R17PS00304.pdf
PDF 8 MB Posted
- Attached to
- NK- KIRWIN DAM SPILLWAY GATES REHAB
- Solicitation number
- R17PS00304
About this file
Solicitation Package
View the file
Other files
| File | Type | Posted |
|---|---|---|
| R17PS00304_Amendment_No_0004.pdf | ||
| R17PS00304_Amend_0003.pdf | ||
| R17PS00304_Amendment_0002.pdf | ||
| R17PS00304_Amendment_0001.pdf |
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
U.S. Department of the Interior Bureau of Reclamation March 2017
Request For Proposals (RFP) Solicitation No. R17PS00304
Kirwin Dam Spillway Gates Guide Replacement and Maintenance Painting
(RAX ACTIVITY NO. 12109)
Kirwin Unit Solomon Division Pick-Sloan Missouri Basin Program Kansas
This Page Intentionally Left Blank
KIRWIN DAM SPILLWAY GATES
GUIDE REPLACEMENT AND MAINTENANCE PAINTING
Pick-Sloan Missouri Basin Program Kansas
FOREWORD
Work to be performed under this solicitation is to be performed at the Bureau of Reclamation’s Kirwin Dam facility in Kansas. Kirwin Dam spillway is located approximately 1 mile south of the town of Kirwin, KS, along South 1st Street. It is also approximately 13 miles southeast of Phillipsburg, KS on the east side of the Kirwin Reservoir and the Kirwin National Wildlife Refuge.
Work under these specifications:
A. Repair of the existing slide gate frames which includes:
1. Complete removal of the existing steel slide gate frame components and replacing with new galvanized steel components; and,
2. Temporary removal of the existing cast iron gate frame components, cleaning surface scale/rust from the components, and permanently reinstalling the components.
B. Application of new 3-coat coating system of the following:
1. 15 gate lift structure access plates (both sides) and associated imbedded frames located in the gallery of the concrete spillway crest structure;
2. 15 sluice bulkhead gate access plates (both sides) and associated imbedded frames located in the gallery of the concrete spillway crest structure;
3. The first 1-foot of the 10-inch diameter gate air vent piping openings interiors located in the spillway sluice openings; and,
4. Handling and disposal of all waste material.
C. Application of new 2-coat coating system for spot repairs of existing coating system and handle and dispose of all waste materials for the following description of elements:
1. Access houses stairway metalwork.
EMAIL INQUIRIES REGARDING THIS SOLICITATION SHOULD BE MADE TO:
Contractual Matters: Michael Birkland, Contracts Specialist Billings, Montana Email: mbirkland@usbr.gov
PRE-PROPOSAL SITE VISIT: An organized site visit will be held on Tuesday, , 2017 at :00 a.m. entral at the Kirwin Dam. Directions :
From Kirwin, Kansas, drive south on S 1st St. approximately 3/4 miles to the north spillway access road located on the west side of the road. Follow road 1/4 miles to the dam. If you have questions about the site visit, contact John Foreman at 970-962-4527.
Attendees are to provide and wear safety boots, hard hats, and safety vests. Prospective offerors are strongly encouraged to attend the walk-thru and visit the site to gain first-hand knowledge of the work requirements and site conditions. Failure of the prospective offerors to inspect the site will not relieve the offerors from the responsibility to properly estimate the difficulty or cost of the project and successfully perform the work in accordance with the requirements of the contract.
PROPOSAL DUE DATE AND TIME: For date and place proposals are due, see “SOLICITATION, OFFER, AND AWARD,” Standard Form 1442, immediately following the Table of Contents.
ORAL INFORMATION: In accordance to provision 52.214-06 of the Federal Acquisition Regulation, oral explanations, information, or instruction given before the award of the contract will not be binding.
SAFETY AND HEALTH MANUAL: For information regarding Bureau of Reclamation's publication "Reclamation Safety and Health Standards" (RSHS) November 2009 Edition, which is applicable to work under this contract, see clause WBR 1452.223- 81 (Safety and Health) of the solicitation. The electronic version of the publication can be found at: https://www.usbr.gov/safety/rshs/index.html
SAM: Effective July 29, 2012, any contractor interested in doing business with the federal government must register in the System for Award Management (SAM) database prior to award of a contract or agreement. SAM is a federal government owned and operated free website, which consolidates the central contractor registration (CCR), the online representations and certifications application (ORCA), and the excluded parties list system
(EPLS).
DUNS: The vendor's DUN & Bradstreet number and banking information are required for registration. Contractors may obtain information on registration and annual confirmation requirements via the SAM website accessed through https://www.sam.gov/portal/public/sam/ or by the federal service desk at 1-866-606-8220.
IPP: Payment requests for the anticipated contract must be submitted electronically through the U.S. Department of the Treasury’s Internet Payment Platform system (IPP).
The IPP website address is: https://www.ipp.gov. The contractor must use the IPP website to register access and use IPP for submitting requests for payment. Contractor assistance with enrollment can be obtained by contacting the ipp production helpdesk via email ippgroup@bos.frb.org or phone (866) 973-3131. If the contractor is unable to comply with the requirement to use ipp for submitting invoices for payment, the contractor must submit a waiver request in writing to the contracting officer with its proposal or quotation.
METHOD OF PROCUREMENT: This procurement is set-aside for Total Small Business Concerns and is a construction acquisition, pursuant to Federal Acquistioon Regulations (FAR) Part 15.
