Solicitation - FA500021R0080.pdf

PDF 3 MB Posted

Attached to
FXSB 21-1077, Bunkroom Hallway Rpr Federal contract opportunity
Solicitation number
fa500021R0080
Issued by
Department of the Air Force Pacific Air Forces

View the file

Other files for this federal contract opportunity

Other files attached to FXSB 21-1077, Bunkroom Hallway Rpr, newest first.
File Type Posted
Solicitation Amendment_FA500021R00800001 (Summary of Changes).pdf PDF
Attch5_JBER Lock Standards.pdf PDF
Attch11_Q and A.docx DOCX document
Attch3_Drawing Set.pdf PDF
Attch10_ AF_66 Submittal-FXSB 21-1077 X.xlsx.pdf PDF
Attch9_Asbestos Abated Areas Test Results.pdf PDF
Attch8_Environmental Protection Specs on JBER (28 Oct 2020 Rev 3).pdf PDF
Attch7_ JBER Telecom Criteria Requirements.pdf PDF
Attch6_Contractors Fire Safety Guide.pdf PDF
Attch2_ Price Schedule.pdf PDF
Attch1_FXSB 21-1077 SOW.pdf PDF
Attch4_Revised JBER CAD.pdf PDF
Show all 12

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

SOLICITATION, OFFER AND AWARD 1. THIS CONTRACT IS A RATED ORDER

UNDER DPAS (15 CFR 7900)

RATING PAGE OF PAGES

2. CONTRACT NUMBER 3. SOLICITATION NUMBER 4. TYPE OF SOLICITATION 5. DATE ISSUED 6. REQUISITION/PURCHASE NUMBER

CODE7. ISSUED BY 8. ADDRESS OFFER TO (If other than item 7)

NOTE: In sealed bid solicitations "offer" and "offeror" mean "bid" and "bidder".

SOLICITATION

9. Sealed offers in original and copies for furnishings the supplies or services in the Schedule will be received at the place specified in item 8, or if hand carried, in the depository located in until local time

CAUTION - LATE Submissions, Modifications, and Withdrawals: See Section L, Provision No. 52.214-7 or 52.215-1. All offers are subject to all terms and conditions contained in this solicitation.

10. FOR

INFORMATION

CALL:

A. NAME B. TELEPHONE (NO COLLECT CALLS)

AREA CODE NUMBER EXTENSION

C. E-MAIL ADDRESS

11. TABLE OF CONTENTS

(X) SEC. DESCRIPTION PAGE(S) (X) SEC. PAGE(S)DESCRIPTION

A B C D E F G H

I

J

K

L

M EVALUATION FACTORS FOR AWARD

INSTRUCTIONS, CONDITIONS, AND NOTICES TO OFFERORS

REPRESENTATIONS, CERTIFICATIONS AND OTHER

STATEMENTS OF OFFERORS

PART IV - REPRESENTATIONS AND INSTRUCTIONS

LIST OF ATTACHMENTS

PART III - LIST OF DOCUMENTS, EXHIBITS AND OTHER ATTACH.

CONTRACT CLAUSESSOLICITATION/CONTRACT FORM

SUPPLIES OR SERVICES AND PRICES/COSTS

DESCRIPTION/SPECS./WORK STATEMENT

PACKAGING AND MARKING

INSPECTION AND ACCEPTANCE

DELIVERIES OR PERFORMANCE

CONTRACT ADMINISTRATION DATA

SPECIAL CONTRACT REQUIREMENTS

NOTE: Item 12 does not apply if the solicitation includes the provisions at 52.214-16, Minimum Bid Acceptance Period.

OFFER (Must be fully completed by offeror)

12. In compliance with the above, the undersigned agrees, if this offer is accepted within calendar days (60 calendar days unless a different period is inserted by the offeror) from the date for receipt of offers specified above, to furnish any or all items upon which prices are offered at the set opposite each item, delivered at the designated point(s), within the time specified in the schedule.

13. DISCOUNT FOR PROMPT PAYMENT

(See Section I, Clause No. 52.232-8)

14. ACKNOWLEDGMENT OF AMENDMENTS

(The offeror acknowledges receipt of amendments to the SOLICITATION for offerors and related documents numbered and dated):

10 CALENDAR DAYS (%) 20 CALENDAR DAYS (%) 30 CALENDAR DAYS (%) CALENDAR DAYS(%)

DATEAMENDMENT NO.AMENDMENT NO. DATE

15A. NAME AND

ADDRESS

OF OFFER-

OR

CODE FACILITY 16. NAME AND THE TITLE OF PERSON AUTHORIZED TO SIGN OFFER

(Type or print)

15B. TELEPHONE NUMBER

AREA CODE NUMBER EXTENSION

15C. CHECK IF REMITTANCE ADDRESS IS

DIFFERENT FROM ABOVE - ENTER SUCH

ADDRESS IN SCHEDULE.

17. SIGNATURE 18. OFFER DATE

AWARD (To be completed by Government)

19. ACCEPTED AS TO ITEMS NUMBERED 20. AMOUNT 21. ACCOUNTING AND APPROPRIATION

22. AUTHORITY FOR USING OTHER THAN FULL OPEN COMPETITION:

10 U.S.C. 2304 (c) ( )41 U.S.C. 3304(a)

24. ADMINISTERED BY (If other than Item 7)

26. NAME OF CONTRACTING OFFICER (Type or print)

IMPORTANT - Award will be made on this Form, or on Standard Form 26, or by other authorized official written notice.

