Sol_140P4220R0014.pdf
PDF 421 KB Posted
- Attached to
- HAMP CUPOLA WOODWORK REPAIR
- Solicitation number
- 140P4220R0014
About this file
This request for proposal solicits construction services for repairing wood elements of the cupola at the Hampton National Historic Site in Towson, Maryland. Services include removing and replacing the slate roof perimeter, restoring the rusticated wood base and entablature, restoring windows and installing new cedar and metal roofs. The NAICS code is 238350 and size standard is $16.5 million. The wage determination applies rates for Baltimore County, Maryland. The contract will be a firm-fixed price awarded based on technical evaluation and price to the best-value offer. The contractor must be knowledgeable in historic preservation standards and have experience with historically significant structures. Insurance, bonds and disadvantaged business participation are required. A site visit will be held on August 4 and questions are due by August 7 to the National Park Service for consideration by the closing date.
View the file
Other files
| File | Type | Posted |
|---|---|---|
| Sol_140P4220R0014_Amd_0004.pdf | ||
| General References_0004.doc | DOC document | |
| Hazardous Materials Form_0004.doc | DOC document | |
| Pre-Bid RFIs_0002.docx | DOCX document | |
| Sol_140P4220R0014_Amd_0002.pdf | ||
| HAMP Cupola Price Sheet_0003.xlsx | XLSX spreadsheet | |
| Sol_140P4220R0014_Amd_0003.pdf | ||
| Sol_140P4220R0014_Amd_0001.pdf | ||
| Hampton Mansion CD.pdf | ||
| Wage Determination MD20200030.pdf | ||
| Experience Questionnaire.docx | DOCX document | |
| E54 COVID-19 Guidance OSHA.pdf | ||
| B08 Price Schedule.docx | DOCX document | |
| Hampton Specifications.pdf |
Show all 14
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
SOLICITATION, OFFER,
AND AWARD
2. TYPE OF SOLICITATION
6. PROJECT NO. 4. CONTRACT NO. 5. REQUISITION/PURCHASE REQUEST NO.
PAGE OF PAGES
7. ISSUED BY CODE 8. ADDRESS OFFER TO
SOLICITATION
(Construction, Alteration, or Repair)
1. SOLICITATION NO. 3. DATE ISSUED
IMPORTANT -- The "offer" section on the reverse must be fully completed by offeror.
9.
INFORMATION
a. NAME b. TELEPHONE NO. (Include area code) (NO COLLECT CALLS)
NOTE: In sealed bid solicitations "offer" and "offeror" mean "bid" and "bidder."
CALL:
FOR
SEALED BID (IFB)
NEGOTIATED (RFP)
0040479884
DOI, NPS, NERO & NER SOUTH MABO
National Park Service
Northeast Regional Contracting South/Philadelphia MABO
PNC
1234 Market Street, 20th Floor
Philadelphia PA 19107
L.J. Gravelle
LJ_Gravelle@nps.gov
Lawrence Gravelle (717) 338-4481
1x 07/22/2020
140P4220R0014
10. THE GOVERNMENT REQUIRES PERFORMANCE OF THE WORK DESCRIBED IN THESE DOCUMENTS (Title, identifying no., date)
REPAIR WOOD ELEMENTS OF THE MANSION CUPOLA HAMPTON NATIONAL HISTORIC SITE, TOWSON, MD
Request for Proposal (RFP) to construction firms with the capability to perform the work in accordance with the attached specifications. The requirement is being solicited under FAR Parts 15 and 36. This contract requires the contractor to provide all tools, labor, equipment, supervision, transportation, correspondence, supplies, staging, and materials necessary to complete this requirement.
The NAICS code for this requirement is 238350 Finish Carpentry Contractors with a size standard of $16.5 million
Size Magnitude for this project is between $1,000,0000 and $5,000,000
Wage Determination (WD): The applicable WD for this requirement is MD 20200030 and the work will take place in Baltimore County, MD.
This contract is being solicited as a 100% Certified Disadvantaged Small Business set-aside. All responsible contractors may submit an offer for consideration.
Continued ...
11. The Contractor shall begin performance
12a. THE CONTRACTOR MUST FURNISH ANY REQUIRED PERFORMANCE AND PAYMENT BONDS?
award, notice to proceed. The performance period is mandatory negotiable. (See ________________________________________________.)
13. ADDITIONAL SOLICITATION REQUIREMENTS:
a. Sealed offers in original and is not required.is, b. An offer guarantee
c. All offers are subject to the (1) work requirements, and (2) other provisions and clauses incorporated in the solicitation in full text or by reference.
(date). If this is a sealed bid solicitation, offers will be publicly opened at that time. Sealed envelopes containing offers shall be marked to show the offeror's name and address, the solicitation number, and the date and time offers are due.
d. Offers providing less than
12b. CALENDAR DAYSYES NO
(If "YES", indicate within how many calendar days after award in Item 12b.)
10 365 calendar days and complete it within ________________ ________________ calendar days after receiving
FAR 52.211-10
08/21/2020
NSN 7540-01-155-3212
x x x x copies to perform the work required are due at the place specified in Item 8 by _____________ ___________________ (hour) local time calendar days for Government acceptance after the date offers are due will not be considered and will be rejected . _________________
STANDARD FORM 1442 (Rev. 4-85)
Prescribed by GSA
FAR(48 CFR) 53.236-1(d)
17. The offeror agrees to perform the work required at the prices specified below in strict accordance with the terms of this solicitation, if this offer is accepted by the Government in writing within ____________________ calendar days after the date offers are due. (Insert any number equal to or greater than the minimum requirement stated in item 13d. Failure to insert any number means the offeror accepts the minimum in item 13d.)
14. NAME AND ADDRESS OF OFFEROR (Include ZIP Code) 15. TELEPHONE NO. (Include area code)
16. REMITTANCE ADDRESS (Include only if different than item 14.)
CODE FACILITY CODE
AMOUNTS
18. The offeror agrees to furnish any required performance and payment bonds.
19. ACKNOWLEDGEMENT OF AMENDMENTS
OFFER (Must be fully completed by offeror)
(The offeror acknowledges receipt of amendments to the solicitation -- give number and date of each)
AMENDMENT NO.
DATE.
20a. NAME AND TITLE OF PERSON AUTHORIZED TO SIGN OFFER (Type or print) 20b. SIGNATURE 20c. OFFER DATE
AWARD (To be completed by Government)
21. ITEMS ACCEPTED:
22. AMOUNT 23. ACCOUNTING AND APPROPRIATION DATA
24. SUBMIT INVOICES TO ADDRESS SHOWN IN
(4 copies unless otherwise specified)
ITEM 25. OTHER THAN FULL AND OPEN COMPETITION PURSUANT TO
26. ADMINISTERED BY CODE 27. PAYMENT WILL BE MADE BY
CONTRACTING OFFICER WILL COMPLETE ITEM 28 OR 29 AS APPLICABLE
(Contractor is required to sign this document and return (Contractor is not required to sign this document.)
Your offer on this solicitation is hereby accepted as to the items listed. This award consummates the contract, which consists of (a) the Government solicitation and your offer, and (b) this contract award.
No further contractual document is necessary.
