtures etc.
Confirm with P.O.C. before removal.
• Contractor to always uphold a clean and organized environment.
o Daily site cleanup.
• Remove and dispose all taken out/ scrap material from site. Confirm with P.O.C. before removal.
• Project to include top to bottom/ surrounding effected damaged areas neatening and finishing.
• Contractors will be liable for repairs or replacement of damaged fixtures and fittings.
• 12 Month workmanship guarantee on all surfaces.
https://www.builders.co.za/Doors-and-Windows/Door-Accessories/Door-Handles/Dortello-Bodo-Tube-Lever-Handle-with-Keyhole-Escutcheon/p/000000000000422632 https://www.builders.co.za/Doors-and-Windows/Door-Accessories/Door-Handles/Dortello-Bodo-Tube-Lever-Handle-with-Keyhole-Escutcheon/p/000000000000422632 https://www.builders.co.za/Doors-and-Windows/Door-Accessories/Door-Handles/Dortello-Bodo-Tube-Lever-Handle-with-Keyhole-Escutcheon/p/000000000000422632
Interior painting and repairs.
Oom Jochem 225
P a g e 6 | 10
7. Point of Contact:
(a) U.S. Embassy Pretoria, Project Manager
Etienne Smit
(b) U.S. Embassy Pretoria- Procurement.
Before PO is issued, all communication to route via Pretoria Procurement agent assigned to the project.
8. Location of residence:
Oom Jochem 225, Pretoria.
9. Project duration:
Three weeks.
10. Picture indications: Partial indications only, not to be mistaken for full SOW.
Interior painting and repairs.
Oom Jochem 225
P a g e 7 | 10
Mission Post Occupational Safety & Health:
Post Occupational Safety & Health Officers (POSHOs) wants to ensure all contractors and subcontractors are conducting their duties on behalf of the U.S. government safely and healthfully. This guidance aims to ensure compliance with current safety regulations as well as the health and safety of personnel, avoiding any damage or injury. The Contractor will accept all legal requirements or regulations currently enforced concerning safety for staff, technicians, and other workers and the public whom the work may directly or indirectly impact.
The Contracting Officer’s Representative (COR) will ensure that all safety requirements are implemented before and during the work project. As needed, the COR will contact the POSHO to share any safety-related information and ensure all safety standards are followed. Contractors must submit a detailed, site-specific safety plan in their statement of work (SOW) as part of the tender documents, addressing hazard mitigation and control methods.
REQUIREMENTS:
1. General Safety
a. The Contractor must demonstrate an understanding of their responsibilities related to the safety and health requirements by addressing hazards in the pre-planning processes and meetings.
b. Before starting a project, the Contractor must review the work site and identify hazards that may occur while performing the work project.
c. The Contractor is expected to provide a “competent person” to implement the site safety and health plan and oversee its strict compliance. A competent person is an individual who, by way of training and/or experience, is knowledgeable of applicable standards, capable of identifying workplace hazards related to the specific operation, is designated by the employer, and has the authority to take appropriate actions.
d. The Contractor must provide proof of payment of local insurance for all employees involved in the work project for the duration of the project. This information must be included as part of the safety file.
e. The Contractor will conduct a safety briefing before starting daily work.
f. Any Contractor personnel who show signs of intoxication will be denied entry into the work area.
g. The Contractor shall ensure personnel working at the site are trained and aware of potential hazards. The
Contractor shall unequivocally ensure that personnel have proper safety equipment to prevent accidental injury per the contract's requirements.
h. The Contractor must accept the safety and health standards established by the U.S. Embassy.
i. All workers shall remove any chains, rings, watches, bracelets, and other jewelry during the execution of the work project. Medical bracelets are excluded.
j. Smoking is strictly prohibited at the work site, and personnel will only use areas identified as “designated smoking areas.” The consumption of marijuana or similar recreational substances is strictly prohibited on U.S. government-held properties.
k. The Contractor will report accidents and near misses to the COR, who will pass the proper data to the POSHO.
2. Barricading and Warning Signs The Contractor must place provisional barricades and warning signs to maintain a safe and accessible path of travel for all pedestrians, including those with disabilities, to avoid accidents with third parties. Barricades alert others about hazards created by construction activities and should be used to control vehicular traffic around the work site. The Contractor shall:
a. Erect and maintain proper barricades for the duration of the contract, including fencing material, traffic cones, caution tape, and temporary curb rams, complying with all applicable access codes and regulations.
b. Ensure that no construction materials are stored and/or positioned in the path of travel.
c. Maintain the construction barriers in a sound, neat, and clean condition.
