This statement of work outlines the requirements for a construction project to build a new water well at Luke Air Force Base. The contractor will be required to provide materials and a portion of labor, including over 600 feet of 8.625 inch diameter steel casing and screen, drilling mud additives, cement, and test pumping equipment. The Air National Guard will perform the well drilling. The contractor must have the required materials on site by July 30th and complete all work within 30 calendar days of notice to proceed. Luke Air Force Base will provide some materials including cable and pipe. The purpose of the project is to repair Well 21 at an estimated depth of 1,000 feet.
View the file
Other files
| File | Type | Posted |
|---|---|---|
| Solicitation Amendment FA488721Q00250002 SF 30.pdf | ||
| 06-11-21 Well 21 Contractor Unit Price Spreadsheet.xlsx | XLSX spreadsheet | |
| 06-10-21 Well 21 Addendum I.docx | DOCX document | |
| REV V SOW El Mirage Well 21 - 11 June 2021.docx | DOCX document | |
| 06-10-21 Well 21 RFIs 1-14.xlsx | XLSX spreadsheet | |
| Solicitation Amendment FA488721Q00250001 SF 30.pdf | ||
| Solicitation - FA488721Q0025.pdf |
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
The information herein is For Official Use Only (FOUO) which must be protected under the Freedom of Information Act of 1966 and Privacy Act of 1974, as amended. Unauthorized disclosure or misuse of this PERSONAL INFORMATION may result in criminal and/or civil penalties.
STATEMENT OF WORK
June 4, 2021
Well 21 Project at 7105 N. El Mirage
1. OVERVIEW
The purpose of this project is to provide all material and labor for construction of a new water well, entitled, “Well 21” at Luke AFB, with an estimated depth of approximately 1,000 feet.
DEFINITION OF TERMS
“Contractor” defines all contractors bidding on this project.
“AZ ARNG” (the Arizona National Guard) refers to the party performing the well drilling operation.
“Luke AFB” refers to the contractual party receiving all bids.
“Project” shall refer to Well 21 Project at 7105 N. El Mirage.
2. DESCRIPTION OF WORK
2.1. This Project includes all incidental modifications to existing infrastructure needed to install, replace and test work to be performed as listed in description of work below.
2.2. Performance Period: all work shall be completed within 30 calendar days after the Notice to Proceed is issued. Contractor is responsible to check on all material lead-times to facilitate the Project Schedule. If any materials are not available, Contractor shall immediately notify Luke AFB POC by email and by phone.
2.3. General Construction
2.3.1. Luke AFB will furnish supplies and install new soft starter panel box with disconnect.
Trench and material to install new conduit and wire to within approximately 200' of existing well. Contractor shall re-use existing meter and service entrance section.
2.3.2. Luke AFB will provide all materials and install a new concrete well pad, and above ground 8" (approximate diameter listed) steel piping with gate valve above ground.
2.3.3. Contractor shall supply and install the following: check valve, air release, sample port, and new underground pipe approximately 200' from existing well.
2.3.4. The AZ ARNG will be performing the drilling operations, to include the development of the well. Contractor shall provide technical expertise for the Well 21 Project, during the Project, as required by Luke AFB.
2.3.5. The Contractor’s drilling license will be utilized to comply with all governing authority legal requirements for the Well 21 Project. The use of the Contractor’s drilling license for this Project will be provided in the Contractor’s proposal.
2.3.6. The Contractor is responsible to secure all permits and licenses required by all governing authorities for the Well 21 Project. This includes but is not limited to: all design drawings, specifications, applications, etc., and documentation required by governing agencies for all permits, temporary and permanent, required for the Well 21 Project.
2.3.7. The Contractor will provide their expertise and technical knowledge to the AZ ARNG, throughout the entire Project, including but not limited to assisting with, advising, materials procurement, construction, testing, development and final permitting of the Well 21.
2.3.8. The Contractor will provide all as-built drawings, logs, and other Project paperwork as solely required by Luke AFB.
The information herein is For Official Use Only (FOUO) which must be protected under the Freedom of Information Act of 1966 and Privacy Act of 1974, as amended. Unauthorized disclosure or misuse of this PERSONAL INFORMATION may result in criminal and/or civil penalties.
2.3.9. The Contractor will provide all required materials, to include, but not limited to, the Estimated List of Materials (attached list below) to the AZ ARNG necessary to execute this Project.
3. ESTIMATED LIST OF MATERIALS ON HAND AT LUKE AFB
3.1. Luke AFB currently has:
3.1.1. 640 feet of Pump Cable
3.1.2. 31 ea. 2-3/8 in. pipe.
3.1.3. 6 in. Flow Meter
3.2. Listed below are the required list of materials, to be on site by 30 July, from the Contractor necessary to perform a successful drilling operation.
3.2.1. List of Materials:
Estimated List of Contractor Supplied Materials for Well 21
Qty Unit Description
630 FT
8.625" OD x .250" WALL; ASTM A139; COPPER BEARING STEEL; BLANKCASING; 20' LENGTHS;
W/ WELD COLLARS
370 FT
8.625" OD x .250" WALL; ASTM A139; COPPER BEARING STEEL; FUL FLO LOUVERED SCREEN;
.060" SLOT; 20' LENGTHS; W/ WELD COLLARS - (THEORETICAL COLLAPSE STRENGTH =
1019..97 psi)
1 Each 8.625" O.D.; COPPER BEARING STEEL PLATE; W/ LOW CARBON STEEL SE HEAD 1 Each 8.625" LANDING CLAMP - 6" LENGTH, 8" EARS, (16 TON RATING) 1 Each 14.75" DRAG BIT. MEDIUM HARD
20 FT 20" X 20' X .250 WALL SURFACE CONDUCTOR
448 Each BAGS SODA ASH - 50# BAG; (56 BAGS/PALLET) 384 Each BAGS QUICK-GEL - 50# BAGS; (48 BAGS/PALLET) 80 Each BAGS EZ MUD GOLD - 50# BAGS - (48 BAGS/PALLET) 80 Each BAGS QUICK TROL GOLD 50# BAGS; (36 BAGS/PALLET) 80 Each PAILS QUICK TROL GOLD LV - 40# PAILS; (36 PAILS/PALLET) 48 Each BAGS HOLEPLUG 3/8" - 50 # BAG; (48 BAGS PER PALLET) (USED FOR20' BENTONITE SEAL)
20 Each BAGS PORTLAND CEMENT FOR SURFACE SEAL, 94# BAGS
16 Each
STEEL HING-TYPE CENTRALIZER FOR 8.625" O.D. (RECOMMENDED TO RUN CENTRALIZERS
EVERY 60')
16 Each SUPER SACKS 3000 LB SUPER SACK 6-9 SILICA SAND 1 Each FURNISH & INSTALL TEST PUMPING EQUIPMENT
48 Hours PUMPING RATE - HOURLY; DEVELOPMENT - TESTING 1 Each 200 KW GENERATOR RENTAL, FOR PUMP TESTING
50 Each 20’ LENGTHS OF 4” DIAMETER COPPER BEARING STEEL PLATE PIPING
840 FT DISCHARGE PIPING, AIR VENT, MISL FITTINGS ETC
END STATEMENT OF WORK