30a. NAME AND TITLE OF CONTRACTOR OR PERSON AUTHORIZED TO SIGN (Type or print) 31a. NAME OF CONTRACTING OFFICER (Type or print)
30b. SIGNATURE 30c. DATE 31b. UNITED STATES OF AMERICA 31c. DATE
BY
2PAGE OF
DOI, NPS, NER - Central MABO - GETT 791 Baltimore Ave
Gettysburg PA 17325
NC2
Lawrence Gravelle
28. NEGOTIATED AGREEMENT 29. AWARD
Contractor agrees to furnish and deliver all items or perform all work requirements identified on this form and any continuation sheets for the consideration stated in this contract. The rights and obligations of the parties to this contract shall be governed by (a) this contract award, (b) the solicitation, and (c) the clauses, representations, copies to issuing office.)
10 U.S.C. 2304(c) 41 U.S.C. 253(c)
STANDARD FORM 1442 (REV. 4-85) BACK
Continued...
ITEM NO.
(A)
SUPPLIES/SERVICES
(B)
QUANTITY
(C)
UNIT
(D)
UNIT PRICE
(E)
AMOUNT
(F)
NAME OF OFFEROR OR CONTRACTOR
3 49
CONTINUATION SHEET
REFERENCE NO. OF DOCUMENT BEING CONTINUED PAGE OF
140P4220R0014
A firm-fixed price contract will be awarded to the responsive contractor submitting the proposal the represents the best value to the Government.
Award will be made based on an evaluation of technical factors and price. The selected
Contractor must be knowledgeable in Standards for
Historic Preservation and have experience in working on structures of historic significance.
See RFP Section L, Instructions, Conditions, and
Notices to Offerors for applicable Special
Instructions including what to submit with the proposal.
Note: Certificate of Insurance, Payment and
Performance Bond, and Bid Guarantee are required.
See section I of the clauses for additional information.
Site Visit: An organized site visit will be held on August 4, 2020 at 11:00 AM EST. Participants should meet at 535 Hampton Lane Towson, MD 21286.
All participants WILL BE REQUIRED TO WEAR A MASK
TO ATTEND. Please RSVP to John Holtzinger, Project Manager at John_Holtzinger@nps.gov by
July 31, 2020
All questions regarding this solicitation shall be submitted via email to L.J. Gravelle, Contract
Officer at LJ_Gravelle@nps.gov
Questions shall be submitted by August 7, 2020 at
4:00 PM EST.
Delivery: 365 Days After Notice to Proceed
Delivery Location Code: 0009060043
NPS, Hampton NHS
535 Hampton Lane
Towson MD 21286 US
00010 Cupola Woodwork Repair
Product/Service Code: Z1JA
Product/Service Description: MAINTENANCE OF
MUSEUMS AND EXHIBITION BUILDINGS
NSN 7540-01-152-8067 OPTIONAL FORM 336 (4-86)
Sponsored by GSA
FAR (48 CFR) 53.110
Solicitation Document No. Document Title 140P4220R0014 HAMP – Repair Wood Elements of Mansion Cupola
TABLE OF CONTENTS
SECTION A – SOLICITATION/CONTRACT FORM
SECTION B – SUPPLIES OR SERVICES AND PRICES
SECTION C – DESCRIPTIONS/SPECIFICATIONS/STATEMENT OF WORK
SECTION D – PACKAGING AND MARKING
SECTION E – INSPECTION AND ACCEPTANCE
52.246-12 INSPECTION OF CONSTRUCTION (AUG 1996)
SECTION F – DELIVERIES OR PERFORMANCE
PROVISIONS OR CLAUSES INCORPORATED BY REFERENCE IAW FAR 52.252-1 OR 52.252-2:
52.242-14 -- SUSPENSION OF WORK (APR 1984)
52.211-10 COMMENCEMENT, PROSECUTION, AND COMPLETION OF WORK (APR 1984)
SECTION G – CONTRACT ADMINISTRATION DATA
1452.201-70 AUTHORITIES AND DELEGATIONS (SEPT 2011)
DOI Local Clause: Electronic Invoicing and Payment Requirements - Invoice Processing Platform (IPP) (April 2013) Contract Administration
SECTION H – SPECIAL CONTRACT REQUIREMENTS
SPECIAL CLAUSE 1: KEY PERSONNEL
CONTRACT WORK HOURS (NOV 2007)
CONSTRUCTION WAGE RATES
SEASONAL SHUTDOWN
NOTICE TO CONTRACTORS CONTRACTOR PERFORMANCE ASSESSMENT REPORTING SYSTEM
(DECEMBER 2015)
SPECIAL REQUIREMENTS FOR CORONAVIRUS PANDEMIC (COVID-19)
SECTION I – CONTRACT CLAUSES
PROVISIONS OR CLAUSES INCORPORATED BY REFERENCE IAW FAR 52.252-1 OR 52.252-2:
52.202-1 DEFINITIONS (JUN 2020)
52.203-3 GRATUITIES (APR 1984)
52.203-5 COVENANT AGAINST CONTINGENT FEES (MAY 2014)
52.203-6 RESTRICTIONS ON SUBCONTRACTOR SALES TO THE GOVERNMENT (JUN 2020)
52.203-7 ANTI-KICKBACK PROCEDURES (JUN 2020)
52.203-8 CANCELLATION, RESCISSION AND RECOVERY OF FUNDS FOR ILLEGAL OR IMPROPER
ACTIVITY (MAY 2014)
52.203-10 PRICE OR FEE ADJUSTMENT FOR ILLEGAL OR IMPROPER ACTIVITY (MAY 2014)
52.203-12 LIMITATION ON PAYMENT TO INFLUENCE CERTAIN FEDERAL TRANSACTIONS (JUN
2020)
52.203-17 CONTRACTOR EMPLOYEE WHISTLEBLOWER RIGHTS AND REQUIREMENT TO INFORM
EMPLOYEES OF WHISTLEBLOWER RIGHTS (JUN 2020)
52.203-19 – PROHIBITION ON REQUIRING CERTAIN INTERNAL CONFIDENTIALITY AGREEMENTS
OR STATEMENTS (JAN 2017)
52.204-4 PRINTED OR COPIED DOUBLE SIDED ON POSTCONSUMER FIBER CONTENT PAPER
(MAY 2011)
52.204-10 REPORTING EXECUTIVE COMPENSATION AND FIRST TIER SUBCONTRACT AWARDS
(JUN 2020)
52.204-13 SYSTEM FOR AWARD MANAGEMENT MAINTENANCE (JUL 2016)
52.204-14 SERVICE CONTRACT REPORTING REQUIREMENTS (OCT 2016)
52.204-25 PROHIBITION ON CONTRACTING FOR CERTAIN TELECOMMUNICATIONS AND VIDEO
SURVEILLANCE SERVICES OR EQUIPMENT
52.209-6 PROTECTING THE GOVERNMENT'S INTEREST WHEN SUBCONTRACTING WITH
CONTRACTORS DEBARRED, SUSPENDED, OR PROPOSED FOR DEBARMENT (JUN 2020)
52.209-10 PROHIBITION ON CONTRACTING WITH INVERTED DOMESTIC CORPORATIONS (NOV
2015)
52.215-2 AUDIT AND RECORDS-NEGOTIATION (JUN 2020)
