This environmental assessment and finding of no significant impact document describes the proposed construction of a new greenhouse at the USDA Agricultural Research Service Wellington Farm in Geneva, New York. Key details include that the greenhouse will measure approximately 60 feet by 96 feet and include a steel frame, polycarbonate glazing, and a concrete floor. The document evaluates the potential environmental impacts of the proposal and determines there will be no significant effects to land use, aesthetics, air quality, noise levels, geology and soils, water resources, biological resources, cultural resources, socioeconomics, infrastructure and utilities, or hazardous materials. Accordingly, the document concludes that the requirements of the applicable regulations have been satisfied and a finding of no significant impact is appropriate.
This federal contract opportunity solicitation is seeking proposals to design-build two high tunnel greenhouses at the USDA Agricultural Research Service Plant Genetic Resources Unit in Geneva, New York. Interested vendors should review solicitation number 12305B22R0018 for requirements, evaluation factors, and submission instructions. The procurement is set aside for small businesses only and has an estimated value between $500,000 to $1 million. Proposals are due under a lowest price technically acceptable evaluation. The period of performance is 210 days after notice to proceed. Payment and performance bonds are required for awards over $150,000. An organized site visit will be held on August 23rd and questions are due by August 26th. The solicitation requires the use of biobased products where available.
View the file
Other files for this federal contract opportunity
| File | Type | Posted |
|---|---|---|
| Amendment 1 - QandA - Wellington High Tunnels.pdf | ||
| 12305B22R0018 Wellington High Tunnels.pdf | ||
| QASP - Wellington High Tunnels.pdf | ||
| Self Performed Work worksheet.docx | DOCX document | |
| EMR Certification - Wellington High Tunnels.docx | DOCX document | |
| PWS Wellington High Tunnels Geneva NY.pdf | ||
| SUBMITTAL LOG - Wellington High Tunnels .xlsx | XLSX spreadsheet | |
| WD NY20220032 22JUL22 - Wellington High Twr Geneva NY.pdf |
On GovTribe
Work with this file on GovTribe
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
ENVIRONMENTAL
ASSESSMENT
WELLINGTON
FARM
HIGH TUNNELS
GREENHOUSE
PLANT GENETICS
RESEARCH UNIT
GENEVA, NY
Prepared for:
U.S. Department of Agriculture Agricultural Research Service
MARCH 2022
USDA-ARS
Geneva, NY
Environmental Assessment Wellington High Tunnels
1. Introduction The US Department of Agriculture (USDA) Agricultural Research Service (ARS) has completed this Environmental Assessment (EA) and Finding of No Significant Impact (FONSI) for the proposed action described below. The EA has been prepared in accordance with the National Environmental Policy Act (NEPA) of 1969, as amended (42 US Code § 4321 et seq.); the Council on Environmental Quality Regulations implementing NEPA (40 Code of Federal Regulations [CFR] §§ 1S00-1S08); and the USDA ARS Procedures for Implementing NEPA (1 CFR § S20). This EA evaluates the potential for significant effects to the quality of the human environment from the Proposed Action.
2. Purpose and Need
The USDA, ARS, Plant Genetic Resources Unit (PGRU), in Geneva, NY requires two new high tunnel greenhouses to be used to continue operations in the preservation of valuable vegetable and hemp germplasm and will be used by the Seeds, Clonal, and Hemp Groups.
Not having these structures has constrained PGRU operations for the last 10 years. As the hemp germplasm project is a recent addition to the crop germplasm conservation efforts, newly available funding from this project will be used to support the addition of this vital infrastructure upgrade.
3. Proposed Action The proposed action is to construct a new greenhouse at the USDA-ARS Wellington Farm, located at 2865 Preemption Road (County Road 6) in Geneva, NY. It will be an approximately 60’ x 96’ (5,760 SF) greenhouse to include steel framing, polycarbonate glazing on roof and endwalls, rollup sidewalls, ventilation, and concrete flooring. The greenhouse was originally planned to be two separate 30’ x 96’ greenhouses. However, the design changed to make one greenhouse with the same approximate square-footage and footprint.
4. Alternatives Considered The USDA ARS considered the No Action Alternative, as required by 40 CFR § 1S02.14. This alternative is retained for comparative analysis in this EA. The No Action Alternative was determined to be unacceptable as it would not allow the program to meet its needs. Therefore, it was dismissed.
March 2022 Page 1
5. Technical Resource Areas
• Land Use Is the Proposed Action likely to have a significant impact on current land use?
Yes □ No X The existing land use is agriculture and research. There would be no change to the site as a result of the Proposed Action.
Are the Alternatives likely to have a significant impact on current land use?
Yes□ No X The No Action Alternative would be the existing condition.
• Aesthetics Visual Resources Is the Proposed Action likely to have a significant impact on aesthetics or visual resources?
Yes□ No X The Proposed Action would include the construction of an approximately 5,760 square-foot greenhouse. Although the project involves the installation of the greenhouse, it will fit with existing structures, and it’s visual and aesthetic impact will not be significant
Is the No Action Alternative likely to have a significant impact on aesthetics or visual resources?
Yes □ No X
• Air Quality Is the Proposed Action likely to have a significant impact on air quality?
Yes □ No X The installation of the greenhouse would have minimal impact to the air quality, as only construction-related vehicles would give off exhaust during the construction. Additionally, dust control measures will be incorporated by the contractor to reduce any fugitive dust issues. Once the construction is complete, there will be no change in greenhouse gas emissions.
