Tab_13_Amendment_2_Attachment_1_REVISED_00_00_01_-_Specifications.pdf
PDF 1 MB Posted
- Attached to
- Cutter Lateral Reach 22B Federal contract opportunity
- Solicitation number
- R16PS01019
About this file
Attachment 1 - Revised Specifications
View the file
Other files for this federal contract opportunity
Show all 25
On GovTribe
Work with this file on GovTribe
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Navajo Gallup Water Supply Project Cutter Lateral - Reach 22B Solicitation No.
Table of Contents
00 01 10 - 1
SECTION C - DESCRIPTION / SPECIFICATIONS
TABLE OF CONTENTS
DIVISION 01 - GENERAL REQUIREMENTS
01 11 00 Summary of Work 01 14 10 Use of Site 01 31 19 Project Management and Coordination 01 31 30 Contract Document Management System 01 32 10 Construction Program 01 33 00 Submittals 01 33 26 Electrical Drawings and Data 01 35 10 Safety Data Sheets 01 35 20 Safety and Health 01 35 22 First Aid 01 35 30 Contractor’s Onsite Safety Personnel 01 42 10 Reference Standards 01 46 00 Quality Procedures 01 46 20 Testing Agency Services 01 51 00 Temporary Utilities 01 55 00 Vehicular Access and Parking 01 55 20 Traffic Control 01 56 10 Protection of Existing Installations 01 56 15 Protection of Existing Utilities 01 56 20 Existing Fences 01 56 32 Temporary Safety Fence 01 57 20 Environmental Controls 01 57 30 Water Pollution Control 01 57 50 Tree and Plant Protection 01 57 60 Protected Species 01 57 90 Preservation of Historical and Archeological Data 01 60 00 Product Requirements 01 71 20 Surveying 01 74 00 Cleaning and Waste Management 01 78 30 Project Record Documents
DIVISION 03 - CONCRETE
03 11 10 Concrete Forming 03 20 00 Concrete Reinforcing 03 30 00 Cast-In-Place Concrete 03 48 00 Precast Concrete Structures 03 63 00 Epoxy Grout
00 01 10 - 2
DIVISION 04 - MASONRY
04 22 10 Reinforced Concrete Unit Masonry Assemblies
DIVISION 05 - METALS
05 21 00 Steel Joists 05 30 00 Metal Roof Deck 05 50 00 Metal Fabrications
DIVISION 07 - THERMAL AND MOISTURE PROTECTION
07 41 13 Preinsulated Metal Roof Panels 07 42 13 Preinsulated Metal Wall Panels 07 72 30 Roof Hatches
DIVISION 08 - OPENINGS
08 34 53 Security Doors and Frames 08 71 00 Door Hardware
DIVISION 09 - FINISHES
09 65 10 Rubber Wall Base 09 96 20 Coatings
DIVISION 10 - SPECIALTIES
10 14 26 Utility Markers
DIVISION 22 - PLUMBING
22 11 35 Pre-manufactured Pump Station 22 13 16 Foundation and Building Drainage Piping
DIVISION 23 - HEATING, VENTILATING, AND AIR-CONDITIONING (HVAC)
23 05 93 Testing, Adjusting, and Balancing for HVAC Equipment 23 33 10 Duct Accessories 23 34 00 HVAC Fans 23 82 39 Unit Heaters
00 01 10 - 3
DIVISION 25 - INTEGRATED AUTOMATION
25 00 01 Control and Monitoring 25 00 02 Programmable Controller 25 08 10 Automation System Testing, Acceptance, and Training
DIVISION 26 - ELECTRICAL
26 05 02 Basic Electrical Materials and Methods 26 05 10 Conductors and Cables 26 05 13 Medium-Voltage Power Cable System 26 05 20 Grounding and Bonding 26 05 33 Raceways and Boxes 26 05 90 Wiring Checkout and Tests 26 13 26 Metal-Clad Switchgear 26 16 13 Primary Unit Substation 26 22 12 Dry-Type Transformers 26 24 41 Distribution Panelboards 26 27 40 Wiring Devices 26 42 10 Buried Galvanic Anode Cathodic Protection and Corrosion Monitoring Systems 26 42 11 Submerged Galvanic Anode Cathodic Protection System for Welded Tanks 26 42 12 Bolted Tank Submerged Galvanic Anode Cathodic Protection System 26 51 00 Interior Lighting 26 52 00 Emergency and Exit Lighting 26 56 00 Exterior Lighting
DIVISION 27 - COMMUNICATIONS
27 15 00 Communications Cabling 27 20 01 Radio Equipment 27 30 01 Telephone Equipment
DIVISION 28 - ELECTRONIC SAFETY AND SECURITY
28 10 01 Security and Surveillance Equipment 28 31 00 Fire Detection and Alarm
DIVISION 31 - EARTHWORK
31 02 10 Water for Dust Abatement 31 02 30 Dust Palliative 31 11 00 Clearing and Grubbing 31 14 10 Stripping 31 23 02 Compacting Earth Materials 31 23 10 Earthwork
00 01 10 - 4
31 23 22 Pipe Trench Earthwork 31 23 39 Disposal of Excavated Materials 31 23 70 Controlled Low Strength Materials (CLSM) 31 31 30 Soil-Applied Herbicide 31 37 00 Riprap
DIVISION 32 - EXTERIOR IMPROVEMENTS
32 15 10 Gravel Surfacing 32 31 10 Chain Link Fence 32 91 60 Erosion Control Blanket 32 92 20 Seeding
DIVISION 33 - UTILITIES
33 05 21 Bored Utility Crossings 33 09 08 Probe Magnetic Flowmeter 33 11 10 Pipeline General Requirements 33 11 12 Steel Line Pipe 33 11 13 Ductile Iron Pipe 33 11 13 Ductile Iron Pipe 33 11 16 PVC Pressure Pipe 33 11 18 HDPE Pressure Pipe 33 11 19 Fiberglass Pipe 33 11 50 Pipe Crossings at Existing Utility Pipelines 33 12 05 NAPI Turnout 33 12 10 Valves and Equipment for Line Pipe Installations 33 16 14 Air Chambers 33 16 50 Steel Tanks 33 21 95 Metal Piping for Line Pipe Installations 33 42 30 Corrugated Metal Pipe Culvert
DIVISION 35 - WATERWAY AND MARINE CONSTRUCTION
35 21 95 Steel Pipe 35 22 15 Valves and Equipment 35 42 35 Bank Protection
DIVISION 48 - ELECTRICAL POWER GENERATION
48 14 00 Solar And Electrical Equipment
DIVISION 52 - DRAWINGS
52 00 00 Drawings
00 01 10 - 5
DIVISION 53 - GEOLOGIC INVESTIGATIONS AND RECORDS
53 10 00 Geology 53 20 00 Records of Geologic and Subsurface Investigations
END OF CONTENTS
00 01 10 - 6
This page intentionally left blank.
