This document summarizes a federal indefinite delivery/indefinite quantity construction multiple award task order contract opportunity and related sample task order special contract requirements.

The U.S. Army Corps of Engineers, New England District seeks to award a five-year $90 million ID/IQ MATOC for vertical and horizontal construction services to a target of six small businesses. Task orders will typically range from $500,000 to $10 million for repairs, renovations, and construction projects at military and federal agency facilities throughout New England and New York. The scope of work includes structural, mechanical, and civil systems as well as environmental abatement, testing, and commissioning. The district intends to use best value procurement and issue this solicitation in July 2020 to support customers such as the Air and Army National Guard, various federal agencies, and service branches. Sample task order requirements specify commencement timelines, liquidated damages, insurance, and performance standards.

View the file

Other files for this federal contract opportunity

Other files attached to Indefinite Delivery/Indefinite Quantity Construction Multiple Award Task Order Contract, newest first.
File Type Posted
W912WJ20R0005 0006.pdf PDF
W912WJ20R0005 0005.pdf PDF
WBS format for Sample Task Order_rev 5-28-2020.xlsx XLSX spreadsheet
Prime Binding Rates Excel Sheet_rev 5-28-20.xlsx XLSX spreadsheet
W912WJ20R0005-00004.pdf PDF
Attachment 0001 - Prime Binding Rates Excel Sheet_rev 5-18-20.xlsx XLSX spreadsheet
02 82 14.00 10 - B. 673 Asbestos Report - Merged.pdf PDF
WBS format for Sample Task Order Attachment.pdf PDF
W912WJ20R0005-0003.pdf PDF
W912WJ20R0005-0002.pdf PDF
W912WJ20R0005 0001.pdf PDF
Specifications - Sample TO.pdf PDF
00 41 00.doc DOC document
Sample Task Order Rates Excel Sheet.xlsx XLSX spreadsheet
Wage Determination MA20200013.pdf PDF
Prime Binding Rates Excel Sheet.xlsx XLSX spreadsheet
W912WJ20R0005 Solicitation.pdf PDF
Drawings - Sample TO.pdf PDF
Show all 18

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Interior Renovations, Building 673, Fort Devens, Massachusetts

SECTION 00 80 00

SPECIAL CONTRACT REQUIREMENTS

1.1 COMMENCEMENT, PROSECUTION AND COMPLETION OF WORK (APR 1984) FAR 52.211-10

The Contractor shall be required to:

(1) commence work under this contract within 15 calendar days after the date the Contractor receives the notice to proceed,

(2) prosecute the work diligently, and

(3) complete the entire work ready for use not later than 330 calendar days after the date the Contractor receives notice to proceed. The time stated for completion shall include final cleanup of the premises. See Subpart "Work Sequence" in Section 01 11 00 SUMMARY OF WORK.

1.2 LIQUIDATED DAMAGES - CONSTRUCTION (Sept 2000) FAR 52.211-12

(a) If the Contractor fails to complete the work within the time specified in the contract, the Contractor shall pay liquidated damages to the Government in the amount of $2,679.00 for each calendar day of delay until the work is completed or accepted.

(b) If the Government terminates the Contractor's right to proceed, liquidated damages will continue to accrue until the work is completed. These liquidated damages are in addition to excess costs of repurchase under the Termination clause.

1.3 TIME EXTENSIONS (Sept 2000) FAR 52.211-13

Time extensions for contract changes will depend upon the extent, if any, by which the changes cause delay in the completion of the various elements of construction. The change order granting the time extension may provide that the contract completion date will be extended only for those specific elements related to the changed work and that the remaining contract completion dates for all other portions of the work will not be altered. The change order also may provide an equitable readjustment of liquidated damages under the new completion schedule.

1.4 CONTRACT DRAWINGS AND SPECIFICATIONS (AUG 2000) DFARS 252.236-7001

(a) The Government will provide to the Contractor, without charge, one set of contract drawings and specifications, except publications incorporated into the technical provisions by reference. The drawings will be provided to the Contractor in electronic or paper media as chosen by the Contracting Officer.