PART I – TABLE OF CONTENTS
AND
THE SCHEDULE
Kirwin Dam Spillway Gates Guide Replacement and Maintenance Painting
Solicitation R1 PS00304 Specifications No. 60-C0640
Table of Contents - 1
TABLE OF CONTENTS
PART 1 – THE SCHEDULE
SECTION A – Solicitation, Offer, and Award Form (SF 1442)
SECTION B – Supplies or Services and Prices
SECTION C – Specification/Drawings/Maps
DIVISION 01 – GENERAL REQUIREMENTS
01 11 00 Summary of Work 01 14 10 Use of Site 01 14 20 Dam and Reservoir Operations 01 33 00 Submittals 01 35 10 Safety Data Sheets 01 35 20 Safety and Health 01 35 30 Contractor’s Onsite Safety and Health Personnel 01 42 10 Reference Standards 01 46 00 Quality Procedures 01 51 00 Temporary Utilities 01 55 00 Vehicular Access and Parking 01 56 10 Protection of Existing Installations 01 56 15 Protection of Existing Utilities 01 57 20 Environmental Controls 01 57 30 Water Pollution Control 01 57 60 Protected Species 01 74 00 Cleaning and Waste Management 01 78 30 Project Record Documents
DIVISION 02 – EXISTING CONDITIONS
02 83 30 Removal and Disposal of Coatings Containing Heavy Metals
DIVISION 05 – METALS
05 50 00 Metal Fabrications
DIVISION 09 – FINISHES
09 96 20 Coatings
DIVISION 32 – EXTERIOR IMPROVEMENTS
32 92 20 Seeding and Soil Supplements
Solicitation R1 PS00304 Specifications No. 60-C0640
Table of Contents - 2
DIVISION 51 – INFORMATION AVAILABLE TO OFFERORS
51 00 00 Information Available to Offerors 51 00 02 Reservoir Elevation Data 51 02 83 Existing Coatings Test Results 51 09 96 Photographs
DIVISION 52 – DRAWINGS
52 00 00 Drawings
SECTION D – Not Used
SECTION E – Inspection and Acceptance E.1 Material and Workmanship E.2 Inspection of Construction
SECTION F – Deliveries or Performance F.1 Commencement, Prosecution, and Completion of Work F.2 Variation in Estimated Quantity F.3 Suspension of Work
SECTION G – Contract Administration Data G.1 Authorities and Delegations G.2 Electronic Invoicing and Payment Requirements
SECTION H – Special Contract Requirements H.1 Site Security
PART II – CONTRACT CLAUSES
SECTION I – Contract Clauses I.1 Clauses By Reference I.2 Prohibition on Contracting with Entities that Require Certain Internal
Confidentiality Agreements I.3 Commercial and Government Entity Code Maintenance I.4 Order of Precedence – Sealed Bidding I.5 Minimum Wages Under Executive Order 13658 I.6 Subcontractor Responsibility Matters Regarding Compliance with Labor Laws
Under Executive Order 13673 I.7 Compliance with Labor Laws Under Executive Order 13673 I.8 Paycheck Transparency Under Executive Order 13673 I.9 Paid Sick Leave Under Executive Order 13706 I.10 Buy American Act – Construction Materials
Solicitation R1 PS00304 Specifications No. 60-C0640
Table of Contents - 3
I.11 Bid Guarantee I.12 Additional Bonding I.13 Performance and Payment Bonds - Construction I.14 Payments Under Fixed-Price Construction Contracts I.15 Prompt Payment for Construction Contracts I.16 Differing Site Conditions I.17 Accident Prevention I.18 Schedules For Construction Contracts I.19 Specification and Drawings for Construction Contracts Alt II I.20 Changes I.21 Restriction on Endorsements I.22 Release of Claims I.23 Examination of Records By the Department of Interior I.24 Liability Insurance I.25 Safety and Health I.26 Protecting Federal Employees and the Public From Exposure to Tobacco Smoke I.27 Certification of Representations I.28 Equipment Ownership I.29 Payment for Mobilization and Preparatory Work I.30 Other Contracts I.31 Preservation of Cultural Resources I.32 Security Requirements I.33 Modification Proposals
PART III – DOCUMENTS, EXHIBITS, AND OTHER
SECTION J – List of Documents, Exhibits, and Other Attachments Wage Determination Standard Form 24 – Bid Guarantee Past Jobs Reference List Past Performance Questionnaire
DIAPR 2011-06
PART IV – REPRESENTATIONS AND INSTRUCTIONS
SECTION K – Representations, Certifications and Other Statements of Offerors K.1 Prohibition on Contracting with Entities That Require Certain Internal
Confidentiality Agreements K.2 Annual Representations and Certifications K.3 Information Regarding Responsibility Matters
SECTION L – Instructions, Conditions and Notices to Bidders L.1 System for Award Management L.2 Commercial and Government Entity Code Reporting L.3 Submission of Offers in the English Language
Solicitation R1 PS00304 Specifications No. 60- 0640
Table of Contents - 4
L.4 Submission of Offers in U.S. Currency L.5 Instructions to Offerors L.6 Type of Contract L.7 Construction Wage Rate Requirements L.8 Notice of Requirement for Affirmative Action to Ensure Equal Employment
Opportunity for Construction L.9 Site Visit (Construction) L.10 Preparation of Proposals L.11 Use and Disclosure of Proposal Information L.12 Service of Protest L.13 Notice of Intent to Acquire Metric Products and Services L.14 Source Evaluation and Selection Procedures L.15 General Proposal Instructions L.16 Technical Proposal Instructions L.17 Pricing Proposal Instructions L.18 Instruction for Mobilization and Preparatory Work L.19 Authorized Workers Notice to Potential
SECTION M – Evaluation Factors for Award M.1 Evaluation Factors for Award M.2 Notice of World Trade Organization Government Procurement Agreement
Evaluations
SECTION A
SOLICITATION, OFFER, AND AWARD
(STANDARD FORM 1442)
SECTION B
THE SCHEDULE
Schedule B - 1
Kirwin Dam Spillway Gates Guide Replacement and Maintenance Painting
Solicitation R1 PS00304 Specifications No. 60-C0640
CONTINUATION OF SECTION B – SUPPLIES OR SERVICES AND PRICES
KIRWIN DAM
SPILWWAY GATES GUIDE REPLACEMENT AND MAINTENANCE PAINTING
Kirwin Unit, Solomon Division Pick-Sloan Missouri Basin Program
Kansas
B.1 SCHEDULE
(a) Offers will be considered for award on the following schedule, but no offer will be considered for award on only a part of the schedule.
(b) All offers are subject to the terms and conditions of this solicitation.
(c) The quantities in the schedule[s] are estimated quantities for comparison of offers only, and except as provided in the contract clause at FAR 52.211-18, Variation in Estimated Quantity, no claim shall be made against the Government for overruns or underruns.
(d) See the contract clause at WBR 1452.232-81, Payment for Mobilization and Preparatory Work, for CLIN 1.