Submittals
01 33 00 - 1
SECTION 01 33 00
SUBMITTALS
PART 1 GENERAL
1.01 MEASUREMENT AND PAYMENT
A. Cost:
1. Include in prices offered in the Price Schedule for other items of work.
1.02 REFERENCE STANDARDS
A. American Society of Mechanical Engineers (ASME)
1. ASME Y14.1-12 Decimal-inch Drawing Sheet Size and Format
B. National Institute of Building Sciences (NIBS)
1. NIBS NCS-14 United States National CAD Standards, Version 6
1.03 DEFINITIONS
A. Days: Calendar days.
B. Required Submittal Number (RSN): Identifies items to be submitted together as a complete submittal.
C. Submittal Types, as listed in Table 01 33 00A - List of Submittals:
1. A - Action:
a. Government will respond as to adequacy of submittal.
b. Action Submittals: Considered “shop drawings” within the terms of the clause at FAR 52.236-21, Specifications and Drawings for Construction.
2. I - Informational:
a. Government will acknowledge receipt of Informational submittals.
b. Government may reject an Informational submittal when the submittal does not satisfy contract requirements. Correct mistakes or deficiencies in rejected Informational submittals and resubmit.
c. Informational Submittals: Considered “shop drawings” within terms of the clause at FAR 52.236-21, Specifications and Drawings for Construction, except that approval by Government is not required.
01 33 00 - 2
1.04 SUBMITTAL REQUIREMENTS
A. In case of conflict between requirements of this section and requirements included elsewhere in these specifications, requirements included elsewhere take precedence.
B. General:
1. Prepare in English.
2. Label with contract number and title, and RSN.
3. Measurement Units: US Customary Units.
4. Electronic Documents:
a. Searchable .pdf.
b. Includes submittals which are not drawings or photographs.
C. Drawings:
1. Minimum Identification in Title Block:
a. Contract number and title.
b. Contractor’s or supplier’s title and drawing number.
c. Date.
2. Reserve 3 by 3 inch space next to title block for review stamps.
3. Size: D size (22 inches by 34 inches) as defined by ASME Y14.1.
4. Draw to scale using computer drafting or drafting equipment, unless otherwise specified.
a. Computer drafted drawings:
1) In accordance with NIBS NCS.
2) Electronic file format: Compatible with AUTOCAD, Version 2015 or later.
3) Compile using “eTransmit” utility in AUTOCAD.
b. Drawing prepared with drafting equipment, when allowed: Lettering shall be neat.
5. Drawings Designated as “Government Format” in Specifications:
a. Computer drafted.
b. Government will provide an electronic AutoCAD format template.
c. Title block and sheet format:
1) As shown on standard drawing 40-D-7102.
2) Government will provide template.
01 33 00 - 3
3) Government will provide specific title block information to be used.
6. Final Drawings:
a. Computer drafted.
b. Government will provide an electronic AutoCAD format template.
c. Show as-built changes, including revision dates, made during installation.
Indicate changes by clouding.
7. Electronic Files:
a. On CD or DVD discs.
D. Product Data:
1. Mark manufacturer's data for commercial products or equipment, such as catalog cut sheets.
a. Identify manufacturer's name, type, model, size, and characteristics.
b. Illustrate that product or equipment meets requirements of specifications.
c. Mark items to be furnished in a manner that will photocopy (no highlighter).
d. Strike through items that do not apply.
E. Certifications:
1. Certifications by a Registered Professional: Signed and sealed by registered professional.
2. Manufacturer’s Certifications: Signed by authorized representative of manufacturer.
F. Manuals:
1. Copies:
a. Printed copies: Bound and indexed.
b. Electronic copies: Searchable Adobe pdf on CD or DVD discs.
1) Bookmark longer files to assist in navigating file.
2) Electronic files may be submitted as separate parts of a manual.
After each separate electronic file is approved, compile each approved electronic file to assemble an entire manual which shall be consistent with a single final manual submittal.
2. Contents:
a. Parts identification lists, lists of special tools, and accessories.
b. Schematics and wiring diagrams.
01 33 00 - 4
c. Detailed instructions for installing, operating, lubricating, and maintaining equipment.
d. As-built drawings, photographs, and test records or reports if required by the specifications.
G. Photographs:
1. Include negatives or digital files on CD or DVD in .jpeg or similar format.
H. Samples and Color Selection Submittals:
1. Label with complete manufacturer's product and color identification.
2. Include type and quantity of materials specified in the referenced section in each “set” of samples.
3. Samples: Representative of product to be installed. Xerographic sheets for color selection are not acceptable.
4. Color Chips: Sample paint chips. Ink color reproductions are not acceptable.
5. Label each sample, sample kit, set of color chips, or color chart with contract number and title.
6. Government will select architectural color and pattern after product approval.
1.05 SUBMITTALS PROCEDURES
A. Submit only checked submittals. Submittals without evidence of Contractor's approval will be returned for resubmission.
B. Submit complete sets of required materials for each RSN as specified in “Submittals Required” column in Table 01 33 00A - List of Submittals. A complete set includes listed items for RSNs with multiple parts.
C. Submit sets specified in “Sets to be sent:” columns in Table 01 33 00A - List of Submittals.
1. Submittals identified with “CDMS” in the “Sets to be sent” column shall be submitted electronically in accordance with Section 01 31 30 - Contract Document Management System.
D. Include the following information in transmittal letters:
1. Contract number and title.
2. RSN for each attached submittal.
3. Responsible code.
4. Number of sets for each RSN.
5. Identify submittal as initial or resubmittal.
01 33 00 - 5
E. Resubmittal of submittals not approved:
1. Mark changes such that they are readily identifiable and show revision date.
2. Describe reasons for significant changes in transmittal letter.
3. Resubmit returned submittals within 28 days after receiving the comments, unless otherwise directed.
4. Requirements for initial submittals apply to resubmittals.
1.06 REVIEW OF SUBMITTALS
A. Time Required:
1. Submittal review will require 21 days for review of each submittal or resubmittal, unless otherwise specified.
2. Time required for review of each submittal or resubmittal begins when complete sets of materials required for a particular RSN are received and extends through return mailing postmark date.
B. Time in Excess of Specified:
1. CO may extend contract completion date to allow additional time for completing work affected by excess review time.
a. Time extension will be to extent that excess review time caused delay to contract completion date.
b. Time extension will not exceed time used in excess of specified number of days for review of submittals or resubmittals.
c. Concurrent days of excess review time resulting from review of 2 or more separate submittals or resubmittals will be counted only once in extending contract completion date.
2. No time extension will be allowed if Contractor fails to make complete action submittals in sequence and within time periods specified.
3. Adjustment for delay will be made only to the extent that:
a. Approval was required under the contract, and.
b. Requests for approval were properly and timely submitted and were approved.
4. Adjustment will be subject to terms of paragraphs (b) and (c) of clause at FAR 52.242-14, Suspension of Work; however, no such delay shall be deemed to be a “suspension order” as term is used in that clause.
C. Return of Submittals:
1. Return of submittals will be by CDMS response or hard copy, as applicable.
2. Action Submittals: 1 set of submittals required for action will be returned either approved, approved with comments or not approved.
01 33 00 - 6
a. Revise and resubmit submittals not approved.
b. Do not change designs without approval of CO after drawings, documentation, and technical data have been approved.