(b) The Contractor shall-

(1) Check all drawings furnished immediately upon receipt;

(2) Compare all drawings and verify the figures before laying out the work;

(3) Promptly notify the Contracting Officer of any discrepancies;

(4) Be responsible for any errors that might have been avoided by complying with this paragraph (b); and

(5) Reproduce and print contract drawings and specifications as needed.

(c) In general--

(1) Large-scale drawings shall govern small-scale drawings; and

(2) The Contractor shall follow figures marked on drawings in preference to scale measurements.

(d) Omissions from the drawings or specifications or the misdescription of details of work that are manifestly necessary to carry out the intent of the drawings and specifications, or that are customarily performed, shall not relieve the Contractor from performing such omitted or misdescribed details of the work. The Contractor shall perform such details as if fully and correctly set forth and described in the drawings and specifications.

(e) The work shall conform to the specifications and to the contract drawings. The Contract Drawings are identified on the "Index to Drawings" found on Sheet G-001 of the set of Contract Drawings

(f) Information drawings (structural as-builts) accompany this specification and are intended only to show the original construction. Drawings are the property of the Government and shall not be used for any purpose other than that intended by the specifications.

1.5 DESIGNATED BILLING OFFICE

Reference Contract Clause titled "PROMPT PAYMENT FOR CONSTRUCTION CONTRACTS" located in the CONTRACT CLAUSES. The "designated billing office" will be the Construction Area Engineer, Resident Engineer or project office where the Contracting Officer Representative for this contract is located. The Contractor will be notified of the exact location of this office at the project preconstruction conference specified in Section 01 11 00 SUMMARY OF WORK.

1.6 TIME EXTENSIONS FOR UNUSUALLY SEVERE WEATHER (OCT 1989) ER 415-1-15

(a) This provision specifies the procedure for the determination of time extensions for unusually severe weather in accordance with the CONTRACT CLAUSE entitled, "DEFAULT (FIXED PRICE CONSTRUCTION)." In order for the Contracting Officer to award a time extension under this clause, the following conditions must be satisfied.

(1) The weather experienced at the project site during the contract period must be found to be unusually severe, that is, more severe than the adverse weather anticipated for the project location during any given month.

(2) The unusually severe weather must actually cause a delay to the completion of the project. The delay must be beyond the control and without the fault or negligence of the Contractor.

(b) The following schedule of monthly anticipated adverse weather delays is based on National Oceanic and Atmospheric Administration (NOAA) or similar data for the project location and will constitute the base line for monthly weather time evaluations. The Contractor's progress schedule must reflect these anticipated adverse weather delays in all weather dependent activities.

MONTHLY ANTICIPATED ADVERSE WEATHER DELAY WORK DAYS

BASED ON 5 DAY WORK WEEK

JAN FEB MAR APR MAY JUN

(7) (5) (3) (2) (1) (1)

JUL AUG SEP OCT NOV DEC

(1) (1) (1) (1) (2) (5)

(c) Upon acknowledgment of the Notice to Proceed (NTP) and continuing throughout the contract, the Contractor will record on the daily CQC report, the occurrence of adverse weather and resultant impact to normally scheduled work. Actual adverse weather delay days must prevent work on critical activities for 50 percent or more of the Contractor's scheduled work day. The number of actual adverse weather delay days shall include days impacted by actual adverse weather (even if adverse weather occurred in previous month), be calculated chronologically from the first to the last day of each month, and be recorded as full days. If the number of actual adverse weather delay days exceeds the number of days anticipated in paragraph b, above, the Contracting Officer will convert any qualifying delays to calendar days, giving full consideration for equivalent fair weather work days, and issue a modification in accordance with the contract clause entitled "DEFAULT (FIXED PRICE CONSTRUCTION)".

1.7 BID GUARANTEE (SEP 1996) FAR 52.228-1

(a) Failure to furnish a bid guarantee in the proper form and amount, by the time set for opening of bids, may be cause for rejection of the bid.