AUTHORIZED FOR LOCAL REPRODUCTION

Previous edition is unusable

23. SUBMIT INVOICES TO ADDRESS SHOWN IN

(4 copies unless otherwise specified)

25. PAYMENT WILL BE MADE BY

27. UNITED STATES OF AMERICA

(Signature of Contracting Officer)

28. AWARD DATE

CODE

ITEM

STANDARD FORM 33 (REV. 6/2014)

Prescribed by GSA - FAR (48 CFR) 53.214 (c)

SEALED BID (IFB)

NEGOTIATED (RFP)

(Hour) (Date)

PART I - THE SCHEDULE PART II - CONTRACT CLAUSES

FA500021R0080

Section A - Solicitation/Contract Form

Section B - Supplies or Services and Prices/Cost

Additional Information/Notes

Item Supplies/Service Quantity Unit Unit Price Amount

Project consists of work to replace doors, install new laminate flooring and wall mounted electrical outlets and COMM lines.

Project Code: FXSB 21-1077 Firm Fixed Price

1 Project

Section C - Description/Specifications/Statement of Work

Project is to be implemented while accommodating user needs of the facility. Contractor shall request approval of any downtime/outages a minimum of 10 work days in advance. Of particular importance is the necessity to protect users and occupants of the facility from falling debris and life safety issues. Contractor staging areas will be identified by the Facility Manager, Fire Department, and 673 CES/CENMP. Safety areas and caution notices are to be provided by the Contractor.

Requirements The project consists of work to replace doors, install new laminate flooring and wall mounted electrical outlets and COMM lines.

Section D - Packaging and Marking

Section E - Inspection and Acceptance

Section F - Deliveries or Performance

Contractor Destination

FoB Details

Contractor Destination

Section G - Contract Administration Data

Number Title Effective Date 252.232-7003 Electronic Submission of Payment Requests and Receiving Reports. 2018-12 252.236-7000 Modification Proposals--Price Breakdown 1991-12 DFARS Clauses Incorporated by Full Text 252.232-7006 Wide Area WorkFlow Payment Instructions. 2018-12

(a) Definitions. As used in this clause- Department of Defense Activity Address Code (DoDAAC) is a six position code that uniquely identifies a unit, activity, or organization.

Document type means the type of payment request or receiving report available for creation in Wide Area WorkFlow (WAWF).

Local processing office (LPO) is the office responsible for payment certification when payment certification is done external to the entitlement system.

Payment request and receiving report are defined in the clause at 252.232-7003, Electronic Submission of Payment Requests and Receiving Reports.

(b) Electronic invoicing. The WAWF system provides the method to electronically process vendor payment requests and receiving reports, as authorized by Defense Federal Acquisition Regulation Supplement (DFARS) 252.232-7003, Electronic Submission of Payment Requests and Receiving Reports.

(c) WAWF access. To access WAWF, the Contractor shall-

(1) Have a designated electronic business point of contact in the System for Award Management at https://www.

sam.gov; and

(2) Be registered to use WAWF at https://wawf.eb.mil/ following the step-by-step procedures for selfregistration available at this web site.

(d) WAWF training. The Contractor should follow the training instructions of the WAWF Web-Based Training Course and use the Practice Training Site before submitting payment requests through WAWF. Both can be accessed by selecting the Web Based Training link on the WAWF home page at https://wawf.eb.mil/

(e) WAWF methods of document submission. Document submissions may be via web entry, Electronic Data Interchange, or File Transfer Protocol.

(f) WAWF payment instructions. The Contractor shall use the following information when submitting payment requests and receiving reports in WAWF for this contract or task or delivery order:

(1) Document type. The Contractor shall submit payment requests using the following document type(s):

(i) For cost-type line items, including labor-hour or time-and-materials, submit a cost voucher.

(ii) For fixed price line items

(A) That require shipment of a deliverable, submit the invoice and receiving report specified by the Contracting Officer.

N/A

(B) For services that do not require shipment of a deliverable, submit either the Invoice 2in1, which meets the requirements for the invoice and receiving report, or the applicable invoice and receiving report, as specified by the Contracting Officer.

Construction Invoice

(iii) For customary progress payments based on costs incurred, submit a progress payment request.

(iv) For performance based payments, submit a performance based payment request.

(v) For commercial item financing, submit a commercial item financing request.

(2) ) Fast Pay requests are only permitted when Federal Acquisition Regulation (FAR) 52.213-1 is included in the contract.

(f) [Note: The Contractor may use a WAWF combo document type to create some combinations of invoice and receiving report in one step.]

(3) Document routing. The Contractor shall use the information in the Routing Data Table below only to fill in applicable fields in WAWF when creating payment requests and receiving reports in the system.

Routing Data Table* | Field Name in WAWF || Data to be entered in WAWF |

| Pay Official DoDAAC || __F87700__ | | Issue By DoDAAC || __FA5000__ | | Admin DoDAAC || __FA5000__ | | Inspect By DoDAAC || __F1W3EA__ | | Service Approver (DoDAAC) || __F1W3EA__ | | Service Acceptor (DoDAAC) || __F1W3EA__ |

(4) Payment request. The Contractor shall ensure a payment request includes documentation appropriate to the type of payment request in accordance with the payment clause, contract financing clause, or Federal Acquisition Regulation 52.216-7, Allowable Cost and Payment, as applicable.

(5) Receiving report. The Contractor shall ensure a receiving report meets the requirements of DFARS Appendix F.

(g) WAWF point of contact.

(1) The Contractor may obtain clarification regarding invoicing in WAWF from the following contracting activities WAWF point of contact.

alfredia.tyler@us.af.mil/ donald.dougherty.1@us.af.mil

(2) Contact the WAWF helpdesk at 866-618-5988, if assistance is needed.

(End of clause)

Section H - Special Contract Requirements

Section I - Contract Clauses

FAR Clauses Incorporated by Reference Number Title Effective Date 52.203-11 Certification and Disclosure Regarding Payments to Influence Certain Federal 2007-09 Transactions.

