This solicitation requests proposals for the design-build of Wellington High Tunnels at the USDA Agricultural Research Service Field Research Implementation and Information Delivery Northeast Area facility in Geneva, New York. Offerors must provide stamped electrical drawings and site plans ensuring drainage is directed away from buildings to prevent ponding. The requirement is set aside for small businesses with a size standard of $39.5 million. The construction magnitude is between $500,000 and $1 million, and the period of performance is 210 days from notice to proceed. Payment and performance bonds are required for awards exceeding $150,000. A mandatory site visit will be held on August 23rd, with registration due by August 22nd. Questions are due by August 26th with responses published as amendments. Biobased products must be utilized where reasonably available and priced.
View the file
Other files for this federal contract opportunity
| File | Type | Posted |
|---|---|---|
| Amendment 1 - QandA - Wellington High Tunnels.pdf | ||
| 12305B22R0018 Wellington High Tunnels.pdf | ||
| Self Performed Work worksheet.docx | DOCX document | |
| EMR Certification - Wellington High Tunnels.docx | DOCX document | |
| PWS Wellington High Tunnels Geneva NY.pdf | ||
| Geneva Wellington HHGH High Tunnel EA.pdf | ||
| SUBMITTAL LOG - Wellington High Tunnels .xlsx | XLSX spreadsheet | |
| WD NY20220032 22JUL22 - Wellington High Twr Geneva NY.pdf |
On GovTribe
Work with this file on GovTribe
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
QUALITY ASSURANCE SURVEILLANCE PLAN
WELLINGTON HIGH TUNNELS
GENEVA, NY
PWS
PARA
ELEMENT
EVALUATED
PERFORMANCE
OBJECTIVE
PERFORMANCE THRESHOLD SURVEILLANCE
METHOD
1 Properly sized electrical service
Evaluation to meet the electrical requirements of greenhouse and pavilion kits.
Stamped electrical drawings Submittal and approval of electrical drawings.
2 Suitable site drainage
Evaluation to ensure drainage is directed away from build-ings’ foundations and pre-vent ponding on site.
Stamped site plans. Submittal and approval of site plans.