(e) Definitions:
(1) CLIN – Contract Line Item Number
SCHEDULE
CLIN Section Supplies or Services Quantity and Unit
Unit Price
Amount
1 WBR
1452.232-81
Mobilization and Preparatory Work
For the lump sum of $
2 02 83 30 Handling and Disposing of Coatings Containing Heavy Metals
For the lump sum of $
3 05 50 00 Sluice Gate Frames for 15 Gates
15 ea $ $
4 09 96 20 Sluice Gate Lift Structure Access Plates and Frames
660 ft2 $ $
5 09 96 20 Bulkhead Gate Access Plates and Frames
660 ft2 $ $
Solicitation R1 PS00304 Specifications No. 60-C0640
Price Schedule B - 2
SCHEDULE
CLIN Section Supplies or Services Quantity and Unit
Unit Price
Amount
6 09 96 20 10-Inch Diameter Gate Air Vent Piping Openings
40 ft2 $ $
7 09 96 20 Access Houses Stairway Metalwork
264 ft2 $ $
TOTAL FOR SCHEDULE $ _
END OF SCHEDULE
SECTION C
THE SPECIFICATIONS
Guide Replacement and Maintenance Painting Specification No.60-C0649
Summary of Work 01 11 00 - 1
SECTION 01 11 00
SUMMARY OF WORK
PART 1 GENERAL
1.01 LOCATION
A. Work is located at the Kirwin Reservoir in Phillips County, Kansas, approximately 1 mile south of Kirwin, KS along South 1st Street. It is also approximately 13 miles southeast of Phillipsburg, KS on the east side of the Kirwin Reservoir and the Kirwin National Wildlife Refuge.
1.02 PRINCIPAL COMPONENTS OF WORK
A. Repair of the existing slide gate frames which includes:
1. Complete removal of the existing steel slide gate frame components and replacing with new galvanized steel components; and,
2. Temporary removal of the existing cast iron gate frame components, cleaning surface scale/rust from the components, and permanently reinstalling the components.
B. Application of new 3-coat coating system of the following:
1. 15 gate lift structure access plates (both sides) and associated imbedded frames located in the gallery of the concrete spillway crest structure;
2. 15 sluice bulkhead gate access plates (both sides) and associated imbedded frames located in the gallery of the concrete spillway crest structure;
3. The first 1-foot of the 10-inch diameter gate air vent piping openings interiors located in the spillway sluice openings; and,
4. Handling and disposal of all waste material.
C. Application of new 2-coat coating system for spot repairs of existing coating system and handle and dispose of all waste materials for the following description of elements:
1. Access houses stairway metalwork.
1.03 SPECIFICATIONS REQUIREMENTS
A. Requirements in Division 1, General Requirements, apply to Divisions 2 through 53.
B. Imperative statements in these specifications are Contractor requirements, unless otherwise stated.
C. Where specifications are written in streamlined form, the words “shall be” are included by inference where a colon (:) is used within the sentence or phrase.
Summary of Work 01 11 00 - 2
1.04 DEFINITIONS
A. When the specifications use a word or term defined in the Federal Acquisition Regulations (FAR), the definition of the word or term shall be in accordance with FAR sections in effect at the time the solicitation was issued.
1.05 ACRONYMS
A. The following acronyms apply to specifications Divisions 1 through 53:
1. CO: Contracting Officer
2. COR: Contracting Officer’s Representative
PART 2 PRODUCTS
Not Used
PART 3 EXECUTION
Not Used
END OF SECTION
Use of Site 01 14 10 - 1
SECTION 01 14 10
USE OF SITE
PART 1 GENERAL
1.01 MEASUREMENT AND PAYMENT
A. Cost:
1. Include in prices offered in the Schedule for other items of work.
1.02 REFERENCE STANDARDS
A. Bureau of Reclamation (USBR)
1. USBR Cleaning Manual Inspection and Cleaning Manual for Equipment and Vehicles to Prevent the Spread of Invasive Species (Technical memorandum No. 86-68220-07-05) 2012 Edition available online at:
http://www.usbr.gov/mussels/prevention
1.03 SUBMITTALS
A. Submit the following in accordance with Section 01 33 00 - Submittals.
B. RSN 01 14 10-1, Land Use and Landscape Rehabilitation Plan:
1. For each Contractor use site on Government land.
a. Show use location and extent of impact. Uses include but are not limited to the following:
1) Buildings and service areas including offices, shops, warehouses, storage areas, fuel and oil storage areas, and fabrication yards.
2) Temporary parking areas and roads, borrow areas, stockpile and staging areas and haul routes.
3) Utilities including air, power, and water lines; fire hydrants; and compressor station.
4) First-aid and medical facilities.
5) Areas for processing, storing, and disposing of waste materials from construction operations.
6) Temporary fences.
b. Describe methods to preserve, protect, and repair if damaged, vegetation (such as trees, shrubs, and grass) and other landscape features on or adjacent to the jobsite, which are not to be removed and which do not
Use of Site 01 14 10 - 2 interfere with the work required under this contract. Include methods to mark work area limits, protect disturbed areas, and prevent erosion.
c. Describe methods to protect, and repair if damaged, existing improvements and utilities at or near the jobsite.
d. Describe methods for removing temporary structures and facilities, cleanup, and rehabilitating site after completion of construction activities.
e. The plan should minimize the amount of disturbed area and limit the impact of construction activities.
2. Submit revised drawings of changes in use of Government land made during design and erection stages or after use of Government land is in operation.
1.04 PROJECT CONDITIONS
A. Government land located within the project area may be used for required construction facilities.
1. The project site is located just south of Kirwin, KS in Rooks County on the east side of Kirwin reservoir. It lies approximately 13 miles southeast of Phillipsburg, KS. Refer to Figure 1 of this Section and Sheet 1 (Drawing 371-D-1) in Section 52 00 00 – Drawings.
B. Location, construction, operation, maintenance, and removal of construction facilities on Government land will be subject to approval of the COR.
C. Do not interfere with work of other contractors or the Government in vicinity, or with reservations made by the Government for use of such land.
D. Housing for construction personnel will not be permitted on Government land.
E. Working hours are 7:00 A.M. – 5:30 P.M. Monday through Friday.
F. Contractor shall request in writing additional working hours within a single shift at least 7 days prior to need, from COR.
G. Contractor shall request in writing additional full shift at least 21 days prior to need, from
COR.
