This document is a construction management procedure issued by the Central Florida Tourism Oversight District (CFTOD) Public Works Department that establishes required storm preparation protocols for all contractors and permit holders performing active work on CFTOD properties and public rights-of-way. The procedure, effective May 2026, outlines mandatory safeguarding measures contractors must implement upon issuance of tropical storm warnings, hurricane watches, and hurricane warnings. Upon issuance of a Tropical Storm Warning, contractors must remove obstructions from public storm drainage and sanitary sewage systems, clear construction debris, and backfill open trenches within 24 hours. Upon issuance of a Hurricane Watch, all right-of-way construction operations must be suspended immediately, material and equipment deliveries halted, drainage and sewage systems cleared, and roll-off trash containers removed from the public right-of-way within 24 hours. Upon issuance of a Hurricane Warning, contractors must remove all equipment and materials from the public right-of-way or consolidate them in secured areas with safety markings, lower crane booms, restore normal traffic operations, secure barricades and signage, and complete all preparations within 12 hours of the warning or 12 hours before projected landfall, whichever occurs first.

The procedure requires contractors to monitor public storm advisories and immediately commence storm preparation activities regardless of time of day, weekends, or holidays. Contractors must provide CFTOD with names and contact information of designated emergency response personnel available to respond following official clearance. Pre-storm video and photographic documentation with date and time subtitles are recommended. Post-storm resumption of work or entry into public rights-of-way requires prior authorization from the Public Works Department, determined on a case-by-case basis. The Contractor's emergency response personnel must promptly assess worksites, identify and mitigate any damage or safety hazards, verify utility operations, and coordinate all remediation efforts with the Construction Management Department. Construction activities are prohibited from resuming prior to receiving written authorization or direction from CFTOD. No exemptions apply to this procedure, which is subject to annual review.

Text of this file

OversightDistrict.org file_0.png file_1.wmf file_2.png file_3.wmf

Construction Management

SA-03

Required Storm Preparation Procedures for Public Right-of-Way and Public Property Procedure Number:

XXXX

Version: May 2026 Category:

04 – Construction Pages: 6 Developed by:

Construction Management Division of Public Works Effective: May 2026 Exemptions: No Exemptions Minimum Procedure Review Period: Annually

Revision Revision Date Description Effective Date June 2017 Original Revision June 2017 May 2026 Revision May 2026

Purpose The purpose of the procedure is to outline the steps that need to be taken in order to secure construction and roadway sites in advance of an expected hurricane or other severe storm event.

Contractors I Permit holders are encouraged to take proactive measures in securing their work site and the public rights-of-way to ensure public safety and the protection of completed work in the event of tropical cyclone activity. Contractors I Permit holders should monitor public storm advisories and individual storm progress.

Scope This procedure applies to all construction and roadway contractors performing active work under contract with the Central Florida Tourism Oversight District (CFTOD) on any of the CFTOD properties and roadways and is administered by the Construction Management & Planning and Engineering Divisions of the Public Works Department.

Definitions Not applicable.

Procedures file_4.wmf

Tropical Storm Warning Issued Upon the issuance of a Tropical Storm Warning for CFTOD property, all contractors I permit holders performing work on public property or in the public right-of-way shall immediately safeguard the work and property within and adjacent to the project work area as follows:

Remove obstructions from the public storm drainage system and make all necessary repairs to allow for the collection and discharge of storm water runoff.
Remove obstructions from the public sanitary gravity and force main sewage system and complete all necessary repairs to allow for collection and conveyance of sanitary sewage.
Remove all construction debris and backfill all open trenches to provide a temporary surface suitable for vehicular and pedestrian traffic. Steel plating will not be permitted.

Tropical storm warning preparation tasks should be completed within 24 hours of issued warning.

Hurricane Watch Issued Upon the issuance of a Hurricane Watch for CFTOD property, all contractors I permit holders performing work on public property or in the public right-of-way shall immediately safeguard the work and property within and adjacent to the project work area as follows:

All right-of-way construction operations shall be suspended immediately. Construction activity on CFTOD projects or within the public rights-of-way, not directly related to the safeguarding of public property or public rights-of-way, will not be permitted.
All right-of-way construction permits will be suspended immediately.
Delivery of material or equipment to CFTOD projects or projects within the public rights-of-way will be suspended immediately.
Remove all obstructions from the public storm drainage system and make all necessary repairs to allow for the collection and discharge of storm water runoff.
Remove obstructions from the public sanitary gravity and force main sewage system and complete all necessary repairs to allow for collection and conveyance of sanitary sewage.
Backfill open trenches and provide a temporary surface suitable for vehicular and pedestrian traffic. Steel plating will not be permitted.
Schedule roll-off trash collection and remove roll-off container(s) from the public right-of-way.

CFTOD personnel will evaluate site conditions and may identify construction equipment that contractors and permit holders must remove from the site upon issuance of a hurricane warning.

Hurricane watch preparation tasks should be completed within 24 hours of issued watch.

Hurricane Warning Issued Upon the issuance of a Hurricane Warning for the CFTOD, all contractors I permit holders performing work on public property or in the public right-of-way shall immediately safeguard the work and property within and adjacent to the project work area as follows:

Remove all equipment and material from the public right-of-way. Equipment and material that cannot be removed must be condensed into a single area out of the public roadway. Equipment that cannot be removed out of the public right of way shall be supplemented with appropriate safety markings, to the satisfaction of District personnel, to increase visibility in heavy rain or flooding situations.
In accordance with traffic modification standards, remove all MOT and restore normal vehicular traffic operation. In cases where MOT may not be safely removed, the District Construction Project Manager/Traffic Engineer must be notified immediately. Barricades and signage must be secured with direct burial or sand bagging. If deemed necessary by CFTOD personnel, the placement of concrete barriers may be required. The District Construction Project Manager/Traffic Engineer may impose additional site securing requirements, as deemed necessary.

Remove all construction debris, unused barricades, construction materials, permit boards, portable toilets, and similar material. Material may be stored in a secured building on site.

Crane booms shall be lowered in a safe position.
Contractors may be advised to take additional measures, at the discretion of CFTOD personnel, which are deemed necessary to secure the public right-of-way and ensure public safety.
Contractor I Permit holders are advised to record pre-storm video I photos with date/time subtitles.
Contractors shall provide CFTOD with the names and contact information of designated emergency response personnel who will be available to respond following the official “all clear” issued by the CFTOD Emergency Management Team.

Hurricane warning preparation tasks must be completed within 12 hours of issued warning or 12 hours prior to projected landfall, whichever is first.

Contractors I permit holders shall immediately commence storm preparation procedures upon the issuance of a hurricane watch I warning, regardless of time or day.

Regular work hours, time of day, weekends, or holidays will not be considered as providing any exemption from compliance with required completion time.

All preparations in accordance with these procedures shall be completed within the prescribed timeframe.

Post-Storm Event Procedures

Contractors and Permit Holders shall not resume work or enter the public rights‑of‑way without prior authorization from the Public Works Department. Authorization to resume operations will be determined on a case‑by‑case basis, based on the condition of the work and the surrounding area.

Construction Management will assess and promptly communicate post‑storm damage and required corrective actions to project stakeholders.
The Contractor’s emergency response personnel shall promptly assess all assigned worksites and take appropriate actions to identify, address, and mitigate any damage or safety hazards, including verification of utility operations. Coordinate all necessary remediation efforts with the Construction Management Department.

DO NOT COMMENCE SUSPENDED CONSTRUCTION ACTIVITIES PRIOR TO RECEIVING AUTHORIZATION OR DIRECTION FROM THE CENTRAL FLORIDA TOURISM OVERSIGHT DISTRICT.

Other files

Show all 17

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

File details come from the government source that posted it. Updated .