Is the No Action Alternative likely to have a significant impact on air quality?
There would be no impact to air quality as a result of the No Action Alternative.
March 2022 Page 2
• Noise Is the Proposed Action likely to have a significant impact on noise?
Yes □ No X Construction activities associated with the Proposed Action would not be expected to produce noise in excess of 90 dBA. The USDA ARS would limit construction activities to normal business hours.
Is the No Action Alternative likely to have a significant impact on noise?
Yes □ No X I The No Action Alternative would have no impact on ambient noise levels. I
• Geology, Topography, Soils Is the Proposed Action likely to have a significant impact on geology, topography, or soils?
Yes□ No X The project involves the construction of an approximately 3,000 square-foot greenhouse.
The project would involve the grading of the site to blend with the existing topography, and therefore would not significantly impact existing geology, topography or soils. Minor subsurface work is projected.
Is the No Action Alternative soils?
likely to have a significant impact on geology, topography, or
• Water Resources (surface, ground, wetlands, floodplains) Is the Proposed Action likely to have a significant impact on water resources?
Yes□ No X
As indicated by the New York State Environmental Resource Tracker, the project is not located within any wetland, floodplain, or “Rare Plants or Animals” area. Based on the project location and proposed project activity, no significant impact is expected.
Is the No Action Alternative likely to have a significant impact on water resources?
March 2022 Page 3
• Biological Resources Is the Proposed Action likely to have a significant impact on biological resources?
Yes□ No X
As indicated by the New York State Environmental Resource Tracker, the project is not located within any wetland, floodplain, or “Rare Plants or Animals” area. Based on the project location and proposed project activity, no significant impact is expected.
Is the No Action Alternative likely to have a significant impact on biological resources?
• Cultural Resources Is the Proposed Action likely to have a significant impact on cultural resources?
Yes □ No X There are no cultural resources located at the site. Therefor there was no requirement to complete a Determination of Eligibility for the National Register of Historic Places.
Is the No Action Alternative likely to have a significant impact on cultural resources?
The No Action Alternative would be the existing condition.
• Socioeconomics/Environmental Justice Is the Proposed Action likely to have a significant impact on socioeconomics or environmental justice?
Yes□ No X There would be no adverse impacts to socioeconomics or environmental justice concerns as a result of the Proposed Action. The Proposed Action could produce short-term positive effects through creation of construction jobs.
Is the No Action Alternative likely to have a significant impact on socioeconomics or environmental justice?
Yes□ No X
The No Action Alternative would be the existing condition. No short-term jobs would be created.
March 2022 Page 4
• Infrastructure and Utilities Is the Proposed Action likely to have a significant impact on infrastructure or utilities?
Yes □ No X Electrical and other utilities will installed in accordance with design plans, and in accordance with all appropriate regulations and guidelines. but this would not be a significant impact.
Is the No Action Alternative likely to have a significant impact on infrastructure or utilities?
• Hazardous and Toxic Materials and Wastes Is the Proposed Action likely to have a significant impact on hazardous and toxic materials and wastes?
Yes □ No X No hazardous or toxic wastes are expected to be generated during the construction, and no additional waste streams will occur once the construction is completed. There are no existing structures or facilities on the proposed project site, so no hazardous materials currently exist at the project site.
Is the No Action Alternative likely to have a significant impact on hazardous and toxic materials and wastes?
March 2022 Page 5
• Cumulative Effects Is the Proposed Action likely to have any cumula1ive effects when considering other past, present, and reasonably foreseeable projects in the area?
Yes □ No X The project will not change the current use of the site, and will not involve significant changes to existing noise, topographical, or infrastructure conditions. As such, the Proposed Action would not be expected to contribute incrementally to adverse cumulative effects to any specific resource area. As such, no significant cumulative effects would be anticipated.
Is the No Action Alternative likely to have any cumulative effects when considering other past, present. and reasonably foreseeable projects in the area?
Yes □- No X The No Action Alternative would be the existing condition.
6. References
See Attachments section
March 2022 Page 6
7. Finding of No Significant Impact Based on my review of the data and analysis presented in this EA, I conclude that the Proposed Action, with implementation of the mitigation measures identified herein, would not have a significant adverse individual or cumulative impacts to the quality of the human environment. As such, an Environmental Impact Statement, as defined under the NEPA, is not warranted and will not be prepared.
To minimize the potential for adverse effects, the USDA ARS will:
• Suppress fugitive dust and particulate matter by applying water to the site, as necessary;
cover exposed materials, as necessary; minimize equipment operation to the extent possible, including minimizing idling and operating time; and use ultra-low sulfur diesel fuel (as required by Federal law) during all construction activities
Accordingly, the requirements of the referenced regulations have been satisfied, and I conclude that FONSI is appropriate.
Printed Name
Title
Signature
Date
March 2022 Page 7
Attachments:
Project Site Plan
Geneva NY Wellington High Tunnel EA Resources Map
Crusher Run
Rimol 96x30’
Rimol 96x30’
Crusher Run Parking
Expand and deepen 3 side bays for equip storage
Conc Slab
Move pole towers to slab; rotate 90 for access
Saw dust bay
Saw dust bay
Wellington Barn 200’ l x 60’ w
90’
Remove old H20 tank
Wet fruit/veg processing awning
"Rare animals/plants"
Project Location
Stream
| Geneva Wellington HHGH High Tunnel EA |
| • Water Resources (surface, ground, wetlands, floodplains) |
| Cumulative Effects |
| Attachments: |
| Project Site Plan |