3. Personal Protective Equipment (PPE)
a. All Contractor personnel must use the PPE required per the contracted work.
b. The Contractor must inspect and maintain spare PPE in case of equipment damage, deterioration, or loss.
c. The PPE must meet the technical specifications required by local and international standards.
d. All sharp cutting tools must be carried in tool-carrying cases. Under no circumstances shall they be carried on-person in uniform pockets.
Interior painting and repairs.
Oom Jochem 225
P a g e 8 | 10
e. In those takes where certified PPE is required, the Contractor must provide the current certification to the POSHO via the COR.
f. The Contractor must provide records of PPE received for all the employees involved in the task.
4. Safety Inspections
a. All tools, equipment, and machinery used in executing the contracted work must be inspected by a competent person before starting the project.
b. COR and/or safety representatives of the U.S. Embassy may inspect the Contractor's equipment, tools, and machinery at any time and request a change if necessary.
5. Hand & Power Tool Safety
a. The Contractor must ensure the safety of all tools and equipment its employees use.
b. All hand and power tools must be inspected regularly and maintained in good condition per the manufacturer's specifications. Tools that are damaged must be removed from service.
c. The Contractor shall ensure that all tools are used only for their intended purposes.
6. Emergency Response
a. In case of an emergency within U.S. government facilities or during the execution of contracted work on behalf of the U.S. government, all Contractor personnel must follow the instructions given by the USG representative who is supervising the work or the POSHO and/or the Regional Security Officer.
b. The Contractor shall ensure that a fully serviced fire extinguisher and first aid kit are readily available on-site for the work project.
c. The Contractor must not obstruct emergency response equipment such as first aid kits, fire extinguishers, fire cabinets, defibrillators, spill kits, stretchers, eye wash stations, or safety signage.
7. High-Risk Work
a. The Contractor shall submit training certificates for each employee conducting the task. These certificates must be submitted to the POSHO via the COR at least three days before the start of the work project.
b. The Contractor shall prepare a work permit specifically for the task, which must be provided to the COR before the initiation of work.
c. The execution of high-risk activities will be carried out with at least two employees present. Both employees must be capable of performing duties as spotters for unseen hazards and as buddy persons who can render first aid or give notice in case of emergency.
8. Electrical Safety
a. The Contractor shall fully comply with the Department of State standards related to electrical safety work practices and work de-energized to prevent any incident that may impact the safety and health of personnel or any electrical systems in U.S. government-held properties.
b. It is Departmental policy that energized or “live” parts to which an employee may be exposed must be de-energized before the employee works on or near them. If de-energizing “live” parts introduces or increases hazards or otherwise makes the work unfeasible, the Contractor must notify the COR to report such a situation and await further guidance.
c. All personnel conducting electrical work shall be sufficiently trained and considered competent before performing such work.
d. The Contractor should identify all potential sources of electrical energy likely to cause death, injury, or serious physical harm.
e. The Contractor shall ensure all work follows all applicable local regulations, U.S. standards, and international codes.
f. The Contractor must provide the appropriate equipment and tools for the work in compliance with the contract requirements.
g. During work on the electrical system, Contractor personnel must remove conductive jewelry such as watches, rings, chains, and bracelets.
h. The Contractor shall ensure non-conductive (fiberglass) ladders are used for electrical work or work near electrical hazards.
Interior painting and repairs.
Oom Jochem 225
P a g e 9 | 10
9. Fall Protection According to U.S. Occupational Safety & Health Administration (OSHA) standards, all work performed at more than 1.22 meters (4 feet) in general industry workplaces and 1.83 meters (6 feet) at construction sites is considered “work at heights.”
The Contractor must strictly comply with the following requirements when working at heights:
a. All equipment at elevated surfaces must meet ANSI Z359.1 standards or the international equivalent.
b. All ladders and stepladders must have two locking spreaders and have a minimum weight rating of 250 lbs. (113.4 kg). All ladders must be inspected by a competent person before use and immediately remove noncompliant ladders from service.
c. All Contractor personnel using equipment for work at heights must follow the instructions and warnings associated with such equipment.
d. Contractor personnel will not use ladders, piping, or pipe supports as anchor points for work.
e. If an anchor point does not offer the recommended resistance for fall protection (2,268 kg or 5,000 lbs), the
Contractor must provide PPE for heights with dampers that may decrease the impact force.
f. Scissor scaffolds are strictly prohibited. Only adequately certified multidirectional and modular scaffolding is authorized for use.
g. Use dielectric ladders to work with electricity and in areas with electrical influence.
h. Standing on or above the second top rung of ladders is forbidden.
i. A minimum period of eight working days before the start of the work project, the Contractor shall submit to the
POSHO via the COR fall prevention and protection training certificates for all workers who will perform the job.