(b) The bidder shall furnish a bid guarantee in the form of a firm commitment, e.g., bid bond supported by good and sufficient surety or sureties acceptable to the Government, postal money order, certified check, cashier's check, irrevocable letter of credit, or, under Treasury Department regulations, certain bonds or notes of the United States. The Contracting Officer will return bid guarantees, other than bid bonds, (1) to unsuccessful bidders as soon as practicable after the opening of bids, and (2) to the successful bidder upon execution of contractual documents and bonds (including any necessary coinsurance or reinsurance agreements), as required by the bid as accepted.

(c) The amount of the bid guarantee shall be twenty percent of the bid price or $3,000,000, whichever is less.

(d) If the successful bidder, upon acceptance of its bid by the Government within the period specified for acceptance, fails to execute all contractual documents or furnish executed bond(s) within 10 days after receipt of the forms by the bidder, the Contracting Officer may terminate the contract for default.

(e) In the event the contract is terminated for default, the bidder is liable for any cost of acquiring the work that exceeds the amount of its bid, and the bid guarantee is available to offset the difference.

1.8 INSURANCE REQUIRED

In accordance with CONTRACT CLAUSE titled "INSURANCE - WORK ON A GOVERNMENT INSTALLATION" the Contractor shall procure and maintain during the entire period of his performance under this contract the following kinds and minimum amounts of insurance:

Type Amount Workmen's Compensation and Employers' Not less than $100,000

Liability Insurance.

The Contractor shall comply with all applicable Workmen's Compensation Statutes and shall furnish evidence of Employers'

Liability Insurance.

General Liability Insurance Minimum limits of

Bodily injury liability insurance on $500,000 per accident the comprehensive form of policy.

Automobile Liability Insurance Minimum limits of

Bodily injury liability and property $200,000 per person and damage liability insurance on the $500,000 per accident comprehensive form of policy and shall for bodily injury and cover the operation of all automobiles $20,000 per accident for used in performance of the contract. property damage.

1.9 PERFORMANCE OF WORK BY THE CONTRACTOR (APR 1984) FAR 52.236-1

The Contractor shall perform on the site, and with its own organization, work equivalent to at least twenty percent (20%) of the total amount of work to be performed under the contract. This percentage may be reduced by a supplemental agreement to this contract if, during performing the work, the Contractor requests a reduction and the Contracting Officer determines that the reduction would be to the advantage of the Government.

1.10 WARRANTY OF CONSTRUCTION (MAR 1994) FAR 52.246-21 Alternate I

(a) In addition to any other warranties in this contract, the Contractor warrants, except as provided in paragraph (i) of this clause, that work performed under this contract conforms to the contract requirements and is free of any defect in equipment, material, or design furnished, or workmanship performed by the Contractor or any subcontractor or supplier at any tier.

(b) This warranty shall continue for a period of 1 year from the date of final acceptance of the work. If the Government takes possession of any part of the work before final acceptance, this warranty shall continue for a period of 1 year from the date the Government takes possession.

(c) The Contractor shall remedy at the Contractor's expense any failure to conform, or any defect. In addition, the Contractor shall remedy at the Contractor's expense any damage to Government-owned or controlled real or personal property, when that damage is the result of--

(1) The Contractor's failure to conform to contract requirements; or

(2) Any defect of equipment, material, workmanship, or design furnished.

(d) The Contractor shall restore any work damaged in fulfilling the terms and conditions of this clause. The Contractor's warranty with respect to work repaired or replaced will run for 1 year from the date of repair or replacement.

(e) The Contracting Officer shall notify the Contractor, in writing, within a reasonable time after the discovery of any failure, defect, or damage.

(f) If the Contractor fails to remedy any failure, defect, or damage within a reasonable time after receipt of notice, the Government shall have the right to replace, repair, or otherwise remedy the failure, defect, or damage at the Contractor's expense.

(g) With respect to all warranties, express or implied, from subcontractors, manufacturers, or suppliers for work performed and materials furnished under this contract, the Contractor shall--

(1) Obtain all warranties that would be given in normal commercial practice;

(2) Require all warranties to be executed, in writing, for the benefit of the Government, if directed by the Contracting Officer; and

(3) Enforce all warranties for the benefit of the Government, if directed by the Contracting Officer.

(h) In the event the Contractor's warranty under paragraph (b) of this clause has expired, the Government may bring suit at its expense to enforce a subcontractor's, manufacturer's, or supplier's warranty.

