SCB_AWRF_Generator_Controls_Switchgear_-_Bid_Form_(BLA_BLB)_Contracts_10-29-24.xlsx
XLSX spreadsheet 20 KB Posted
- Attached to
- SCB Replacement of Generator Controls and Switchgear (PID 004906DE) State and local contract opportunity
- Solicitation number
- 25-0073-ITB-C
- Issued by
- Pinellas County, Clewiston City, Florida
About this file
The document is a Bid Form for the Pinellas County Public Works Department's South Cross Bayou Advanced Waste Reclamation Facility (AWRF) Generator Controls and Switchgear Replacement project, located in Florida. The project involves removing and replacing two switchboard line-ups, including utility circuit breakers, generator circuit breakers, feeder circuit breakers, group mounted devices, and automatic failover systems. The bid (No. 25-0073-ITB-C) covers a comprehensive scope of work with nine primary line items, including mobilization, switchgear replacement for two separate systems (BLA and BLB), demolition of existing switchgear, SCADA HMI modification, temporary generator sets, arc flash risk assessment, O&M manuals, and project closeout documentation.
The total engineer's estimated project cost is $2,032,000, with significant allocations for switchgear replacement ($1,854,000), mobilization ($113,000), building permit allowance ($15,000), and unspecified funds ($50,000). The bid includes provisions for temporary equipment, technical documentation, and risk assessment, indicating a complex infrastructure upgrade project. The line items are priced as lump sum (LS) or per unit, with specific costs assigned to each component of the switchgear replacement and associated work. The project appears to be fully funded and ready for implementation, with detailed specifications for equipment replacement and system integration at the South Cross Bayou Advanced Waste Reclamation Facility.
View the file
Other files for this state and local contract opportunity
Show all 22
On GovTribe
Work with this file on GovTribe
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Bid Form BID NAME: SOUTH CROSS BAYOU AWRF GENERATOR CONTROLS AND SWITCHGEAR REPLACEMENT (BLA&BLB)
PID NO. 004906DE
BID NO. 25-0073-ITB-C
| Engineer's Estimate | |||||
| Pay Item No. | Description | Quantity | Unit | Unit Price | Amount |
| Utilites | |||||
| 1 | Mobilization / Demobilization | 1 | LS | 113,000.00 | $ 113,000.00 |
| Utilities Subtotal | $ 113,000.00 | ||||
| Switchgear Replacement/Demolition | |||||
| 3.1 | 3-1: Switchgear BLA | 1 | LS | 773,000.00 | $ 773,000.00 |
| 3.2 | 3-2: Switchgear BLB | 1 | LS | 773,000.00 | $ 773,000.00 |
| 3.3 | 3-3: Demolition of Exisiting Switchgear BLA | 1 | LS | 44,000.00 | $ 44,000.00 |
| 3.4 | 3-4: Demolition of Exisiting Switchgear BLB | 1 | LS | 44,000.00 | $ 44,000.00 |
| 3.5 | 3-5: Plant SCADA HMI Modification | 1 | LS | 20,000.00 | $ 20,000.00 |
| 3.6 | 3-6: Temporary Engine/Generator Sets, Fuel Tank and Cabling | 1 | LS | 86,000.00 | $ 86,000.00 |
| 3.7 | 3-7: Arc Flash Risk Assessment and Labeling | 1 | LS | 63,000.00 | $ 63,000.00 |
| 3.8 | 3-8: O&M Manuals and As-Built Drawings | 1 | LS | 25,000.00 | $ 25,000.00 |
| 3.9 | 3-9: Project Closeout Documents | 1 | LS | 26,000.00 | $ 26,000.00 |
| Switchgear Replacement/Demolition Subtotal | $ 1,854,000.00 | ||||
| Permits | |||||
| 2 | Building Permit Allowance | 15000 | EA | 1.00 | $ 15,000.00 |
| Permits Subtotal | $ 15,000.00 | ||||
| Unspecified Work | |||||
| 4 | Unspecified Funds | 50000 | EA | 1.00 | $ 50,000.00 |
| Unspecified Work Subtotal | $ 50,000.00 | ||||
| TOTAL | $ 2,032,000.00 |