52.203-12 Limitation on Payments to Influence Certain Federal Transactions. 2010-10 52.203-18 Prohibition on Contracting with Entities that Require Certain Internal Confidentiality Agreements or Statements-Representation. 2017-01 52.203-19 Prohibition on Requiring Certain Internal Confidentiality Agreements or Statements. 2017-01 52.204-7 System for Award Management. 2018-10 52.204-13 System for Award Management Maintenance. 2018-10 52.204-16 Commercial and Government Entity Code Reporting. 2016-07 52.204-23 Prohibition on Contracting for Hardware, Software, and Services Developed or Provided by Kaspersky Lab and Other Covered Entities. 2018-07 52.209-10 Prohibition on Contracting with Inverted Domestic Corporations. 2015-11 52.213-4 Terms and Conditions-Simplified Acquisitions (Other Than Commercial Items). 2019-10 52.219-6 Deviation 2019-O0003 Notice of Total Small Business Set-Aside (DEVIATION 2019-O0003) 2011-11 52.219-13 Notice of Set-Aside of Orders. 2011-11 52.219-14 Limitations on Subcontracting. 2017-01 52.222-6 Construction Wage Rate Requirements. 2018-08 52.222-7 Withholding of Funds. 2014-05 52.222-8 Payrolls and Basic Records. 2018-08 52.222-9 Apprentices and Trainees. 2005-07 52.222-10 Compliance with Copeland Act Requirements. 1988-02 52.222-11 Subcontracts (Labor Standards). 2014-05 52.222-12 Contract Termination-Debarment. 2014-05 52.222-13 Compliance with Construction Wage Rate Requirements and Related Regulations. 2014-05 52.222-14 Disputes Concerning Labor Standards. 1988-02 52.222-15 Certification of Eligibility. 2014-05 52.222-62 Paid Sick Leave Under Executive Order 13706. 2017-01 52.223-18 Encouraging Contractor Policies to Ban Text Messaging While Driving. 2011-08 52.223-19 Compliance with Environmental Management Systems. 2011-05 52.223-21 Foams. 2016-06 52.228-2 Additional Bond Security. 1997-10 52.228-11 Pledges of Assets. 2018-08 52.228-14 Irrevocable Letter of Credit. 2014-11 52.232-27 Prompt Payment for Construction Contracts. 2017-01 52.233-3 Protest after Award. 1996-08 52.236-5 Material and Workmanship. 1984-04 52.236-7 Permits and Responsibilities. 1991-11 52.242-14 Suspension of Work. 1984-04 52.243-1 Alternate I Changes-Fixed-Price. - (Alternate I) 1987-08 52.243-5 Changes and Changed Conditions. 1984-04 52.249-4 Termination for Convenience of the Government (Services) (Short Form). 1984-04 DFARS Clauses Incorporated by Reference Number Title Effective Date 252.203-7000 Requirements Relating to Compensation of Former DoD Officials 2011-09 252.203-7002 Requirement to Inform Employees of Whistleblower Rights. 2013-09 252.204-7003 Control of Government Personnel Work Product. 1992-04 252.204-7008 Compliance with Safeguarding Covered Defense Information Controls. 2016-10 252.204-7012 Safeguarding Covered Defense Information and Cyber Incident Reporting. 2016-10 52.211-10 Commencement, Prosecution, and Completion of Work.

As prescribed in 11.404(b), insert the following clause in solicitations and contracts when a fixed-price construction contract is contemplated. The clause may be changed to accommodate the issuance of orders under indefinite-delivery contracts for construction.

COMMENCEMENT, PROSECUTION, AND COMPLETION OF WORK (APR 1984)

The Contractor shall be required to (a) commence work under this contract within 180 calendar days after the date the Contractor receives the notice to proceed, (b) prosecute the work diligently, and (c) complete the entire work ready for use not later than 180 days.* The time stated for completion shall include final cleanup of the premises.

* The Contracting Officer shall specify either a number of days after the date the contractor receives the notice to proceed, or a calendar date.

(End of clause 52.232-8 Discounts for Prompt Payment.

As prescribed in 32.111(b)(1), insert the following clause:

DISCOUNTS FOR PROMPT PAYMENT (FEB 2002)

(a) Discounts for prompt payment will not be considered in the evaluation of offers. However, any offered discount will form a part of the award, and will be taken if payment is made within the discount period indicated in the offer by the offeror. As an alternative to offering a discount for prompt payment in conjunction with the offer, offerors awarded contracts may include discounts for prompt payment on individual invoices.

(b) In connection with any discount offered for prompt payment, time shall be computed from the date of the invoice. If the Contractor has not placed a date on the invoice, the due date shall be calculated from the date the designated billing office receives a proper invoice, provided the agency annotates such invoice with the date of receipt at the time of receipt. For the purpose of computing the discount earned, payment shall be considered to have been made on the date that appears on the payment check or, for an electronic funds transfer, the specified payment date. When the discount date falls on a Saturday, Sunday, or legal holiday when Federal Government offices are closed and Government business is not expected to be conducted, payment may be made on the following business day.

(End of clause)

52.232-16 Progress Payments.

As prescribed in 32.502-4(a), insert the following clause:

PROGRESS PAYMENTS (JUN 2020)

The Government will make progress payments to the Contractor when requested as work progresses, but not more frequently than monthly, in amounts of $2,500 or more approved by the Contracting Officer, under the following conditions:

(a) Computation of amounts.

(1) Unless the Contractor requests a smaller amount, the Government will compute each progress payment as 80 percent of the Contractor's total costs incurred under this contract whether or not actually paid, plus financing payments to subcontractors (see paragraph (j) of this clause), less the sum of all previous progress payments made by the Government under this contract. The Contracting Officer will consider cost of money that would be allowable under Federal Acquisition Regulation (FAR)31.205-10 as an incurred cost for progress payment purposes.