PART 2 PRODUCTS
Use of Site 01 14 10 - 3
PART 3 EXECUTION
3.01 CLEANING
A. Construction equipment:
1. Before bringing on site, clean construction equipment to remove dirt, vegetation, and other organic material to prevent introduction of noxious weeds, and invasive plant and animal species.
2. Contractor cleaning procedures shall result in equipment being cleaned as well or better than the procedures described in USBR Cleaning Manual.
3. The COR will inspect construction equipment following procedures described in USBR Cleaning Manual before allowing the equipment onsite.
3.02 RESTORATION
A. Restore Contractor use areas to pre-construction condition. These areas would include, but not limited to, any staging, storage, parking or surface work areas.
B. Restore temporary construction roads to original contours and make impassable to vehicular traffic when no longer required.
C. After completion of work, regrade and scarify Government land used for construction purposes and not required for completed installation so that surfaces blend with natural terrain and are in a condition that will facilitate revegetation, provide proper drainage, and prevent erosion. Seed regraded area in accordance with Section 32 92 20 – Seeding and Soil Supplements.
Use of Site 01 14 10 - 4
Figure 1: Site Map
END OF SECTION
Kirwin Reservoir
Spillway
S. 1st Street
Spillway Crest
To Kirwin, KS
To Stockton, KS
North Access Houses
N
Undeveloped access road to North Access House
Undeveloped access road to South Access House
South Access Houses
Dam and Reservoir Operations 01 14 20 - 1
SECTION 01 14 20
DAM AND RESERVOIR OPERATIONS
PART 1 GENERAL
1.01 COST
A. Include cost in prices offered in the Schedule for other items of work.
1.02 REFERENCES
A. Bureau of Reclamation (USBR)
1. RSHS Reclamation Safety and Health Standards, including revisions posted at:
http://www.usbr.gov/ssle/safety/RSHS/rshs.html
1.03 SUBMITTALS
A. Submit the following in accordance with Section 01 33 00 – Submittals
B. RSN 01 14 20-1, Spillway Gate Operation Schedule:
1. Spillway Gate (slide gate) operation shall be performed by a Government Representative. The Contractor will supply the COR with a proposed schedule of when slide gate operation will be necessary to accomplish the requirements of these Specifications. Adjustments to the schedule can be made with a 24-hour advance notice to the on-site Government Representative.
1.04 OPERATIONAL RESPONSIBILITY
A. Reclamation is responsible for overall operations of the Kirwin Reservoir. Kirwin Irrigation District #1 is responsible for certain operation and maintenance functions when the storage level is above elevation 1662.30 feet and below elevation 1729.25 feet.
B. The Corps of Engineers (COE) is responsible for the flood control operations when the reservoir is in the exclusive flood pool, elevation 1729.25 feet to 1757.30 feet.
C. Between elevations 1757.30 feet to 1779.00 feet, flood control regulation is transferred back to Reclamation.
1.05 KIRWIN RESERVOIR OPERATIONS
A. The Government will not attempt to operate the reservoir (Kirwin Reservoir) to accommodate the Contractor’s construction activities.
1. The Government will attempt, in a limited capacity, to operate Kirwin reservoir to accommodate the Contractor’s construction activities. Construction of the spillway slide gates will depend on hydrologic conditions and annual irrigation
Dam and Reservoir Operations 01 14 20 - 2 draw down to a maximum water elevation of 1718.0. The Government will not draw down the water elevation to 1718.0 to specifically accommodate construction. However, if the water elevation is drawn down to elevation 1718.0 through the course of normal operating conditions and the Government proceeds with the contract award, the Government will operate and maintain water elevations, to the best of its ability, at or below elevation 1718.0 for a maximum of 75 days.
2. During normal water years, the Maximum Water Surface Elevation is 1729.25.
Kirwin Reservoir has a history of not recharging to this level following dry or high irrigation demand years.
3. Actual reservoir conditions may change due to flood events.
4. Plans are intended to show the probable limits of operations and, therefore, actual conditions and operations could vary widely from the plans.
B. The Contractor’s construction operations shall be coordinated to maintain Government access to all critical facilities and to prevent interference with Government operations for controlling the releases.
1.06 SPILLWAY OPERATIONS – RESERVOIR RELEASES
A. Substantial increases in inflows are often generated by upstream flash flood conditions and are extremely unpredictable. Inflows can increase quickly resulting in spillway releases being required within a 24-hour period; however, this is generally during the April-July runoff season.
B. It should be noted for scheduling purposes that spillway releases are not anticipated;
however:
1. If releases are required, the COR will provide written notification to the Contractor. The Contractor must remove personnel and equipment from the reservoir and spillway within 24-hours of such notification.
PART 2 PRODUCTS
Not Used
PART 3 EXECUTION
Submittals 01 33 00 - 1
SECTION 01 33 00
SUBMITTALS
PART 1 GENERAL
1.01 MEASUREMENT AND PAYMENT
A. Cost:
1. Include in prices offered in the Schedule for other items of work.
1.02 REFERENCE STANDARDS
A. American Society of Mechanical Engineers (ASME)
1. ASME Y14.1-2005(2010) Decimal Inch Drawing Sheet Size and Format
B. National Institute of Building Sciences (NIBS)
1. NIBS NCS-2011 United States National CAD Standards, Version 5
1.03 DEFINITIONS
A. Days: Calendar days.
B. Required Submittal Number (RSN): Identifies items to be submitted together as a complete submittal.
C. Submittals: Considered “shop drawings” within the terms of the clause at FAR 52.236- 21, Specifications and Drawings for Construction.
1.04 SUBMITTAL REQUIREMENTS
A. In case of conflict between requirements of this section and requirements included elsewhere in these specifications, requirements included elsewhere take precedence.
B. General:
1. Prepare in English.
2. Label with contract number and title, and RSN.
3. Measurement units: US Customary Units.
C. Drawings:
1. Minimum identification in title block:
a. Contract number and title.
b. Contractor’s or supplier’s title and drawing number.
Submittals 01 33 00 - 2
c. Date.
2. Provide space next to title block for review stamps.
3. Print Size: D size (22 inches by 34 inches).
4. Draw to scale using computer drafting or drafting equipment, unless otherwise specified.
a. Lettering shall be neat when drawing preparation with drafting equipment is allowed.