52.215-8 ORDER OF PRECEDENCE – UNIFORM CONTRACT FORMAT (OCT 1997)
52.219-6 NOTICE OF TOTAL SMALL BUSINESS SET-ASIDE (NOV 2011)
52.219-8 UTILIZATION OF SMALL BUSINESS CONCERNS (NOV 2016)
52.219-14 LIMITATIONS ON SUBCONTRACTING (NOV 2011)
52.219-28 POST AWARD SMALL BUSINESS PROGRAM REPRESENTATIONS (MAY 2020)
52.222-3 CONVICT LABOR (JUN 2003)
52.222-4 CONTRACT WORK HOURS AND SAFETY STANDARDS ACT - OVERTIME COMPENSATION
(MAY 2014)
52.222-6 CONSTRUCTION WAGE RATES REQUIREMENT (MAY 2014)
52.222-7 WITHHOLDING OF FUNDS (MAY 2014)
52.222-8 PAYROLLS AND BASIC RECORDS (MAY 2014)
52.222-10 COMPLIANCE WITH COPELAND ACT REQUIREMENTS (FEB 1988)
52.222-11 SUBCONTRACTS (LABOR STANDARDS) (MAY 2014)
52.222-12 CONTRACT TERMINATION - DEBARMENT. (MAY 2014)
52.222-13 COMPLIANCE WITH DAVIS-BACON AND RELATED ACT REGULATIONS (MAY 2014)
52.222-14 DISPUTES CONCERNING LABOR STANDARDS (FEB 1988)
52.222-15 CERTIFICATION OF ELIGIBILITY (MAY 2014)
52.222-21 PROHIBITION OF SEGREGATED FACILITIES (APR 2015)
52.222-23 NOTICE OF REQUIREMENT FOR AFFIRMATIVE ACTION TO ENSURE EQUAL
EMPLOYMENT OPPORTUNITY FOR CONSTRUCTION (FEB 1999)
52.222-26 EQUAL OPPORTUNITY (SEPT 2016)
52.222-27 AFFIRMATIVE ACTION COMPLIANCE REQUIREMENTS FOR CONSTRUCTION (APR 2015)
52.222-37 EMPLOYMENT REPORTS ON VETERANS (JUN 2020)
52.222-40 NOTIFICATION OF EMPLOYEE RIGHTS UNDER THE NATIONAL LABOR RELATIONS ACT
(DEC 2010)
52.222-50 COMBATING TRAFFICKING IN PERSONS (MAY 2015)
52.222-54 EMPLOYMENT ELIGIBILITY VERIFICATION (OCT 2015)
52.222-55 MINIMUM WAGES UNDER EXECUTIVE ORDER 13658 (DEC 2015)
52.222-62 PAID SICK LEAVE UNDER EXECUTIVE ORDER 13706 (JAN 2017)
52.223-2 AFFIRMATIVE PROCUREMENT OF BIOBASED PRODUCTS UNDER SERVICE AND
CONSTRUCTION CONTRACTS (SEPT 2013)
52.223-3 HAZARDOUS MATERIAL IDENTIFICATION AND MATERIAL SAFETY DATA. (JAN 1997) -
ALTERNATE I (JUL 1995)
52.223-5 POLLUTION PREVENTION AND RIGHT-TO-KNOW INFORMATION (MAY 2011)
52.223-6 DRUG-FREE WORKPLACE (MAY 2001)
52.223-17 AFFIRMATIVE PROCUREMENT OF EPA-DESIGNATED ITEMS IN SERVICE AND
CONSTRUCTION CONTRACTS (MAY 2008)
52.223-18 ENCOURAGING CONTRACTOR POLICIES TO BAN TEXT MESSAGING WHILE DRIVING
(JUN 2020)
52.225-13 RESTRICTIONS ON CERTAIN FOREIGN PURCHASES (JUN 2008)
52.227-1 AUTHORIZATION AND CONSENT (JUN 2020)
52.227-2 NOTICE AND ASSISTANCE REGARDING PATENT AND COPYRIGHT INFRINGEMENT (JUN
2020)
52.227-4 PATENT INDEMNITY-CONSTRUCTION CONTRACTS (DEC 2007)
52.228-2 ADDITIONAL BOND SECURITY (OCT 1997)
52.228-5 INSURANCE - WORK ON A GOVERNMENT INSTALLATION (JAN 1997)
52.228-11 PLEDGES OF ASSETS (JAN 2012)
52.228-12 PROSPECTIVE SUBCONTRACTOR REQUESTS FOR BONDS (MAY 2014)
52.228-14 IRREVOCABLE LETTER OF CREDIT MAY 2014)
52.228-15 PERFORMANCE AND PAYMENT BONDS - CONSTRUCTION (JUN 2020)
52.229-3 FEDERAL, STATE, AND LOCAL TAXES (FEB 2013)
52.232-5 PAYMENTS UNDER FIXED-PRICE CONSTRUCTION CONTRACTS (MAY 2014)
52.232-16 PROGRESS PAYMENTS (JUN 2020)
52.232-17 INTEREST (MAY 2014)
52.232-23 -- ASSIGNMENT OF CLAIMS (MAY 2014)
52.232-27 PROMPT PAYMENT FOR CONSTRUCTION CONTRACTS (MAY 2014)
52.232-33 PAYMENT BY ELECTRONIC FUNDS TRANSFER – SYSTEM FOR AWARD MANAGEMENT
(JUL 2013)
52.232-39 UNENFORCEABILITY OF UNAUTHORIZED OBLIGATIONS (JUN 2013)
52.232-40 PROVIDING ACCELERATED PAYMENTS TO SMALL BUSINESS SUBCONTRACTORS
(DEC 2013)
52.233-1 DISPUTES. (MAY 2014) - ALTERNATE I (DEC 1991)
52.233-3 PROTEST AFTER AWARD (AUG 1996)
52.233-4 APPLICABLE LAW FOR BREACH OF CONTRACT CLAIM (OCT 2004)
52.236-2 DIFFERING SITE CONDITIONS (APR 1984)
52.236-3 SITE INVESTIGATION AND CONDITIONS AFFECTING THE WORK (APR 1984)
52.236-5 MATERIAL AND WORKMANSHIP (APR 1984)
52.236-8 OTHER CONTRACTS (APR 1984)
52.236-9 PROTECTION OF EXISTING VEGETATION, STRUCTURES, EQUIPMENT, UTILITIES, AND
IMPROVEMENTS (APR 1984)
52.236-10 OPERATIONS AND STORAGE AREAS (APR 1984)
52.236-11 USE AND POSSESSION PRIOR TO COMPLETION (APR 1984)
52.236-12 CLEANING UP (APR 1984)
52.236-13 ACCIDENT PREVENTION (NOV 1991)
52.236-14 AVAILABILITY AND USE OF UTILITY SERVICES (APR 1984)
52.236-15 SCHEDULES FOR CONSTRUCTION CONTRACTS (APR 1984)
52.236-17 LAYOUT OF WORK (APR 1984)
52.236-21 SPECIFICATIONS AND DRAWINGS FOR CONSTRUCTION (FEB 1997)
52.236-26 PRECONSTRUCTION CONFERENCE (FEB 1995)
52.242-13 BANKRUPTCY (JUL 1995)
52.243-4 CHANGES (JUN 2007)
52.244-6 SUBCONTRACTS FOR COMMERCIAL ITEMS (JUN 2020)
52.246-21 WARRANTY OF CONSTRUCTION (MAR 1994)
52.248-3 VALUE ENGINEERING-CONSTRUCTION-ALTERNATE I (OCT 2015)
52.249-2 TERMINATION FOR CONVENIENCE OF THE GOVERNMENT (FIXED-PRICE). (APR 2012)
ALT I (SEPT 1996)
52.249-10 DEFAULT (FIXED-PRICE CONSTRUCTION) (APR 1984)
52.253-1 COMPUTER GENERATED FORMS (JAN 1991)
52.222-9 APPRENTICES AND TRAINEES (JUL 2005)
52.222-35-- Equal Opportunity for Veterans (JUN 2020)
52.222-36-- Equal Opportunity for Workers with Disabilities (JUN 2020)
52.225-9 -- BUY AMERICAN–CONSTRUCTION MATERIALS (MAY 2014)
52.228-1 BID GUARANTEE (SEPT 1996)
52.236-6 SUPERINTENDENCE BY THE CONTRACTOR (APR 1984)
52.236-7 PERMITS AND RESPONSIBILITIES (NOV 1991)
52.252-2 CLAUSES INCORPORATED BY REFERENCE (FEB 1998)
1452.203-70 RESTRICTIONS ON ENDORSEMENTS (JUL 1996)
1452.204-70 RELEASE OF CLAIMS -- DEPARTMENT OF THE INTERIOR (JUL 1996)
1452.228-70 LIABILITY INSURANCE (JUL 1996)