(2) The amount of financing and other payments for supplies and services purchased directly for the contract are limited to the amounts that have been paid by cash, check, or other forms of payment, or that are determined due and will be paid to subcontractors-

(i) In accordance with the terms and conditions of a subcontract or invoice; and

(ii) Ordinarily within 30 days of the submission of the Contractor's payment request to the Government.

(3) The Government will exclude accrued costs of Contractor contributions under employee pension plans until actually paid unless-

(i) The Contractor's practice is to make contributions to the retirement fund quarterly or more frequently; and

(ii) The contribution does not remain unpaid 30 days after the end of the applicable quarter or shorter payment period (any contribution remaining unpaid shall be excluded from the Contractor's total costs for progress payments until paid).

(4) The Contractor shall not include the following in total costs for progress payment purposes in paragraph (a)

(1) of this clause:

(i) Costs that are not reasonable, allocable to this contract, and consistent with sound and generally accepted accounting principles and practices.

(ii) Costs incurred by subcontractors or suppliers.

(iii) Costs ordinarily capitalized and subject to depreciation or amortization except for the properly depreciated or amortized portion of such costs.

(iv) Payments made or amounts payable to subcontractors or suppliers, except for-

(A) Completed work, including partial deliveries, to which the Contractor has acquired title; and

(B) Work under cost-reimbursement or time-and-material subcontracts to which the Contractor has acquired title.

(5) The amount of unliquidated progress payments may exceed neither (i) the progress payments made against incomplete work (including allowable unliquidated progress payments to subcontractors) nor (ii) the value, for progress payment purposes, of the incomplete work. Incomplete work shall be considered to be the supplies and services required by this contract, for which delivery and invoicing by the Contractor and acceptance by the Government are incomplete.

(6) The total amount of progress payments shall not exceed 80 percent of the total contract price.

(7) If a progress payment or the unliquidated progress payments exceed the amounts permitted by paragraphs (a)

(4) or (a)(5) of this clause, the Contractor shall repay the amount of such excess to the Government on demand.

(8) Notwithstanding any other terms of the contract, the Contractor agrees not to request progress payments in dollar amounts of less than $2,500. The Contracting Officer may make exceptions.

(9) The costs applicable to items delivered, invoiced, and accepted shall not include costs in excess of the contract price of the items.

(b) Liquidation. Except as provided in the Termination for Convenience of the Government clause, all progress payments shall be liquidated by deducting from any payment under this contract, other than advance or progress payments, the unliquidated progress payments, or 80 percent of the amount invoiced, whichever is less. The Contractor shall repay to the Government any amounts required by a retroactive price reduction, after computing liquidations and payments on past invoices at the reduced prices and adjusting the unliquidated progress payments accordingly. The Government reserves the right to unilaterally change from the ordinary liquidation rate to an alternate rate when deemed appropriate for proper contract financing.

(c) Reduction or suspension. The Contracting Officer may reduce or suspend progress payments, increase the rate of liquidation, or take a combination of these actions, after finding on substantial evidence any of the following conditions:

(1) The Contractor failed to comply with any material requirement of this contract (which includes paragraphs

(f) and (g) of this clause).

(2) Performance of this contract is endangered by the Contractor's--

(i) Failure to make progress; or

(ii) Unsatisfactory financial condition.

(3) Inventory allocated to this contract substantially exceeds reasonable requirements.

(4) The Contractor is delinquent in payment of the costs of performing this contract in the ordinary course of business.

(5) The fair value of the undelivered work is less than the amount of unliquidated progress payments for that work.

(6) The Contractor is realizing less profit than that reflected in the establishment of any alternate liquidation rate in paragraph (b) of this clause, and that rate is less than the progress payment rate stated in paragraph (a)(1) of this clause.

(d) Title.

(1) Title to the property described in this paragraph (d) shall vest in the Government. Vestiture shall be immediately upon the date of this contract, for property acquired or produced before that date. Otherwise, vestiture shall occur when the property is or should have been allocable or properly chargeable to this contract.

(2) "Property," as used in this clause, includes all of the below-described items acquired or produced by the Contractor that are or should be allocable or properly chargeable to this contract under sound and generally accepted accounting principles and practices.

(i) Parts, materials, inventories, and work in process;

(ii) Special tooling and special test equipment to which the Government is to acquire title;

(iii) Nondurable (i.e., noncapital) tools, jigs, dies, fixtures, molds, patterns, taps, gauges, test equipment, and other similar manufacturing aids, title to which would not be obtained as special tooling under paragraph (d)(2)

(ii) of this clause; and

(iv) Drawings and technical data, to the extent the Contractor or subcontractors are required to deliver them to the Government by other clauses of this contract.

(3) Although title to property is in the Government under this clause, other applicable clauses of this contract; e.

g., the termination clauses, shall determine the handling and disposition of the property.

(4) The Contractor may sell any scrap resulting from production under this contract without requesting the Contracting Officer's approval, but the proceeds shall be credited against the costs of performance.

(5) To acquire for its own use or dispose of property to which title is vested in the Government under this clause, the Contractor must obtain the Contracting Officer's advance approval of the action and the terms. The Contractor shall (i) exclude the allocable costs of the property from the costs of contract performance, and (ii) repay to the Government any amount of unliquidated progress payments allocable to the property. Repayment may be by cash or credit memorandum.

(6) When the Contractor completes all of the obligations under this contract, including liquidation of all progress payments, title shall vest in the Contractor for all property (or the proceeds thereof) not-

(i) Delivered to, and accepted by, the Government under this contract; or

(ii) Incorporated in supplies delivered to, and accepted by, the Government under this contract and to which title is vested in the Government under this clause.