5. Government Format drawings:
a. Prepare drawings designated as “Government Format” in the specifications as follows:
1) Title block and sheet format:
a) As shown on Drawing 40-D-7102.
b) Government will provide specific title block information to be used.
2) Drawing format:
a) AUTOCAD, Version 2007 or later.
b) In accordance with NIBS NCS.
3) Size: D-size (22-inch by 34-inch) as defined by ASME Y14.1.
4) Government will provide an electronic AutoCAD template.
6. Final drawings:
a. Drawing format: AUTOCAD, Version 2007 or later.
b. Show as-built changes, including revision dates, made during installation.
Indicate changes by clouding.
c. Electronic files: On CD or DVD discs.
d. Original plots: D size (22 inches by 34 inches).
e. Government will provide an electronic AutoCAD template.
D. Product Data:
1. Mark manufacturer's data for commercial products or equipment, such as catalog cut sheets.
a. Identify manufacturer's name, type, model, size, and characteristics.
b. Illustrate that product or equipment meets requirements of specifications.
c. Mark items to be furnished in a manner that will photocopy (no highlighter).
d. Strike through items that do not apply.
Submittals 01 33 00 - 3
E. Certifications:
1. Certifications by a registered professional: Signed and sealed by registered professional.
2. Manufacturer’s certifications: Signed by authorized representative of manufacturer.
1.05 SUBMITTALS PROCEDURES
A. Submit only checked submittals. Submittals without evidence of Contractor's approval will be returned for resubmission.
B. Submit complete sets of required materials for each RSN as specified in “Submittals Required” column in Table 01 33 00A - List of Submittals. A complete set includes all listed items for RSNs with multiple parts.
C. Submit sets specified in “Sets to be sent:” columns in Table 01 33 00A - List of Submittals.
1. Electronic submittals:
a. In Portable Document Format (PDF).
b. Include RSN transmittal letter.
c. Do not include Personally Identifiable Information (PII) in electronic submittals.
2. Submit electronic submittals via email or CD/DVD based on size:
a. The Government can receive e-mails up to 25 MB. However, e-mails over 10 MB should be considered extra large. E-mailing of electronic submittals exceeding 10 MB should only occur after transmittal of larger size e-mail has been verified.
b. Address e-mail of electronic submittals less than extra large size to:
1) sha-GPR-CONSTSVCS@usbr.gov
c. Include electronic submittals that are too large to e-mail with paper copy of submittal. These electronic submittals shall be on CD or DVD.
D. Include the following information in transmittal letters:
1. Contract number and title.
2. RSN for attached submittal.
3. Responsible code.
4. Number of sets for each RSN.
5. Identify submittal as initial or resubmittal.
E. Resubmittal of submittals not approved:
Submittals 01 33 00 - 4
1. Mark changes such that they are readily identifiable and show revision date.
2. Describe reasons for significant changes in transmittal letter.
3. Resubmit returned submittals within 28 days after receiving the comments, unless otherwise directed.
4. Requirements for initial submittals apply to resubmittals.
F. Each submittal shall be submitted under a separate transmittal letter. Multiple RSNs submitted under a single letter will be returned to the Contractor for resubmittal.
1.06 REVIEW OF SUBMITTALS
A. Time Required:
1. Submittal review will require 21 days for review of each submittal or resubmittal, unless otherwise specified.
2. Time required for review of each submittal or resubmittal begins when complete sets of materials required for a particular RSN are received and extends through return mailing postmark date.
B. Time in Excess of Specified:
1. The CO may extend the contract completion date to allow additional time for completing work affected by excess review time.
a. The time extension will be to the extent that excess review time caused delay to the contract completion date.
b. The time extension will not exceed the time used in excess of the specified number of days for review of submittals or resubmittals.
c. Concurrent days of excess review time resulting from review of two or more separate submittals or resubmittals will be counted only once in extending the contract completion date.
2. No time extension will be allowed if the Contractor fails to make complete action submittals in sequence and within time periods specified.
3. Adjustment for delay will be made only to the extent that:
a. Approval was required under the contract, and
b. Requests for approval were properly and timely submitted and were approved.
4. Adjustment will be subject to terms of paragraphs (b) and (c) of the clause at FAR 52.242-14, Suspension of Work, however, no such delay shall be deemed to be a “suspension order” as the term is used in that clause.
C. Submittal Response:
Submittals 01 33 00 - 5
1. A response letter from the COR for each submittal will be sent to the Contractor indicating if the submittal is either approved, approved subject to identified changes, or not approved.
a. Revise and resubmit submittals not approved.
b. Do not change designs without approval of the COR after drawings, documentation, and technical data have been approved.
1.07 TRANSMITTAL
A. Addresses for codes listed in Table 01 33 00A - List of Submittals:
1. Where the recipient is the Contracting Officer, address the transmittal letter to Bureau of Reclamation, Attention: GP-5000, P.O. Box 36900, Billings, MT 59107-6900. Physical address is 2021 4th Avenue North, Billings, MT 59101.
2. Where the recipient is the Contracting Officer’s Representative, address the transmittal letter to Bureau of Reclamation, Attention: GP-2600, P.O. Box 36900, Billings, MT 59107-6900. Physical address is 2021 4th Avenue North, Billings, MT 59101.