10. Scaffolding
a. The Contractor is responsible for providing safe conditions when using, erecting, and breaking down scaffolding.
b. Scaffolds should be erected and dismantled by competent workers under the supervision of knowledgeable and experienced supervisors.
c. Scaffolds should be erected on a rigid surface, capable of carrying the maximum intended load without settling or displacement.
d. Ensure the scaffold is equipped with standard guardrails and toe boards on all open sides and ends of platforms
1.22 to 3.05 meters (4 to 10 feet) in height.
e. Provide an access ladder or equivalent safe access.
f. The work platform must be fully planked. All vertical plumbs must have base plates for stability.
g. Supported scaffolds with a height-to-base width ratio of more than four to one (4:1) shall be restrained from tipping by guying, tying, bracing, or equivalent means.
11. Hazard Communication (Chemical Substances) Safety
a. If the contracted task requires chemicals, the Contractor must comply with the specifications required by local law and/or U.S. standards for storage, handling, transportation, and disposal.
b. The Contractor is responsible for verifying the correct handling of each product, such as storage, labeling, required
PPE, and waste disposal, in compliance with safety and environmental regulations.
c. The Contractor shall have accessible copies of Safety Data Sheets (SDS) for each chemical brought onto a U.S.
government-held property. The SDS of hazardous materials must be shared with the COR for review by the POSHO.
d. Use and store all hazardous or flammable chemicals in approved containers on the project site. Food and beverage containers or unauthorized spray bottles must never be used to store chemicals.
12. Lifting Loads, Use of Cranes, or Elevating Work Platforms Safety
a. The Contractor shall submit certificates of the equipment used for the work to the POSHO via the COR before the start of any task. This includes forklifts, cranes, elevating platforms, and the like.
b. The Contractor shall submit certificates for all slings, chains, shackles, or other elements used for lifting loads to the POSHO via the COR.
c. The Contractor shall submit certificates of all personnel performing the task to the POSHO via the COR.
d. The Contractor shall present, in writing, the loading and unloading procedure to the COR before the operation.
e. The Contractor shall establish a plan to ensure the lifting capacity of the crane and/or its arm is relative to its load.
Interior painting and repairs.
Oom Jochem 225
P a g e 10 | 10
13. Welding Safety
a. Before cutting, welding, or any other open flame operation is permitted, the COR shall inspect the area to reduce the potential of an uncontrolled ignition of materials.
b. The Contractor shall obtain a hot work permit through the COR from the POSHO before any cutting, welding, or open flame activity within occupied existing facilities, within 12.2 meters (40 feet) of any structure, in areas where potential combustion hazards exist such as fuel storage tanks, and all confined spaces regardless of location.
c. Establish work area barriers according to the work to protect pedestrians. These barriers shall comply with OSHA standards and the hot work policy established by the POSHO.
d. A serviced fire extinguisher shall be maintained on-site and in a state of readiness for instant use.
e. Cutting, welding, and any other open flame operation shall be performed only in areas that are or have been made fire safe. When the task cannot be relocated, the area shall be made safe by removing or protecting combustibles from ignition sources.
f. The Contractor shall ensure all welder operators and attendants exposed to the hazard use proper PPE.
14. Confined Spaces Safety For any work to be performed in confined spaces, the Contractor shall consult with the POSHO to identify and comply with the mandatory requirements established by the U.S. Department of State.
SAFETY ADMINISTRATION
The COR will work directly with the Contractor to ensure all safety requirements are met as described in this guidance. The COR will report any deficiencies found before or during the execution of the work project to the
POSHO.
If the COR identifies unsafe acts or conditions that could significantly affect the safety and health of Embassy personnel, contractors, subcontractors, third parties, or U.S. government property, the work can be suspended by the COR or the POSHO until such an act or condition is appropriately resolved. If different work conditions appear during the work project, the COR can indicate further safety requirements to the Contractor.
End of SOW