(7) The terms of this contract concerning liability for Government-furnished property shall not apply to property to which the Government acquired title solely under this clause.

(e) Risk of loss. Before delivery to and acceptance by the Government, the Contractor shall bear the risk of loss for property, the title to which vests in the Government under this clause, except to the extent the Government expressly assumes the risk. The Contractor shall repay the Government an amount equal to the unliquidated progress payments that are based on costs allocable to property that is lost (see 45.101).

(f) Control of costs and property. The Contractor shall maintain an accounting system and controls adequate for the proper administration of this clause.

(g) Reports, forms, and access to records.

(1) The Contractor shall promptly furnish reports, certificates, financial statements, and other pertinent information (including estimates to complete) reasonably requested by the Contracting Officer for the administration of this clause. Also, the Contractor shall give the Government reasonable opportunity to examine and verify the Contractor's books, records, and accounts.

(2) The Contractor shall furnish estimates to complete that have been developed or updated within six months of the date of the progress payment request. The estimates to complete shall represent the Contractor's best estimate of total costs to complete all remaining contract work required under the contract. The estimates shall include sufficient detail to permit Government verification.

(3) Each Contractor request for progress payment shall:

(i) Be submitted on Standard Form 1443, Contractor's Request for Progress Payment, or the electronic equivalent as required by agency regulations, in accordance with the form instructions and the contract terms;

and

(ii) Include any additional supporting documentation requested by the Contracting Officer.

(h) Special terms regarding default. If this contract is terminated under the Default clause, (i) the Contractor shall, on demand, repay to the Government the amount of unliquidated progress payments and (ii) title shall vest in the Contractor, on full liquidation of progress payments, for all property for which the Government elects not to require delivery under the Default clause. The Government shall be liable for no payment except as provided by the Default clause.

(i) Reservations of rights.

(1) No payment or vesting of title under this clause shall-

(i) Excuse the Contractor from performance of obligations under this contract; or

(ii) Constitute a waiver of any of the rights or remedies of the parties under the contract.

(2) The Government's rights and remedies under this clause-

(i) Shall not be exclusive but rather shall be in addition to any other rights and remedies provided by law or this contract; and

(ii) Shall not be affected by delayed, partial, or omitted exercise of any right, remedy, power, or privilege, nor shall such exercise or any single exercise preclude or impair any further exercise under this clause or the exercise of any other right, power, or privilege of the Government.

(j) Financing payments to subcontractors. The financing payments to subcontractors mentioned in paragraphs (a)(1) and (a)(2) of this clause shall be all financing payments to subcontractors or divisions, if the following conditions are met:

(1) The amounts included are limited to-

(i) The unliquidated remainder of financing payments made; plus

(ii) Any unpaid subcontractor requests for financing payments.

(2) The subcontract or interdivisional order is expected to involve a minimum of approximately 6 months between the beginning of work and the first delivery; or, if the subcontractor is a small business concern, 4 months.

(3) If the financing payments are in the form of progress payments, the terms of the subcontract or interdivisional order concerning progress payments-

(i) Are substantially similar to the terms of this clause for any subcontractor that is a large business concern, or this clause with its Alternate I for any subcontractor that is a small business concern;

(ii) Are at least as favorable to the Government as the terms of this clause;

(iii) Are not more favorable to the subcontractor or division than the terms of this clause are to the Contractor;

(iv) Are in conformance with the requirements of FAR 32.504(e); and

(v) Subordinate all subcontractor rights concerning property to which the Government has title under the subcontract to the Government's right to require delivery of the property to the Government if-

(A) The Contractor defaults; or

(B) The subcontractor becomes bankrupt or insolvent.

(4) If the financing payments are in the form of performance-based payments, the terms of the subcontract or interdivisional order concerning payments-

(i) Are substantially similar to the Performance-Based Payments clause at FAR 52.232-32 and meet the criteria for, and definition of, performance-based payments in FAR part 32;

(ii) Are in conformance with the requirements of FAR 32.504(f); and

(iii) Subordinate all subcontractor rights concerning property to which the Government has title under the subcontract to the Government's right to require delivery of the property to the Government if-

(A) The Contractor defaults; or

(B) The subcontractor becomes bankrupt or insolvent.

(5) If the financing payments are in the form of commercial item financing payments, the terms of the subcontract or interdivisional order concerning payments-

(i) Are constructed in accordance with FAR 32.206(c) and included in a subcontract for a commercial item purchase that meets the definition and standards for acquisition of commercial items in FAR parts 2 and 12;

(ii) Are in conformance with the requirements of FAR 32.504(g); and

(iii) Subordinate all subcontractor rights concerning property to which the Government has title under the subcontract to the Government's right to require delivery of the property to the Government if-

(A) The Contractor defaults; or

(B) The subcontractor becomes bankrupt or insolvent.

(6) If financing is in the form of progress payments, the progress payment rate in the subcontract is the customary rate used by the contracting agency, depending on whether the subcontractor is or is not a small business concern.

(7) Concerning any proceeds received by the Government for property to which title has vested in the Government under the subcontract terms, the parties agree that the proceeds shall be applied to reducing any unliquidated financing payments by the Government to the Contractor under this contract.

(8) If no unliquidated financing payments to the Contractor remain, but there are unliquidated financing payments that the Contractor has made to any subcontractor, the Contractor shall be subrogated to all the rights the Government obtained through the terms required by this clause to be in any subcontract, as if all such rights had been assigned and transferred to the Contractor.