PART 2 PRODUCTS
Not Used
PART 3 EXECUTION
Submittals 01 33 00 - 6
Table 01 33 00A. – List of Submittals **CO indicates Contracting Officer and COR indicates Contracting Officer’s Representative
RSN
Clause or
Section Title
Submittals required Due date or delivery time
Respon-sible code
Sets to be sent: **
CO COR
1 Bonds 52.228-15
Performance and Payment Bonds
Within 10 calendar days after award
CO 1 paper 0
2 Insurance-work on a Government Installation 1452.228-70
1) Written certification that the required insurance has been obtained
2) Current certification of insurance for each subcontractor
Before commencing on-site work
CO 1 paper
1 paper
3 Liability Insurance 1452.228-70
Acceptable Certificate of Liability Insurance
Prior to commencement of work under the contract
CO 1 paper 0
4 Equal Opportunity 52.222-26
Information required by Executive Order 112246
(SF-100)
Within 30 days following award
CO 1 paper 0
5 Reporting Executive Compensation and First Tier Subcontract Awards 52.204-10
Certification that executive compensation and subcontract awards were reported
Within 10 days of each report being submitted
CO 1 paper 0
6 Site Security
GP-7
List of all contractor and subcontractor employees
At least 10 days prior to arriving at worksite
COR 0 2 paper
7 Site Security
GP-7
List of all vehicles and equipment to be brought onsite
At least 10 days prior to arriving at worksite
COR 0 2 paper
8 Release of Claims 1452.204-70
Release of Claims (DI-
137) against the Government
After completion of the work and prior to final payment
CO 1 paper 0
9 Labor Standards Data 52.222-11
1) List of subcontractors
2) Statement and Acknowledgement Form (SF-1413) for each subcontract
Within 14 days after award of contract
COR 1 paper
1 paper
1 paper + 1 electronic
1 paper + 1 electronic
10 Payrolls 52.222-08
Copies of all payrolls Weekly for each week of contract performance
COR 1 paper 2 paper
11 Schedules for Construction Contracts 52.236-15
Practicable schedule Within 5 days after work commences on the contract or another period of time as determined by Contracting Officer
COR 1 paper 1 paper + 1 electronic
Submittals 01 33 00 - 7
RSN
Clause or
Section Title
Submittals required Due date or delivery time
Respon-sible code
Sets to be sent: **
CO COR
12 Schedules for Construction Contracts 52.236-15
Updated schedule showing actual progress
Monthly or as directed by the Contracting Officer
COR 1 paper 1 paper + 1 electronic
DIVISION 1 – General 01 14 10-1 Use of Site Land Use and Landscape
Rehabilitation Plan At least 28 days before use of Government land
COR 0 1 paper + 1 electronic
01 14 20-1 Dam and Reservoir Operations
Spillway Gate Operation Schedule
At least 21 days before installation
COR 0 1 paper + 1 electronic
01 35 10-1 Safety Data Sheets
Complete LHM and SDS At least 21 days before jobsite delivery of hazardous material
COR 0 1 paper + 1 electronic
01 35 10-2 Safety Data Sheets
Updated LHM and SDS At least 21 days before jobsite delivery of hazardous material not previously listed
COR 0 1 paper + 1 electronic
01 35 20-1 Safety and Health
Safety Program Submitted and accepted before commencing onsite work. See section 3 of RSHS
COR 0 1 paper + 1 electronic
01 35 20-2 Safety and Health
Monthly Accident Summary Report
First day of each month.
See paragraph 3.8 of
RSHS
COR 0 1 paper + 1 electronic
01 35 20-3 Safety and Health
Respirator User Documentation
At least 21 days before arriving at worksite
COR 0 2 paper
01 35 20-4 Safety and Health
Crane Training Certificates
At least 21 days before arriving at worksite.
COR 0 2 paper
01 35 20-5 Safety and Health
Other Training Certificates
At least 21 days before arriving at worksite
COR 0 2 paper
01 35 30-1 Contractor’s Onsite Safety and Health Personnel
Qualifications At least 21 days before beginning on-site work
COR 0 2 paper
01 35 30-2 Contractor’s Onsite Safety and Health Personnel
CIH Inspection Reports Submit to COR within 7 days of the inspection
COR 0 1 paper + 1 electronic
01 35 30-3 Contractor’s Onsite Safety and Health Personnel
Safety Inspection Reports Submit to COR monthly COR 0 1 paper + 1 electronic
01 46 00-1 Quality Procedures
Contractor Quality Control Program
At least 28 days before commencing construction activities
COR 0 1 paper + 1 electronic
01 46 00-2 Quality Procedures
Contractor’s Daily Reports
Submit daily reports weekly
COR 0 1 paper + 1
Submittals 01 33 00 - 8
RSN
Clause or
Section Title
Submittals required Due date or delivery time
Respon-sible code
Sets to be sent: **
CO COR
01 46 00-3 Quality Procedures
Quality Control Supervisor
At least 28 days before commencing construction activities
COR 0 2 paper
01 46 00-4 Quality Procedures
Contractor Quality Testing Plan
At least 28 days before commencing construction activities
COR 0 1 paper + 1 electronic
01 46 00-5 Quality Procedures
Summary Monthly Test Results
At least once a month when construction has been done in that month
COR 0 1 paper + 1 electronic
01 56 10-1 Protection of Existing Installations
Plan for Protecting Existing Installations
At least 21 days prior to start of construction
COR 0 1 paper + 1 electronic
01 57 20-1 Environmental Controls
Copy of Applicable Air Quality Permit
At least 21 days prior to start of construction
COR 0 1 paper + 1 electronic
01 57 30-1 Water Pollution Control
Water Management Plan At least 28 days before commencing on-site construction work
COR 0 1 paper + 1 electronic
01 57 30-2 Water Pollution Control
Spill Prevention Control and Countermeasure (SPCC) Plan
At least 28 days before delivery or storage of oil.
COR 0 1 paper + 1 electronic
01 57 40-1 Pesticides Pesticide Use Plan At least 60 days prior to application of first pesticide
COR 0 1 paper + 1 electronic
01 74 00-1 Cleaning and Waste Management
Waste Production and Disposal Plan
At least 21 days before beginning onsite work
COR 0 1 paper + 1 electronic
01 74 00-2 Cleaning and Waste Management
Waste Production and Disposal Records
Within 7 days of waste disposal
COR 0 1 paper + 1 electronic
01 74 00-3 Cleaning and Waste Management
Environmental Consultant Resume
At least 21 days before beginning environmental assessment
COR 0 2 paper
01 74 00-4 Cleaning and Waste Management
Environmental Site Assessment
Within 14 days of completion of work
COR 0 1 paper + 1 electronic
01 78 30-1 Project Record Documents
Final As-built Drawings Within 15 days of completion of work
COR 0 1 paper + 1 electronic
DIVISION 2 – EXISTING CONDITIONS
02 83 30-1 Removal and
Disposal of Coatings Containing Heavy Metals
Qualifications At least 21 days prior to beginning on-site work
COR 0 1 paper + 1 electronic
02 83 30-2 Removal and Disposal of Coatings Containing Heavy Metals
Plans At least 21 days prior to beginning on-site work
Submittals 01 33 00 - 9
RSN
Clause or
Section Title
Submittals required Due date or delivery time
Respon-sible code
Sets to be sent: **
CO COR
02 83 30-3 Removal and Disposal of Coatings Containing Heavy Metals
Plans Heavy Metal Exposure Certifications and Test Results
At least 20 days prior to beginning on-site work
COR 0 1 paper + 1 electronic
02 83 30-4 Removal and Disposal of Coatings Containing Heavy Metals
Preconstruction Test Results
Within 2 days after tests are completed
COR 0 1 paper + 1 electronic
02 83 30-5 Removal and Disposal of Coatings Containing Heavy Metals
Working Level Test Results
Within 2 days after tests are completed
COR 0 1 paper + 1 electronic
02 83 30-6 Removal and Disposal of Coatings Containing Heavy Metals
Post-construction Test Results
At least 10 days following the beginning of the work week.