3. Informational Submittals: Government will acknowledge Informational submittals.
a. Informational submittals will not be returned when they satisfy contract requirements.
b. Informational submittals that do not satisfy contract requirements may be returned for resubmittal or additional information may be requested.
1.07 HARD COPY TRANSMITTALS
A. Addresses for codes listed in Table 01 33 00A - List of Submittals:
1. Contracting Officer, Bureau of Reclamation, Attn UC-840, 125 South State St, Room 6107, Salt Lake City, UT 84138-1147.
2. Construction Engineer, Bureau of Reclamation, 1235 La Plata Hwy, Farmington, New Mexico, 87401.
3. Technical Service Center, Bureau of Reclamation, Attn: 86-68510, P.O. Box 25007, Denver CO 80225-0007; Express Mail: Sixth and Kipling, Building 67, Room 152.
B. Send original transmittal letter with appropriate number of sets to office listed in “Responsible Code” column in Table 01 33 00A - List of Submittals.
1. Responsible codes starting with “86-6” are located in Technical Service Center.
Send these submittals to the TSC address shown above.
C. Send copy of transmittal letter with appropriate number of sets to offices that are not responsible code, but show “Sets to be sent” in Table 01 33 00A - List of Submittals.
D. When “Sets to be sent” is 0, send a copy of transmittal letter to that office.
E. Submittals required by specifications, but not listed in Table 01 33 00A - List of Submittals:
1. Submit in accordance with this section.
2. Submit to CE unless otherwise specified.
PART 2 PRODUCTS
Not Used
01 33 00 - 7
PART 3 EXECUTION
Not Used
01 33 00 - 8
Table 01 33 00A. - List of Submittals
* Submittal Types: A - Action, I - Information ** CO indicates Contracting Officer, CE indicates Construction Engineer, and TSC indicates Technical Service Center. CDMS indicates Contract Document Management System.
RSN
Clause or
Section Title
Submittals required Due date or delivery time
Type
Respon-sible code
Sets to be sent: **
CO CE TSC
01 14 10-1 Use of Site Land Use and Landscape Rehabilitation Plan
At least 28 days before use of Government land
A CE CDMS
01 31 19-1 Project Management and Coordination
Written Summary Monthly once on-site construction begins
A CE CDMS
01 31 19-2 Project Management and Coordination
Off Easement Land Use Coordination
At least 4 months prior to use of land
A CE CDMS
01 31 30-1 Contract Document Management System
Approval Data Within 7 days of Award A CE 0 1 0
01 31 30-2 Contract Document Management System
Final Data Within 14 days of completion of work
I CE 0 2 2
01 32 10-1 Construction Program
Representative Information
Within 7 days after receipt of Notice of Award
I CE CDMS
01 32 10-2 Construction Program
Baseline Schedule Within 21 days after receipt of Notice to Proceed
A CE 0 5 3
01 32 10-3 Construction Program
Updated Schedule Reports
With monthly requests for progress payments.
A CE CDMS
01 32 10-4 Construction Program
Time Impact Analysis
Within 28 days after CO directs a contract change, with any proposal for a future modification, with any value engineering proposal, or with any request or claim for an equitable adjustment to the contract
A CE CDMS
01 35 10-1 Safety Data Sheets
Complete LHM and
SDS
At least 14 days before jobsite delivery of hazardous material
I CE CDMS
01 35 10-2 Safety Data Sheets
Updated LHM and
SDS
At least 14 days before jobsite delivery of hazardous material not previously listed
I CE CDMS
01 33 00 - 9
Table 01 33 00A. - List of Submittals
* Submittal Types: A - Action, I - Information ** CO indicates Contracting Officer, CE indicates Construction Engineer, and TSC indicates Technical Service Center. CDMS indicates Contract Document Management System.
RSN
Clause or
Section Title
Submittals required Due date or delivery time
Type
Respon-sible code
Sets to be sent: **
CO CE TSC
01 35 20-1 Safety and Health
Emergency Action Plans Written Program and Training Records
At least 21 days before beginning onsite work
A CE CDMS
01 35 20-2 Safety and Health
Job Hazard Analyses
(JHA)
At least 28 days before beginning onsite work
A CE CDMS
01 35 20-3 Safety and Health
Exposer Assessment Form
At least 28 days before beginning onsite work
A CE CDMS
01 35 20-4 Safety and Health
Monthly Accident Summary Report
First day of each month. See paragraph
3.8 of RSHS.
A CE CDMS
01 35 20-5 Safety and Health
Respirator User Documentation
At least 30 days before beginning onsite work
A CE CDMS
01 35 20-6 Safety and Health
Crane Training Certificates
At least 28 days before beginning onsite work
A CE CDMS
01 35 20-7 Safety and Health
Other Training Certificates, as applicable
At least 28 days before beginning onsite work
A CE CDMS
01 35 22-1 First-Aid Medical Facilities Plan
Submitted and approved before start of operations
A CO CDMS
01 35 30-1 Contractor‘s Onsite Safety Personnel
Resume At least 14 days before beginning on-site construction
I CE CDMS
01 35 30-2 Contractor’s Onsite Safety Personnel
Safety Inspection Reports
Once each week I CE CDMS
01 46 20-1 Testing Agency Services
Testing Agency Services Plan
At least 28 days before testing is required
A CE CDMS
01 55 00-1 Vehicular Access and Parking
Initial Digital Recording
At least 21 days before beginning on-site work
A CE 0 1 0
01 55 00-2 Vehicular Access and Parking
Post Construction Digital Recording
At least 21 days before leaving site.
A CE 0 1 0
01 55 00-3 Vehicular Access and Parking
Post Repair Digital Recording
Within 14 days of making repairs.
A CE 0 1 0
01 55 20-1 Traffic Control
Traffic Control Plan At least 60 days before affecting public traffic.
A CE CDMS
01 33 00 - 10
Table 01 33 00A. - List of Submittals
* Submittal Types: A - Action, I - Information ** CO indicates Contracting Officer, CE indicates Construction Engineer, and TSC indicates Technical Service Center. CDMS indicates Contract Document Management System.