(9) To facilitate small business participation in subcontracting under this contract, the Contractor shall provide financing payments to small business concerns, in conformity with the standards for customary contract financing payments stated in FAR 32.113. The Contractor shall not consider the need for such financing payments as a handicap or adverse factor in the award of subcontracts.

(k) Limitations on undefinitized contract actions. Notwithstanding any other progress payment provisions in this contract, progress payments may not exceed 80 percent of costs incurred on work accomplished under undefinitized contract actions. A "contract action" is any action resulting in a contract, as defined in subpart 2.1, including contract modifications for additional supplies or services, but not including contract modifications that are within the scope and under the terms of the contract, such as contract modifications issued pursuant to the Changes clause, or funding and other administrative changes. This limitation shall apply to the costs incurred, as computed in accordance with paragraph (a) of this clause, and shall remain in effect until the contract action is definitized. Costs incurred which are subject to this limitation shall be segregated on Contractor progress payment requests and invoices from those costs eligible for higher progress payment rates. For purposes of progress payment liquidation, as described in paragraph (b) of this clause, progress payments for undefinitized contract actions shall be liquidated at 80 percent of the amount invoiced for work performed under the undefinitized contract action as long as the contract action remains undefinitized. The amount of unliquidated progress payments for undefinitized contract actions shall not exceed 80 percent of the maximum liability of the Government under the undefinitized contract action or such lower limit specified elsewhere in the contract.

Separate limits may be specified for separate actions.

(l) Due date. The designated payment office will make progress payments on the _________ [Contracting Officer insert date as prescribed by agency head; if not prescribed, insert "30th"] day after the designated billing office receives a proper progress payment request. In the event that the Government requires an audit or other review of a specific progress payment request to ensure compliance with the terms and conditions of the contract, the designated payment office is not compelled to make payment by the specified due date. Progress payments are considered contract financing and are not subject to the interest penalty provisions of the Prompt Payment Act.

(m) Progress payments under indefinite-delivery contracts. The Contractor shall account for and submit progress payment requests under individual orders as if the order constituted a separate contract, unless otherwise specified in this contract.

(End of clause) 52.236-27 Site Visit (Construction).

As prescribed in 36.523 , insert a provision substantially the same as the following:

SITE VISIT (CONSTRUCTION) (FEB 1995)

(a) The clauses at 52.236-2, Differing Site Conditions, and 52.236-3, Site Investigations and Conditions Affecting the Work, will be included in any contract awarded as a result of this solicitation. Accordingly, offerors or quoters are urged and expected to inspect the site where the work will be performed.

(b) An organized site visit has been scheduled for 1 September 2021 at 10:00 AM AKST.

(c) Participants will meet at- Interested parties will check-in at the project location at Building B11415, JBER-(E), AK.

Contractors that wish to attend and require base access, shall provide the following information for individuals attending NLT 27 August 2021 by 12:00 PM AKST to alfredia.tyler@us.af.mil and Cassandra.Woodard @us.af.

mil. No more than two individuals per contractor:

**SAMPLE**

Company Member 1: Name, Phone, Email, Driver's license number with State, and Date of Birth.

Provide the information NLT 27 August 2021 by 4:00 PM AKST via email, to the following addresses: alfredia.

tyler@us.af.mil and Cassandra.woodard@us.af.mil.

Please go to the Ft. Richardson Visitors Center gate to obtain a visitor pass once confirmation is provided, if needed. Please allow for some delay while obtaining the pass.

The following information will be required when getting your pass:

1) License

2) Registration

3) Proof of Insurance

Questions/requests for clarifications shall be submitted in writing NLT 03 September 2021 by 2:00 PM AKST via email to alfredia.tyler@us.af.mil and Cassandra.woodard@us.af.mil.

Responses to questions/requests for clarifications will be posted NLT 07 September 2021 by PM AKST. No additional questions will be received after 07 September 2021 by 2:00 PM.

Proposals shall be due 13 September 2021 NLT 2:00 PM AKST.

Note All, due to JBER Installation COVID Policy (Dated 30 Jul 21) - this applies to personnel who live, work and recreate on JBER as well as visitors to the installation.

Mask Wear - Based off the substantial or high community transmission rate within our local area DoD requires all Service Members, Federal employees, onsite contractor employees, and visitors, regardless of vaccination status, to wear a mask in an indoor setting on the installation and other facilities, owned, leased or otherwise controlled by DoD (reference q).

Per references (f), (g), and (q), exceptions are limited to: 1) inside private dwellings,

2) while driving in vehicles, if an individual is the lone operator or if all occupants in the vehicle are members of the same family group, 3) when an individual is in his or her own office alone with a closed door or alone with an open door and six-feet physical distancing is maintained, 4) when eating or drinking, 5) those with a medical exemption, 6) when actively exercising indoors and established mitigation controls are followed, 7) when necessary to reasonably accommodate a religious belief,

8) when wear interferes with use of personal protective, oxygen, or chemical equipment required for the performance of duties, 9) when clear or unrestricted visualization of verbal communication is essential to safe and effective military operations, 10) while operating machinery, if mask wear impairs safe operation ( e.g., impairing vision of an operator who requires glasses to drive by fogging the lenses), 11) when using equipment, including musical equipment, to perform duties and the equipment cannot be operated when wearing a mask,

12) when the mask is required to be lowered briefly for identification or security purposes, or 13) if mask wear otherwise interferes in the performance of military duties. In all cases, once the situation, impairment or interference ceases, personnel will immediately don their mask. Non-compliance may result in disciplinary or debarment action. In addition to the above, all personnel on JBER regardless of vaccination status are required to wear a mask outdoors on JBER in the following cases: 1) when directed by a commander; 2) when experiencing symptoms consistent with COVID-19; and 3) when required by other federal, state, local, tribal, or territorial laws, rules, and regulations, including local business and workplace guidance.

