Attachment_C2_Annual_Gate_PM_Gate_ _Barrier_PM's.xlsx
XLSX spreadsheet 14 KB Posted
- Attached to
- Perform Maintenance on Gates and Barriers Federal contract opportunity
- Solicitation number
- SB1341-16-RQ-1040
About this file
Attachment C2 Annual Gate PM Gate Barrier PM's
View the file
Other files for this federal contract opportunity
| File | Type | Posted |
|---|---|---|
| Amendment_02_Question_and_Answers_for_SB1341-16RQ-1040.pdf | ||
| Amendment_1-_RFQ-SB1341-16-RQ-1040-FormSF1449.pdf | ||
| Attachment_C4_Quarterly_Pop-up_PM_Gate_ _Barrier_PM's.xlsx | XLSX spreadsheet | |
| Attachment_C1_Monthly_Gate_PM_Gate_ _Barrier_PM's.xlsx | XLSX spreadsheet | |
| Attachment_B-Performance_Work_Statement_SB1341-16-RQ-1040.pdf | ||
| Attachment_C3_Monthly_Pop-up_PM_Gate_ _Barrier_PM's.xlsx | XLSX spreadsheet | |
| RFQ-SB1341-16-RQ-1040-FormSF1449.pdf | ||
| Attachment_A-SB1341-16-RQ-1040-Instructions_Offerors_and_Tech_Eval.pdf | ||
| Attachment_D_-_RFQ_Question_Submittal_Form.xlsx | XLSX spreadsheet | |
| Attachment_F_-_Past_Performance_Questionnaire_PPQ.docx | DOCX document | |
| Attachment_C5_Annual_Pop-up_PM_Gate_ _Barrier_PM's.xlsx | XLSX spreadsheet | |
| Attachment_E_-_Experience_Project_Data_Sheet.docx | DOCX document | |
| Attachment_C6_Lift_Master_Manual_Gate_ _Barrier_PM.pdf |
Show all 13
On GovTribe
Work with this file on GovTribe
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Sheet1
| jpnum | jpdesc | jptask | taskdesc | tasklongdesc |
| JP-MVGT-A | JOBPLAN MOTOR VEHICLE RAISING ARM GATE - ANNUAL | 1 | OBTAIN PM | Obtain PM from COTR. The PM may be issued in a handheld device or paper. |
| JP-MVGT-A | JOBPLAN MOTOR VEHICLE RAISING ARM GATE - ANNUAL | 3 | SCHEDULE THE PM | Schedule the PM with the COTR. NO equipment will be shut down without scheduling with the COTR. |
| JP-MVGT-A | JOBPLAN MOTOR VEHICLE RAISING ARM GATE - ANNUAL | 5 | REVIEW | Review all steps in PM. |
Review safety requirements for this equipment and space Review manufacturer's instructions and equipment history record, if available.
Maintenance operations must be carried out by qualified technicians in compliance with the safety warnings stated in Automatic Systems America, Inc., Technical Manual for model BL-229(High speed electrical rising barrier) Chapter 1.
| JP-MVGT-A | JOBPLAN MOTOR VEHICLE RAISING ARM GATE - ANNUAL | 7 | EQUIPMENT SHUTDOWN SAFETY | Maintenance operations must be carried out by qualified technicians in compliance with the safety warnings stated in Automatic Systems America, Inc., Technical Manual for model BL-229(High speed electrical rising barrier) Chapter 1. Shut-down is necessary; de-energize, tag, and lock out electrical circuits to motors, pumps, control circuits, etc and de-energize pressure in lines before working on equipment. |
| JP-MVGT-A | JOBPLAN MOTOR VEHICLE RAISING ARM GATE - ANNUAL | 9 | CHECK WITH OPERATING OR AREA PERSONNEL | Check with operating or area personnel for any deficiencies. |
| JP-MVGT-A | JOBPLAN MOTOR VEHICLE RAISING ARM GATE - ANNUAL | 10 | SECURE THE GATE LANE | Secure the gate lane that is to be tested so that there will be no vehicle traffic. |
Have Police/Security personnel insure that there are no persons with 25 feet of the gate/operator.
JP-MVGT-A JOBPLAN MOTOR VEHICLE RAISING ARM GATE - ANNUAL 20 RECORD CYCLES Unlock and remove the side panel without damaging the ground wire that connects it to the housing.
At the control board, go to �Counter 2� and record the number of cycles, then reset counter #2. Close and lock side panel.
| JP-MVGT-A | JOBPLAN MOTOR VEHICLE RAISING ARM GATE - ANNUAL | 30 | LOCKOUT/TAGOUT POWER | Lockout/tagout all power to gate operator. |
| JP-MVGT-A | JOBPLAN MOTOR VEHICLE RAISING ARM GATE - ANNUAL | 40 | CHECK THE BALANCE OF BOOM ARM WITH SPRING TENSION | The tension of the spring must be adjusted in such a way as to insure minimal effort for the motor |
both at the opening and the closing of the gate arm. See Automatic Systems America, Inc., Technical Manual for model BL-229(High speed electrical rising barrier) Chapter 4 for instructions.
JP-MVGT-A JOBPLAN MOTOR VEHICLE RAISING ARM GATE - ANNUAL 50 CHECKS Check the level of the arm, adjust as needed.
Check that all the nuts and screws of the mechanical unit are tight.
Check that all the electrical connections are tight.
| JP-MVGT-A | JOBPLAN MOTOR VEHICLE RAISING ARM GATE - ANNUAL | 55 | RESTORE POWER | Restore power to gate operator |
| JP-MVGT-A | JOBPLAN MOTOR VEHICLE RAISING ARM GATE - ANNUAL | 60 | FINAL TEST | The gate operator must be completely visible by maintenance personnel before being activated for testing. Have the security guard at the gate press the open button for the gate arm to raise, and then place the test appliance where the gate arm will strike it when closing. Once clear have the security guard press the close button. The gate arm MUST reverse on contact with the test appliance or stop dependent on the programming of the sensor. If it does not, the force or limit of travel will need to be adjusted and then retest the gate operator. See Automatic Systems America, Inc., Technical Manual for model BL-229(High speed electrical rising barrier) Chapter 4. Failure to adjust and retest the gate operator properly can increase the risk of injury or death. |
| JP-MVGT-A | JOBPLAN MOTOR VEHICLE RAISING ARM GATE - ANNUAL | 999 | COMPLETE PM | Complete the PM on handheld or paper; noting condition, suspect problems, parts used, gauge/meter readings, etc. |
NOTIFY COTR IF ANY EQUIPMENT REQUIRES REPLACEMENT AND NOTE ON PM.