RSN
Clause or
Section Title
Submittals required Due date or delivery time
Type
Respon-sible code
Sets to be sent: **
CO CE TSC
01 55 20-2 Traffic Control
Permit Applications At least 60 days before affecting public traffic
A CE CDMS
01 55 20-3 Traffic Control
Permits At least 14 days before affecting public traffic
I CE CDMS
01 56 10-1 Protection of Existing Installations
Plan for Protecting Existing Installations
At least 28 days before start of onsite construction work
A CE CDMS
01 56 15-1 Protection of Existing Utilities
Utility Owner Acknowledgment
At least 28 days before start of onsite construction work
A CE CDMS
01 56 15-2 Protection of Existing Utilities
Utility Investigation At least 7 days after completing investigation
I CE CDMS
01 57 20-1 Environment al Controls
Copy of Applicable Air Quality Permit
At least 14 days before beginning on-site work
I CE CDMS
01 57 30-1 Water Pollution Control
Updated Stormwater Pollution Prevention Plan (SWPPP)
At least 28 days before commencing construction activities
A CE CDMS
01 57 30-2 Water Pollution Control
Spill Prevention Control and Countermeasure (SPCC) Plan
At least 28 days before delivery or storage of oil
A CE CDMS
01 57 50-1 Tree and Plant Protection
Protection Plan At least 28 days before commencing on site construction work
A CE CDMS
01 57 90-1 Preservation of Historical and Archeologic al Data
Alternate Use Area or Borrow Area
At least 28 days before commencing on site construction work
A CE CDMS
01 71 20-1 Surveying Surveying Plan At least 28 days before beginning survey work
A CE CDMS
01 71 20-2 Surveying Resume At least 28 days before beginning survey work;
At least 28 days before personnel change
I CE CDMS
01 71 20-3 Surveying Accuracy Check Results
At least 28 days before beginning work
I CE CDMS
01 71 20-4 Surveying Completed and Reduced Survey Notes
Within 2 days of completing and reducing notes
I CE CDMS
01 71 20-5 Surveying Original Field Survey Books
Weekly I CE CDMS
01 33 00 - 11
Table 01 33 00A. - List of Submittals
* Submittal Types: A - Action, I - Information ** CO indicates Contracting Officer, CE indicates Construction Engineer, and TSC indicates Technical Service Center. CDMS indicates Contract Document Management System.
RSN
Clause or
Section Title
Submittals required Due date or delivery time
Type
Respon-sible code
Sets to be sent: **
CO CE TSC
01 71 20-6 Surveying Quantity Survey Notes and Computations
Accompanying progress payment requests
I CE CDMS
01 71 20-7 Surveying Workday's Survey Notes
At conclusion of workday if requested by Government
I CE CDMS
01 74 00-1 Cleaning and Waste Management
Waste Production and Disposal Plan
At least 28 days before starting onsite work
I CE CDMS
01 74 00-2 Cleaning and Waste Management
Waste Production and Disposal Records
Within 7 days of waste disposal
I CE CDMS
01 74 00-3 Cleaning and Waste Management
Environmental Consultant Resume
At least 28 days before beginning environmental assessment
I CE CDMS
01 74 00-4 Cleaning and Waste Management
Environmental Site Assessment
Within 14 days of completion of work
I CE CDMS
01 78 30-1 Project Record Documents
Progress As-built Drawings
Within 14 days of completion of structures or every 14 days whichever is fewer.
I CE 0 1 1
CDMS
01 78 30-1 Project Record Documents
Final As-built Drawings
Within 14 days of completion of work
I CE 0 1 1
CDMS
03 20 00-1 Concrete Reinforcing
Reinforcement Diagrams and Lists
At least 42 days before placing concrete
A 86-68530 CDMS
03 30 00-1 Cast-In- Place Concrete
Approval Data At least 42 days before placing concrete
A 86-68530 CDMS
03 30 00-2 Cast-In- Place Concrete
Certifications At least 42 days before placing concrete
A 86-68530 CDMS
03 30 00-3 Cast-In- Place Concrete
Cementitious Materials Certification and Test Reports
At least 42 days before placing concrete
A 86-68530 CDMS
03 30 00-4 Cast-In- Place Concrete
Test Reports At least 42 days before placing concrete
A 86-68530 CDMS
03 48 00-1 Precast Concrete Structures
Product Drawings and Data
At least 42 days before casting first structure
A 86-68120 CDMS
01 33 00 - 12
Table 01 33 00A. - List of Submittals
* Submittal Types: A - Action, I - Information ** CO indicates Contracting Officer, CE indicates Construction Engineer, and TSC indicates Technical Service Center. CDMS indicates Contract Document Management System.
RSN
Clause or
Section Title
Submittals required Due date or delivery time
Type
Respon-sible code
Sets to be sent: **
CO CE TSC
03 48 00-2 Precast Concrete Structures
Mix Design At least 42 days before casting first structure
I 86-68530 CDMS
03 48 00-3 Precast Concrete Structures
Curing, Handling and Storage Requirements
At least 42 days before casting first structure
A 86-68530 CDMS
03 63 00-1 Epoxy Grout Approval Data At least 42 days before placing grout
A 86-68530 CDMS
04 22 10-1 Reinforced Concrete Unit Masonry Assemblies
Approval Data At least 42 days before beginning construction with concrete masonry units
A 86-68120 CDMS
04 22 10-2 Reinforced Concrete Unit Masonry Assemblies
Sample Kit At least 42 days before beginning construction with concrete masonry units
A 86-68120 0 0 1
04 22 10-3 Reinforced Concrete Unit Masonry Assemblies
Certifications At least 42 days before beginning construction with concrete masonry units
A 86-68120 CDMS
04 22 10-4 Reinforced Concrete Unit Masonry Assemblies
Mix Design At least 42 days before beginning construction with concrete masonry units
A 86-68120 CDMS
04 22 10-5 Reinforced Concrete Unit Masonry Assemblies
Instructions At least 42 days before beginning construction with concrete masonry units
A 86-68120 CDMS
05 21 00-1 Steel Joists Approval Drawings, Data, and Certification
At least 42 days before fabricating joists
A 86-68120 CDMS
05 21 00-2 Steel Joists Welder Qualifications
At least 42 days before fabricating joists
A 86-68120 CDMS
05 21 00-3 Steel Joists Inspection Reports Within 30 days of completing inspection
A 86-68120 CDMS
05 30 00-1 Metal Roof Deck
Approval Drawings and Data
At least 42 days before installing roof deck
A 86-68120 CDMS
05 30 00-2 Metal Roof Deck
Welder Qualifications
At least 42 days before installing roof deck
A 86-68120 CDMS
01 33 00 - 13
Table 01 33 00A. - List of Submittals
* Submittal Types: A - Action, I - Information ** CO indicates Contracting Officer, CE indicates Construction Engineer, and TSC indicates Technical Service Center. CDMS indicates Contract Document Management System.