Section J - List of Attachments

Attch1_FXSB 21-1077 SOW Attch2_ Price Schedule Attch3_Drawing Set Attch4_Revised JBER CAD Attch5_JBER Lock Standards, October 3, 2017.docx Attch6_Contractors Fire Safety Guide Attch7_ JBER Telecom Criteria Requirements Attch8_Environmental Protection Specs on JBER (28 Oct 2020 Rev 3) Attch9_Asbestos Abated Areas Test Results Attch10_ AF_66 Submittal-FXSB 21-1077 X.xlsx

Section K - Representations, Certification, and other Statements of Offerors

Section L - Instrs., Conds., and Notices to Offerors

Section L - Instructions, Conditions, and Notices to Offerors (Non-commercial)

PROPOSAL PREPARATION INSTRUCTIONS

A. To assure timely and equitable evaluation of proposals, offerors must follow the instructions contained herein. Offerors are required to meet all solicitation requirements, including terms and conditions, representations and certifications, and technical requirements, in addition to those identified as evaluation factors or subfactors. Offerors must clearly identify any exception to the solicitation terms and conditions and provide complete accompanying rationale. The response shall consist of Three (3) separate parts; Part I - Summary and Miscellaneous Data, Part II - Price Proposal and, Part III - Technical Proposal.

B. The contracting officer has determined there is a high probability of adequate price competition in this acquisition. Upon examination of the initial offers, the contracting officer will review this determination and if, in the contracting officer's opinion, adequate price competition exists within the parameters of 13.106-2, no additional data will be requested. However, if at any time during this competition the contracting officer determines that adequate price competition no longer exists, offerors may be required to submit other than certified cost or pricing data IAW FAR 15.402(a)(2) to the extent necessary for the contracting officer to determine the reasonableness and affordability of the price.

C. Specific Instructions:

1. Only submit electronic copies of the proposal

2. Submit copies via email to the Government POC's in the posting.

1. PART I - SUMMARY AND MISCELLANEOUS DATA. Submit electronic copy only.

(a) The offeror shall provide a concise summary and master table of contents of the entire proposal.

(b) Complete blocks 12, 13, 15A, 15B, 15C,16,17, and 18 of the RFP, SF33 In doing so, the offeror accedes to the contract terms and conditions as written in the RFP Sections A through K. These sections constitute the model contract.

(c) Complete block 14 of the RFP Section A, SF 33, if any solicitation amendment(s) to the original solicitation documents was/were issued. Amendments will not be counted against the page limits.

(d) Complete the necessary fill-ins and certifications in Sections I through K. Section K shall be returned in its entirety. For Sections C through I, the offeror shall submit only those pages that require a fill-in.

(e) If applicable, provide a copy of the letter from the Small Business Administration (SBA) showing proof of Section 8(a) status.

2. PART II - PRICE PROPOSAL - Submit electronic copy only.

(a) This part shall contain a completed Section B (Supplies or Services and Prices/Costs).

(b) Insert proposed unit prices and extended amounts in Section B for each Contract Line Item Number (CLIN) or Sub CLIN (SCLIN), including all option periods. The extended amount must equal the unit price multiplied by the number of units. It is imperative that mathematical calculations are correct; particular care should be taken to ensure the amounts match when using a spreadsheet program, such as Microsoft EXCEL. The unit prices and extended amounts are limited to two decimal places.

(c) Extreme care should be exercised to ensure that no price data of any kind are included in any other Part of the proposal.

3. PART III - TECHNICAL PROPOSAL - Submit electronic copy only.

The factor is met when the offeror provided a proposal that identifies and meets all requirements stated in the attached SOW. Structure specifications shall be submitted with proposal.

4. Format for proposal Parts I, II, and III, shall be as follows:

(a) Each written Part of the proposal shall contain a Table of Contents, Cross References, and the List of Tables and Drawings (if applicable).

(b) one electronic copy of each Part of the entire offer must be submitted. The electronic version of the proposal shall be submitted in a format readable by Microsoft Office 2010 which includes software programs such as WORD, EXCEL, or PowerPoint. For those pages of the proposal that cannot be submitted using Microsoft Office, such as the Standard Form 33, offerors shall include those pages electronically using Adobe Acrobat portable document files (.pdf) format. The Price Part shall be submitted in EXCEL spreadsheet format and MS WORD for price narrative. The electronic version shall be submitted via email to alfredia.tyler@us.af.mil and anna_maria.smith.1@us.af.mil. USB flash drives, floppy disks, and zip disks are not acceptable.

D. General Information:

1. Offerors are cautioned that JBER has visitor control procedures requiring individuals not affiliated with the installation to obtain a visitor pass prior to entrance. Late proposals will be processed in accordance with FAR 52.215-1(c)(3),"Submission, modification, revision, and withdrawal of proposals."

FEDERAL HOLIDAYS: The following Federal Legal Holidays are observed by this base:

New Year's Day (1 January) Birthday of Martin Luther King (Third Monday in January) Washington's Birthday (Third Monday in February) Memorial Day (Last Monday in May) Juneteenth (19 June) Independence Day (4 July) Labor Day (First Monday in September) Columbus Day (Second Monday in October) Veterans Day (11 November) Thanksgiving Day (Fourth Thursday in November) Christmas Day (25 December)

CLAUSES INCORPORATED BY REFERENCE

52.204-7 System for Award Management OCT 2016 52.216-1 Type Of Contract APR 1984 52.222-5 Construction Wage Rate Requirements--Secondary Site of the Work MAY 2014 52.252-1 Solicitation Provisions Incorporated By Reference FEB 1998 52.252-5 Authorized Deviations In Provisions APR 1984

Section M - Evaluation Factors for Award

Section M - Evaluation Factors for Award

EVALUATION FACTORS FOR AWARD:

This is a sole source 8(a) Lowest Price Technically Acceptable (LPTA) source selection conducted in accordance with Federal Acquisition Regulation (FAR) Part 15, Department of Defense (DoD) FAR Supplement Procedures, Guidance and Information Subpart 215.3, and Air Force FAR Supplement (AFFARS) Mandatory Procedure (MP) 5315.3. By submission of its offer in accordance with the instructions provided in Section L - Instrs., Conds., and Notices to Offerors, the offeror accedes to the terms of this model contract.