1452.236-70 PROHIBITION AGAINST USE OF LEAD-BASED PAINT (JUL 1996)
SECTION J – LIST OF DOCUMENTS, EXHIBITS AND OTHER ATTACHMENTS
SECTION K – REPRESENTATIONS, CERTIFICATIONS AND OTHER STATEMENTS OF OFFERORS
PROVISIONS OR CLAUSES INCORPORATED BY REFERENCE IAW FAR 52.252-1 OR 52.252-2:
52.204-19 INCORPORATION BY REFERENCE OF REPRESENTATIONS AND CERTIFICATIONS (DEC
2014)
52.209-7 INFORMATION REGARDING RESPONSIBILITY MATTERS (JULY 2013)
52.222-38 COMPLIANCE WITH VETERANS’ EMPLOYMENT REPORTING REQUIREMENTS (FEB
2016)
52.223-4 RECOVERED MATERIAL CERTIFICATION (MAY 2008)
52.236-28 PREPARATION OF PROPOSALS—CONSTRUCTION (OCT 1997)
52.203-2 Certificate of Independent Price Determination (APR 1985)
52.204-8 -- ANNUAL REPRESENTATIONS AND CERTIFICATIONS (JAN 2018)
52.204-20 Predecessor of Offeror (JUL 2016)
52.204-24 Representation Regarding Certain Telecommunications and Video Surveillance Services or Equipment (Dec 2019)
52.204-26 Covered Telecommunications Equipment or Service-Representation (Dec 2019)
52.209-5 Certification Regarding Responsibility Matters (Oct 2015)
52.222-22 Previous Contracts and Compliance Reports (FEB 1999)
52.225-10 Notice of Buy American Requirement—Construction Materials (MAY 2014)
SECTION L – INSTRUCTIONS, CONDITIONS AND NOTICES TO OFFERORS
PROVISIONS OR CLAUSES INCORPORATED BY REFERENCE IAW FAR 52.252-1 OR 52.252-2:
52.204-7 SYSTEM FOR AWARD MANAGEMENT (JUL 2013)
52.204-16 COMMERCIAL AND GOVERNMENT ENTITY CODE REPORTING (JUL 2016)
52.204-18 COMMERCIAL AND GOVERNMENT ENTITY CODE MAINTENANCE (JUL 2015)
52.204-22 – ALTERNATIVE LINE ITEM PROPOSAL (JAN 2017)
52.222-5 CONSTRUCTION WAGE RATE REQUIREMENTS—SECONDARY SITE OF THE WORK (MAY
2014)
52.232-13 NOTICE OF PROGRESS PAYMENTS (APR 1984)
52.216-1 -- TYPE OF CONTRACT (APR 1984)
52.222-5 Construction Wage Rate Requirements—Secondary Site of the Work (MAY 2014)
52.222-23 Notice of Requirement for Affirmative Action to Ensure Equal Employment Opportunity for Construction (FEB 1999)
52.233-2 -- SERVICE OF PROTEST (SEP 2006)
52.236-27 -- SITE VISIT (CONSTRUCTION) ALTERNATE I (FEB 1995)
QUESTIONS
PROPOSAL DELIVERY:
SECTION L: INSTRUCTIONS, CONDITIONS, AND NOTICES TO OFFERORS
SECTION M: EVALUATION FACTORS FOR AWARD
SECTION A – SOLICITATION/CONTRACT FORM
This SECTION represents the Solicitation/Contract Form, which includes the SF 1442 - SOLICITATION, OFFER, AND AWARD Document, and its associated pages.
SECTION B – SUPPLIES OR SERVICES AND PRICES
CONTRACT
LINE ITEM
NUMBER
(CLIN)
CONTRACT LINE ITEM (CLI)
TITLE QUANTITY UNIT OF
MEASURE UNIT PRICE TOTAL PRICE
10 Base Bid – Restoration of the Cupola 1 LS
CONTRACT FIRM-FIXED PRICE GRAND TOTAL:
NOTES:
ALL WORK SHALL BE IAW SECTION C - PROJECT SPECIFICATIONS, PROJECT DRAWINGS,
AND OTHER DOCUMENTS.
SEE SECTION L - INSTRUCTIONS FOR THE SUBMISSION OF OFFERS AND OTHER
INFORMATION, FOR PROPOSAL SUBMISSION INSTRUCTIONS AND PROPOSAL FORMAT.
SECTION C – DESCRIPTIONS/SPECIFICATIONS/STATEMENT OF WORK
The subject Solicitation 140P4220R0014, consists of the following construction services to be performed at Mansion Cupola, located at the Hampton National Historic Site (HAMP), Towson, MD.
Restoration of the cupola, including but not limited to: Restoration of the cupola, including but not limited to: removal and replacement of slate roof at perimeter of the cupola, restoration of the rusticated wood base, restoration of the entablature and embedded columns, restoration of wood windows, replacement of the cedar roof, replacement of the metal roofs (flat-seam and standing seam) and restoration of the upper and lower finials.The Project Specifications and drawings consists of the documents attached in the SECTION J - LIST OF ATTACHMENTS.
This acquisition is being conducted per the procedures authorized in Part 15 of the Federal Acquisition Regulations (FAR). The term "bid" and "bidder" (wherever noted), shall mean "Proposal" and "Offeror”, or “Contractor".
SECTION D – PACKAGING AND MARKING
Not applicable.
SECTION E – INSPECTION AND ACCEPTANCE
52.246-12 INSPECTION OF CONSTRUCTION (AUG 1996)
(a) Definition. “Work” includes, but is not limited to, materials, workmanship, and manufacture and fabrication of components.
(b) The Contractor shall maintain an adequate inspection system and perform such inspections as will ensure that the work performed under the contract conforms to contract requirements. The Contractor shall maintain complete inspection records and make them available to the Government. All work shall be conducted under the general direction of the Contracting Officer and is subject to Government inspection and test at all places and at all reasonable times before acceptance to ensure strict compliance with the terms of the contract.
(c) Government inspections and tests are for the sole benefit of the Government and do not—
(1) Relieve the Contractor of responsibility for providing adequate quality control measures;
(2) Relieve the Contractor of responsibility for damage to or loss of the material before acceptance;
(3) Constitute or imply acceptance; or
(4) Affect the continuing rights of the Government after acceptance of the completed work under paragraph (i) of this section.
(d) The presence or absence of a Government inspector does not relieve the Contractor from any contract requirement, nor is the inspector authorized to change any term or condition of the specification without the Contracting Officer’s written authorization.
(e) The Contractor shall promptly furnish, at no increase in contract price, all facilities, labor, and material reasonably needed for performing such safe and convenient inspections and tests as may be required by the Contracting Officer. The Government may charge to the Contractor any additional cost of inspection or test when work is not ready at the time specified by the Contractor for inspection or test, or when prior rejection makes reinspection or retest necessary. The Government shall perform all inspections and tests in a manner that will not unnecessarily delay the work. Special, full size, and performance tests shall be performed as described in the contract.
(f) The Contractor shall, without charge, replace or correct work found by the Government not to conform to contract requirements, unless in the public interest the Government consents to accept the work with an appropriate adjustment in contract price. The Contractor shall promptly segregate and remove rejected material from the premises.
(g) If the Contractor does not promptly replace or correct rejected work, the Government may—
(1) By contract or otherwise, replace or correct the work and charge the cost to the Contractor; or
(2) Terminate for default the Contractor’s right to proceed.
(h) If, before acceptance of the entire work, the Government decides to examine already completed work by removing it or tearing it out, the Contractor, on request, shall promptly furnish all necessary facilities, labor, and material. If the work is found to be defective or nonconforming in any material respect due to the fault of the Contractor or its subcontractors, the Contractor shall defray the expenses of the examination and of satisfactory reconstruction. However, if the work is found to meet contract requirements, the Contracting Officer shall make an equitable adjustment for the additional services involved in the examination and reconstruction, including, if completion of the work was thereby delayed, an extension of time.
(i) Unless otherwise specified in the contract, the Government shall accept, as promptly as practicable after completion and inspection, all work required by the contract or that portion of the work the Contracting Officer determines can be accepted separately. Acceptance shall be final and conclusive except for latent defects, fraud, gross mistakes amounting to fraud, or the Government’s rights under any warranty or guarantee.
(End of clause)
SECTION F – DELIVERIES OR PERFORMANCE
PROVISIONS OR CLAUSES INCORPORATED BY REFERENCE IAW FAR 52.252-1 OR 52.252-2:
52.242-14 -- SUSPENSION OF WORK (APR 1984)
52.211-10 COMMENCEMENT, PROSECUTION, AND COMPLETION OF WORK (APR 1984)
The Contractor shall be required to (a) commence work under this contract within 10 calendar days after the date the Contractor receives the notice to proceed, (b) prosecute the work diligently, and (c) complete the entire work ready for use not later than 365 calendar days from issuance of the notice to proceed. The time stated for completion shall include final cleanup of the premises.
SECTION G – CONTRACT ADMINISTRATION DATA
1452.201-70 AUTHORITIES AND DELEGATIONS (SEPT 2011)
(a) The Contracting Officer is the only individual authorized to enter into or terminate this contract, modify any term or condition of this contract, waive any requirement of this contract, or accept nonconforming work.
(b) The Contracting Officer will designate a Contracting Officer's Representative (COR) at time of award. The COR will be responsible for technical monitoring of the contractor's performance and deliveries. The COR will be appointed in writing, and a copy of the appointment will be furnished to the Contractor. Changes to this delegation will be made by written changes to the existing appointment or by issuance of a new appointment.
(c) The COR is not authorized to perform, formally or informally, any of the following actions:
(1) Promise, award, agree to award, or execute any contract, contract modification, or notice of intent that changes or may change this contract;
(2) Waive or agree to modification of the delivery schedule;
(3) Make any final decision on any contract matter subject to the Disputes Clause;
(4) Terminate, for any reason, the Contractor's right to proceed;
(5) Obligate in any way, the payment of money by the Government.
(d) The Contractor shall comply with the written or oral direction of the Contracting Officer or authorized representative(s) acting within the scope and authority of the appointment memorandum. The Contractor need not proceed with direction that it considers to have been issued without proper authority. The Contractor shall notify the Contracting Officer in writing, with as much detail as possible, when the COR has taken an action or has issued direction (written or oral) that the Contractor considers to exceed the COR's appointment, within 3 days of the occurrence. Unless otherwise provided in this contract, the Contractor assumes all costs, risks, liabilities, and consequences of performing any work it is directed to perform that falls within any of the categories defined in paragraph (c) prior to receipt of the Contracting Officer's response issued under paragraph (e) of this clause.
(e) The Contracting Officer shall respond in writing within 30 days to any notice made under paragraph (d) of this clause. A failure of the parties to agree upon the nature of a direction, or upon the contract action to be taken with respect thereto, shall be subject to the provisions of the Disputes clause of this contract.
(f) The Contractor shall provide copies of all correspondence to the Contracting Officer and the COR.
(g) Any action(s) taken by the Contractor, in response to any direction given by any person acting on behalf of the
Government or any Government official other than the Contracting Officer or the COR acting within his or her appointment, shall be at the Contractor's risk.
(End of clause)
DOI Local Clause: Electronic Invoicing and Payment Requirements - Invoice Processing Platform (IPP) (April 2013)
Payment requests must be submitted electronically through the U. S. Department of the Treasury's Invoice Processing Platform System (IPP).
"Payment request" means any request for contract financing payment or invoice payment by the Contractor. To constitute a proper invoice, the payment request must comply with the requirements identified in the applicable Prompt Payment clause included in the contract, or the clause 52.212-4 Contract Terms and Conditions - Commercial Items included in commercial item contracts. The IPP website address is: https://www.ipp.gov.
Under this contract, the following documents are required to be submitted as an attachment to the IPP invoice:
a. Proper invoice. A complete copy of each invoice, which includes the Contract award number, period of performance, invoice number, Contractor name and address, and all other required documents must be attached in IPP.
b. The Contractor’s request should be submitted to the Contracting Officer’s Representative (COR) and to the Contracting Officer concurrently. Each request for progress payments should include the following substantiation:
(i) An itemization of the amounts requested, related to the various elements of work required by the contract covered by the payment requested.
(ii) A listing of the amount included for work performed by each subcontractor under the contract.
(iii) A listing of the total amount of each subcontract under the contract.
(iv) A listing of the amounts previously paid to each such subcontractor under the contract.
(v) Additional supporting data in a form and detail required by the Contracting Officer, as applicable.
c. Contractor certification. Along with each request for progress payments, the Contractor shall furnish the following certification, or payment shall not be made:
I hereby certify, to the best of my knowledge and belief, that --
(1) The amounts requested are only for performance in accordance with the specifications, terms, and conditions of the contract;
(2) All payments due to subcontractors and suppliers from previous payments received under the contract have been made, and timely payments will be made from the proceeds of the payment covered by this certification, in accordance with subcontract agreements and the requirements of chapter 39 of Title 31, United States Code;
(3) This request for progress payments does not include any amounts which the prime contractor intends to withhold or retain from a subcontractor or supplier in accordance with the terms and conditions of the subcontract; and
(4) This certification is not to be construed as final acceptance of a subcontractor’s performance.
The Contractor must use the IPP website to register access and use IPP for submitting requests for payment. The Contractor Government Business Point of Contact (as listed in SAM) will receive enrollment instructions via email from the Federal Reserve Bank of Boston (FRBB) within 3 - 5 business days of the contract award date. Contractor assistance with enrollment can be obtained by contacting the IPP Production Helpdesk via email ippgroup@bos.frb.org or phone (866) 973-3131.
If the Contractor is unable to comply with the requirement to use IPP for submitting invoices for payment, the Contractor must submit a waiver request in writing to the Contracting Officer with its proposal or quotation.
(End of Local Clause)
Contract Administration
Contracting Personnel responsible for administering this contract:
L.J. Gravelle, Contract Officer NPS Interior Region 1, North Atlantic - Appalachian 791 Baltimore St.
Gettysburg, PA 17325 Phone: 717.338.4481 LJ_Gravelle@nps.gov
SECTION H – SPECIAL CONTRACT REQUIREMENTS
SPECIAL CLAUSE 1: KEY PERSONNEL
(a) The Contractor shall assign to this contract the following key personnel:
Prime Contractor Project Manager Site Superintendent Quality Control Supervisor
Subcontractors (Trades) Carpentry Wood Shingle Roofing Slate Roofing Sheet Metal Roofing Wood Window Restoration Plastering Lightning Protection
(b) During the first 90 days of performance, the Contractor shall make no substitutions of key personnel unless the substitution is necessitated by illness, death, or termination of employment. The Contractor shall notify the Contracting Officer within 15 calendar days after the occurrence of any of these events and provide the information required by paragraph (c) below. After the initial 90-day period, the Contractor shall submit the information required by paragraph (c) to the Contracting Officer at least 15 days prior to making any permanent substitutions.
(c) The Contractor shall provide a detailed explanation of the circumstances necessitating the proposed substitutions, complete resumes for the proposed substitutes, and any additional information requested by the Contracting Officer.
Proposed substitutes should have comparable qualifications to those of the persons being replaced. The Contracting Officer will notify the Contractor within 15 calendar days after receipt of all required information of the decision on substitutions. This clause will be modified to reflect any approved changes of key personnel.
(End of clause)
CONTRACT WORK HOURS (NOV 2007)
The performance period established for this contract is based upon all work being conducted during regular working hours. Regular working hours are limited to the time between 8:00 am to 4:30 pm Monday through Friday, excluding Government holidays. If the Contractor desires to carry on work outside regular hours, including Saturdays, Sundays, and Government holidays, a request must be submitted to the Contracting Officer’s Representative in sufficient time to allow satisfactory arrangements to be made by the Government for access to the work site and inspection.
(End of Clause)
CONSTRUCTION WAGE RATES
DOL Wage Rates apply for this project and are attached to this document (reference Section J). The project is located in Baltimore County in Maryland.
(End of Clause)
SEASONAL SHUTDOWN
(a) It is recognized that seasonal climatic conditions regularly occur that restrict and in some cases prohibit normal construction activities. The actual timing of a seasonal shutdown will be determined by mutual agreement between the Contractor and the Contracting Officer. The Contractor shall give the Contracting Officer at least two weeks’ notice prior to the anticipated resumption of work. The actual date that work is resumed is subject to the approval of the Contracting Officer. The amount of time during a seasonal shutdown is taken into consideration when the completion time as stated in the Contract is determined. Therefore, the contract time will not be extended due to seasonal shutdowns.
(End of clause)
NOTICE TO CONTRACTORS CONTRACTOR PERFORMANCE ASSESSMENT
REPORTING SYSTEM (DECEMBER 2015)
1. FAR 42.1502 directs all Federal agencies to collect past performance information on contracts. The Department of the Interior (DOI) has implemented the Contractor Performance Assessment Reporting System (CPARS) to comply with this regulation. One or more past performance evaluations will be conducted in order to record your contract performance as required by FAR 42.15.
2. The past performance evaluation process is a totally paperless process using CPARS. CPARS is a web-based system that allows for electronic processing of the performance evaluation report. Once the report is processed, it is available in the Past Performance Information Retrieval System (PPIRS) for Government use in evaluating past performance as part of a source selection action.
3. We request that you furnish the Contracting Officer (CO) with the name, position title, phone number, and email address for each person designated to have access to your firm's past performance evaluation(s) for the contract no later than 30 days after award. Each person granted access will have the ability to provide comments in the Contractor portion of the report and state whether or not the Contractor agrees with the evaluation, before returning the report to the Assessing Official (AO). Information in the report must be protected as source selection sensitive information not releasable to the public.
4. When your Contractor Representative(s) are registered in CPARS, they will receive an automatically generated email with detailed login instructions. Further details, systems requirements, and training information for CPARS is available at https://www.cpars.gov/.
5. Within 60 days after the end of a performance period, the AO will complete an interim or final past performance evaluation, and the report will be accessible at https://www.cpars.gov/.
a. Contractor Representatives may then provide comments in response to the 6.evaluation, or return the evaluation without comment.
b. Your comments should focus on objective facts in the AO's narrative and should a)provide your views on the causes and ramifications of the assessed performance.
c. All information provided should be reviewed for accuracy prior to submission.
d. If you elect not to provide comments, please acknowledge receipt of the evaluation by indicating
"No comment" in the space provided, and then selecting “Accept the Ratings and Close the Evaluation”.
e. Your response is due within 60 calendar days after receipt of the CPAR. On day 15, the evaluation will become available in PPIRS-RC marked as “Pending” with or without comments and whether or not it has been closed.
f. If you do not sign and submit the CPAR within 60 days, it will automatically be returned to the Government and will be annotated: "The report was delivered/received by the contractor on (date). The contractor neither signed nor offered comment in response to this assessment."
6. The following guidelines apply concerning your use of the past performance evaluation:
Protect the evaluation as source selection information. After review, transmit the evaluation by completing and submitting the form through CPARS. If for some reason you are unable to view and/or https://www.acquisition.gov/sites/default/files/current/far/html/Subpart%2042_15.html https://www.acquisition.gov/sites/default/files/current/far/html/Subpart%2042_15.html https://www.cpars.gov/ https://www.cpars.csd.disa.mil/ https://www.cpars.gov/ submit the form through CPARS, contact the CO for instructions.
a. Strictly control access to the evaluation within your organization. Ensure the evaluation is never released to persons or entities outside of your control.
b. Prohibit the use of or reference to evaluation data for advertising, promotional material, pre-award surveys, responsibility determinations, production readiness reviews, or other similar purposes.
7. If you wish to discuss a past performance evaluation, you should request a meeting in writing to the CO no later than seven days following your receipt of the evaluation. The meeting will be held in person or via telephone or other means during your 60-day review period.
A copy of the completed past performance evaluation will be available in CPARS for your viewing and for Government use supporting source selection actions after it has been finalized.
(End of Notice)
SPECIAL REQUIREMENTS FOR CORONAVIRUS PANDEMIC (COVID-19)
1. Contractors are responsible for their employees’ safety and the safety of job site visitors during the performance of this contract. We encourage contractors to follow guidance from the Department of Labor, Occupational Safety and Health Administration (OSHA), the Centers for Disease Control and Prevention (CDC), and all other applicable local, city, and state mandates. We encourage contractors to develop policies for infection prevention and an Infectious Disease Preparedness and Response Plan.
2. To the extent appropriate, Contractors should include the protective health and safety measures they intend to implement related to COVID-19 in any accident prevention or safety submittals required under this contract.
These plans should contain preventive measures the contractor intends to follow while performing work on government property as well as responsive and corrective actions to be taken if an employee exhibits symptoms or tests positive for COVID-19.