RSN
Clause or
Section Title
Submittals required Due date or delivery time
Type
Respon-sible code
Sets to be sent: **
CO CE TSC
07 41 13-1 Preinsulated Metal Roof Panels
Sample and Color Sample Kit
At least 42 days before installing panels
A 86-68120 0 0 1
07 41 13-2 Preinsulated Metal Roof Panels
Product Data and Shop Drawings
At least 42 days before installing panels
A 86-68120 CDMS
07 41 13-3 Preinsulated Metal Roof Panels
Closeout Maintenance Data
Within 14 days of installing panels
A 86-68120 CDMS
07 42 13-1 Preinsulated Metal Wall Panels
Sample and Color Sample Kit
At least 42 days before installing panels
A 86-68120 0 0 1
07 42 13-2 Preinsulated Metal Wall Panels
Product Data and Shop Drawings
At least 42 days before installing panels
A 86-68120 CDMS
07 42 13-3 Preinsulated Metal Wall Panels
Closeout Maintenance Data
Within 14 days of installing panels
A 86-68120 CDMS
08 34 53-1 Security Doors and Frames
Approval Drawings and Data
At least 42 days before installing doors
A 86-68120 CDMS
08 34 53-2 Security Doors and Frames
Instructions At least 42 days before installing doors
A 86-68120 CDMS
08 71 00-1 Door Hardware
Approval Data At least 42 days before installing hardware
A 86-68120 CDMS
08 71 00-2 Door Hardware
Instructions At least 42 days before installing hardware
A 86-68120 CDMS
09 65 10-1 Rubber Wall Base
Approval Data and Color Sample Kit
At least 42 days before installing wall base
A 86-68120 CDMS
09 65 10-2 Rubber Wall Base
Instructions At least 42 days before installing wall base
A 86-68120 CDMS
09 96 20-1 Coatings Approval Data At least 42 days before beginning coating work
A 86-68540 CDMS
09 96 20-2 Coatings Final Approval Data At least 42 days before beginning coating work
A 86-68540 CDMS
09 96 20-3 Coatings Contractor Testing Data for “Shop or Field Applied” Coatings
At least 42 days before beginning coating work
A 86-68540 CDMS
10 14 26-1 Utility Markers
Utility Marker Plan At least 42 days before start of construction activities
01 33 00 - 14
Table 01 33 00A. - List of Submittals
* Submittal Types: A - Action, I - Information ** CO indicates Contracting Officer, CE indicates Construction Engineer, and TSC indicates Technical Service Center. CDMS indicates Contract Document Management System.
RSN
Clause or
Section Title
Submittals required Due date or delivery time
Type
Respon-sible code
Sets to be sent: **
CO CE TSC
22 11 35-1 Pre- Manufacture d Pump Station
Pre-construction Data and Drawings
At least 42 days before fabrication or procurement
A 86-68410 CDMS
22 11 35-2 Pre- Manufacture d Pump Station
Manufacturer Post Production Testing Results
At least 42 days before fabrication or procurement
A 86-68410 CDMS
22 11 35-3 Pre- Manufacture d Pump Station
Manufacturer On-site Testing Results and Final Documents
At least 42 days before fabrication or procurement
A 86-68420 0 1 1
CDMS
22 13 16-1 Foundation and Building Drainage Piping
Approval Data Within 42 days after Notice to proceed
A 86-68410 CDMS
23 05 93-1 Testing, Adjusting, and Balancing for HVAC Equipment
Approval Data Within 42 days after Notice to proceed
A 86-68410 CDMS
23 05 93-2 Testing, Adjusting, and Balancing for HVAC Equipment
Certified Testing Adjusting and Balance Reports
Within 14 days of final testing
A 86-68410 CDMS
23 33 10-1 Duct Accessories
HVAC Accessories Approval Data
Within 42 days after Notice to proceed
A 86-68410 CDMS
23 33 10-2 Duct Accessories
HVAC Accessories Final Data
Within 14 days of final testing
A 86-68410 CDMS
23 34 00-1 HVAC Fans Approval Data Within 42 days after Notice to proceed
A 86-68410 CDMS
23 34 00-2 HVAC Fans Final Data Within 14 days of final testing
A 86-68410 CDMS
23 82 39-1 Unit Heaters Approval Data Within 42 days after Notice to proceed
A 86-68410 CDMS
23 82 39-2 Unit Heaters Final Data Within 14 days of final testing
A 86-68410 CDMS
01 33 00 - 15
Table 01 33 00A. - List of Submittals
* Submittal Types: A - Action, I - Information ** CO indicates Contracting Officer, CE indicates Construction Engineer, and TSC indicates Technical Service Center. CDMS indicates Contract Document Management System.
RSN
Clause or
Section Title
Submittals required Due date or delivery time
Type
Respon-sible code
Sets to be sent: **
CO CE TSC
25 00 01-1 Control and Monitoring
Approval Data - Monitoring and Control Systems Technical Specialist Work Summary
Within 42 days after Notice to Proceed
A 86-68450 CDMS
25 00 01-2 Control and Monitoring
Approval Drawings and Data
Within 42 days after Notice to Proceed
A 86-68450 CDMS
25 00 01-3 Control and Monitoring
Approval Data - Software Development Documentation
Within 42 days after Notice to Proceed
A 86-68450 CDMS
25 00 01-4 Control and Monitoring
Check Prints At same time as equipment is shipped to the site
A 86-68450 CDMS
25 00 01-5 Control and Monitoring
Approval Data - Final Drawings, Documentation, and Operations and Maintenance Manuals
Within 42 days after Notice to Proceed
A 86-68450 CDMS
25 00 02-1 Programmab le Controller
Approval Drawings Within 42 days after Notice to Proceed
A 86-68450 CDMS
25 00 02-2 Programmab le Controller
Approval Data Within 42 days after Notice to Proceed
A 86-68450 CDMS
25 00 02-3 Programmab le Controller
Final Drawings, Documentation, and Operations and Maintenance Manuals
Within 28 days after installation
I 86-68450 CDMS
25 08 10-1 Automation System Testing, Acceptance, and Training
FAT Procedure and Start Date
At least 42 days before beginning test
A 86-68450 CDMS
25 08 10-2 Automation System Testing, Acceptance, and Training
FAT Test Report Not more than 28 days after test
I 86-68450 CDMS
25 08 10-3 Automation System Testing, Acceptance, and Training
SPAT Procedure and Start Date
At least 42 days before beginning test
A 86-68450 CDMS
01 33 00 - 16
Table 01 33 00A. - List of Submittals
* Submittal Types: A - Action, I - Information ** CO indicates Contracting Officer, CE indicates Construction Engineer, and TSC indicates Technical Service Center. CDMS indicates Contract Document Management System.
RSN
Clause or
Section Title
Submittals required Due date or delivery time
Type
Respon-sible code
Sets to be sent: **
CO CE TSC
25 08 10-4 Automation System Testing, Acceptance, and Training
SPAT Test Report Not more than 28 days after test
I 86-68450 CDMS
25 08 10-5 Automation System Testing, Acceptance, and Training
OAT Procedure and Start Date
At least 42 days before beginning test
A 86-68450 CDMS
25 08 10-6 Automation System Testing, Acceptance, and Training
OAT Report Not more than 28 days after test
I 86-68450 CDMS
25 08 10-7 Automation System Testing, Acceptance, and Training
Training Plan No less than 42 days before first commissioning is scheduled to begin
I 86-68450 CDMS
26 05 10-1 Conductors and Cables
Approval Data Within 42 days after Notice to Proceed
A 86-68430 CDMS
26 05 10-2 Conductors and Cables
Field Test Reports Not more than 30 days after test
I 86-68430 CDMS
26 05 13-1 Medium- Voltage Power Cable System
Approval Drawings and Data
Within 42 days after Notice to Proceed
A 86-68430 CDMS
26 05 13-2 Medium- Voltage Power Cable System
Field Test Reports Within 14 days after tests are completed
I 86-68430 CDMS
26 05 20-1 Grounding and Bonding
Approval Drawings and Data
Within 42 days after Notice to Proceed
A 86-68430 CDMS
26 05 20-2 Grounding and Bonding
Test Reports Within 14 days after tests are completed
I 86-68430 CDMS
26 05 33-1 Raceways and Boxes
Approval Drawings and Data
Within 42 days after Notice to Proceed
A 86-68430 CDMS
26 13 26-1 Medium- Voltage Metal-Clad Switchgear
Approval Drawings and Data
Within 42 days after Notice to Proceed
A 86-68430 CDMS
01 33 00 - 17
Table 01 33 00A. - List of Submittals
* Submittal Types: A - Action, I - Information ** CO indicates Contracting Officer, CE indicates Construction Engineer, and TSC indicates Technical Service Center. CDMS indicates Contract Document Management System.
