PPQ.docx

DOCX document 29 KB Posted

Attached to
BASE OPERATIONS SUPPORT SERVICES (BOS), AVON PARK - AMENDMENT 02 Federal contract opportunity
Solicitation number
FA481421R0002
Issued by
Department of the Air Force Air Mobility Command

About this file

This document contains a past performance questionnaire and details of a related federal contract opportunity. The past performance questionnaire is a template for offerors and customers to evaluate performance on previous contracts. It requests information on contract details and performance ratings for quality, management, schedule, price, communications, safety and environmental standards.

The related federal contract opportunity is a solicitation from the Department of the Air Force for base operations support services at Avon Park Air Force Range in Florida. Services include range maintenance, target construction and maintenance, civil engineering, roads and grounds upkeep, infrastructure maintenance, refuse collection, custodial work, administrative support, supply, fuels management, IT, transportation, environmental programs and hazardous waste handling. The opportunity is set aside for small businesses under NAICS code 561210. A pre-proposal conference will be held on May 25th and requests for information are due by June 2nd. The fixed-price contract has a one-year base period and six one-year options.

View the file

Other files for this federal contract opportunity

Other files attached to BASE OPERATIONS SUPPORT SERVICES (BOS), AVON PARK - AMENDMENT 02, newest first.
File Type Posted
Experience Summary Sheet (Amendment 01).docx DOCX document
DRAFT AFMAN 13-212 - Apr 2021.pdf PDF
Appendix A - Workload amended 9 June 2021 (Amendment 01).pdf PDF
Appendix F - Support Agreements MOAs and Contracts amended 9 June 2021 (Amendment 01).pdf PDF
Appendix J - Forms Reports Submittals and Technical Letters amended 9 June 2021 (Amendment 01).pdf PDF
RFI Response Sheet Avon Park BOS - Final.xlsx XLSX spreadsheet
Solicitation Amendment FA481421R00020001 SF 30.pdf PDF
Atch 1 PWS BOS Services Avon Park Amended 9 June 2021 (Amendment 01).pdf PDF
Past Performance Summary Sheet (PPSS).docx DOCX document
Experience Worksheet.docx DOCX document
Appendix B - Maps and Site Plans - Amendment 01.pdf PDF
PRE-PROPOSAL CONFERENCE 25 May 2021.pptx PPTX presentation
Solicitation - FA481421R0002.pdf PDF
FA481421R0002 RFI Submission Form.docx DOCX document
Appendix D - Facilities Systems and Equipment.pdf PDF
Appendix I - Minimum Essential Level Vehicles.pdf PDF
Appendix J - Forms Reports Submittals and Technical Letters.pdf PDF
Appendix A - Workload Estimate.pdf PDF
Appendix F - Support Agreements MOAs and Contracts.pdf PDF
Atch 2 QASP.pdf PDF
Atch 3 Wage Determination 2015-4541 Rev 11.pdf PDF
Appendix E - Applicable Publications.pdf PDF
Atch 1 PWS BOS Services Avon Park.pdf PDF
Atch 4 CBA ASRC IAMAW.pdf PDF
Appendix B - Maps and Site Plans V.2.pdf PDF
Appendix C - Government Furnished Property.pdf PDF
Appendix G - Contractor Employee Certifications.pdf PDF
Appendix H - Acronyms_Definitions v.2.pdf PDF
Show all 28

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Past Performance Being Evaluated: To Be Completed by Offeror

Performance Task Area:

Performance Rating:

Performance Task Description:

Performance Location:

Contract Title Performance was Accomplished Under:

Contract/Project # Performance was Accomplished Under:

Contract Award Cost:

Contract Award Date:

Contract Completion Date:

Prime Contractor:

Customer Rep Name:

Customer Rep phone #:

Customer Rep email:

Past Performance : To Be Completed by Customer

Customer Rep Name:

Customer Rep phone #:

Customer Rep email:

Exceptional
Very Good
Satisfactory
Marginal
Not Satisfactory

Quality of Service

(1) The Contractor provided a product or service that conformed to contract requirements, specifications, and standards of good workmanship

(2) The Contractor provided full staffing with qualified personnel appropriate to the effort performed

(3) The Contractor provided equipment, and materials that were appropriate to the effort performed

Overall Quality of Service Rating

Management

The Contractor had control of the work site and his subcontractor at all times

The Contractors on site manager ensured all his the activities were well managed and met Gov Standards

The Contractors Site manager addressed any issues in a timely manner

The Contractor was cooperative in addressing issues and worked well with the government, subcontractors, other contractors not under his/her control, and customers.

Overall Management Rating

Quality

The Contractor followed his companies Quality Control (QC) plan

The Contractor had the design drawing/specifications on hand at the job site

The Contractor followed the design drawing/specifications or formally requested a deviation in writing before using an alternate approach

The Contractor ensured all work was accomplished to industry standard or better

The Contractor self-identified work that did not meet standard and corrected it without government direction

Overall Quality Rating

Schedule

The Contractor met the schedule to design and construct the project

Overall Schedule Rating

Price

The Contractor did not submit extraneous claims for additional compensation

The Contractor fairly priced any modifications

Overall Price Rating

Communications

The Contractor outlined his schedule in advance and kept the customer and inspector updated on activities

The Contractor identified any foreseeable issues with the customer and the government in advance

The Contractor was open and honest in communications

The Contractor answered questions in a timely manner

Overall Communications Rating

Safety

The Contractor carefully followed all safety regulations

The Contractor kept a clean and organized work site

Overall Safety Rating

Environmental

The Contractor ensured his work was conducted in accordance with all environmental laws and regulations

Overall Project Execution Rating

Additional Comments: