Section C – Descriptions and Specifications

PERFORMANCE WORK STATEMENT

0100000 – General Information

Spec Item
Title
Description
1
General Information
1.1
Overview
The base scope of this project is to completely demolish 6 facilities and restore the sites. The project will consist of complete facility demolition, including the total removal of all foundations, removal and disposal of all utilities, site amenities, and associated site features. Demolition will include the termination of all site utilities (water, power, telecommunications etc.). Hazardous material testing and containment will be performed at all sites prior to the start of demolition. Site restoration activities will include back filling, grading and seeding the disturbed sites. A listing and brief description of the facilities to be demolished are as follows:

· Building 370 – Rocket Laboratory - an existing one-story building, with an attic, on a slab on grade. The building footprint is approximately 2,200 square feet. This building acted as an explosive research facility. It houses multiple storage rooms and two toilet rooms. This building was built in 1944 as a rocket laboratory. There was an addition and renovation done to the building in 1991.

· Building 370A – Magazine (adjacent to Building 370) - an existing one-story building, on a slab on grade. The building footprint is approximately 175 square feet. This building acted as a magazine for the explosive research facility. It is a single room building. This building was built in 1944.

· Building 370B – Boiler House (adjacent to Building 370) - an existing one- story building, on a slab on grade. The building footprint is approximately 150 square feet. The building acted as a boiler house for the explosive research facility. The building was built in 1944.

· Building 409 – Magazine/Weighing Room (adjacent to Building 370) - an existing one story structure comprised of two Quonset hut-like structures partially built into grade with a 6” concrete slab. The footprints of the two structures are approximately 195 square feet and 130 square feet. The structures have a concrete retaining wall at their faces and extending out perpendicular from the faces. This building acted as a magazine and weighing room for the explosive research facility. This building was built in 1948.

· Building 462 – Systems Integration Lab - an existing one story structure comprised of a Quonset hut-like structure with a 6” concrete slab. The footprint of the structure is approximately 1,365 square feet. The structure has a 6” concrete turn down foundation walls and a 2’-0” wide concrete steam trench. This building acted as an Interior Ballistic Lab and later as a Weapons System Integration Lab. This building was built in 1949.

· Building 1352 – Storage/Test Fixture Assembly Building (adjacent to Building 370) – an existing one-story building, on a slab on grade. The building footprint is approximately 150 square feet. This building acted as a RDT&E Storage Facility and Test Fixture Assembly Building. It is a single room building. This building was built in 1975.

1.2
Project Location
All work is to take place at Naval Support Activity South Potomac (NSASP) Dahlgren, VA for Buildings 370, 370A, 370B, 409, 462 and 1352. Exact locations are listed in J- C.1.001.
1.3
Acquisition of Additional Work
The Government reserves the right to acquire additional services at additional locations in addition to the services and locations identified in the recurring work requirements of this contract. Additional services will be incorporated into the contract in accordance with the CHANGES clause, SECTION I or ordered under the indefinite delivery indefinite quantity provisions of the contract. Items of work not covered by this contract but within the general intent are considered in the scope of this contract.
1.4
Background Information
The Naval Support Activity South Potomac (NSASP) Dahlgren, VA encompasses 4,000 acres in King George County. The NSASP is a Test and Evaluation Center for Naval Research and Development.
1.5
Verification of Workload and Conditions
Throughout the PWS, the workload data is generally referred to as being located in Section J. Section J provides data such as inventories, maps, floor plans, and tables to represent the type, quantity and location of services to be provided. However, offerors are encouraged to visit the project site during the site visit for offerors and to visit the technical library during posted hours as part of its due diligence to assess the nature of work and conditions under which work is to be performed.
1.6
Climate Patterns
See NOAA website for climate information
1.7
Related Information
There are four types of Related Information that can be found in the Description and Related Information columns of the specification as follows:

Informational Notes as used throughout this PWS provides additional information to offerors to be used in developing a thorough understanding of the work to be performed in this contract. Any block of text marked “Informational Notes” throughout Annexes 1 through 18 is subject to this disclaimer. Offerors may not rely upon the "Informational Notes" as material representations of the Government. Information provided in "Informational Notes" does not create a contractual requirement on either party to this contract.

Clarifying Information describes client expectations in a more detailed manner than the Performance Objective and Performance standard alone.

Constraining Information describes limitations to the work performed to meet the Performance Objective and Performance Standard.

Requirement Information further describes client requirements associated with each Performance Objective.

1.8
Navy Approach to Service Contracting
The Department of Navy (DoN) spends over $1 billion in annual obligations to meet global requirements for facility operations and maintenance provided through Facility Support Contracts (FSC) and additional billions to provide other base operations support services (OBOS). The Head of the Contracting Activity (HCA) of the Naval Facilities Engineering Command (NAVFAC) has focused increased attention on re-engineering FSC contracts in response to customer and industry feedback, budget constraints, and the impact of a variety of contracting, program management and financial management regulations. The Navy also supports the following principles:
1.8.1
Partnering Philosophy
The first principle is that the Navy views its contractors as partners and not just abstract service providers. The Navy wants its contractors to succeed because partners' success drives the Navy's successful mission completion. Within the bounds of acquisition policy the Navy intends to work to find solutions that will be beneficial to both the Government and its partners.
1.8.2
Contractor's Knowledge
The second principle is that the Navy will receive insightful management from its contractors. This management will include the knowledge, skills, authority and willingness to use contractor resources to find better ways of serving Navy clients’ strategic and operational goals and objectives. The Navy's use of performance-based objectives evidences this principle. Although performance work statements will typically contain several levels of performance assessment, the Navy wants its contractors to exercise maximum discretion within bounds of prudent risk management to adjust processes and resources needed to reach specified objectives at the highest performance level.
1.8.3
Industry Best Practices
The third principle is that the Navy will adopt industry best commercial practices and maintain state-of-the-art service delivery. It is the Navy's and contractor's responsibility as partners to reach this goal. To that end, the Navy's emphasis will be in evaluating performance objectives (end results).
1.9
Standard Template
Key to implementing a programmatic approach is using a standard template that ensures Navy-wide consistency yet affords appropriate tailoring to meet local needs. This contract conforms to the standard template and has been tailored for this solicitation. NAVFAC intends to use this template-based approach for future service contracts. Offerors should develop an understanding of the template as part of performing due diligence in reaching an understanding of the Navy’s requirements and expectations.

The standard template contains 18 standard annexes. Annex 1 will always contain information that is relevant to the entire scope of the contract. Annex 2 contains on-site project management and administration requirements that are relevant to the entire scope of the contract. Annexes 3 through 18 contain the technical information and requirements peculiar to that technical annex. Within each technical annex, the organization of information and requirements are also standardized. Specification item 1 will always contain General Information. Specification item 2 will always contain the management and administrative requirements. Specification item 3 will always contain the Recurring Work requirements. Specification item 4 will always contain the Non-Recurring Work requirements. Requirements and standards for higher level specification items apply to all subordinate specification items, e.g., Specification Item 3 standards apply to all recurring work specification items. Specification Item 3.1 is applicable to all 3.1 subordinate specification items. Specification Items 3.2 and 3.3 are not considered subordinate to 3.1. All costs associated with Annexes 1 and 2 and Specification items 1 and 2 must be priced and distributed within Specification Item 3 of Annexes 3 through 18.

1.10
Navy PBSA Approach
The Navy’s approach to performance-based service acquisition (PBSA) includes four component parts which are 1) performance outcomes, 2) measurable standards, 3) consideration of incentives, and 4) performance assessment plan.
1.11
General Requirements
The Contractor shall provide all labor, management, supervision, tools, materials, equipment, incidental engineering, disposal, the compilation and submission of all documentation required by this contract, and transportation necessary to demolish facilities as described herein and on contract drawings.
1.11.1
Site Demolition Work
Existing building utility connections, including water, power and communications shall be removed from the building/tower back to the nearest supplying manholes or transformers and water/sanitary sewer lines removed back to main lines and suitably plugged or capped at the removal limits.

Utility demolition and removal must be coordinated with on-site personnel for planned outages. Contractor personnel shall allow at least two weeks for outage request approvals prior to performing the work.

Existing sidewalks, pavements and other associated features will be completely removed. (On the site visit, the Customer has decided to keep all existing pavement around the site to remain in-place.)

Contractor shall install and maintain sediment and erosion control measures, such as, silt fence and storm water inlet protection prior to the start of site demolition work.

1.11.2
Building/Structure Demolition Work
Demolish the structures to include the tower truss, porches, stairs and landings, walls,

Structures shall be demolished in a systematic manner, from the top of the structure to the ground.

Mechanical Work:

Remove all mechanical, plumbing, and fire protection systems and equipment completely, including but not limited to: air compressor units, exhaust fans, unit heaters, pumps, water heaters, air handling equipment, sprinkler system components, ductwork and diffusers, mechanical and plumbing piping, valves, control components, panels and wiring. Remove any existing, external, above-ground piping routing to facility and support structures.

Remove air conditioning, refrigeration, and other equipment containing refrigerants without releasing chlorofluorocarbon refrigerants to the atmosphere in accordance with the Clean Air Act Amendment of 1990. Recover all refrigerants prior to removing any air conditioning, refrigeration, and other equipment containing refrigerants and dispose of in accordance with Class I and Class II ODS as defined in Section 602 (a) and (b) of the Clean Air Act. Place recovered ODS in cylinders meeting AHRI Guidelines K suitable for type ODS (filled to no more than 80% capacity)and provide appropriate labeling and turn into the Navy as directed by the Contracting Officer.

Electrical Work:

Remove all electrical systems and equipment completely, including but not limited to lighting, receptacles, disconnects, electrical wiring and conduit.

1.11.3
Contractor Cleanup
Contractor shall be responsible for and not limited to:

· Providing necessary safety to protect any adjacent existing buildings, landscape and associated features.

· Cleaning up debris on project site at the end of each working day.

· Properly dispose of removed materials and debris at completion of project.

· Disposal of demolished material and equipment.

1.11.4
Site Restoration
Contractor shall be responsible for and not limited to:

· After completion of the demolition, all disturbed areas shall be re-graded to restore natural drainage patterns and returned to open turf cover with topsoil or clean fill and seeding. The demolition site shall be compacted, graded and free from protrusions, demolition debris and abrupt edges.

· Once seed is established and approval is given by the Environmental Department Representative, Contractor shall remove sediment and erosion control devices.

1.11.5
General Hazardous Component Abatement
Reports, performed in 1990, identify that ACM are not present in the facility. A report for each of the following: asbestos, lead based paint, mercury, and PCBs will need to be performed to support this project. The General Contractor is required to hire, as a first tier subcontractor, a PQP to ensure compliance with the approved work plans and perform independent inspections, testing and verification of the hazardous components work including: asbestos, lead containing paint, mercury containing equipment, LLR components, PCBs, animal droppings, molds and spores.

During the site visit, it was discovered that asbestos tiles (9” x 9”) were discovered in Building 370, under the existing 12” x 12” VCT tiles. The 9” x 9” tiles also contain asbestos mastic/glue to adhere the tiles to the concrete floor. It was also noted that Building 370A (Boiler Room) has a below-grade fuel oil tank (500 Gallon) that needs to emptied, cleaned, removed and transported off-site. Additionally, the steam pipes both underground in the steam trench and aboveground going from Building 370A to Building 1352 could possibility have asbestos containing materials.

1.11.6
General Explosive Contamination Abatement
Structures, in which explosive materials have been managed and/or stored, may contain explosive residues hidden within cracks, crevices, under flooring, in ventilation ducts, behind wall panels, etc. Friction or impact from dismantling the structural components can present a potential detonation hazard that must be evaluated and addressed prior to dismantling/demolition operations. The decommissioning and demolition of an explosives contaminated structure may present unobvious hazards requiring application of specialized knowledge and expertise as well as implementation of established regulatory safety programs. Consequently, the decommissioning and demolition of structures should be preceded by a comprehensive planning process and be conducted in accordance with both established and project-specific safety procedures. This process shall include a Safety and Environmental Hazard Review and Site Inspection, Work Plan Development, Obtain Permits, Gain Approval, Implementation of Work Plan, Test Debris and Soil for Reactivity/Toxicity. Activities involving ammunition and explosives or their constituents or chemical warfare agents have additional requirements as specified in EM 385-1-97, Explosives Safety and Health Requirements Manual. If tests show no reactivity/toxicity in debris and soil, then maintain a complete written project report. Properly dispose of nonhazardous non-combustible materials. If tests show reactivity/toxicity in debris and soil, dispose of materials in accordance with applicable Hazardous Waste Regulations.

Structures Containing Blasting Agents: Decontamination of structures that have contained blasting agents composed of high percentages of water soluble, hygroscopic salts such as ammonium nitrate and fuels may be achieved by sweeping or other physical means. Water wash down usually results in the safe decontamination of this building category. In certain cases, collecting and treating the wash down water may be required. Open burning is not recommended for this explosives contaminated building category. Structures Containing Black Powder and Pyrotechnic Mixtures: Decontamination of black powder and similar pyrotechnic mixtures may also be achieved by mechanical cleaning followed by water wash down. However, due to the ease of ignition after drying, burning is recommended for this building category.

Structures Containing Other Explosive Chemicals and Compounds: Water insoluble molecular explosives such as nitroglycerin, tetryl, TNT, PETN, RDX, and HMX require special decontamination and dismantling procedures. These procedures may include sweeping and physical removal followed by steam cleaning of equipment and the use of solvents, such as acetone, or a desensitizing oil prior to the removal of threaded fittings. Trinitroresorcinol, lead styphnate, lead azide, mercury fulminate and other initiating explosives are quite sensitive to initiation by heat, impact and friction. These materials present the supplemental problem of residual metal contamination after the criteria of reactivity is eliminated. Structures that have contained these two groups of explosives require soil monitoring to assure complete, safe closure of the site. Bioremediation or ash and soil removal may be required. It is highly recommended that buildings used to manufacture or process any of these two groups of explosives be burned to eliminate possible hazards associated with reactive materials that may have accumulated in cracks, crevices or larger spaces within the floors and walls.

Unexploded Ordinance (UXO)/Munitions & Explosives of Concern (MEC) Monitoring & Clearance: The project sites are located within the Range limits of NSA South Potomac Dahlgren and therefore, require UXO/MEC monitoring and clearance. The approved work plan and DB specifications will need to indicate the area to be monitored and include the pertinent conditions and constraints that will be imposed on the Construction Contractor. The project locations will require all of the site clearance and/or excavation work to be monitored by a qualified/certified UXO Technician and/or coordinated with a Government provided MEC Contractor via the NAVFAC KO.

0200000 – Management and Administration

Table of Contents

Spec Item
Title
2
Management and Administration
2.1
Definitions and Acronyms
2.2
General Information
2.2.1
Government Regular Working Hours
2.2.1.1
Observed Federal Holidays
2.2.1.2
Restriction to Contractor Working Hours
2.2.2
Wage Determinations
2.2.3
Requirements Hierarchy
2.3
General Administrative Requirements
2.3.1
Required Conferences and Meetings
2.3.2
Partnering
2.3.2.1
Formal Partnering
2.3.2.2
Contract Partnering Administration
2.3.2.3
Contract Partnering Session Attendees
2.3.3
Permits and Licenses
2.3.4
Insurance
2.3.4.1
Certificate of Insurance
2.3.4.2
Minimum Insurance Amounts
2.3.5
Protection of Government Property
2.3.6
Government Information Technology (IT) System
2.3.7
Directives, Instructions, and References
2.3.8
Base Map
2.3.9
Invoicing Procedures
2.4
Government-Furnished Property, Materials and Services
2.4.1
Government-Furnished Facilities (GFF)
2.4.2
Government-Furnished Utilities
2.4.2.1
Other Utilities
2.4.3
Government-Furnished Materials (GFM)
2.4.4
Government-Furnished Equipment (GFE)
2.4.5
Government-Furnished Services (GFS)
2.5
Contractor-Furnished Items
2.6
Management
2.6.1
Work Control
2.6.2
Work Schedule
2.6.3
Deliverables
2.6.4
Service Interruptions
2.6.5
Quality Management System (QMS)
2.6.5.1
Quality Management (QM) Plan
2.6.5.2
Quality Inspection and Surveillance
2.6.5.3
Quality Inspection and Surveillance Report
2.7
Personnel Requirements
2.7.1
Key Personnel
2.7.1.1
Project Manager (PM)
2.7.1.2
Quality Manager
2.7.1.3
Site Safety and Health Officer (SSHO)
2.7.1.4
Environmental/Energy Manager
2.7.1.5
Archeological Consultant
2.7.2
Employee Requirements
2.7.2.1
Employee Certification and Training
2.7.2.2
Employee Appearance
2.7.2.3
Employee Conduct
2.7.2.4
Identification as Contractor Employee
2.7.2.5
Removal of Employees
2.7.2.6
Proof of Legal Residency
2.7.3
Enterprise-wide Contractor Manpower Reporting Application (eCMRA)
2.8
Security Requirements
2.8.1
Employee Listing
2.8.2
Vehicles
2.8.3
Passes and Badges
2.8.4
Access to Installation
2.8.4.1
DBIDS Program
2.8.4.2
DBIDS Paper Pass
2.8.5
Access to Buildings
2.8.6
Access Arrangements
2.8.6.1
Escort Arrangement for Secured Areas
2.8.7
Employ Status
2.9
Contractor Safety Program
2.9.1
Accident Prevention Plan (APP)
2.9.2
Activity Hazard Analysis (AHA)
2.9.3
Safety and Occupational Health (SOH) Risks and Compliance Plans
2.9.3.1
Alcohol and Drug Abuse Prevention Plan
2.9.3.2
Chemical Hazard Communication Program
2.9.3.3
Confined Space Program
2.9.3.4
Critical Lift Plan
2.9.3.5
Fall Prevention and Protection Plan
2.9.3.6
Demolition Plan
2.9.3.7
Asbestos Abatement Plan
2.9.3.8
Respiratory Protection Plan
2.9.3.9
Lead Abatement Compliance Plan
2.9.4
Crane Operations
2.9.4.1
Crane Inspections
2.9.4.2
Rigging Gear
2.9.4.3
Crane Operators
2.9.5
Accident and Damage Reporting
2.9.5.1
Accident Reporting and Notification Criteria
2.9.5.2
Recordable Injuries or Illnesses
2.9.5.3
High Visibility Accident
2.9.5.4
Medical Treatment
2.9.5.5
WHE Accident
2.9.6
Fire Protection
2.9.7
Monthly On-Site Labor Report
2.9.8
OSHA Citations and Violations
2.9.9
Safety Inspections and Monitoring
2.9.10
Safety Certification
2.9.11
Safety Apparel on Jobsites
2.9.12
Emergency Medical Treatment
2.9.13
Excavations
2.9.13.1
Excavation Permit
2.9.13.2
Notification Prior to Excavation

2.9.13.3

Sediment Control and Storm Water Management

2.9.14
Explosives
2.10
Environmental Management and Sustainability
2.10.1
Water Conservation Plan
2.10.2
Environmental Protection
2.10.2.1
ODS Requirements for Refrigerant Recycling
2.10.2.2
Non-Hazardous Waste Disposal
2.10.2.3
Hazardous Waste Disposal
2.10.2.4
Spill Prevention, Containment, and Clean-up
2.10.2.5
Hazardous Material Management
2.10.2.6
Protection of Endangered and Threatened Species (Flora and Fauna)
2.10.2.7
Noise Control
2.10.2.8
Salvage
2.10.2.9
Asbestos Containing Material (ACM)
2.10.2.10
Mold Containing Material (MCM)
2.10.3
Sustainable Procurement and Practices
2.10.3.1
Environmentally Preferable Products
2.10.3.2
Use of Recovered Materials
2.10.3.3
Use of Bio based Products
2.11
Disaster Preparedness
2.12
Protection of Historical, Archaeological, and Natural Resources
2.13
Air Quality
2.14
Safe Drinking Water Act

0200000 - Management and Administration

Spec Item
Title
Description
2
Management and Administration
2.1
Definitions and Acronyms
Definitions and Acronyms are listed in J-0200000-01.
2.2
General Information
2.2.1
Government Regular Working Hours
The Government's regular working hours are from 0700-1630, five days per week, Monday through Friday, except observed Federal holidays. Exceptions to the regular hours of operation are detailed in subsequent sections of this PWS. Work in certain annexes or sub-annexes require Contractor continuous operations, 24 hours a day, every day of the year including holidays. The performance of other work requirements shall be accomplished within the Government’s regular working hours unless the specific work requirement specified herein necessitates otherwise. Any other work outside Government regular working hours requires prior KO approval.
2.2.1.1
Observed Federal Holidays
The Government observes the following holidays: New Year’s Day, Martin Luther King Jr.’s Birthday, President’s Day, Memorial Day, Independence Day, Labor Day, Columbus Day, Veterans’ Day, Thanksgiving Day, and Christmas Day.
2.2.1.2
Restriction to Contractor Working Hours
If the Contractor wishes to work outside of the Government's regular working hours for the Contractor’s convenience, the Contractor shall submit a written Request to Work Outside Government’s Regular Working Hours per Section F. Excludes work to be performed during specified hours.
2.2.2
Wage Determinations
Wage Determinations are included in J-0200000-02.
2.2.3
Requirements Hierarchy
Requirements or definitions specified in each spec item of this contract apply to subordinate paragraphs. For example, requirements shown in spec item 3.1 would apply to spec items 3.1.1, 3.1.2, 3.1.2.1 and so on.

Likewise, Performance Standards specified at a lower digit level (i.e. spec item 3.1.1, 3.1.2, 3.1.2.1) apply when performance is assessed at a higher tier (i.e., spec item 3.1) based on the composite work requirements.

2.3
General Administrative Requirements
2.3.1
Required Conferences and Meetings
The Contractor may be required to attend administrative and coordination meetings.
2.3.2
Partnering
To increase the likelihood of successful performance of this contract, the Government requires cohesive partnerships with its Contractors and subcontractors. Key stakeholders, including the supported commands who will receive services, principal individuals from NAVFAC, the performance assessment team, and representative(s) of the installation(s) will be invited to participate in the partnering process. Key members of the prime and subcontractor’s teams, including senior management personnel must participate. The partnership will draw on the strength of each organization in an effort to achieve quality contract services done right the first time, within the contract price, as scheduled, and without any safety mishaps.

Partnering should accomplish three goals:

- The first goal is to develop a cohesive team with common purpose, commitment and established communication processes.

- The second goal of partnering is contract specific, identifying risks and opportunities for the team to address.

- The third goal is to sustain the Partnership throughout the contract by identifying and addressing issues that affect the Partnership.

2.3.2.1
Informal Partnering
The Contracting Officer shall organize the initial Partnering Meeting with key personnel of the project team, including Contractor's personnel and Government personnel. The initial session will be scheduled concurrent with the Pre-Performance Conference and held no later than 30 days after award and will be held at a Government provided facility as designated by the KO.

The Initial Informal Partnering Session will be conducted and facilitated using electronic media (a video and accompanying forms) provided by Contracting Officer. The senior Government stakeholder present will lead the meeting, however, the Contractor’s PM or senior representative is encouraged to participate as co-lead.

The Partners will determine the frequency of the follow-on sessions.

2.3.2.2
Contract Partnering Administration
Upon award, the ACO will contact the Contractor, supported command(s), Region, and Installation(s) stakeholders, and the performance assessment team to discuss implementation of partnering. Commence discussions with the Contractor to select a facilitator and location that are acceptable to both partners. A partnership agreement, The Charter, should be in place as early as possible so issues arising, even before work begins, can be resolved using the issues resolution process. Replacement of Core Management Team members (stakeholders who attended the initial session and manage the contract work day-to-day) is discouraged since it will disrupt the synergy that has been developed. If replacement of a team member proves to be unavoidable, a follow-on partnering session must be held to officially turn the responsibilities of the position over to the new member.

The Core Management Team consisting of the attendees below must be present during the initial and all follow-on partnering sessions. These are the core mandatory attendees. Other stakeholders may attend if they desire or as recommended by the partners.

2.3.2.3
Contract Partnering Session Attendees

The Contractor shall bring the necessary personnel to successfully partner on this contract. Asterisk indicates mandatory personnel.

* President/Vice President

* Project Manager

* Quality Manager

* Site Safety and Health Officer

2.3.3
Permits and Licenses
The Contractor shall obtain all required permits, licenses, and authorizations to perform work under this contract and comply with all the applicable Federal, state and local laws and regulations.

The Contractor shall submit copies of Permits and Licenses per Section F.

The Contractor must maintain/provide the necessary licensed personnel to repair/maintain all systems within this contract to include but not limited to: HVAC, Exhaust Hoods, Fire Protection Systems, Boilers, DDC, etc. Personnel repairing/maintaining DDC systems shall have the appropriate certifications to conduct work on Johnson and Siemens systems and other systems in this contract.

2.3.4
Insurance
The Contractor shall submit a Certificate of Insurance per Section F as evidence of the existence of the following insurance coverage in amounts not less than the amounts specified below in accordance with the FAR Clause 52.228-5, INSURANCE – WORK ON A GOVERNMENT INSTALLATION. This insurance must be maintained during the performance period.
2.3.4.1
Certificate of Insurance
The Certificate of Insurance shall provide for at least 30 calendar days’ written notice to the KO by the insurance company prior to cancellation or material change in policy coverage. Other requirements and information are contained in the aforementioned insurance clause.
2.3.4.2
Minimum Insurance Amounts
The Contractor shall procure and maintain, during the entire period of performance under this contract, the following minimum insurance coverage:

Comprehensive General Liability: $500,000 per occurrence

Automobile Liability: $200,000 per person, $500,000 per occurrence, $20,000 per occurrence for property damage

Workmen's Compensation: As required by Federal and state worker's compensation and occupational disease statutes

Employer's Liability coverage: $100,000, except in states where worker's compensation may not be written by private carriers

Other as required by state law.

2.3.5
Protection of Government Property
During execution of the work, the Contractor shall protect Government property. The Contractor shall return areas damaged as a result of negligence under this contract to their original condition at no cost to the Government.
2.3.6
Government Information Technology (IT) System
Additional information about NMCI may be obtained at http://www.dxc.technology.
2.3.7
Directives, Instructions, and References
Department of Defense (DoD), Secretary of the Navy (SECNAV), Chief of Naval Operations (OPNAV), and other applicable Directives, Instructions, and References are listed in J-0200000-03. The Contractor shall comply with the most current version of directives, instructions, and references including versions published during the term of the contract.
2.3.8
Base Maps
See J-0200000-04 for maps.
2.3.9
Invoicing Procedures
Refer to Section G,
2.4
Government-Furnished Property, Materials and Services
In accordance with FAR 52.245, GOVERNMENT PROPERTY and NAVFAC Clause 5252.245-9300, GOVERNMENT-FURNISHED PROPERTY, MATERIALS AND SERVICES, and the following paragraphs, the Government will furnish or make available to the Contractor certain Government-owned facilities, utilities, materials, equipment and services for use in connection with this contract as stated below.
2.4.1
Government-Furnished Facilities (GFF)
A list of Government Furnished Facilities is provided in J-0200000-05.
2.4.2
Government-Furnished Utilities
The Government will furnish water and electricity at existing outlets required for the work to be performed under the contract at no cost to the Contractor. Information concerning the location of existing outlets may be secured from the KO. The Contractor shall provide and maintain, at its expense, the necessary service lines from the existing Government outlets to the work site. Contractor shall provide and maintain backflow prevention devices on connections to domestic water lines and electrical transformer provisions on connections to electric lines. Contractor shall meet all Federal, State, local, and installation codes and regulations for backflow prevention devices and electrical transformer provisions. Services required by the Contractor, for which there are no available Government outlets, shall be provided by the Contractor at no cost to the Government.
2.4.2.1
Other Utilities
Except as specified in this clause, the Contractor shall make arrangements to obtain all utilities at its expense
2.4.3
Government-Furnished Materials (GFM)
No Government Furnished Materials provided.
2.4.4
Government-Furnished Equipment (GFE)
No Government Furnished Equipment provided.
2.4.5
Government-Furnished Services (GFS)
No Government Furnished Services provided.
2.5
Contractor-Furnished Items
Except for items identified as Government Furnished, the Contractor shall provide all equipment, materials, parts, supplies, components, and facilities to perform the requirements of this contract. The KO may inspect Contractor-furnished items for adequacy and compliance with contract requirements. Inadequate or unsafe items shall be removed and replaced by the Contractor at no cost to the Government. Materials containing asbestos, lead, and polychlorinated biphenyls (PCBs) shall not be brought onsite. Energy efficient tools and equipment shall be used when available. The KO may at any time require Samples, Material Safety Data Sheets (MSDS) or Manufacturer’s Data Cut Sheets of Materials used in this contract.
2.6
Management
The Contractor shall manage the total work effort associated with the services required herein to meet the performance objectives and standards. Such management includes but is not limited to planning, scheduling, cost accounting, report preparation, establishing and maintaining records, and quality assurance. The Contractor shall provide a staff with the necessary management expertise to ensure performance objectives and standards are met.

The Contractor shall submit a Work Management Plan per Section F.

2.6.1
Work Control
The Contractor shall implement all necessary work control procedures to ensure timely accomplishment of work requirements, as well as to permit tracking and reporting of work in progress. The Contractor shall plan and schedule work to assure material, labor, and equipment are available to complete work requirements within the specified time limits and in conformance with the quality standards established herein. Verbal scheduling and work status updates shall be provided when requested by the KO. A status update of any item of work must be provided within two hours of the inquiry during regular working hours, and by 0800 the following work day for inquiries after regular working hours.
2.6.2
Work Schedule
The Contractor's work shall not interfere with normal Government business. In those cases, where some interference is unavoidable, the Contractor shall minimize the impact and effects of the interference. The Contractor shall provide advance access of all of its work schedules to the Government. The Contractor shall notify the KO of any difficulty in scheduling work due to Government controls.
2.6.3
Deliverables
Records and reports are specified in Section C and listed as deliverables in Section F. The Contractor shall submit accurate and complete documents within the required timeframes as specified in Section F.

Government acceptance of deliverables will not relieve the Contractor of the responsibility for any error or omission which may exist in the deliverable, as the Contractor is responsible for all requirements of this contract.

The Contractor shall establish and maintain a secure website for posting an electronic copy of all deliverables listed in Section F. The Contractor shall allow only authorized Government and Contractor personnel to access the website. Government personnel access shall be limited to viewing and downloading of deliverables, but restricted from posting to the website. The Contractor shall notify the Government by email whenever there are new or updated deliverables posted to the website. Each deliverable posting on the website and each email notification shall include the title of the deliverable, the spec item requiring the deliverable, and the date and time the deliverable was posted. All deliverables shall be available to authorized Government personnel 24 hours/day and 365 days/year for the duration of the contract.

2.6.4
Service Interruptions
If any utilities or other services must be discontinued (even temporarily) due to scheduled contract work, the Contractor shall notify the KO, COR, affected tenants, and customers in accordance with local procedures. If the discontinued service is due to an emergency breakdown the Contractor shall notify the KO, COR, affected tenants and customers as soon as practicable.

The Facilities & Energy Operations Cell (FEOC), located at the Washington Navy Yard, must be kept informed of all service interruptions including location, system, impacted buildings, timeframes, and any reference ticket, maintenance, or task order associated.

2.6.5

Quality Management System (QMS)
The Contractor shall establish and maintain a complete QMS program in accordance with the provisions specified herein. The Contractor’s QMS program shall provide an effective and efficient means of identifying and correcting problems throughout the entire scope of operations. The Contractor's QMS program shall address:

· Accurate documentation of work processes, procedures, and output measures.

· A systematic procedure for assessing compliance with performance objectives and standards.

· Accurate documentation of quality inspections and surveillance conducted throughout the execution of work.

· Assessment-driven corrective actions and process adjustments as appropriate in a timely manner.

2.6.5.1
Quality Management (QM) Plan
The Contractor shall develop and submit a QM Plan per Section F. The QM Plan shall describe the QMS methodology and approaches used under this contract. If any changes are made during the period of performance, submit to the KO a revised QM Plan for acceptance.

The Contractor’s QM Plan shall include, at a minimum, the following:

· Policy and objectives of Quality Management System (QMS)

· Quality organization

· List of personnel

· Responsibilities & lines of authority

· Training and qualifications

· Approach to assuring quality of services provided and conformance with performance objectives and standards

· Methods and procedures for effective planning, operation and control of processes and performance of work

· Procedures for inspection and surveillance of services

· Scheduling and performance of inspection and surveillance

· Measurement, data collection and analysis

· Corrective action, preventive action, and continuous improvement

· Oversight of subcontracted work

· Documentation and records management

· Communication with government (customers)

2.6.5.2
Quality Inspection and Surveillance
The Contractor shall establish and maintain an inspection and surveillance system in accordance with the FAR Clause 52.246-4, INSPECTION OF SERVICES – FIXED PRICE, to ensure that the work performed conforms to the contract requirements. The Contractor shall document and maintain a file of all scheduled and performed inspections and surveillances, inspection and surveillance results, and dates and details of corrective and preventive actions. The quality inspection and surveillance file shall be the property of the Government and made available during the Government’s regular working hours. The file shall be turned over to the KO within five calendar days of termination of the contract.
2.6.5.3
Quality Inspection and Surveillance Report
The Contractor shall submit a copy of the Contractor Quality Inspection and Surveillance Report per Section F. The Contractor Quality Inspection and Surveillance Report shall include a summary and results of the quality inspection and surveillance events performed and assessment-driven corrective actions and process adjustments during the previous month. The Government may adjust the frequency of the submittal based on the Contractor’s quality of performance.
2.6.8
System and Equipment Replacement
The Contractor shall maintain the integrity and performance of existing energy saving, water conservation or other sustainability design features of systems and equipment in the performance of repair and replacement work. Except where otherwise specified, replacement components shall be of the same model/style or equivalent as the component being replaced. Substitutes for replacement components must be accepted by the KO prior to use. The KO will furnish available information for the existing systems and equipment.
2.7
Personnel Requirements
The Contractor shall comply with the personnel requirements stated below.
2.7.1
Key Personnel
The Contractor shall submit a List of Key Personnel and Qualifications per Section F. The Contractor shall provide any additional information requested by the KO necessary to certify their qualifications.

The Contractor shall submit an Organizational Chart per Section F showing lines of authority of the key personnel and on-site supervisor(s) for this contract. The chart shall include names of personnel and their position title in this contract. As a minimum, include the PM, Quality Manager, SSHO, and on-site supervisor(s) and who they will report directly to for this contract. The key personnel shall be revised as applicable for the contract.

2.7.1.1
Project Manager (PM)
The Contractor shall provide a PM and designated alternate, as applicable, who has the have full authority to act for the Contractor on all contract matters relating to this contract. The PM or alternate shall be available during the Government's regular working hours and shall be available within one hour after the Government's regular working hours.

The PM shall have at least five years of experience in managing a workforce providing services on contracts of similar size, scope and complexity.

2.7.1.2
Quality Manager
The Contractor shall provide a Quality Manager or designated alternate shall be on-site within during the Government's regular working hours and shall be available on-site within two hours after the Government’s regular working hours. The Quality Manager must report directly to a senior corporate official and shall not report directly to the Project Manager.

The Quality Manager shall have fulfilled the following pre-requisite training and experiences before being hired as the Quality Manager under this contract:

The Quality Manager shall have at least five years of experience in preparing and enforcing QMS programs on contracts of similar size, scope and complexity. The Quality Manager shall not be the same person as the SSHO.

2.7.1.3
Site Safety and Health Officer (SSHO)
The SSHO must meet the requirements of EM 385-1-1 Section 1 and ensure that the requirements of 29 CFR 1926.16 are met for the project. Provide a Safety oversight team that includes a minimum of one Competent Person at each project site to function as the Site Safety and Health Officer (SSHO). The SSHO or an equally-qualified Designated Representative/alternate shall be on-site at all times when work is being performed to implement and administer the Contractor's safety program and government-accepted Accident Prevention Plan. The SSHO's training, experience, and qualifications shall be as required by EM 385-1-1 paragraph 01.A.17, entitled SITE SAFETY AND HEALTH OFFICER (SSHO), and all associated sub-paragraphs.

A Competent Person shall be provided for all of the hazards identified in the Contractor's Safety and Health Program in accordance with the accepted Accident Prevention Plan, and shall be on-site at all times when the work that presents the hazards associated with their professional expertise is being performed. Provide the credentials of the Competent Persons(s) to the Contracting Officer for acceptance in consultation with the Safety Office.

The Contractor shall provide a SSHO whose primary duty and responsibility is to prepare and enforce the Contractor’s safety program on this contract. The SSHO shall have fulfilled the following pre-requisite training and experiences before being hired as the SSHO under this contract:

The SSHO shall have completed five years of satisfactory experience in preparing and enforcing safety programs on contracts of similar size and complexity in the past or three years’ experience if he possesses a Certified Safety Professional (CSP) or safety and health degree. The SSHO shall have completed the OSHA 30-hour construction safety class or equivalent and maintain competency through 24 hours of formal safety and health related coursework every four years. The SSHO shall not be the same person as the project manager.

2.7.1.4
Environmental/Energy Manager
The Contractor shall provide an Environmental/Energy Manager whose primary duty and responsibility is to ensure Contractor operations adhere to the goals and policies of the Environmental Management System, the Installation Energy Plan, and other specified Sustainability requirements affecting this contract. The Environmental/Energy Manager shall develop, implement and monitor environmental strategies, policies and programs that promote sustainable development and examine the contract activities to establish where improvements can be made and ensure compliance with environmental legislation and energy policy.

The Environmental/Energy Manager shall have a minimum two years experience with environmental procedures similar to those of this contract; familiarity with Environmental Management Systems (EMSs); and knowledge of environmental regulations and federal energy laws and policy (including energy and water reduction requirements and renewable energy requirements) that are applicable to operations similar to those of this contract.

2.7.1.5
Archeological Consultant
The contractor shall provide an archeological staff member or archeological consultant to advise and provide cultural resource and archeological support during the demolition of buildings 370, 370A, 370B, 409, and 462. These locations have been identified as cultural resource and/or archeological sites which may contain artifacts or other items of historical value. There are no known artifacts in the limits of disturbance for these locations slated for demolition, however it is strongly suspected that there are other archeological artifacts in the surrounding area. This consultant shall work with the government’s resident archeologist and the environmental department and State Historic Preservation Office (SHPO) to mitigate unneeded disturbances in order to prevent the unearthing of potential artifacts. This consultant shall be present at the site for whenever the contractor will be disturbing any earth at these locations.
2.7.2
Employee Requirements
The Contractor shall provide experienced, qualified, and capable personnel to perform the work in this contract. Personnel shall be fully knowledgeable of all safety, environmental, and energy requirements associated with the work they perform. Personnel shall speak, read, and comprehend English to the extent that they can perform the contract requirements and comply with installation emergency procedures.
2.7.2.1
Employee Certification and Training
The Contractor shall maintain personnel certification, training, and licensing records for employee requirements specified herein and within all technical annexes/sub-annexes. Certification, training, and licensing records shall be kept current and on file for the duration of the contract including all option periods. Records shall be made available for Government review within 4 hours of request.
2.7.2.2
Employee Appearance
The Contractor shall ensure that all employees present a professional appearance that is appropriate for their position. The KO reserves the right to determine the acceptability of any clothing worn. All Contractor/subcontractor employees working under this contract shall be identified by a distinctive nameplate, emblem, or patch attached in a prominent place on an outer garment. Employee identification shall not be substituted for station required passes or badges.
2.7.2.3
Employee Conduct
Contractor employees shall conduct themselves in a proper, efficient, courteous and businesslike manner.

With respect to the National Anthem, please see guidance below.

Weekday National Anthem Broadcast on Giant Voice System

The National Anthem will play at 8 a.m. over the "Giant Voice" public broadcast system installed on board all facilities on this contract. This will be the case every weekday morning, Monday through Friday. We are accustomed to hearing the National Anthem at sporting events or military ceremonies. Most Americans - through observation, if nothing else - know the proper response is to give our attention to the music, placing our hand over our heart, halting conversation and standing at attention until the music stops. Where does this etiquette come from? It has its roots in Navy Regulations (Article 1206) as well as U.S. Code Title 36, Section 301 regarding the National Anthem. The following protocol is directed during a rendition of the National Anthem. When the American flag is displayed, all present except those in uniform should stand at attention facing the flag with the right hand over the heart. Men not in uniform, wearing a hat, should remove their hat with their right hand and hold the hat at the left shoulder, the hand being over the heart.