COR 0 1 paper + 1 electronic
02 83 30-8 Removal and Disposal of Coatings Containing Heavy Metals
Certificate of Disposal Within 7 days of waste disposal
COR 0 1 paper + 1 electronic
DIVISION 05 - METALS
05 50 00-1 Metal
Fabrications Test Reports At least 21 days before installation COR 0 1 paper + 1 electronic 05 50 00-2 Metal
Fabrications Shop Drawings At least 28 days before installation COR 0 1 paper + 1 electronic 05 50 00-3 Metal
Fabrications Installation Plan At least 21 days before installation COR 0 1 paper + 1 electronic
DIVISION 09 - FINISHES
09 96 20-1 Coatings Approval Data At least 20 days prior to beginning on-site work COR 0 1 paper + 1 electronic 09 96 20-2 Coatings Final Approval Data At least 20 days prior to beginning on-site work COR 0 1 paper + 1 electronic 09 96 20-3 Coatings Certifications At least 21 days prior to beginning on-site work COR 0 1 paper + 1 electronic 09 96 20-4 Coatings Documentation At least 21 days prior to beginning on-site work COR 0 1 paper + 1 electronic 09 96 20-5 Coatings Contractor Quality
Testing Data for “Field Applied” Coatings
Within 14 days of completion of work
COR 0 1 paper + 1 electronic
DIVISION 32 – EXTERIOR IMPROVEMENTS
32 92 20-1 Seeding and Soil
Supplements Seeding Plan At least 20 days prior to beginning of on-site work
Submittals 01 33 00 - 10
RSN
Clause or
Section Title
Submittals required Due date or delivery time
Respon-sible code
Sets to be sent: **
CO COR
32 92 20-2 Seeding and Soil Supplements
Certifications At least 20 days prior to beginning of on-site work
COR 0 1 paper + 1
Safety Data Sheets 01 35 10 - 1
SECTION 01 35 10
SAFETY DATA SHEETS
PART 1 GENERAL
1.01 MEASUREMENT AND PAYMENT
A. Cost:
1. Include in prices offered in the Schedule for other items of work.
1.02 DEFINITIONS
A. LHM: List of Hazardous Materials
B. SDS: Safety Data Sheet.
1. Referred to as Material Safety Data Sheets in the clause at 52.223-3, Hazardous Material Identifications and Material Safety Data - Alternate 1.
1.03 APPLICATION
A. For the purposes of this contract, “delivered under this contract” in paragraph (b) of the clause at FAR 52.223-3, Hazardous Material Identification and Material Safety Data - Alternate 1, includes:
1. Materials delivered to the Government.
2. Materials incorporated into the work.
3. Materials used by the Contractor during contract performance at the jobsite.
1.04 SUBMITTALS
A. Submit the following in accordance with Section 01 33 00 - Submittals.
B. RSN 01 35 10-1, Complete LHM and SDS.
C. RSN 01 35 10-2, Updated LHM and SDS:
1. Comply with paragraph (e) of clause at FAR 52.223-3, Hazardous Material Identification and Material Safety Data - Alternate 1.
1.05 DELIVERY
A. Do not deliver hazardous materials to jobsite which are not included on the original or previously updated LHM and SDS before receipt of updated LHM and SDS by the Contracting Officer’s Representative.
Safety Data Sheets 01 35 10 - 2
PART 2 PRODUCTS
Not Used
PART 3 EXECUTION
Safety and Health 01 35 20 - 1
SECTION 01 35 20
SAFETY AND HEALTH
PART 1 GENERAL
1.01 MEASUREMENT AND PAYMENT
A. Cost:
1. Include the cost of complying with this section in the prices offered in the Schedule for other items of work.
1.02 REFERENCE STANDARDS
A. Bureau of Reclamation (USBR)
1. RSHS Reclamation Safety and Health Standards, including revisions posted at:
http://www.usbr.gov/ssle/safety/RSHS/rshs.html
2. FIST 1-1 (2012) Hazardous Energy Control Program
a. Available on the Internet at:
www.usbr.gov/power/data/fist_pub.html
B. Occupational Safety and Health Administration (OSHA)
1. 29 CFR Part 1910 Occupational Safety and Health Standards
2. 29 CFR Part 1926 Safety and Health Regulations for Construction
3. Available on the Internet at www.osha.gov.
C. American Conference of Governmental Industrial Hygienists (ACGIH), Threshold Limit Values (TLVs)
1. Available at www.acgih.org
1.03 SUBMITTALS
A. Submit the following in accordance with Section 01 33 00 - Submittals.
B. RSN 01 35 20-1, Safety Program:
1. Submit a comprehensive, job-specific safety and health program in accordance with Section 01 33 00 – Submittals and in accordance with the requirements of Section 3.3 of the Reclamation Safety and Health Standards (RSHS) and these specifications.
2. The Safety Program will not be accepted for review by the COR unless it addresses, in order, lettered and numbered per Appendix B of the RSHS, a
Safety and Health 01 35 20 - 2 comprehensive narrative for each applicable item in the outline and program elements contained in these specifications.
3. Generic company safety programs are not acceptable. The Safety Program must be site specific for this contract.
4. The Contractor’s Safety Program must be submitted and accepted by Reclamation prior to commencing onsite work, including mobilization.
5. The Safety Program Statement of Responsibility must state that “the contractor is responsible for ensuring that all work will be in compliance with Reclamation Safety and Health Standards and these specifications.”