(i) Unless a defect is caused by the negligence of the Contractor or subcontractor or supplier at any tier, the Contractor shall not be liable for the repair of any defects of material or design furnished by the Government nor for the repair of any damage that results from any defect in Government-furnished material or design.

(j) This warranty shall not limit the Government's rights under the Inspection and Acceptance clause of this contract with respect to latent defects, gross mistakes, or fraud.

(k) Defects in design or manufacture of equipment specified by the Government on a 'brand name and model' basis, shall not be included in this warranty. In this event, the Contractor shall require any subcontractors, manufacturers, or suppliers thereof to execute their warranties, in writing, directly to the Government.

1.11 CONTRACTOR PERFORMANCE EVALUATIONS

In accordance with the provisions of Subpart 36.201 (Evaluation of Contractor Performance) of the Federal Acquisition Regulation (FAR), construction Contractor's performance shall be evaluated throughout the performance of the contract. The United States Army Corps of Engineers (USACE) follows the procedures outlined in Engineering Regulation 415-1-17 to fulfill this FAR requirement. For construction contracts awarded at or above $650,000.00, the USACE will evaluate contractor's performance annually and at completion and prepare a performance report using the Contractor Performance Assessment Reporting System (CPARS), which is now a web-based system. After an evaluation (interim or final) is written up by the USACE, the Contractor will have the ability to access, review and comment on the evaluation for a period of 60 days. Accessing and using CPARS typically requires specific software, called PKI certification, which is installed on the user's computer. However, although users are encouraged to use PKI certificates whenever possible, a waiver has been approved to allow industry users to access the system without a PKI certificate. Contractors wishing to log on without a PKI certificate should select the "Contractor (pending PKI)" logon option. The certification is a Department of Defense item and was implemented to provide security in electronic transactions. The certification software could cost approximately $110 - $125 per certificate per year and is purchased from an External Certificate Authorities (ECA) vendor. Current information about the PKI certification process and for contacting vendors can be found on the web site: http://www.cpars.navy.mil/. If the Contractor wishes to participate in the performance evaluation process, access to CPARS and PKI certification is the sole responsibility of the Contractor.

1.12 EQUIPMENT OWNERSHIP AND OPERATING EXPENSE SCHEDULE (MAR 1995) UAI 52.249-5000

(a) This special contract requirement does not apply to terminations. See 52.249-5000, Basis for Settlement of Proposals, and FAR Part 49.

(b) Allowable cost for construction and marine plant and equipment in sound workable condition owned or controlled and furnished by a contractor or subcontractor at any tier shall be based on actual cost data for each piece of equipment or groups of similar serial and series for which the Government can determine both ownership and operating costs from the contractor's accounting records. When both ownership and operating costs cannot be determined for any piece of equipment or groups of similar serial or series equipment from the contractor's accounting records, costs for that equipment shall be based upon the applicable provisions of EP 1110-1-8, Construction Equipment Ownership and Operating Expense Schedule, Region 1. Working conditions shall be considered to be average for determining equipment rates using the schedule unless specified otherwise by the contracting officer. For equipment not included in the schedule, rates for comparable pieces of equipment may be used or a rate may be developed using the formula provided in the schedule. For forward pricing, the schedule in effect at the time of negotiations shall apply. For retroactive pricing, the schedule in effect at the time the work was performed shall apply.

(c) Equipment rental costs are allowable, subject to the provisions of FAR 31.105(d)(ii) and FAR 31.205-36, Rental Costs. Rates for equipment rented from an organization under common control, lease-purchase arrangements, and sale-leaseback arrangements, will be determined using the schedule, except that actual rates will be used for equipment leased from an organization under common control that has an established practice of leasing the same or similar equipment to unaffiliated lessees.

(d) When actual equipment costs are proposed and the total amount of the pricing action exceeds the SAT, the contracting officer shall request the contractor to submit either certified cost or pricing data, or partial/limited data, as appropriate. The data shall be submitted on Standard Form 1411, Contract Pricing Proposal Cover Sheet.

-- End of Document -- Document 00 80 00 Page 1