RSN
Clause or
Section Title
Submittals required Due date or delivery time
Type
Respon-sible code
Sets to be sent: **
CO CE TSC
26 13 26-2 Medium- Voltage Metal-Clad Switchgear
Wiring Diagrams Within 14 days after tests are completed
I 86-68430 CDMS
26 13 26-3 Medium- Voltage Metal-Clad Switchgear
Check Prints At same time as equipment is shipped to the site
A 86-68430 CDMS
26 13 26-4 Medium- Voltage Metal-Clad Switchgear
Factory Test Reports Within 14 days after tests are completed
I 86-68430 CDMS
26 13 26-5 Medium- Voltage Metal-Clad Switchgear
Field Test Reports Within 14 days after tests are completed
I 86-68430 CDMS
26 13 26-6 Medium- Voltage Metal-Clad Switchgear
Final Drawings Within 14 days after installation
A 86-68430 CDMS
26 13 26-7 Medium- Voltage Metal-Clad Switchgear
Operation and Maintenance Instruction Book
Within 14 days after installation
I 86-68430 CDMS
26 16 13-1 Primary Unit Substation
Approval Drawings and Data
Within 42 days after Notice to Proceed
A 86-68430 CDMS
26 16 13-2 Primary Unit Substation
Schematic and Wiring Diagrams
Within 42 days after Notice to Proceed
A 86-68430 CDMS
26 16 13-3 Primary Unit Substation
Factory Test Notification
At least 14 days prior to testing
A 86-68430 CDMS
26 16 13-4 Primary Unit Substation
Check Prints At same time as equipment is shipped to the site
A 86-68430 CDMS
26 16 13-5 Primary Unit Substation
Factory Test Reports Within 14 days after tests are completed
A 86-68430 CDMS
26 16 13-6 Primary Unit Substation
Field Test Reports Within 14 days after tests are completed
A 86-68430 CDMS
26 16 13-7 Primary Unit Substation
Final Drawings Within 28 days after installation
A 86-68430 CDMS
26 16 13-8 Primary Unit Substation
Operation and Maintenance Instruction Book
Within 14 days after Final Drawings acceptance
A 86-68430 CDMS
01 33 00 - 18
Table 01 33 00A. - List of Submittals
* Submittal Types: A - Action, I - Information ** CO indicates Contracting Officer, CE indicates Construction Engineer, and TSC indicates Technical Service Center. CDMS indicates Contract Document Management System.
RSN
Clause or
Section Title
Submittals required Due date or delivery time
Type
Respon-sible code
Sets to be sent: **
CO CE TSC
26 22 12-1 Dry-Type Transformer s
Approval Data Within 42 days after Notice to proceed
A 86-68430 CDMS
26 22 12-2 Dry-Type Transformer s
Operation and Maintenance Instruction Book
Within 14 days after installation
I 86-68430 CDMS
26 24 41-1 Distribution Panelboards
Approval Data Within 42 days after Notice to proceed
A 86-68430 CDMS
26 24 41-2 Distribution Panelboards
Approval Layouts Within 42 days after Notice to proceed
A 86-68430 CDMS
26 24 41-3 Distribution Panelboards
Test Data Within 14 days after tests are completed
I 86-68430 CDMS
26 27 40-1 Wiring Devices
Approval Data Within 42 days after Notice to proceed
A 86-68430 CDMS
26 42 10-1 Buried Galvanic Anode Cathodic Protection and Corrosion Monitoring Systems
Certification and Data
At least 42 days before procuring materials
A 86-68540 CDMS
26 42 10-2 Buried Galvanic Anode Cathodic Protection and Corrosion Monitoring Systems
Final Data Within 7 days of final testing
A 86-68540 CDMS
26 42 11-1 Submerged Galvanic Anode Cathodic Protection System for Welded Tanks
Certification and Data
At least 42 days before procuring materials
A 86-68540 CDMS
01 33 00 - 19
Table 01 33 00A. - List of Submittals
* Submittal Types: A - Action, I - Information ** CO indicates Contracting Officer, CE indicates Construction Engineer, and TSC indicates Technical Service Center. CDMS indicates Contract Document Management System.
RSN
Clause or
Section Title
Submittals required Due date or delivery time
Type
Respon-sible code
Sets to be sent: **
CO CE TSC
26 42 11-2 Submerged Galvanic Anode Cathodic Protection System for Welded Tanks
Final Data Within 7 days of final testing
A 86-68540 CDMS
26 42 12-1 Bolted Tank Submerged Galvanic Anode Cathodic Protection System
Certification, Design, and Manufacturer’s Data
At least 42 days before procuring materials
A 86-68540 CDMS
26 42 12-2 Bolted Tank Submerged Galvanic Anode Cathodic Protection System
Final Data Within 7 days of final testing
A 86-68540 CDMS
26 51 00-1 Interior Lighting
Approval Data Within 42 days after Notice to proceed
A 86-68430 CDMS
26 52 00-1 Emergency and Exit Lighting
Approval Data Within 42 days after Notice to proceed
A 86-68430 CDMS
26 56 00-1 Exterior Lighting
Approval Data Within 42 days after Notice to proceed
A 86-68430 CDMS
27 15 00-1 Communicat ions Cabling
Approval Data Within 42 days after Notice to Proceed
A 86-68450 CDMS
27 15 00-2 Communicat ions Cabling
Approval Data Within 42 days after Notice to Proceed
A 86-68450 CDMS
27 20 01-1 Radio Equipment
Approval Drawings and Data
Within 42 days after Notice to Proceed
A 86-68450 CDMS
27 20 01-2 Radio Equipment
Operations and Maintenance Manual
Within 30 days after installation
I 86-68450 CDMS
27 30 01-1 Telephone Equipment
Approval Drawings and Data
Within 42 days after Notice to Proceed
A 86-68450 CDMS
27 30 01-2 Telephone Equipment
Check Prints Within 14 days after installation
A 86-68450 CDMS
27 30 01-3 Telephone Equipment
Operations and Maintenance Manual
Within 30 days after installation
I 86-68450 CDMS
01 33 00 - 20
Table 01 33 00A. - List of Submittals
* Submittal Types: A - Action, I - Information ** CO indicates Contracting Officer, CE indicates Construction Engineer, and TSC indicates Technical Service Center. CDMS indicates Contract Document Management System.