6. The Safety and Health Program shall include but not be limited to the following program elements:
a. Emergency Action Plan
1) Detail coordination plan for outside emergency services including response time and a site visit where a rescue requires special capabilities or equipment.
2) This plan shall address detailed emergency contacts and procedures to be used during an onsite emergency.
b. Confined Space Entry:
1) Include a confined space entry plan for operations that require employees to enter confined spaces.
2) Include engineering controls, personal protective equipment and air monitoring procedures for each confined space.
3) Include Non-Entry and Entry Rescue Plan.
c. Hazardous Energy Control (lockout/tagout)
1) Include the contractor’s written Hazardous Energy Control Program (HECP).
2) Comply with facility HECP procedures and coordinate activities with Reclamation staff.
d. Electrical Safety
1) Include safe work procedures at the site, electrically qualified persons, grounding techniques, use of mobile generators, construction lighting, power tool safety, and use of personal protective equipment.
e. Hot Work and Fire Prevention
1) Include a plan to address hazards associated with hot work.
2) Include list of workplace fire hazards, potential ignition sources, safe work procedures, engineering controls and equipment to be used to prevent fires during the hot work process.
Safety and Health 01 35 20 - 3
f. Job Hazard Analysis
1) Provide a list of proposed JHA’s in the Safety Program for each anticipated work task.
2) A detailed JHA shall be completed onsite prior to starting each work task. Work will not begin on the phase of the work until a JHA is acceptable to the Onsite Government Representative.
3) Activities involving hazardous materials shall have the appropriate Material Safety Data Sheet(s) attached to the JHA.
g. Respiratory Protection
1) Identify respirator users, tasks and operations with recognized respiratory hazards.
2) The plan shall address exposure to respirable silica associated with concrete work as follows.
a) Use of tight fitting half face air purifying respirators with P100 cartridges in the absence of an on-site exposure assessment.
3) The level of respiratory protection may only be diminished on the basis of an exposure assessment conducted by a certified industrial hygienist (CIH) specific to each dust-generating operation that is acceptable to Reclamation.
h. Hearing Conservation
1) Include a task- and site-specific hearing conservation plan.
2) Identify the type of hearing protection and verify that workers are in a Hearing Conservation Program.
i. Crane, Hoisting and Rigging Safety
1) Include operator and rigging safety, materials handling, signaling and communication procedures.
2) All Operators, Riggers and Signalpersons shall be qualified in accordance with OSHA 1926 Subpart CC. Crane Operators shall be certified by an accredited crane operator testing organizations such as NCCCO or equivalent.
3) Reclamation requires an onsite verified load test in accordance with RSHS Appendix F prior to use of cranes.
j. Personal Protective Equipment (PPE)
1) Include a detailed plan for each task that specifies which personal protective equipment shall be used for all construction activities.
2) The employer must ensure that the PPE is verified by the manufacturer for the intended use and protection.
Safety and Health 01 35 20 - 4
3) Provide appropriate PPE at no cost to the employees
k. Hazard Communication
1) Include a written Hazard Communication plan. .
2) The safety and health practices, procedures, and protective equipment used for new and existing products shall be based upon the health hazards identified in the SDS.
l. Fall Protection and Prevention
1) Detail safe work procedures, training and engineering controls for work in elevated areas where employees are exposed to a fall.
2) The Contractor shall use engineered fall protection systems, fall restraint, and/or fall arrest systems for work in elevated areas. Warning line and safety monitoring systems are not permitted.
m. Scaffolding Safety and Design
1) Include a scaffolding plan indicating what type of scaffolding will be used at the site and provide drawings, design specifications, manufacturer information, fall protection procedures and falling object protection.
2) Prepared or reviewed and signed by a qualified Professional Engineer (P.E.) except when manufactured systems and standard designs are used.
C. RSN 01 35 20-2, Monthly Accident Summary Report:
1. Form 7-2218 or other acceptable form in accordance with paragraph 3.8 of RSHS.
2. Submit on the first day of every month.
D. RSN 01 35 20-3, Respirator User Documentation:
1. Submit documentation of medical qualifications less than 12 months old for all respirator users at the site.
2. Submit results of fit tests less than 12 months old for all users of tight fitting negative pressure respirators at the site.
E. RSN 01 35 20-4, Crane Training Certificates:
1. Qualifications for all riggers and signalpersons.
2. Crane Operator Qualifications:
a. Certifications for all crane and hoist operators.
b. Medical Qualifications to operate a crane in accordance with RSHS Section 19.5.
F. RSN 01 35 20-5, Other Training Certificates:
Safety and Health 01 35 20 - 5
1. First Aid/CPR certifications for all personnel on site. Training shall be in accordance with the American Red Cross or the American Heart Association.
2. Proof of fall protection and prevention training for employees who work in elevated areas.
3. Proof of Lockout/tagout training for all employees who will work in any area protected by lockout/tagout and hazardous energy control procedures.
4. Proof of training for all contractor employees involved with confined space entry work.
5. Training certifications and experience for scaffolding competent person.
1.04 SAFETY AND HEALTH
A. Comply with RSHS, local safety programs, and any other referenced safety and health standards. Perform work in accordance with the specific safety program elements and referenced standards.
B. Provide and maintain a work environment and procedures that will:
1. Safeguard the public, Government personnel, and Contractor employees from Contractor operations and activities that are unsanitary, hazardous, or dangerous to health and safety.
2. Avoid interruptions of site operations and delays in project completion dates.
3. Control costs in contract performance.
C. For each operation requiring the use of heavy equipment, in addition to the use of backup alarms and high visibility vests, include in the JHA specific steps to ensure the protection of onsite personnel (internal traffic control) from the hazards of being struck by or caught between moving equipment while working around such equipment. Possible methods of controlling said hazards may include radio communications, backup cameras and/or proximity devices, designated observers, etc. Provide all appropriate safety barricades, signs, and warnings. Erect or label all limited approach and arc flash hazard boundaries for exposed energized equipment. Coordinate these activities with Reclamation electricians.
D. Comply specifically with all requirements contained in RSHS Section 3- Contractor Requirements.
E. Investigate and report all accidents, incidents and near misses in accordance with RSHS Section 3.7.
F. When the Contractor fails or refuses to promptly correct a compliance directive, the…