3. Upon contract award, contractors should communicate with the Contracting Officer regarding contractor decisions and actions to protect the health and safety of workers for the duration of contract performance under which pandemic conditions exist.
4. The following websites provide additional guidance and information:
a) https://www.coronavirus.gov/
b) https://www.osha.gov/SLTC/covid-19/
c) https://www.cdc.gov/coronavirus/2019-ncov/index.html
d) https://www.cdc.gov/coronavirus/2019-ncov/community/organizations/construction-workers.html
e) https://www.fema.gov/coronavirus
f) https://www.nps.gov/aboutus/news/public-health-update.htm
(End of Notice) https://www.coronavirus.gov/ https://www.osha.gov/SLTC/covid-19/ https://www.cdc.gov/coronavirus/2019-ncov/index.html https://www.cdc.gov/coronavirus/2019-ncov/community/organizations/construction-workers.html https://www.fema.gov/coronavirus https://www.nps.gov/aboutus/news/public-health-update.htm
SECTION I – CONTRACT CLAUSES
PROVISIONS OR CLAUSES INCORPORATED BY REFERENCE IAW FAR 52.252-1 OR 52.252-2:
52.202-1 DEFINITIONS (JUN 2020)
52.203-3 GRATUITIES (APR 1984)
52.203-5 COVENANT AGAINST CONTINGENT FEES (MAY 2014)
52.203-6 RESTRICTIONS ON SUBCONTRACTOR SALES TO THE GOVERNMENT (JUN 2020)
52.203-7 ANTI-KICKBACK PROCEDURES (JUN 2020)
52.203-8 CANCELLATION, RESCISSION AND RECOVERY OF FUNDS FOR ILLEGAL OR IMPROPER ACTIVITY (MAY 2014)
52.203-10 PRICE OR FEE ADJUSTMENT FOR ILLEGAL OR IMPROPER ACTIVITY (MAY 2014)
52.203-12 LIMITATION ON PAYMENT TO INFLUENCE CERTAIN FEDERAL TRANSACTIONS (JUN 2020)
52.203-17 CONTRACTOR EMPLOYEE WHISTLEBLOWER RIGHTS AND REQUIREMENT TO INFORM EMPLOYEES
OF WHISTLEBLOWER RIGHTS (JUN 2020)
52.203-19 – PROHIBITION ON REQUIRING CERTAIN INTERNAL CONFIDENTIALITY AGREEMENTS OR
STATEMENTS (JAN 2017)
52.204-4 PRINTED OR COPIED DOUBLE SIDED ON POSTCONSUMER FIBER CONTENT PAPER (MAY 2011)
52.204-10 REPORTING EXECUTIVE COMPENSATION AND FIRST TIER SUBCONTRACT AWARDS (JUN 2020)
52.204-13 SYSTEM FOR AWARD MANAGEMENT MAINTENANCE (JUL 2016)
52.204-14 SERVICE CONTRACT REPORTING REQUIREMENTS (OCT 2016)
52.204-25 PROHIBITION ON CONTRACTING FOR CERTAIN TELECOMMUNICATIONS AND VIDEO SURVEILLANCE
SERVICES OR EQUIPMENT
52.209-6 PROTECTING THE GOVERNMENT'S INTEREST WHEN SUBCONTRACTING WITH CONTRACTORS
DEBARRED, SUSPENDED, OR PROPOSED FOR DEBARMENT (JUN 2020)
52.209-10 PROHIBITION ON CONTRACTING WITH INVERTED DOMESTIC CORPORATIONS (NOV 2015)
52.215-2 AUDIT AND RECORDS-NEGOTIATION (JUN 2020)
52.215-8 ORDER OF PRECEDENCE – UNIFORM CONTRACT FORMAT (OCT 1997)
52.219-6 NOTICE OF TOTAL SMALL BUSINESS SET-ASIDE (NOV 2011)
52.219-8 UTILIZATION OF SMALL BUSINESS CONCERNS (NOV 2016)
52.219-14 LIMITATIONS ON SUBCONTRACTING (NOV 2011)
52.219-28 POST AWARD SMALL BUSINESS PROGRAM REPRESENTATIONS (MAY 2020)
52.222-3 CONVICT LABOR (JUN 2003)
52.222-4 CONTRACT WORK HOURS AND SAFETY STANDARDS ACT - OVERTIME COMPENSATION (MAY 2014)
52.222-6 CONSTRUCTION WAGE RATES REQUIREMENT (MAY 2014)
52.222-7 WITHHOLDING OF FUNDS (MAY 2014)
52.222-8 PAYROLLS AND BASIC RECORDS (MAY 2014)
52.222-10 COMPLIANCE WITH COPELAND ACT REQUIREMENTS (FEB 1988)
52.222-11 SUBCONTRACTS (LABOR STANDARDS) (MAY 2014)
52.222-12 CONTRACT TERMINATION - DEBARMENT. (MAY 2014)
52.222-13 COMPLIANCE WITH DAVIS-BACON AND RELATED ACT REGULATIONS (MAY 2014)
52.222-14 DISPUTES CONCERNING LABOR STANDARDS (FEB 1988)
52.222-15 CERTIFICATION OF ELIGIBILITY (MAY 2014)
52.222-21 PROHIBITION OF SEGREGATED FACILITIES (APR 2015)
52.222-23 NOTICE OF REQUIREMENT FOR AFFIRMATIVE ACTION TO ENSURE EQUAL EMPLOYMENT
OPPORTUNITY FOR CONSTRUCTION (FEB 1999)
52.222-26 EQUAL OPPORTUNITY (SEPT 2016)
52.222-27 AFFIRMATIVE ACTION COMPLIANCE REQUIREMENTS FOR CONSTRUCTION (APR 2015)
52.222-37 EMPLOYMENT REPORTS ON VETERANS (JUN 2020)
52.222-40 NOTIFICATION OF EMPLOYEE RIGHTS UNDER THE NATIONAL LABOR RELATIONS ACT (DEC 2010)
52.222-50 COMBATING TRAFFICKING IN PERSONS (MAY 2015)
52.222-54 EMPLOYMENT ELIGIBILITY VERIFICATION (OCT 2015)
52.222-55 MINIMUM WAGES UNDER EXECUTIVE ORDER 13658 (DEC 2015)
52.222-62 PAID SICK LEAVE UNDER EXECUTIVE ORDER 13706 (JAN 2017)
52.223-2 AFFIRMATIVE PROCUREMENT OF BIOBASED PRODUCTS UNDER SERVICE AND CONSTRUCTION
CONTRACTS (SEPT 2013)
52.223-3 HAZARDOUS MATERIAL IDENTIFICATION AND MATERIAL SAFETY DATA. (JAN 1997) - ALTERNATE I
(JUL 1995)
52.223-5 POLLUTION PREVENTION AND RIGHT-TO-KNOW INFORMATION (MAY 2011)
52.223-6 DRUG-FREE WORKPLACE (MAY 2001)
52.223-17 AFFIRMATIVE PROCUREMENT OF EPA-DESIGNATED ITEMS IN SERVICE AND CONSTRUCTION
CONTRACTS (MAY 2008)
52.223-18 ENCOURAGING CONTRACTOR POLICIES TO BAN TEXT MESSAGING WHILE DRIVING (JUN 2020)
52.225-13 RESTRICTIONS ON CERTAIN FOREIGN PURCHASES (JUN 2008)
52.227-1 AUTHORIZATION AND CONSENT (JUN 2020)
52.227-2 NOTICE AND ASSISTANCE REGARDING PATENT AND COPYRIGHT INFRINGEMENT (JUN 2020)
52.227-4 PATENT INDEMNITY-CONSTRUCTION CONTRACTS (DEC 2007)
52.228-2 ADDITIONAL BOND SECURITY (OCT 1997)
52.228-5 INSURANCE - WORK ON A GOVERNMENT INSTALLATION (JAN 1997)
52.228-11 PLEDGES OF ASSETS (JAN 2012)
52.228-12 PROSPECTIVE SUBCONTRACTOR REQUESTS FOR BONDS (MAY 2014)
52.228-14 IRREVOCABLE LETTER OF CREDIT MAY 2014)
52.228-15 PERFORMANCE AND PAYMENT BONDS - CONSTRUCTION (JUN 2020)
52.229-3 FEDERAL, STATE, AND LOCAL TAXES (FEB 2013)
52.232-5 PAYMENTS UNDER FIXED-PRICE CONSTRUCTION CONTRACTS (MAY 2014)
52.232-16 PROGRESS PAYMENTS (JUN 2020)
52.232-17 INTEREST (MAY 2014)
52.232-23 -- ASSIGNMENT OF CLAIMS (MAY 2014)
52.232-27 PROMPT PAYMENT FOR CONSTRUCTION CONTRACTS (MAY 2014)
52.232-33 PAYMENT BY ELECTRONIC FUNDS TRANSFER – SYSTEM FOR AWARD MANAGEMENT (JUL 2013)
52.232-39 UNENFORCEABILITY OF UNAUTHORIZED OBLIGATIONS (JUN 2013)
52.232-40 PROVIDING ACCELERATED PAYMENTS TO SMALL BUSINESS SUBCONTRACTORS (DEC 2013)