RSN
Clause or
Section Title
Submittals required Due date or delivery time
Type
Respon-sible code
Sets to be sent: **
CO CE TSC
27 30 01-4 Telephone Equipment
Field Operational Checkout Test Report
At least 42 days before beginning test
I 86-68450 CDMS
28 10 01-1 Security and Surveillance Equipment
Approval Drawings and Data
Within 42 days after Notice to Proceed
A 86-68450 CDMS
28 10 01-2 Security and Surveillance Equipment
Test Procedure and Start Date
At least 42 days before beginning test
I 86-68450 CDMS
28 10 01-3 Security and Surveillance Equipment
Test Report Not more than 28 days after test
I 86-68450 CDMS
28 10 01-4 Security and Surveillance Equipment
Check Prints At same time as equipment is shipped to the site
A 86-68450 CDMS
28 10 01-5 Security and Surveillance Equipment
Final Drawings and Operations and Maintenance Manuals
Within 28 days after installation
I 86-68450 CDMS
28 31 00-1 Fire Detection and Alarm
Approval Data Within 42 days after Notice to Proceed
A 86-68450 CDMS
28 31 00-2 Fire Detection and Alarm
Testing Procedure and Notification
At least 42 days before beginning test
I 86-68450 CDMS
28 31 00-3 Fire Detection and Alarm
Test Reports Not more than 28 days after test
I 86-68450 CDMS
28 31 00-4 Fire Detection and Alarm
Training Materials Within 28 days after installation
I 86-68450 CDMS
28 31 00-5 Fire Detection and Alarm
Operation and Maintenance Instruction Book
Within 28 days after installation
I 86-68450 CDMS
31 02 10-1 Water for Dust Abatement
Meter Calibration At least 42 days before beginning on-site work
A CE CDMS
31 02 30-1 Dust Palliative
Proposed Application Area for Dust Palliative
At least 42 days before beginning on-site work
A CE CDMS
31 23 02-1 Compacting Earth Materials
Test Results Within 7 days after completion of tests
I CE CDMS
01 33 00 - 21
Table 01 33 00A. - List of Submittals
* Submittal Types: A - Action, I - Information ** CO indicates Contracting Officer, CE indicates Construction Engineer, and TSC indicates Technical Service Center. CDMS indicates Contract Document Management System.
RSN
Clause or
Section Title
Submittals required Due date or delivery time
Type
Respon-sible code
Sets to be sent: **
CO CE TSC
31 23 70-1 Controlled Low Strength Material
(CLSM)
Approval Data For CLSM Produced Without Native Soil
At least 42 days before placing
A 86-68530 CDMS
31 23 70-2 Controlled Low Strength Material
(CLSM)
Approval Data For CLSM Produced With Native Soil
At least 42 days before placing
A CE CDMS
31 23 70-3 Controlled Low Strength Material
(CLSM)
Contractor Field Quality Testing Results
Within 7 days of testing A CE CDMS
31 31 30-1 Soil-Applied Herbicide
Use Plan At least 28 days before placing
A CE CDMS
31 31 30-2 Soil-Applied Herbicide
Applier Certification At least 28 days prior to beginning work
A CE CDMS
31 37 00-1 Riprap Approval Data and Test Results
At least 42 days before placing lining
A CE CDMS
32 15 10-1 Gravel Surfacing
Gravel Certification At least 42 days before placing surfacing
A CE CDMS
32 15 10-2 Gravel Surfacing
Geofabric Installation
At least 42 days before placing surfacing
A CE CDMS
32 15 10-3 Gravel Surfacing
Geofabric Certification
At least 42 days before placing surfacing
A CE CDMS
32 31 10-1 Chain Link Fence
Certification At least 42 days before installing fencing
A CE CDMS
32 91 60-1 Erosion Control Blanket
Manufacturer’s Information
At least 28 days before placing blanket
A CE CDMS
32 91 60-2 Erosion Control Blanket
Installation Plan At least 28 days before placing blanket
A CE CDMS
32 92 20-1 Seeding Seeding Plan At least 28 days before seeding
A CE CDMS
32 92 20-2 Seeding Certifications At least 28 days prior to beginning work
A CE CDMS
33 05 21-1 Bored Utility Crossings
Placement Plan At least 28 days prior to beginning work
01 33 00 - 22
Table 01 33 00A. - List of Submittals
* Submittal Types: A - Action, I - Information ** CO indicates Contracting Officer, CE indicates Construction Engineer, and TSC indicates Technical Service Center. CDMS indicates Contract Document Management System.
RSN
Clause or
Section Title
Submittals required Due date or delivery time
Type
Respon-sible code
Sets to be sent: **
CO CE TSC
33 05 21-1 Bored Utility Crossings
Material Certification
At least 28 days prior to beginning work
A CE CDMS
33 09 08-1 Probe Magnetic Flowmeter
Approval Data At least 42 days before procurement
A 86-68410 CDMS
33 09 08-2 Probe Magnetic Flowmeter
Final Data Within 14 days prior to shipment to site
I 86-68410 CDMS
33 09 08-3 Probe Magnetic Flowmeter
Test Reports Within 14 days of completion of tests
I 86-68410 CDMS
33 11 10-1 Pipeline General Requirement s
Qualifications At least 42 days before pipe fabrication or procurement
A CE CDMS
33 11 10-2 Pipeline General Requirement s
Pipelaying Diagrams At least 42 days before pipe fabrication or procurement
A 86-68140 CDMS
33 11 10-3 Pipeline General Requirement s
Filling and Testing Plan
At least 42 days before pipe fabrication or procurement
A 86-68140 CDMS
33 11 10-4 Pipeline General Requirement s
Floatation Prevention Plan
At least 42 days before pipe fabrication or procurement
A 86-68140 CDMS
33 11 12-1 Steel Line Pipe
Shop Drawings At least 42 days before pipe fabrication or procurement
A 86-68140 CDMS
33 11 12-2 Steel Line Pipe
Ventilation Plan At least 42 days before pipe fabrication or procurement
A 86-68140 CDMS
33 11 13-1 Ductile Iron Pipe
Shop Drawings At least 42 days before pipe fabrication or procurement
A 86-68140 CDMS
33 11 16-1 PVC
Pressure Pipe
Shop Drawings At least 42 days before pipe fabrication or procurement
A 86-68140 CDMS
33 11 16-2 PVC
Pressure Pipe
Pipe Manufacture Certification
Within 24 hours of taking measurements
01 33 00 - 23
Table 01 33 00A. - List of Submittals
* Submittal Types: A - Action, I - Information ** CO indicates Contracting Officer, CE indicates Construction Engineer, and TSC indicates Technical Service Center. CDMS indicates Contract Document Management System.