Failure to meet a requirement may result in an offer being determined unacceptable. Award will be made if the offer is determined price fair & reasonable. The evaluation process will include the following:

1. Technical Acceptability Factor. The government will evaluate quotes on a pass/fail basis and assign an Acceptable or Unacceptable rating as described below:

Rating Description:

-Acceptable - Presents a thorough understanding of, and ability to meet objectives outlined in the Statement of Work. Technical narrative, drawings, and all required submittals shall be submitted with quote. Quote and all submittals, drawing, and technical narrative presents sufficient detail to allow the government to make an acceptability determination. Quote meets all requirements of the solicitation.

-Unacceptable - This rating is met when the Offeror does not provide a quote that presents a thorough understanding of, and ability to meet objectives outlined in the Statement of Work. Technical narrative, drawings and required submittals were not provided, or do not meet the specifications outlined in the solicitation. Or sufficient detail was not provided to allow the government to make an acceptability determination.

2. Price Evaluation Factor:

-The government will evaluate the offer. The price evaluation will document the fairness and reasonableness of the price. The government reserves the right to perform price realism analysis. The Contracting Officer may use one or more, but not necessarily all of the evaluation techniques in FAR Part 15.404-1 to determine price reasonableness.

3. Past Performance: The government will evaluate past performance on a pass/fail basis. Quality will be evaluated based upon evaluation ratings in the Federal Past Performance Information Retrieval System (PPIRS), if available. The Government will use past performance information from Contractor Performance Assessment Reporting System (CPARS) IAW FAR Part 42.1503(g), which mandates construction contracts will evaluate CPARS information within six (6) years of the completion of performance of the evaluated contract or order and information contained in Federal Awardee Performance and Integrity Information System (FAPIIS), e.g., terminations for default or cause. Past Performance information may also be obtained from other established systems such as the Electronic Subcontract Reporting System (eSRS), or other databases; and may be obtained from other sources available to the Government, such as the Defense Contract Management Agency; and interviews with Program Managers, Contracting Officers or Fee Determining Officials.

In the case that there is no record of relevant past performance or for whom information on past performance is not available or so sparse that no meaningful past performance rating can be reasonably assigned, the offeror may not be evaluated favorably or unfavorably on past performance. Therefore, the offeror shall be determined to have unknown (or "neutral") past performance. In the context of acceptable/unacceptability, a neutral rating shall be considered "acceptable".

Rating Description:

- Acceptable- Based on the offeror's performance record, the Government has a reasonable expectation that the offeror will successfully perform the required effort, or the offeror's performance record is unknown.

- Unacceptable- Based on the offeror's performance record, the Government does not have a reasonable expectation that the offeror will be able to successfully perform the required effort.

The offeror is cautioned to submit sufficient information and in the format specified in Section L of this solicitation. The offeror may be asked to clarify certain aspects of their quotes. Exchanges conducted to resolve minor or clerical errors will not constitute discussions and the contracting officer reserves the right to award a contract without the opportunity for quote revision. The government intends to award a contract without discussions with the offer. The government, however, reserves the right to conduct discussions if deemed in its best interest.

(End of Section M - Evaluation Factors for Award)

FAR Clauses Incorporated by Full Text 52.225-10 Notice of Buy American Requirement-Construction Materials. 2014-05 As prescribed in 25.1102(b)(1), insert the following provision:

NOTICE OF BUY AMERICAN REQUIREMENT-CONSTRUCTION MATERIALS (MAY 2014)

(a) Definitions. "Commercially available off-the-shelf (COTS) item," "construction material," "domestic construction material," and "foreign construction material," as used in this provision, are defined in the clause of this solicitation entitled "Buy American-Construction Materials" (Federal Acquisition Regulation (FAR) clause 52.225-9).

(b) Requests for determinations of inapplicability. An offeror requesting a determination regarding the inapplicability of the Buy American statute should submit the request to the Contracting Officer in time to allow a determination before submission of offers. The offeror shall include the information and applicable supporting data required by paragraphs (c) and (d) of the clause at FAR 52.225-9 in the request. If an offeror has not requested a determination regarding the inapplicability of the Buy American statute before submitting its offer, or has not received a response to a previous request, the offeror shall include the information and supporting data in the offer.

(c) Evaluation of offers. (1) The Government will evaluate an offer requesting exception to the requirements of the Buy American statute, based on claimed unreasonable cost of domestic construction material, by adding to the offered price the appropriate percentage of the cost of such foreign construction material, as specified in paragraph (b)(3)(i) of the clause at FAR 52.225-9.

(2) If evaluation results in a tie between an offeror that requested the substitution of foreign construction material based on unreasonable cost and an offeror that did not request an exception, the Contracting Officer will award to the offeror that did not request an exception based on unreasonable cost.

(d) Alternate offers. (1) When an offer includes foreign construction material not listed by the Government in this solicitation in paragraph (b)(2) of the clause at FAR 52.225-9, the offeror also may submit an alternate offer based on use of equivalent domestic construction material.

(2) If an alternate offer is submitted, the offeror shall submit a separate Standard Form 1442 for the alternate offer,…

This is the start of the file's text. The full file is on GovTribe.