52.233-1 DISPUTES. (MAY 2014) - ALTERNATE I (DEC 1991)
52.233-3 PROTEST AFTER AWARD (AUG 1996)
52.233-4 APPLICABLE LAW FOR BREACH OF CONTRACT CLAIM (OCT 2004)
52.236-2 DIFFERING SITE CONDITIONS (APR 1984)
52.236-3 SITE INVESTIGATION AND CONDITIONS AFFECTING THE WORK (APR 1984)
52.236-5 MATERIAL AND WORKMANSHIP (APR 1984)
52.236-8 OTHER CONTRACTS (APR 1984)
52.236-9 PROTECTION OF EXISTING VEGETATION, STRUCTURES, EQUIPMENT, UTILITIES, AND
IMPROVEMENTS (APR 1984)
52.236-10 OPERATIONS AND STORAGE AREAS (APR 1984)
52.236-11 USE AND POSSESSION PRIOR TO COMPLETION (APR 1984)
52.236-12 CLEANING UP (APR 1984)
52.236-13 ACCIDENT PREVENTION (NOV 1991)
52.236-14 AVAILABILITY AND USE OF UTILITY SERVICES (APR 1984)
52.236-15 SCHEDULES FOR CONSTRUCTION CONTRACTS (APR 1984)
52.236-17 LAYOUT OF WORK (APR 1984)
52.236-21 SPECIFICATIONS AND DRAWINGS FOR CONSTRUCTION (FEB 1997)
52.236-26 PRECONSTRUCTION CONFERENCE (FEB 1995)
52.242-13 BANKRUPTCY (JUL 1995)
52.243-4 CHANGES (JUN 2007)
52.244-6 SUBCONTRACTS FOR COMMERCIAL ITEMS (JUN 2020)
52.246-21 WARRANTY OF CONSTRUCTION (MAR 1994)
52.248-3 VALUE ENGINEERING-CONSTRUCTION-ALTERNATE I (OCT 2015)
52.249-2 TERMINATION FOR CONVENIENCE OF THE GOVERNMENT (FIXED-PRICE). (APR 2012) ALT I (SEPT 1996)
52.249-10 DEFAULT (FIXED-PRICE CONSTRUCTION) (APR 1984)
52.253-1 COMPUTER GENERATED FORMS (JAN 1991)
52.222-9 APPRENTICES AND TRAINEES (JUL 2005)
(a) Apprentices.
(1) An apprentice will be permitted to work at less than the predetermined rate for the work performed when employed—
(i) Pursuant to and individually registered in a bona fide apprenticeship program registered with the U.S. Department of Labor, Employment and Training Administration, Office of Apprenticeship Training, Employer, and Labor Services (OATELS) or with a State Apprenticeship Agency recognized by the OATELS; or
(ii) In the first 90 days of probationary employment as an apprentice in such an apprenticeship program, even though not individually registered in the program, if certified by the OATELS or a State Apprenticeship Agency (where appropriate) to be eligible for probationary employment as an apprentice.
(2) The allowable ratio of apprentices to journeymen on the job site in any craft classification shall not be greater than the ratio permitted to the Contractor as to the entire work force under the registered program.
(3) Any worker listed on a payroll at an apprentice wage rate, who is not registered or otherwise employed as stated in paragraph (a)(1) of this clause, shall be paid not less than the applicable wage determination for the classification of work actually performed. In addition, any apprentice performing work on the job site in excess of the ratio permitted under the registered program shall be paid not less than the applicable wage rate on the wage determination for the work actually performed.
(4) Where a Contractor is performing construction on a project in a locality other than that in which its program is registered, the ratios and wage rates (expressed in percentages of the journeyman’s hourly rate) specified in the Contractor’s or subcontractor’s registered program shall be observed. Every apprentice must be paid at not less than the rate specified in the registered program for the apprentice’s level of progress, expressed as a percentage of the journeyman hourly rate specified in the applicable wage determination.
(5) Apprentices shall be paid fringe benefits in accordance with the provisions of the apprenticeship program. If the apprenticeship program does not specify fringe benefits, apprentices must be paid the full amount of fringe benefits listed on the wage determination for the applicable classification. If the Administrator determines that a different practice prevails for the applicable apprentice classification, fringes shall be paid in accordance with that determination.
(6) In the event OATELS, or a State Apprenticeship Agency recognized by OATELS, withdraws approval of an apprenticeship program, the Contractor will no longer be permitted to utilize apprentices at less than the applicable predetermined rate for the work performed until an acceptable program is approved.
(b) Trainees.
(1) Except as provided in 29 CFR 5.16, trainees will not be permitted to work at less than the predetermined rate for the work performed unless they are employed pursuant to and individually registered in a program which has received prior approval, evidenced by formal certification by the U.S. Department of Labor, Employment and Training Administration, Office of Apprenticeship Training, Employer, and Labor Services (OATELS). The ratio of trainees to journeymen on the job site shall not be greater than permitted under the plan approved by OATELS.
(2) Every trainee must be paid at not less than the rate specified in the approved program for the trainee’s level of progress, expressed as a percentage of the journeyman hourly rate specified in the applicable wage determination.
Trainees shall be paid fringe benefits in accordance with the provisions of the trainee program. If the trainee program does not mention fringe benefits, trainees shall be paid the full amount of fringe benefits listed in the wage determination unless the Administrator of the Wage and Hour Division determines that there is an apprenticeship program associated with the corresponding journeyman wage rate in the wage determination which provides for less than full fringe benefits for apprentices. Any employee listed on the payroll at a trainee rate who is not registered and participating in a training plan approved by the OATELS shall be paid not less than the applicable wage rate in the wage determination for the classification of work actually performed.