RSN
Clause or
Section Title
Submittals required Due date or delivery time
Type
Respon-sible code
Sets to be sent: **
CO CE TSC
33 11 16-3 PVC
Pressure Pipe
Test Results Within 14 days of completion of tests
I CE CDMS
33 11 18-1 HDPE
Pressure Pipe
Heat Fusion Joint Operator Qualifications
At least 42 days before pipe fabrication or procurement
A CE CDMS
33 11 18-2 HDPE
Pressure Pipe
Shop Drawings At least 42 days before pipe fabrication or procurement
A 86-68140 CDMS
33 11 18-3 HDPE
Pressure Pipe
Certification 14 days before shipping A CE CDMS
33 11 18-4 HDPE
Pressure Pipe
Fusion Procedures At least 42 days before pipe fabrication or procurement
A CE CDMS
33 11 19-1 Fiberglass Pipe
Shop Drawings At least 42 days before pipe fabrication or procurement
A 86-68140 CDMS
33 11 19-2 Fiberglass Pipe
Joint Repair Plan At least 42 days prior to delivery
A 86-68140 CDMS
33 11 50-1 Pipe Crossings at Existing Utility Pipelines
Rubber Gasket Data At least 42 days before pipe fabrication or procurement
A CE CDMS
33 12 10-1 Valves and Equipment for Line Pipe Installations
Commercial Product Data
At least 42 days before fabrication or procurement
A 86-68140 CDMS
33 12 10-2 Valves and Equipment for Line Pipe Installations
Service Manuals Within 14 days after installation
I 86-68140 CDMS
33 16 14-1 Air Chambers
Qualifications At least 42 days before fabrication or procurement
A 86-68420 CDMS
33 16 14-2 Air Chambers
Shop Drawings, Design Calculations, and Design Data
At least 42 days before fabrication or procurement
A 86-68420 CDMS
33 16 14-3 Air Chambers
Surge Analysis At least 42 days before fabrication or procurement
A 86-68420 CDMS
01 33 00 - 24
Table 01 33 00A. - List of Submittals
* Submittal Types: A - Action, I - Information ** CO indicates Contracting Officer, CE indicates Construction Engineer, and TSC indicates Technical Service Center. CDMS indicates Contract Document Management System.
RSN
Clause or
Section Title
Submittals required Due date or delivery time
Type
Respon-sible code
Sets to be sent: **
CO CE TSC
33 16 14-4 Air Chambers
Commercial Products Data
At least 42 days before fabrication or procurement
A 86-68420 CDMS
33 16 14-5 Air Chambers
Service Manuals Within 14 days after installation
I 86-68420 CDMS
33 16 50-1 Steel Tanks Shop Drawings, Design Calculations and Design Data
At least 42 days before fabrication or procurement.
A 86-68420 CDMS
33 16 50-2 Steel Tanks Qualifications At least 42 days before fabrication or procurement.
A 86-68420 CDMS
33 16 50-3 Steel Tanks Nondestructive Weld Test Reports
Within 7 days after installation.
I 86-68420 CDMS
33 16 50-4 Steel Tanks Commercial Products Data
At least 42 days before fabrication or procurement.
A 86-68420 CDMS
33 16 50-5 Steel Tanks Final Drawings and Data
Within 14 days after installation.
I 86-68420 CDMS
33 21 95-1 Metal Piping for Line Pipe Installations
Shop Drawings At least 42 days before fabrication or procurement
A 86-68140 CDMS
33 21 95-2 Metal Piping for Line Pipe Installations
Commercial Products Data
At least 42 days before fabrication or procurement
A 86-68140 CDMS
33 21 95-3 Metal Piping for Line Pipe Installations
Final Drawings Within 14 days after installation
I 86-68140 CDMS
35 21 95-1 Steel Pipe Shop Drawings At least 42 days before fabrication or procurement.
A 86-68420 CDMS
35 21 95-2 Steel Pipe Commercial Products Data
At least 42 days before fabrication or procurement.
A 86-68420 CDMS
35 21 95-3 Steel Pipe Final Drawings Within 14 days after installation
I 86-68420 CDMS
35 22 15-1 Valves and Equipment
Commercial Product Data
At least 42 days before fabrication or procurement.
A 86-68420 CDMS
35 22 15-2 Valves and Equipment
Service Manuals Within 14 days after installation.
I 86-68420 CDMS
35 42 35-1 Bank Protection
Samples Within 14 days after tests are completed
A 86-68240 0 0 1
35 42 35-2 Bank Protection
Certifications Within 14 days after tests are completed
A 86-68240 CDMS
01 33 00 - 25
Table 01 33 00A. - List of Submittals
* Submittal Types: A - Action, I - Information ** CO indicates Contracting Officer, CE indicates Construction Engineer, and TSC indicates Technical Service Center. CDMS indicates Contract Document Management System.
RSN
Clause or
Section Title
Submittals required Due date or delivery time
Type
Respon-sible code
Sets to be sent: **
CO CE TSC
48 14 00-1 Solar and Electrical Equipment
Approval Data Within 42 days after Notice to Proceed
A 86-68430 CDMS
48 14 00-2 Solar and Electrical Equipment
Approval Drawings Within 42 days after Notice to Proceed
A 86-68430 CDMS
48 14 00-3 Solar and Electrical Equipment
Test Report Within 14 days after tests are completed
I 86-68430 CDMS
END OF SECTION
01 33 00 - 26
Concrete Forming
03 11 10 - 1
SECTION 03 11 10
CONCRETE FORMING
PART 1 GENERAL
1.01 MEASUREMENT AND PAYMENT
A. Cost:
1. Include transformer foundation forming in the price in the Price Schedule for Complete Electrical System.
B. Cost:
1. Include thrust block forming in the price in Price Schedule for Line Pipe.
C. Cost:
1. Include in the price in Price Schedule for Air Chamber No. 1.
D. Cost:
1. Include in the price in Price Schedule for Air Chamber No. 2.
E. Cost:
1. Include in the price in Price Schedule for Regulating Tank No. 1.
F. Cost:
1. Include in the price in Price Schedule for Regulating Tank No. 2.
1.02 REFERENCE STANDARDS
A. American Concrete Institute
1. ACI 318-11 Building Code Requirements for Structural Concrete and Commentary
B. APA - The Engineered Wood Association (APA)
1. APA PS 1-09 Structural Plywood
C. Bureau of Reclamation (USBR)
1. RSHS Reclamation Safety and Health Standards, including revisions posted at http://www.usbr.gov/ssle/safety/RSHS/rshs.
html
03 11 10 - 2
D. Western Wood Products Association (WWPA)
1. WWPA WLGR-11 Western Lumber Grading Rules
PART 2 PRODUCTS
2.01 THRUST BLOCKS
A. See Section 33 11 10 - Line Pipe.
2.02 AIR CHAMBER NO. 1 AND NO. 2
A. See Section 33 16 14 - Air Chambers.
2.03 REGULATING TANK NO. 1 AND NO. 2
A. See Section 33 16 50 - Steel Tanks.
PART 3 EXECUTION
3.01 FORM MATERIALS
A. Sheathing or Lining: Conform to Table 03 11 10A - Form Sheathing or Lining Materials, or provide other materials which will produce equivalent results.
Table 03 11 10A - Form Sheathing or Lining Materials
Finish Wood sheathing or lining Steel sheathing or lining
F1 Any grade common board or plywood
Steel sheathing permitted Steel lining permitted
F2 No. 2 common or better, shiplap, or plywood
Steel sheathing permitted Steel lining permitted if approved
F3 Plywood Steel sheathing permitted Steel lining not permitted
B. Steel sheathing is steel sheets not…