J 10 Outline of Transition Plan.docx

DOCX document 13 KB Posted

Attached to
Accident and Sickness Program for Exchanges (ASPE)
Solicitation number
SAQMMA12R0261
Issued by

About this file

Outline of Transition Plan

View the file

Other files

File Type Posted
J 8 Resume Format Template.docx DOCX document
J 10 Outline of Transition Plan.docx DOCX document
J4 Past Performance Questionnaire.docx DOCX document
J 9 Acronym List.docx DOCX document
J 7 Invoice Summary Report Example.docx DOCX document
J 6 Standard Form 1034.far —
Final Sept 11 2012 ASPE SAQMMA12R0261.pdf PDF
MRPT Processing Procedures.pdf PDF
J 11 Past Performance Contract Profile.pdf PDF
J 1 SF3881_tmp91240.far —
J 1 SF3881_tmp91240.far —
J 6 Standard Form 1034.far —
J 9 Acronym List.docx DOCX document
J4 Past Performance Questionnaire.docx DOCX document
J 11 Past Performance Contract Profile.pdf PDF
J 8 Resume Format Template.docx DOCX document
J 7 Invoice Summary Report Example.docx DOCX document
J 10 Outline of Transition Plan.docx DOCX document
MRPT Processing Procedures.pdf PDF
Revised Solicitation SAQMMA12R0261 Aug 10.pdf PDF
MRPT Processing Procedures.pdf PDF
J 6 Standard Form 1034.far —
J4 Past Performance Questionnaire.docx DOCX document
J 1 SF3881_tmp91240.far —
J 9 Acronym List.docx DOCX document
Final Solicitiation SAQMMA12R0261.pdf PDF
J 7 Invoice Summary Report Example.docx DOCX document
J 8 Resume Format Template.docx DOCX document
J 11 Past Performance Contract Profile.pdf PDF
Show all 29

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

J.10 OUTLINE OF THE TRANSITION PLAN

The Transition Plan shall show the activities that need to be carried out to ensure smooth transitioning of applications, portfolio and services with minimal or no disturbance to the ASPE Program.

The total transition period shall not exceed 60 days from contract award.

The Transition Plan identifies all the scope, out-of scope items, all affected areas and documents the overall strategy of transitioning.

At a minimum, it shall include the following: Scope, Transition Strategy, Transition Schedule, Governance covering client and your team along with roles and responsibilities, communication plan, escalation process, Progress review meetings, status reporting, milestones clearly identified, risks, mitigation plan.

The transitioning strategy should include transition strategy for each functional area taking into consideration each line of business.

An example outline is shown below.

· Scope (in-scope and out of scope)

· Transitioning Strategy

· Roles and Responsibilities

· Applications services taking into account each functional area with business line

· Transition Schedule

· Risk Management Plan

· Knowledge transfer Calendar

· Receivables and Deliverables during each phase

· Transition Governance

· Governance Activities

· Communication with various parties

· Escalation Process

· Status Reporting

· Progress Review Meetings

· Team Meetings

· Milestones

· Resource Management Plan

· Training Process